The City looks forward to continuing to work with ACI to complete this important project. <br />CONTRACT TIME <br />Per CO #3, the Contract time was to expire on November 13, 2018, CO #4 will add 33 working days to this Contract, since <br />• ACI vacated the project site on November 16, 2018, allowing the utility companies to continue the utility conversion works. <br />Therefore, between November 13 and 16 of 2018, 3 working days of Contract time extension is needed. <br />• The construction project will be retroactively suspended starting from November 17, 2018, until the utility conversion works are <br />completed. <br />• ACI will have 30 working days to complete all remaining works for the construction project, including all the punch list items. <br />Therefore, the Contract time will need to be increased by 33 working days total. <br />As part of this CO #4, the parties agree that the Contract time will not be extended further, with the exception of: <br />• weather related delays; <br />• delays encountered that are out of the control of the Contractor or the City; <br />• and unanticipated changes to the work where extension of Contract time would otherwise be determined in accordance with <br />Section 1-08 of the WSDOT Standard Specifications, 2016 version. <br />Page 3 of 3 <br />34 <br />