City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
Peggy McCarthy, Finance Director
DATE: August 23, 2013 (Revised after June 25, 2013 Transportation Committee)
SUBJECT: Tukwila Urban Center— Pedestrian /Bicycle Bridge
Project No. 90510403
Acceptance of State Regional Mobility Grant
ISSUE
City acceptance of a State Regional Mobility grant in the amount of $6,870,000 awarded to the Tukwila Urban Center (TUC) Pedestrian/
Bicycle Bridge over the Green River Project.
BACKGROUND
In October 2012, Council authorized staff to submit a grant application to the Washington State Department of Transportation Regional
Mobility program for right -of -way acquisition and construction of the TUC Pedestrian /Bicycle Bridge. This grant application was
successful and funds have been incorporated directly into the Washington State biennial budget. According to CIP Policy, staff must
obtain approval from the full Council before accepting grants.
Design is underway and the 30% plans have been completed and reviewed by staff. Environmental review and permitting are also
underway and full design and permitting is expected to be completed by March 2014. Right -of -way acquisition can take a year to acquire
and the City could start on this process later this year. Construction is currently anticipated to be over an 18 -24 month period to
coordinate with fish windows and other restrictions associated with working over the Green River.
The Transportation Committee asked staff at the June 25th meeting to return to Committee with a funding proposal since the 2013 CIP
sheet (attached) shows $810,000 of expected park impact fees. The draft 2014 CIP sheet (attached) shows the revised expected park
impact fees of $35,000 for 2013 and $55,000 for 2014 and 2015.
DISCUSSION
The Regional Mobility Grant Program requires a local match of at least 20% of the total cost of the project from direct contributions. City
funds, park impact fees and future grants may be used as match, as well as staff salaries and past expenditures, including previously
awarded grants for the design work. The Regional Mobility Grant is a 4 -year award over two state biennial budgets. The award for the
2013 -2015 biennium is $4.6M and the continuing award into the 2015 -2017 biennium is for $2.2M. This is very similar to the awarded
grant for the Transit Center Project from the same agency.
FISCAL IMPACT
On the attached draft 2014 CIP page 12, $145,000 is shown
as Park Impact Fees, although the Park Impact Fee ordinance
is based on up to $1,600,000 to be utilized for the Pedestrian
Bridge Project. To make up the difference for lower than
expected Park Impact Fees and to lessen the impact to the
General Fund, staff is proposing an interfund loan from the
Water Fund in the amount of the Park Impact fee shortfall of
$665,000. The interfund loan will be repaid by future Park
Impact Fees. Staff will return with more information as the
project progresses and is closer to construction with firmer
cost estimates.
Phase
Amount
Funding Source
Amount
Design
$1,633,833
Awarded Grants
$1,496,833
General Fund
102,000
Park Impact Fee
35,000
Right of Way
$1,100,000
Regional Mobility
$870,000
General Fund
140,000
Park Impact Fee
55,000
Construction
$7,485,000
Regional Mobility
$6,000,000
General Fund
800,000
Park Impact Fee
55,000
lnterfund Loan
665,000
Total
$10,218,833
Total
$10,218,833
RECOMMENDATION
Council is being asked to formally accept the State's Regional Mobility Grant for the Tukwila Urban Center Pedestrian /Bicycle Bridge
Project in the amount of $6,870,000 and consider this item on the Consent Agenda at the September 3, 2013 Regular Meeting.
Attachments. May 28, 2013 E -mail Notification of Award
Excerpt from the 2013 -2015 LEAP Transportation Document (ESSB 5024)
Draft 2014 CIP page 12
W: \PW Eng \ PROJECTS \A- RW & RS Projects\TUC Ped Bicycle Bridge (90510403) \ Grants \Info Memo - Grant Acceptance -rev. 8- 12- 13.docx
1
Cyndy Knighton
Prom: Eldridge, Mark <EldridM@wsdot.wa.gov>
Sent: Tuesday, May 28, 2013 11:33 AM
To: Morrison, David; Dong, Jonathan; Kirk McKinley; Cyndy Knighton;
dianas@kitsaptransit.com; Barb Hunter (bhunter@piercetransit.org); Overby, Monica;
Wolterink, Lisa; Otterstrom, Karl; Howell, Gordon; Marcia Smith
(msmith@skagh1ransit.o»g);stevemeU0pdsidgefie|dmm.usHeffennar\Petec
(melissa.cauley@commtrans.org); Kathryn Rasmussen; DBloom@intercitytransit.com;
(BHo|man@intercitytransitzwm);'dorindazosta@seatt|eguv'
(dorinda.costa@seattle.gov); Chuck Green ([huckGKpc-tranong); ju|ies@c-ten.o»g; Kelly
Hayden (khavden@pierce{mnsito»g); 'Barb Savary' (savary@islandtransit.org);
madams@piercetransit.org; (kmcmullen@bft.org); Suing, Troy; Futrell, Kevin
(Kevin.Futrell@yakimawa.gov); dcl@bft.org; AFreeman@intercitytransit.com; Martha
Rose; Dale 0' Brien; (marciaC@ridewta.com) (marciaC@ridewta.com)
Cc: Rutledge, Nicole; Eldridge, Mark
Subject: Regional Mobility Grant Projects for 2013-2015
Welcome!
You're receiving this email because your project(s) has been selected for funding by the Washington State Legislature for
the 2013'2015 biennium. It's been almost a year since the call for new project went out and a lot of energy has been
expended getting to this point, well don&
Now that the project list is complete WSDOT staff will be preparing contracts for each new project. We will also be
preparing contract amendments for the continuing projects. 1 anticipate they will be ready and in your hands by the end
mf]une.
So what happens next? I have a few helpful hints and reminders to pass along:
• Please review your project schedule and make sure it's up to date. If it isn't, then please send me a revised page
bv June 1[^
• Please review your planned expenditures by quarter. If that needs to be updated, then please have that to me
bv June 1nm.
• Any expenditure made on the project before June 30, 2013 can be counted towards your match requirement,
but not eligible for reimbursement.
�
For four year projects make sure your scope of work will get you to the minimum milestones for continued
funding in 2015-2017 biennium. The grant application guide describes the minimum milestones.
• Starting July 1, 2013 any eligible project expense is eligible for reimbursement regardless when the contract is
signed.
• A project Performance Measurement Plan (PMP) is required to be reviewed and approved by WSDOT before a
reimbursement request will be processed and check cut. There are examples of past project PMP's on the
Regional Mobility web page copying is encouraged. Janice Helmann will help you prepare the PMP and will also
be the one reviewing and approving. As you may recall Janice is the person you sent your Year 1 and Year 4 VT
and VMT reduction to in Step 1 of the grant application process. HelmannJ@wsdot.wa.gov 206-464-1284. You
can start on this now and beat the rush.
• The project scope you included in your grant application is what we expect you to build or provide. If the
project scope must change for some reason you must contact me immediately.
• If you're project cost comes in 10% lower than you anticipated you must contact me immediately.
2
• When you do send us a reimbursement reques please make sure its painfully easy for us to track the
expenditures. Some of the reimbursement request are several inches thick and we don't know what numbers
your taking from where. Please use highlighter, sticky notes, a spreadsheet anything to help us follow the rabbit
trail. It will get done faster and you won't get a phone caII from us.
�
The supporting documentation you send should add up to the total expenses on the reimbursement form (we
will send each grantee a custom Reimbursement Request form).
w A project that has more than 20Y6 local match can bill the grant at 100Y6. A project that has 2096 local match
must bill the grant at 80% of the eligible expenses.
• Please use the Regional Mobility Grant funds early, because you don't have to deal with reappropriation
requests and accruals. This will make all our lives easier, but if you can't that's fine too.
w A grantee must bill the grant at Ieast quarterly. Someplace it says a grantee can't bill more than once a month,
but 1 say bill as often as you need to. The caveat 15, please make sure it's for a reasonable amount ($2,000 or
more), because they take time to process and we don't have as many staff as we used to.
The first and mos important thing I do as grant manager is to help you complete your project on time, on budget, and in
scope. The other less glamorous thing deals with accountability and reporting.
Call us any time you have questions. We will do everything we can to help you! 1 plan to schedule a meetings with each
of you over the next few months, because I want us to get to know each other, and you're projects in more detail.
Mark Eldridge
Regional Mobility Grant Program Manager
Park and Ride Lot Program Manager
360'705'7273
2
3
4
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2014 to 2019
PROJECT: Tukwila Urban Center - Pedestrian /Bicycle Bridge Project No. 90510403
DESCRIPTION: Construct a new pedestrian /bicycle bridge over the Green River.
JUSTIFICATION: Pedestrian /bicycle connection between Tukwila's Urban Center and commuter rail /Amtrak station.
Supports local and regional goals and policies regarding and use and transportation in Urban Center.
Pedestrian System Report identified the optimal location for bridge crossing to be south of the Best
STATUS: Western Hotel. Type, Size, and Location Report was completed in 2011. Council approved a design of
a twin -tied arch bridge with no accommodation for a future bridge crossing over West Valley Highway.
MAINT. IMPACT: To be determined.
Design grants: State Enhancement for $190k & $500k, Transit Oriented Development (TOD) planning grant
COMMENT: of $55k, and Federal CMAQ grant of $751 K. WSDOT Regional Mobility construction grant of $6.870M.
Project is on Park Impact Fee list with funding of $2 million with an 80 %/20% split for $1.6M. Interfund loan
of $665k from the Water Enterprise fund will be repaid with future park impact fees.
FINANCIAL Through Estimated
in $000's
2012 2013 2014
2015
2016
2017
2018
2019
BEYOND TOTAL
EXPENSES
Design
585
748
300
1,633
Land (R/W)
1,100
1,100
Const. Mgmt.
1,000
1,000
Construction
6,485
6,485
TOTAL EXPENSES
585
748
1,400
7,485
0
0
0
0
0
10,218
FUND SOURCES
Awarded Grant
540
713
243
1,496
Awarded Reg Mobility
870
6,000
6,870
Park Impact Fees
35
55
55
145
Interfund Loan (Wate )
665
665
City Oper. Revenue
45
0
232
765
0
0
0
0
0
1,042
TOTAL SOURCES
585
748
1,400
7,485
0
0
0
0
0
10,218
2014 - 2019 Capital Improvement Program
12
5