HomeMy WebLinkAboutCOW 2019-01-28 Item 3C - Public Safety Plan - Program Management Quality Assurance Quarterly ReportCOUNCILAGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Allay 's review
Council review
01/28/19
CO
ITEM INFORMATION
ITEM No.
3.C.
STAFF SPONSOR: LAUREL HUMPHREY
ORIGINAL AGENDA DATE: 1/28/19
AGENDA ITEM TITLE Quarterly Report for the Public Safety Plan Program anagement Quality Assurance
(PMQA)
CATEGORY 1 Discussion
1/28/19
El Motion
Mtg Date
0 Resolution
Mtg Date
E] Ordinance
Mfg Date
El Bid Award
Altg Date
0 Public Hearing
Mg Date
Ell Other
Mtg Date
Mg Date
SPONSOR Council ayor LIHR •DCD Hnance flFire LIT'S EP&R PoliceDPW EICotoi
SPONSOR'S Steve Goldblatt, the Council's PMQA consultant will provide the quarterly update.
SUMM\RY
REVIEWED BY El C.O.W. Mtg. E CDN Comm El Finance Comm. E1 Public Safety Comm.
0 Trans &Infrastructure Arts Comm. [1] Parks Comm. 11] Planning Comm.
DATE: COMMITTEE CHAIR:
RECOMMENDATIONS:
SPONSOR/ADMIN,
COMMITTEE
City Council
COST IMPACT / FUND SOURCE
EXPENDITURE -',QUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$ $ $
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
MTG. DATE
ATTACHMENTS
1/28/19
Informational Memorandum dated 1/23/ 9
PowerPoint Presentation
67
68
January 23, 2019
TO: Tukwila City Council
FROM: Steve Goldblatt
PMQA Consultant
RE: Public Safety Plan
January update
Fire Station 51 construction documents are complete. Station 52's schematic design phase
nears completion. Justice Center's construction documents are 75% complete. Program-
ming and master planning of the consolidated shops facilities is underway. Boldfaced en-
tries below are updated from last month's report.
FIRE STATIONS
Site development
Geotechnical exploration will inform site development costs for Fire Station 52. The
City owns the property planned for new Fire Station 54, and its use or disposition will
be a future Council decision. On 22 October, Council approved an amendment to
Lydig's contract for demolition of the structures on the property. Demolition was
completed last month.
Station 51 construction documents
Station 51 design development pricing was presented 27 August in COW, with Council
consensus to move forward to the construction documents phase. Seven Fire Depart-
ment -preferred alternates will be fully designed and included in bid package docu-
ments; Council will decide if/when any or all are adopted. Station 51's Council -ap-
proved budget is $13.3 million. The project team completed the 100% construction
document set last month.
Station 52 schematic design
Weinstein AU's schematic design for Station 52 began in August and has been com-
pleted with Fire Department input. At COW 10 September, Council concurred with
Public Safety's 4 September recommendations to (1) carry the administrative tenant
improvements as an alternate, and (2) select the Fire Department's preferred drive -
through plan. Drive -through Station 52's Council -approved budget is $19.26 million.
Station 54 assessment
On 18 June, Council eliminated new Station 54 from the Plan via Option D-20(f) and
asked for an estimate to make life safety improvements to the existing station. Staff
presented four potential options —with very rough order of magnitude cost esti-
mates —to Public Safety 5 November; see Rachel Bianchi's 30 October memo for de-
tails. Committee consensus was to revisit the options next May after Station 51 and
Justice Center construction costs firm up. The Committee agreed that the existing sta-
tion needs modest maintenance and repairs for the health of firefighters there.
69
FIRE STATIONS continued
Stations' budget
New Station 54's deletion has cost some economy of scale on design, construction, and
dependent costs for Stations 51 and 52. Including Station 54's substantially reduced
scope, the stations' overall Council -approved budget is $34 million. A Weinstein AU
contract amendment was approved by consent at a special Council meeting 10 Decem-
ber.
GC/CM pre -construction services
Lydig has been working with Weinstein AU on Station 51's construction documents
and Station 52's schematic design. Lydig has begun to issue Station 51 bid packages
this month and develop a Maximum Allowable Construction Cost (MACC) for its con-
struction contract amendment. In order to begin Station 5lconstruction in March,
Lydig's MACC contract amendment will be presented to Public Safety 4 March,
COW 11 March, and Council 18 March for approval. For Station 52, Council can
anticipate a mini-MACC contract amendment request by June to begin earthwork
and site utilities and purchase an elevator in July. The full MACC amendment will
follow in the fall to approve the start of Station 52 general construction.
Disadvantaged Business Enterprise and local hiring policies
The Council unanimously passed Resolution 1929 on 2 April, adopting DBE and local
hiring policies for the Plan's projects. The DBE goal is 17% and the local hiring goal is
20%, complementing the City's 10% apprenticeship requirement of Resolution 1814.
The first metrics that the Council sees can be expected mid-2019. Lydig—and BNBuild-
ers for the Justice Center —are ramping up efforts with the DBE community. An up-
date will be presented at Council next month.
JUSTICE CENTER
Property acquisition
The City now owns all nine Justice Center properties except JC-8 (Travelodge). The City
has possession and use of JC-8; ownership is pending the resolution of an easement is-
sue. The team has now completed surveying and Phase Il environmental investigation
on all parcels.
Construction documents
Design development pricing —confirming the Council -approved schematic design
budget of $68.5 million —was presented 8 October in COW, with Council consensus to
move forward to the construction documents phase. DLR completed the 75% con-
struction document set last month. Land use approvals were received last
month. The team submitted a civil permit application in November and a build-
ing permit application this week.
PMQA update January 23, 2019 page 2
70
JUSTICE CENTER continued
GC/CM pre -construction services
BNB performed early abatement and demolition work on the JC-9 property. A BNB
contract amendment for JC-8 property (Travelodge) early abatement and demolition
was recommended by Public Safety 3 December and approved by consent at a special
Council meeting 10 December. The work will begin as soon as Seattle City Light discon-
nects Travelodge service. BNB intends to issue bid packages starting this month
and develop a MACC for its construction contract amendment. In order to begin
construction in April, BNB's mini-MACC contract amendment will be presented
to Public Safety 4 March, COW 11 March, and Council 18 March for approval. The
mini-MACC amendment will allow BNB to proceed with demolition, earthwork,
site utilities, and steel and elevator procurement. The full MACC amendment will
follow in May to approve the start of construction.
CONSOLIDATED SHOPS
Property acquisition
The City now has agreements with all of the property owners, basically securing all
three properties. Ownership of two properties will transfer this year and the other in
five years.
Programming and master planning services
A $365,000 contract (including contingency) with SHKS Architects for shops' program-
ming and master planning services was recommended by Public Safety 1 October and a
majority consensus at COW 8 October and approved 4-3 by Council 5 November. The
first round of workshops with Public Works staff has concluded, and the next round
of staff input and review has begun.
OTHER RESOURCES
Professional services
The Project Executive Team has been working through procurement of additional con-
sultant resources for the Fire Stations and Justice Center. A hazmat contract for
$64,740 with NOVO for work at the Justice Center and existing Fire Station 54 was ap-
proved by Council 15 October. Archeologists and transportation consultants for envi-
ronmental reviews will be procured as needed. Proposed contracts —all within
budget —for (1) Fire Stations 51 and 52 and Justice Center commissioning with
Keithly Barber Associates ($143,069), (2) Fire Stations 51 and 52 and Justice
Center construction testing and inspections with Mayes Testing Engineers
($95,782), and (3) Justice Center forestry and environmental services (as a DLR
amendment for $18,920) were recommended 22 January by Public Safety for
discussion 28 January at COW and consideration by Council 4 February.
PMQA update January 23, 2019 page 3
71
PROGRAM SCHEDULE
Tight schedule
The overall schedule remains very ambitious. With so many activities under way, there
is little room for any missteps to meet the Plan's revised milestones. The Project Exec-
utive Team, City staff, and Council are doing as well as can be expected given all the
new properties' access, due diligence, and acquisition challenges. Fire Station 51 and
Justice Center bidding will begin next month, and construction on both projects in
March/April.
PROGRAM BUDGET
Market conditions
Like the Fire Stations, the Justice Center and Consolidated Shops budgets will need to
be sensitive to tight construction market conditions and increasing property values.
These external budget pressures will manifest themselves as Fire Station 52 and future
consolidated shops project estimates are refined and Station 51 and Justice Center bids
are received.
LEGEND
Meeting target
Proceeding as planned.
Caution advised
Steps needed to meet target.
PMQA update
Correction needed
Steps needed to attempt recovery.
Not meeting target
No recovery plan in place.
January 23, 2019 page 4
72
Tukwila Public Safety Plan
Program Management
Quality Assurance Consultant
Winter Quarter Update
Steve Goldblatt
COW January 28, 2019
Public Safety Plan PMQA Winter Update
• Capable PSP team: City, SOJ; WAU, Lydig; DLR, BNB; SHKS
• GC/CM right approach: better estimating, fewer surprises
• WA Project Review Committee approval on fire stations' use of
GC/CM after initial denial
• PSP has progressed like other public projects, programs
• Tight budgets, schedules
• User needs, expectations » $ approved by the voters
• Hard for all (users, PSP team, Council) with limited budgets
• Initial budgets --> Council -approved budgets
Public Safety Plan PMQA Winter Update
Fire Station 51 nears construction
• GC/CM Lydig began issuing bid packages last week
• Lydig will assemble low responsive bids from low responsible
bidders
• Based on those low bids, Lydig will prepare its Maximum Allowable
Construction Cost (MACC)
• MACC comes to Public Safety 4 March, COW 11 March, and Council
18 March with prices for all design alternates (Council's choice)
• Construction is scheduled to begin in March
Public Safety Plan PMQA Winter Update
Justice Center nears construction
• GC/CM BNBuilders will issue bid packages next week, starting with
early work scopes: demolition, earthwork, site utilities, and steel and
elevator procurement
• BNB will assemble low responsive bids from low responsible bidders
• Based on the early works low bids, BNB will prepare a mini-MACC
• Mini-MACC comes to Public Safety 4 March, COW 11 March,
and Council 18 March
• Early works construction is scheduled to begin in April
Public Safety Plan PMQA Winter Update
Justice Center nears construction
• Based on the remaining low bids, BNB will prepare its full MACC
• MACC comes to Public Safety, COW, and Council in April/May
• General construction is scheduled to begin in April/May
Public Safety Plan PMQA Winter Update
Fire Station 52 construction follows
• Weinstein AU schematic design is complete for the drive-thru plan
• Lydig will issue bid packages next month for early work scopes:
earthwork, site utilities, and elevator procurement
• Lydig will assemble low responsive bids from low responsible
bidders
• Based on the early works low bids, Lydig will prepare a mini-MACC
• Mini-MACC comes to Public Safety, COW, and Council in June
• Early works construction is scheduled to begin in July
Public Safety Plan PMQA Winter Update
Fire Station 52 construction follows
• Upon completion of the design development and construction documents
phases this fall, Lydig will issue the bulk of the bid packages
• Lydig will assemble low responsive bids from low responsible bidders
• Based on those low bids, Lydig will prepare its full Maximum Allowable
Construction Cost (MACC)
• MACC comes to Public Safety, COW, and Council this fall with a price for
the administration build -out alternate (Council's choice)
• General construction is scheduled to begin in this fall
Public Safety Plan PMQA Winter Update
Public Works Facilities master planning underway with staff
• Good Council decision to approve master planning, programming
• Master plan expected in May to Public Safety, COW, and Council
• Based on the master plan, Council will have opportunities to make
deliberate, incremental decisions over many years as $ allow
• Heiser property available as early as 1 July and as late as 31 Dec;
$45,000 monthly rent
• Initial improvements to existing buildings can begin this summer
• UPS property transfers in 2023
Public Safety Plan PMQA Winter Update
• Council has made step-by-step decisions in a natural progression
• Council can't miss any deadlines to meet schedules, budgets
• Council is set up for success based on good information
• Council is prepared to make big $ decisions
• PMQA consultant's role the next two years
• Questions?