HomeMy WebLinkAboutReg 2016-12-05 Item 4D - Final Acceptance - 2016 Overlay and Repair Program with Lakeside Industries for $1,098,062.24COUNCIL AGENDA SYNOPSIS
Initials
Meefin
,g Date
Pre bY
M vie),v
Council review
12/05/16
BG
❑ Resolution
Aft
,g Date
F-1 Ordinance
,g Date
Mt
❑ Bic/Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Eire ❑ IT ❑ P&R ❑ Police E PV
SPONSOR'S The contract with Lakeside Industries, Inc. of Kent, WA is complete for the 2016 Overlay &
SUMMARY Repair Program. This contract improved the roadway at nine locations throughout the City
and a portion of the parking lot at Fort Dent Park. Construction began June 14, 2016 and
was completed on August 12, 2016. No change orders were issued and under-runs credited
($179,894.56). Council is being asked to accept and finalize the contract with Lakeside
Industries for $1,098,062.24.
REVIEWED B Y R cow Mtg. ❑ CA&P Cmte ❑ F&S Cmte Transportation Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 11/21/16 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMI'I'IT,E Majority Approval; Forward to Regular Consent Agenda
COST IMPACT/ FUND SOURCE
ExPENDi'f uRF, RF,QUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$1,098,062.24 $1,360,000.00 $0.00
I
MTG. DATE
RECORD OF COUNCIL ACTION
12/OS/16
ITEM INFORMATION
ITEMNO.
CAS NUMBER: I
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATL: 12/05/16
AGII.NDA ITEM Trri,f," 2016 Overlay & Repair Program
Project Completion and Acceptance
CXIT"GORY F-1 Discussion
Mtg Date
Motion
Mt
,g Date 12105116
❑ Resolution
Aft
,g Date
F-1 Ordinance
,g Date
Mt
❑ Bic/Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Eire ❑ IT ❑ P&R ❑ Police E PV
SPONSOR'S The contract with Lakeside Industries, Inc. of Kent, WA is complete for the 2016 Overlay &
SUMMARY Repair Program. This contract improved the roadway at nine locations throughout the City
and a portion of the parking lot at Fort Dent Park. Construction began June 14, 2016 and
was completed on August 12, 2016. No change orders were issued and under-runs credited
($179,894.56). Council is being asked to accept and finalize the contract with Lakeside
Industries for $1,098,062.24.
REVIEWED B Y R cow Mtg. ❑ CA&P Cmte ❑ F&S Cmte Transportation Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 11/21/16 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMI'I'IT,E Majority Approval; Forward to Regular Consent Agenda
COST IMPACT/ FUND SOURCE
ExPENDi'f uRF, RF,QUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$1,098,062.24 $1,360,000.00 $0.00
Fund Source: 104 ARTERIAL STREETS (PG 18, 2015 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
12/OS/16
MTG. DATE
ATTACHMENTS
12/05/16
Informational Memorandum dated 11/18/16
State of WA Department of Revenue Notice of Completion 16-070
Minutes from the Transportation Committee meeting of 11/21/16
2
W
TO:
FROM
CC:
DATE:
City of Tukwila Allan Ekberg, Mayor
Public Works Department -Bob Giberson, Director
Transportation Committee
Bob Giberson, Public Works Directod?_/
David Sorensen, Project Mamagey
Mayor Ekberg
November 18, 2016
SUBJECT: 2016 Overlay and Repair Program
Project No. 91610401,Contract No. 16-070
Project Completion a0d Acceptance
ISSUE
Accept contract Racomplete and authorize release of retainage.
BACKGROUND
The Notice to Proceed for Contract No. 16-070 with Lakeside Industries, Inc. of Kent, Washington was
issued on June 14'2O16 for the 2O16 Overlay and Repair Project. ThiGovedayp jectprVvdodhotmix
asphalt (HMA) paving at nine locations throughout the City and a portion of the parking lot at Fort Dent
Park. The street improvements included; paving, removing and replacing concrete curbs, gutters,
sidewalks and ADA ramps, installing traffic loops and junction boxes, adjusting surface utilities to
grade, and installing roadway ChaOD8|iZ8tiOO.
ANALYSIS
Construction was physically completed on August 12, 2016. No change orders were executed. Asphalt
quantities and pavement repairs were less than expected, allowing Minkler Boulevard to receive a
complete overlay in lieu of the planned pavement repairs. Het@inage of $54,903.12 is being withheld.
The budget for the 2016 Overlay & Repair construction was $1,360,000.00 and included a 5%
contingency, which was not utilized.
Construction Contract Amount $1,277.958.80
UOd8FnUDS
Total Amount Paid S_tJQ2U62.24
RECOMMENDATION
Council is being asked to formally accept and authorize the release of the retainage, subject to
standard claim and lien release procedures, for the 2016 Overlay and Repair Project vvkhL8k8Side
Industries, Inc. in the final amount Of $1'098.062.24 and consider this item on the Consent Agenda at
the December 5'2O16 Regular Meeting.
Attachment: Notice of Completion Contract No. 16-070
wAPwsng\pROJEcTSmmvanoproj"tsmnnual Overlay aRepair Progr=s\2oo Overlay uRepair Out wrmooc"mrmmm Memo 20m Overlay Closeout nm16wuocx
12
STATg
1889
M Original
❑ Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Date: August 5, 2016 Contractor's UBI Number: 601 - 106 -847
s ,� eVW" b b.,. Ad r'a ,,,. ya ,. ,,M,. i +�✓� i ,r„M � -,.�:. „.y., ,�.., rx,riMu rw w,,.,�4^1 ^� ,xsd n'•SV x 4 � ", 2,.
f / ✓r,rr X,,: � '�4 rt;. �f ,� 1 r . ✓f,4 n✓ �,{ ". 1" n';t'ar vr,y�,"If ,+rh t_�Fi' r,i ?'iF'!.,,'i "�1 r"! 'o; p/dV"v : �h'.3 �t l rr „l�.".a paS"�' � , °,,
„k.P1,r,�,A�W. �;r�, mn,.,_.,. », „:,:��. �,,,...�..�g:..:.,,,M� »,.r„ nx„^Hr,;.Jw,bw.,., ,,, i.r�.g �.�, y, .:.x..,,:, i ,,::.: i, k.:, rxa+„ r. s�� -0��::rr���tt,t��+�fa�^ld:na�^aMp ..���u., .�nha r �n�.,.t ,Y 4,rfi.u,�76 . r✓.xr�,r. �(,�xa..o.,.,
City of Tukwila Assigned to:
6200 Southcenter Boulevard
Tukwila, WA 98188 Date Assigned:
UBI Number: 91- 6001519
Notice is hereby given relative to the completion of contract or project described below
Project Name
Contract Number
Job Order Contracting
City of Tukwila 2016 Overlay Program #91610401
116-070
Yes [� No
El r
Description of Work Done /Include Jobsite Address(es)
Hot Mix Asphalt (HMA) Overlay at the following locations: S 130th Street, 48th Ave S, Interurban Ave S, 52nd Ave S, Fort Dent Way, Minkler Boulevard, Andover Park E, Fort Dent Park, and S 144th Street.
Federally funded transportation project? ❑ Yes d No (if yes, provide Contract Bond Statement below)
Contractor's Name
E -mail Address
Affidavit ID*
Lakeside Industries, Inc.
Craig .Nickel @Lakesidelndustries.com
674247
Contractor Address
Telephone #
PO Box 7016 Issaquah, WA 98027
(425) 313 -2600
If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number.
❑ Retainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects)
Name:
I Bond Number:
Date Contract Awarded
Date Work Commenced
Date Work Completed
Date Work Accepted
5/16/2016
6/15/2016
8/18/2016
Were Subcontracters used on this project? If so, please complete Addendum A. Of"Yes ❑ No
Affidavit ID* - No L &I release will be granted until all affidavits are listed.
Contract Amount
Additions ( + )
Reductions (- )
Sub -Total
Sales Tax Rate 0 %
(If various rates apply, please send a breakdown)
Sales Tax Amount
$ 1,277,956.80
$ 0.00
$ 179,894.56
$ 1,098,062.24
/•: 1•
Liquidated Damages $
0.00
Amount Disbursed $
1,043,159.12
Amount Retained $
54,903.12
I V"IG.- -1 It V3 C, IWU 1111 It ritti3t UC Cl /tItit
TOTAL $ 1,098,062.24
i_t r C. e, C—Z- - o v, �
Note: The Disbursing Officer must submit this,Impleted notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber
Email Address: Diane.Jaber @TukwilaWA.gov
IQ Department of Revenue Washington StateDepamnent of
C Public Works Section Labor & Industries
(360) 704 -5650 Contract Release
PWC @dor.wa.gov (855) 545 -8163, option # 4
ContractRelease@ LN I. WA. GOV
REV 31 0020e (10/26/15) F215 -038 -000 10 -2014
Title: Fiscal Specialist
Phone Number: (206) 433 -1871
Employment Security
Department
Registration, Inquiry,
Standards & Coordination
Unit
(360) 902 -9450
publicworks @esd.wa.g T3
Addendum A: Please List all Subcontractors and Sub-tiers Below
This addendurn can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name:
U131 Number: (Required)
Affidavit ID"':
A & R SAWING & DRILLING CO
601514268
657710
BEST PARKING LOT CLEANING INC
601901928
660899
BROTHER'S TRUCKING L.L.C.
602506532
661327
C & E TRANSPORT CORP
602408510
663713
CASCADE UTILITY ADJUSTING LLC
603407046
672708
CORLISS RESOURCES INC
602237779
675398
GROUND UP ROAD CONST INC
602790246
674709
LAKERIDGE PAVING CO L L C
601592135
660160
MOBY'S 24-HR ST SWPNG SVCS INC
603358194
661278
NORTHWEST SWEEPING
602609350
669278
PIONEER CABLE CONTRACTORS INC
600464'320
67015
SILVERSTREAK INC
600432781
657693
STRIPE RITE INC
601048084
665610
TIGER MOUNTAIN RENTAL, LLC
601720071
660161
WILSON CONCRETE CONST INC
602168956
678707
For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the
[��ashington elay Service by calling 711.
LIU1 31 0020e Addendum (10/26/15) F215-038-000 10-2014
TRANSPORTATION COMMITTEE
• . f - 1 •
City Council Transportation Committee
Meeting Minutes
November 21, 2016 - 5:30 p.m. - Foster Conference Room, 6300 Building
Councilmembers: Verna Seal, Acting Chair; Joe Duffie, {Absent: Dennis Robertson)
Staff: David Cline, Bob Giberson, Dave Sorensen, Jaimie Reavis, Robin Tischmak, Gail
Labanara, Moira Bradshaw, Jack Pace, Laurel Humphrey
CALL TO ORDER: Acting Committee Chair Seal called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. BUSINESSAGENDA
A. Americans with Disabilities Act Transition Plan Update
Staff presented the draft ADA Transition Plan prepared by the Transpo Group. The Plan, a
federal requirement, addresses accessibility within the public right -of -way and will next
undergo a 30 -day public comment period before returning to Council for consideration and
adoption. INFORMATION ONLY.
B. Supplemental Agreement: Americans with Disabilities Act Transition Plan
Staff is seeking Council approval of Supplemental Agreement No. 1 with Transpo Group USA,
Inc. in the amount of $15,700.00 for continued support through the public comment stage and
final editing. If approved, the contract will be extended through April 1, 2017. MAJORITY
APPROVAL. FORWARD TO DECEMBER 5, 2016 REGULAR CONSENT AGENDA.
C. Interagency Agreement: Baker Boulevard Non - Motorized Improvements
Staff is seeking Council approval of an interagency agreement with King County to accept $1
million for the City to complete the Baker Boulevard and Christensen Road segments of the
TUC /TOD Pedestrian Improvements. This will construct buffered bike lanes in each direction
along Baker Boulevard, reduce vehicular travel lanes from four to three, and add a minimum
12 -foot wide side path along Christensen Road. There is no match required for this King County
grant. MAJORITY APPROVAL. FORWARD TO DECEMBER 5, 2016 REGULAR CONSENT
AGENDA.
D. Proiect Completion: 2016 Overlav and Repair Program
Staff is seeking Council approval of project completion and release of the retainage bond to
Lakeside Industries, Inc. in the amount of $1,098,062.24forthe 2016 Overlay and Repair Project.
This project provided hot mix asphalt paving at nine locations and a portion of the parking lot
at Fort Dent Park. Construction was completed on August 12, 2016. MAJORITY APPROVAL.
FORWARD TO DECEMBER 5, 2016 REGULAR CONSENT AGENDA.