HomeMy WebLinkAboutReg 2019-07-15 Item 6C - Reports - City Administrator / 2019 2nd Quarter Work Plan Update / Public Safety Plan Monthly UpdateAllan Ekberg, Mayor
TO:
Mayor's Office - David Cline, City Administrator
The City of opportunity, the community of choice
Mayor Ekberg
Councilmembers
FROM: David Cline, City Administrator
DATE: July 10, 2019
SUBJECT: City Administrator's Report
The City Administrator Report is meant to provide the Council, staff and community an update on
the activities of the City and on issues that concern Tukwila. Please let me know if you have any
questions or need additional information about any of the following items.
Intergovernmental Update
• Association of Washington Cities (AWC) Annual Conference: Council President Hougardy,
City Administrator David Cline and Council Analyst Laurel Humphrey attended the AWC
Annual Conference in Spokane June 25 - 28.
• US Conference of Mayors Annual Meeting: Mayor Ekberg attended the US Conference of
Mayors Annual Meeting June 28 - July 1. At the conference he gave a presentation to the
Jobs, Education and Workforce Development Standing Committee about Partnering with
Local Youth for Success. The presentation highlighted the annual College and Career Fair,
promotion of apprenticeships through the Apprenticeship Guidebook and events, the High
School Internship program and the Tukwila, City of Opportunity Scholarship.
11. Community Events
• Upcoming Events:
o July 24: See You in the Park: Crestview Bark in the Park
o July 27: Touch -a -Truck Westfield Southcenter Mall, south parking lot.
o August 7: See You in the Park: Tukwila Community Center, See You in the Sprinklers
o August 17: Community Garage Sale
o August 21: See You in the Park Sullivan Center Summer Shindig
M. Staff Updates
Public Safety
* The Community Police Team attended the recent See You in The Park event. They also
continue to visit the mosques, monitor homeless camps and conduct orientations at the
International Refugee Committee.
Tukwila City Hall • 6200 Southcenter Boulevard • Tukwila, WA 981 • 206-433-1 • Website: TukwilaWA.gov
163
City Administrator's Report
July 10, 2019
Page 2
Project Updates
• 42" Ave Phase III: Estimated Completion: October 2019
City construction management team and the construction contractor are coordinating to
schedule the project punch list items.
• 53rd Ave S: Estimated Completion: September 2019
Contractor continues to finish up remaining construction and then the project site will be
turned over to utilities for utility conversion. At the same time, the City construction
management team and the construction contractor are also addressing Seattle City Light's
required field changes.
• 2019 Overlay and Repair: Estimated Completion: August 2019
52nd Ave at Interurban Ave S has all new compliant ADA ramps and is prepped for paving
beginning July 8 with completion by July 12. Crews are preparing S 200th St for pavement
planning and repairs and Ft Dent curbing repairs beginning July 8.
• Fire Station 52:
The Planning Commission approved a Conditional Use Permit and Design Review Permit for
Fire Station 52 on June 27. The project will be located adjacent to the City Hall campus and is
slated to break ground on/around July 22.
Boards and Commissions
• Arts Commission: Vacant Position: Position #7 Resident & Student Representative. One
application received.
• Civil Service Commission: No vacancies.
• COPCAB: Vacant Position: Student Representative.
• Equity & Social Justice Commission: Vacant Positions: Position #7 Resident & Student
Representative. One application received.
• Human Services Advisory Board: Vacant Position: Position #3 Resident.
• Landmark Commission: No vacancies.
• Library Advisory Board: Vacant Positions: Position #7 Resident & Student Representative.
• Lodging Tax Advisory Committee: Vacant Position: Position #7 Funded by Tax. One
application received.
• Park Commission: Vacant Positions: Position #4 Resident & Student Representative.
• Planning Commission: No vacancies.
Phone: 206-433-1 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov
164
2019 Workplan
Goal 1
Task Name
Committee
Department
Q1 Accomplishments
Q2 Accomplishments
mmunit of irrvt �n n h r oo an err ran b st
G � A � '� a bo h d5 d '�
Prepare for future growth with regional and local investments
Infrastructure improvements, planning and development code updates, deployment of community technology resources
TIB Rechannelization Plan and zoning update
T&I
PW/DCD
PW/DCD worked with consultants to collect additional traffic modeling data.
Rechannelization study with KPG to 4/2/19 TIC.
Contract was awarded to KPG and kick-off meeting was held in May. Study should be completed by
4th Quarter.
53rd Ave S Residential Improvements
T&I
PW
First lift of asphalt pavement placed 3/27/19
Second lift of pavement and sidewalks were placed in May. Punchlist underway.
42nd Avenue Residential Improvements
T&I
PW
Completed majority of the SCL work, cable to follow.
SCL work has been delayed due to their workload issues.
Strander Blvd Extension
T&I
PW
Completed VE study. Reviewing with design consultant, BergerAbam.
Coucil decided to stop the project at the 6/10/19 COW meeting and directed staff to relinquish funds
to funding agencies.
S 119th St Pedestrian Bridge Repair and Painting
T&I
PW
Discussing options with Trantech Engineering.
Project is going to be put on the CIP in 2021.
S 140th St Intersection Improvements
T&I
PW
Project bid, contract awarded, and installation began 3/18/19.
Project was completed in May with closeout to follow.
Sound Transit TIBS Redevelopment, Boeing Access Station
1405 BRT Updates
T&I/CDN
DCD
Meeting with stakeholders, developing strategy.
On going meetings with ST and Stakeholders.
BNSF Intermodal Facility Access implementation
T&I
PW
Met with BNSF and participated in IMF tour on 3/27/19.
Project was taken to 6/18/19 TIC and to Council on 6/24/19, but was pulled from COW agenda. An
update will be given at a later date with more information.
Tukwila Village Updates - Phase 2 & 3, CDA Board
CDN
MO
Board met monthly. Building A is under construction.
Requested property owner to manage parking. Closing on sale of final parcels anticipated in
Q3.
West Valley Highway (1405 to Strander)
T&I
PW
Project readvertised for design consultant, three interviews in April.
Trantech Engineering was selected as design consultant.
42nd Avenue South Bridge Replacement (Allentown)
T&I
PW
Consultant is preparing grant application to submit to BRAC in April.
Grant application was submitted and waiting for response.
BAR over Airport Way Seismic Refit
T&I
PW
Consultant contract awarded to Trantech Engineering, design is at 10%.
Design is currently at 60%.
Nurture safe and flourishing neighborhoods
Public Safety/First responder services, Phase 1 of Public Safety Plan, park and recreation innovation and accessibility, traffic and pedestrian safety, public art implementation
TMC Updates - Shoreline Master Plan, Sensitive Areas,
Residential Definitions, Short Term Rental Regulations,
Modular Unit
CDN
DCD
Shoreline & Sensitive Areas - released public review drafts, began comment period,
held PC hearing
CC held a public hearing on Shoreline Master Plan update / PC completed their review of the
Sensitive Ares update.
Water/Sewer Projects
T&I
PW
Andover PK E Sewer updates project completed. Water Main break was fixed near IU
hotel, overlay repair included in 2019 Overlay & Repair.
2019 Overlay & Repair Project was awarded and construction started in June.
Traffic Calming
T&I
PW
Data collection was ordered through consultants at various locations.
Making good progress as several radar signs were purchased and crosswalk projects will begin in the
next two months.
Enhanced Code Enforcement
CDN
DCD
Upsated rental houing inspection form, began inspection audit process
Rental Housing Program developing a paperless system
Red Light & School Zone Cameras Pilot Project
Public Safety
POLICE
The Red Light camera project has been brought to committee several times and we
continue to work to answer questions regarding implementation. We are in the
process of collecting new analytical data and will compile that data to assist in
answering the most recent block of questions from the Public Safety Committee.
The Traffic Unit continues to answer council concerns regarding The Red Light Camera
project. The project is scheduled to be presented to Public Safety Committee on 7/15/19
and the subsequent Council meetings
SPRINT
Public Safety
POLICE/PW
Sprint Officers are working, but Officer Kolstad resigned from the department and
Officer D. Delic is in training to take his place.
Officer Deni Delic and Officer Ames worked a combined 305 hours on SPRINT responsibilities
in May and June. They wrote 134 speeding tickets for those two months and 244 total
tickets for the period. Both officers were recently selected for full time traffic duties with a
start date to be determined.
Tukwila Technology Initiatives - Citywide WIFI
Finance
TIS
Purchased Hardware for phase 2, Working with public works to schedule deployment.
Expanded down 37th and 142nd. Working with Seattle Light using an existing pole
attachment agreement to expand for point to point expnasion bridges
cn
cn
7/11/2019
_,2019 Workplan
Goal 1
a Task Name `
Committee
department
co. Accomptishments
Q2 Accomplishments
Technology Academy (Adults and High School Students)
TIS / P&R
The Adult Technology Academy kicks off on April 9th and runs biweekly until June in
the TCC executive conference room from 6:00 to 7:30. Class will focus on MS Office
Productivity tools, Using the world wide web, and using smart phones more effectively.
The City of Tukwila, ESRi, and the Tukwila School District will be kicking off Our second
technology focused summer school class July 1st thru August 8th. Students will be
learning to map data about their communities using ArcGis.
Working with parks and recereation on creating the fall adult programming starting October
8 and completing December 17. Working with school district to integrate ESRi classes into
CTE, Cvics, and Technoolgy. Working with JoAnne Fabian and Brian Seigel from the school
district.
PROS Plan
CDN
P&R
Responses to RFP for consultant services received
MIG Consultant Team has begun the refresh of the park's inventory and services and the community
engagement plan.
Senior Needs Levy & Assessment
CDN
P&R
Older adult survey completed, draft assessment is being reviewed
Survey was completed and presented to City Council. This work effort will assist staff in providing
programs and services now; and it will feed into the PROS plan for future planning.
Artist in Residence Program
CDN
P&R
Artist completed research phase and have started programs in the community
The AiRs mid -year report was presented to CDN in June.
Online Portal of historical facts, photos and events
about the Tukwila Community
MO
Begin identifying historical data and construction of the site
Created an inventory of Mayor's speeches dating back to 1972 in preparation for digitization.
Sullivan Center Service Agreement
CDN
MO
P&R was not selected to coordinate and activate the site.
Tukwila Village Community Development Association board worked on venue management
agreement with Kona Kai Coffee and rental rates and policies.
10-Minute Walk
CDN
P&R
Conducted a walking audit westside of TIB
The 10MWG scope of work has been joined together with the PROS Plan Community
Engagement Plan to better maximize resources. A sub -consultant has been hired by MIG,
the PROS Plan consultant, to assist with this specifically as they have very strong
connections with the Tukwila community.
Lake to Sound Trail
CDN
P&R
Preconstruction meeting March 28
Development of the trail began in June.
Grant Applications - Parks, Port of Seattle Economic
Development
CDN
MO/P&R
P&R applied for several acquisition, art and program grants
City approved to receive $19,800 grant from Port for economic development.
146th Street Play Space
CDN
P&R
Applied for CFT grant to acquire property
The property owner has chosen to go another route and is no longer interested in selling to
the city. The grant application was repurposed to an "Equitable Access Feasibilty Study" that
will focus on identifying key target properities that would help meet the need providing
equitable access to quality parks for all Tukwila residents.
Lockbox upgrade updates
Public Safety
FIRE
Project Manager in place. April 2019 projection due from Vendor
Project is on hold for release of the product from the vendor. April date has been pushed
to late Summer.
Fireworks Permits Approval Process
Public Safety
FIRE
Completed in Q1. All 2019 SeaWolf matches are covered.
In place for the year, this was highlighted by post season games for SeaWolf games. Plans in
place to cover all events at Starfire for 2020, to gain council approval in Q4 2019.
Development Agreements - BECU, Tukwila South,
Homestead Land Trust
CDN
MO/DCD
BECU is considering their development options. Tukwila South will be reviewed in 2020.
Homestead will be reviewed by Council in Q2 2019.
BECU has changed scope of project and is unlikely to need a development agreement. Staff
in discussions with Tukwila South property owner.
Urban Center Growth Strategies
CDN
DCD
Holden Assisted Living received Design Review approval, construction permits under
review
Building permits for Holden Assisted Living apprved
Small Cell Technology Regulations
T&I/CDN
DCD/PW/TIS
On Hold
DCD and PW staff met with Renton staff regarding best practices for Small Cell Technology
Levee Certification /Green River Corridor
T&I/CDN
PW
Consultant has finalized the report. Sharing this with King County FCD.
Presented the list of projects to KCFCD for their inclusion in their CIP project list.
Green the Green Project
T&I/CDN
DCD/PW
Project is ongoing. Rose Grant dedicated add'I $25k.
Riverbank restoration ongoing
Tukwila Locking Mail Box Initiative
Public Safety
Police/PW
PD has purchased (100) 14-16 gauge galvanized steel construction - anti -pry latch mail
boxes at a discount price and will pass -on the benefit to citizens who wish to take
advantage. The $150.00 mail box will cost Tukwila Citizens $108.00. Public Works will
install these boxes upon request.
public Works Street department has installed 42 mailboxes to date with 26 yet to install. Street labor
shows 64 hours at $3,689.54 for the mailbox installation. PD has approved the purchase of 100
mailboxes and has a waiting list in case one of the approved residents does not pay. Three of the
mailboxes approved, two paid, have been low income.
7/11/2019
2019 Workplan
Goal 2
Task Name
Committee
Department
Q1 Accomplishments
Q2 Accomplishments
A` elid Olin OW
Engage community and identify unmet needs
Engaging hard -to -reach communities, predicting and adapting social service needs as growth continues, city internships and job shadow program, apprenticeship promotion, homelessness prevention, school district engagement
Continued partnership with Tukwila School District:
Afterschool Program Update, TSD Capital Plan
CDN
P&R/DCD/ADMIN Assisting with 21st Century 5-year Grant for additional afterschool education programming
SVCS to be provided by TSD
Teen Summer Kick Off was held the last day of school at the FHS football field.
SCORE Financial Update
Public Safety
FINANCE
Update will be presented after the April 1st deadline for Federal Way to rescind their
withdrawal from SCORE and possibly opt out of the bond refinancing.
Public Safety Committee updated on status of Federal Way withdrawing from SCORE ILA
on April 15th Future update on ILA and debt refinancing will occur in August.
Southcenter 50th
Civic discussion between the Police and Foster HS Seniors
CDN
Public Safety
MO Events with chamber will happen later in year.
Police In collaboration with various representatives from the National Organization of Black Law
Enforcement Officers (NOBLE) to include our federal partners, The Tukwila School District
and The Tukwila Police Department, we will join the students on April 17 in a civics
discussion surrounding building trust and legitimacy between LE and the community.
Continued planning final event which will take place in Sept 2019.
PD participated ith the King County Library to review the book "The sun is also a
star" wich deals with issues surrounding inter cultrual relationships and
immigration.
Internship/Job Shadow & Apprenticeships Program
ADMIN SVCS
Internship program posted 4/1 through 4/30; outreach to students at FHS initiated.
62 applications received for the high school internship program; 10 selected.
Interns began on July 8.
Highline Schools
ADMIN SVCS Q3
Q3
SCA, PSRC, AWC, NLC
MO
Ongoing
Local and regional governments
MO
Ongoing
Ongoing
Ongoing
King County -Cities Collaboration (K4C)
DCD
Participate in monthly meetings
Paricipate in monthly meetings
RASKC (Regional Animal Control Services of King County)
MO Issuance of Pet licenses, run reports, attended Q1 meeting.
Issuance of pet licenses, submission of weekly and monthly reports to RASKC and
facilitated outbound calling for license renewals with City volunteer.
Leverage housing partnerships and collaboration
Housing Comprehensive Plan, Regional Affordable Housing Task Force, South King County Housing & Homelessness Partnership, affordable housing incentives
SKCHP Housing Consortium
CDN
DCD/ADMIN SVCS Interlocal adopted, staff attending monthly meetings; Councilmember Seal selected as
Tukwila representatives
Discussed options for SKCHP cities - HB 1406
Implement Housing Element of Comprehensive Plan
CDN
DCD
Development agreement negotiations for Riverton Heights, Bellwether,
Homestead projects; Implementing ADU changes
Bellwether submtted SEPA, and Design Review applications
Minor Home Repair Program
Utility Discounts
CDN
T& I
ADMIN SVCS 2019 funds released; 10 homeowners in the queue.
FINANCE
Surface water discounts have become more generous as they now follow the King County
criteria.
Connect residents to social services
CDN
ADMIN SVCS Human Services received 656 request for services in Q1; up more than 60% from Q1 2018
Joint Recommendation Committee rated the Minor Home Repair program the
top candidate for CBDG funding; 2020 funding expected to be awarded.
Billing for surface water transitioned to King County in January. Current discounts follow
criteria set by King County.
Human Services received 742 requests for services in Q2, compared to 507
requests in 2018 Q2.
7/11/2019
Goal 3
2019 Workplan
rn
03
Task Name
Committee
Department
Q1 Accomplishments
Q2 Accomplishments
Advance Tukwila's economic vitality
Economic Development Plan, regional infrastructure projects, Opportunity Zones, business relationships
Planned Capital Funding
Finance
FINANCE This is a 3rd quarter initiative
Economic Development Plan
Lodging Tax Advisory Committee & Funding Applications
Tukwila Valley South
CDN
CDN
CDN
MO Conducted research in Q1. Will start public outreach in Q2.
MO Reviewed and processed applications. Examined opportunities to collaborate with
Parks Dept on funding art.
MO & DCD Working with developer on residential townhouse design standards Q2 2019.
This will be rolled into a 10-year financial sustainability plan. Work to begin in 2nd quarter on
the financial sustainability plan.
Continued research. Public outreach to start in July.
LTAC and Council approved funding for public art on Strander Boulevard and for
Tukwila Pond. Submitted annual report to State MARC).
Resolve use issue and need to create residental standards and Design Guidelines
Duwamish Corridor EIS Update
CDN
DCD On hold for Boeing action
No action has been taken
Boeing Access Road over BNRR Bridge Rehabilitation
T& 1
PW Project is substantially completed. Traffic will be open in the middle lanes in April,
2019.
Project physically completed with closeout to follow.
Enhanced Business Community Outreach
Finance
MO Will start as time becomes available
Will start as time becomes available
Central Business District Infrastructure Investments
T& 1
PW Finished Sewer Rehab on Andover Park East.
Pavement repair of Andover Pk E included in 2019 O&R.
Seattle Southside Chamber
MO Ongoing
Partnered with Chamber for a retail summit in Q3; Worked with Chamber on outreach
related to solid waste tax increase.
Soundside Alliance for Economic Development
MO Partnered for opportunity zones event on 3/20/19.
Ongoing participation.
7/11/2019
2019 Workplan
Goal 4
Task Name
Committee
Department
Q1 Accomplishments
Q2 Accomplishments
oa or ective C r .a izattorr
Ongoing innovation of organizational systems
Phase 1 of Public Safety Plan implementation, technology -based efficiencies, internal workforce diversity, employee development and professional growth process improvements, long term financial health, priority -based budgeting and performance measures, Equity Policy
implementations
Public Safety Plan
Fire Station 51 & 52 Construction
Public Safety
ADMIN SVCS
Council approved MACC for Fire Station 51; groundbreaking held on 3/30/19. Fire Station 52 in
schematic design phase.
Construction on Fire Station 51 underway. Fire Station mini-MACC under the newly
revised budget. With Council approval in early July, construction to begin on FS 52 in
mid -July.
Justice Center Construction
Public Safety
ADMIN SVCS
Council approved mini-MACC for Justice Center; abatement and demolition to begin 4/1.
Justice Center under construction.
Public Works Master Plan & Implementation
Public Safety
ADMIN SVCS
Master plan underway; all PW user groups involved in planning; multiple tours to other PW
facilities informing master plan.
Master plan nearly finalized; PW all staff have been involved throughout the process.
Council presentation in Q3.
Bond Issuance (UTGO & LTGO)
Finance
FINANCE
Initial meeting held with bond council and PFM to determine timeline to issue bonds.
Legislation to issue both debt issues presented to Finance committee June 24th. Debt issues are
planned for October of 2019
Technology system improvements:
JLARC* required electronic data reporting
requirements for Public Records Requests
(*Washington State Joint Legislative Audit and
Review Committee)
Finance
MO
Data has been compiled electronically from the payroll system and electronic logs for all City
departments in conjunction with 18,000+ records reviewed in Q1 in the Clerk's Office.
Over 5,500 rows of City-wide data to include payroll, legal costs, and annual logs for all
departments have been consolidated and standardized. Staff is incorporating new reporting
metrics from the State and performing calculations to complete submission of the required 2018
annual report by 8/1/2019. Staff in the Clerk's office reviewed over 10,000 records for 33
requests this quarter.
GET -IT - Government Electronic Technology
Initiative for Tukwila (online since 2017)
Finance
MO
This online portal was updated with 46,000 images for Development & Land Use Permits.
Meetings occurred with Public Works and the Fire department to begin the process of
incorporating their records into a system that provides online access for the public.
Guidelines were compiled for Public Works staff to provide direction on preparing records for
incorporation into the online portal for access by staff and the public.
Laserfiche RIO - Electronic Content
Management System
Finance
MO
Ongoing addition of records for online transparency and delivery of documents for Public
Records Requests. Our staff developed an electronic form to allow customers the ability to
request records through the Laserfiche system for seamless communication.
Implementation and configuration of the full Forms module of Laserfiche occurred this quarter
and testing is underway.
Telestaff expansion
Finance
TIS
Fire Department Complete. Starting talks with PD
Completed for fire. On -hold with PD.
Permit Tracking
CDN
TIS/DCD
Ran RFQ, Planning transition to hosted cloud model for TraklT
Ran RFQ, got responses, going with a hosted model with TRAKiT, integrating Bluebeam
and Seamless Gov
GIS
Finance
TIS
Increase in users (ArcGIS Online),Creating Training Plan, Collector Deployed
increased self service with iMap, Updated City assets in GIS data warehouse, Started sampling
content for ESRi Data portal
Implementing Lucity, dashboaring pilot underway, expandng imap.
Bluebeam
Finance
TIS/DCD
Installed blue beam and monitors, conducting training, developing procedures
Accepted our first electronic plan from Boeing through Bluebeam
Tukwila Works
CDN
ADMIN SVCS
86 issues reported in first quarter.
117 issues reported in second quarter.
Lanteria
Finance
ADMIN SVCS
First quarter goals launched.
Trainings provided to departments; evaluations being moved to the proper level.
Streamline & Update Financial Processes
Indirect Cost Allocation
Finance
FINANCE
Will begin review during 2nd quarter.
In process. Anticipated completion of review is set for end of August.
Surface Water Billing transition to King County
Finance
FINANCE
Transition occurred in January. Finance will continue to bill City owned parcels and delinquent
accounts.
Completed.
Healthcare Broker
Finance
ADMIN SVCS
RFP for services out; April 15 is due date.
Preferred vendor selected; presentation to council and final selection Q3.
Fleet Funding
Finance
FINANCE/PW
This is a 3rd quarter initiative.
This will be wrapped into the 10-year financial sustainability plan.
Benefits Update
Finance
ADMIN SVCS
Ongoing meetings and review.
Ongoing meetings and review.
Self -insured healthcare plan
Finance
ADMIN SVCS
Benefit design changes negotiated in 2018 went into effect.
As of Q2 no additional benefit design changes anticipated in 2019.
Business license fee increase and transition to
State
Finance
FINANCE
Fee was increased effective 1/1/19 and State began processing City licenses on 3/28/19.
Completed.
7/11/2019
Goal 4
2019 Workplan
0
Task Name
Committee
Department
Q1 Accomplishments
Q2 Accomplishments
Budget Updates - Priority -Based Budgeting,
Budget Amendments, Streamlined Sales Tax,
2020/2021 Budget Prep
Finance
FINANCE
Update on Priority Based Budgeting presented to Finance Committee.
Interns hired, began working on performance measures.
Financial Sustainability - 10 year model, sales
tax review, reserve policy,
revenue/expenditure review
Finance
FINANCE
This is a 3rd quarter initiative.
Plan for the plan presented to Admin Team in June.
Sale of Properties - Longacres, Travelers Choice,
Newporter, HealthPoint Site
Finance
MO
Continued negotiations with Pulte Homes for Longacres. Initiated negotiations with business
coalition on Travelers Choice site.
Continued negotiations with business coalition for Travelers Choice site and with Pulte
on Longacres site. Anticipate Council discussion on Longacres and HealthPoint sites in
Q3.
Equity Policy Implementation
CDN
ADMIN SVCS
Initial changes to ensure more equitable hiring practices implemented; Community
Engagement Manager brought on board.
Equity Policy Implementation Committee formed; changes made to hiring policies to
align with Equity Policy.
False Fire Alarm Billing
Public Safety
FIRE
Review of current policies, proposals for changes in process.
Working with Finance and Fire Marshall Office
Fire Station 54 Maintenance & Revisit plans
Public Safety
ADMIN SVCS
Second quarter activity.
Preapplication for FEMA grant for seismic and other upgrades turned in; Public Safety
Committee to receive update in Q3.
Fire Department Strategic Plan 2020-2025
Public Safety
FIRE
Collecting Data and developing team.
Command Staff working on design of the plan
Foster Golf Links - Reclaimed water, marketing,
golf carts
CDN
P&R
Created a social media presence and golf interest
The marketing efforts have produced great results shown by the increased number of rounds.
Traffic Impact Fees
T&I
PW
Consultant finished the concurrency study in March. Impact Fees will be developed in the 2nd
quarter.
Staff still working on details and will present to TIC in the third quarter.
Waste Management Contract
T&I
PW
WM presentation to TIC on 4/2/19. Contract extension underway.
Contract extended for four years to October 31, 2023. Recycling surcharge and utility tax
increase to 5/21/19 & 6/18/19 TIC and to Council in July.
7/11/2019
2019WOrkp|8D
Task Name
Committee
Department
Q1 Accomplishments
Q2 Accomplishments
Jad min""
Promote and celebrate City identity
Effective multi -channel communication, Community Connectors, 2020 Census Outreach, Police Department Community Policing Team, Night Out Against Crime, community image investments
Night Out Against Crime
POLICE Night Out Against Crime Planning begins in late May to early June each year. This year the
event |sonAugust 6.
Advertising will begin after the 4th of July.
Census Plan Outreach
CDN
DCD/ADyW|N Onhold for hiring nfnew community engagement manager
Svcs
Community Engagement Manager attending County Complete Count Committee
meetings; planning underway to begin Q4 outreach.
Community Connectors
CDN
AD[W|N5VC3 Presentation given toCouncil.
Connectors continue tnmeet; staff and partner agency working torecruit additional
connectors. Presentation toCouncil per request inO3.
TukTV
Ongoing
Hazelnut
ADMIN SVCS Hazelnut published in February; April edition on track.
Hazelnut published every even -numbered month.
Enhancedwebske
E-Hazelnut
ADMIN SVCS Published every last Monday of the month
Published every last Monday of the month.
See You in the Park
P&R Expanding series & redeveloping site specific event themes.
Two events were held inJune and both were well received bythe community. There
will be two events in July and two in August.
Community calendar
Ongoing
City annual report
ADMIN SVCS Published in first Hazelnut
Complete
Healthy Tukwila
CDN
P&R Community Engagement Q2
Green Tukwila
CDN
P&R Planning work parties for 2OI9
Creative Consultancy SouthcenterDisthct
CDN
Phase 1 conceptual work draft is being reviewed
The proposed Creative Consultancy project did not receive 4Culture funding, however,
the Lodging Tax Advisory Committee recommended using LTAC funds for the project.
The project was approved by the City Council in June. Staff are working on a contract
with the artist and the project will begin in August.
Police Dept. Community Liaison Team
POLICE
The TPDCommunity Liaison Team isworking onissues ofregarding the homeless and
continues to work with our immigrant and refugee population to solve problems in the
community.
The Community Liaison Team was invited bythe |R[todiscuss issues regarding
policing and immigrant refugee issues with a delegation from Brazil who was invited
here by the United Nations. The team also met with a delegation of international
dignitaries who was invited bvthe US State Department todiscuss similar issues.
Special events calendar
"Summer Fun" flier was completed in April.
Ongoing support of block watches
POLICE
PID has been in touch with a number of blockwatches, who report things are going ok. The first
quarter was used to plan for the launch of the Mailbox Program. Additionally, the Community
Police Academy started February Z6thand graduation isMay Z8th. There are 11participants.
Many of the blockwatches assisted with advertising the mailbox program. The
blockwatches report things are going well, with mail theft still a large concern.
-^
-^
7/11/2019
172
TUKVVILAPU0UC SAFETY PLAN
Monthly Update
Overall Plan
Outreach
* Team anticipates another event for the public in late 2019. Ground breaking ceremony
for all Public Safety Plan Projects at the future FS51site was held on Saturday, March
30,2019.
Financial Oversight Committee
• The Committee reported tnCouncil onSeptember 4,3OI8. The Chair ofthe Committee
presented tothe Finance Committee onJune 24,2Ol9.
w Next Committee Report toCouncil scheduled for end ofI029.
Siting Advisory Committee
w The Siting Advisory Committee voted todefer regular meetings aathe major dedsions
have been made. They will meet onanas-needed basis.
Acquisition Lease Updates
0 Process is complete.
Disadvantaged Business Enterprise (DBE) Outreach
° See attached status report from outreach consultant Darling Nava.
Near -term Council Decisions and Key Dates
• Contract amendments toPublic Safety Committee and Council
• Easement authority
• Fire Station 52rnini-M/\[C
• Fire Station 54immediate needs report toPublic Safety
Fire Stations
Siting
0 Complete.
Architecture and Programming
173
Design and Permitting
• Building permit for Station Sl was submitted in October. Building permit was received
in all areas except wetlands report. Permit revisions for accepted alternates for Station
51have been submitted and are under review.
• Station 52 Public Works and initial building permits submitted and under review.
w Station 5Ztraffic determination was submitted |nFebruary, ZOl9with approval received
inApril, 2OI9.
• Station 52 Conditional Use Application and Design Review Application have been
submitted. Hearings Thursday, June Z6/3O19,
Bidding and Construction
w Construction for 5lbegan inMay ZO18.
w Bidding and construction schedule for 52 are on track, early work bidding to start in
June with construction tnbegin in July.
• Fire Station 5lfirst concrete pour done on6/I3.
w See monthly Construction Report for FS 51 construction progress and photos.
Justice Center
Siting
0 Complete.
Architecture and Programming
p Complete.
Design and Permitting
• The project teanlsubrnhtedapplicadonforPubliCVV0rksPernnit(sitevvork/utUities)in
November of2OlG.The PVVpermit was issued onApril 4,
• The project team submitted application for Building Permit inJanuary of3O1g.The
building permit was issued on April 26.
Bidding and Construction
• Construction began in early April, 2019 with mobilization of construction trailers and
fencing, utility disconnect work, excavation in the north lot for stormwater utilities,
contaminated soil removal, hazardous materials abatement and demolition of
remaining buildings oDthe site.
~ Sitework, excavation, contaminated soil removal and underground utility construction
continued throughout June. First footings were poured onJune 13/Z0l9.
• See monthly Construction Report for construction progress and photos.
174
Public Works Facilitv
Siting
w Due diligence items related tosite acquisition are complete. The assessment ofexisting
Structures is complete.
• Lot consolidation for two of the three parcels is underway.
• City to take ownership of Heiser Property at the end of the month; landscape building
property was given to the City on June 24, 2019.
Architecture and Programming`
~ Team solicited for Architectural services. Council approved acontract for programming
and master planning services with SHKSiONovember, 2O18.
• Master planning and programming phase began in late 2018, with regular meetings with
Public Works staff. Master planning and programming jsscheduled tobecompleted in
July Df2OI9.
Design and Permitting
0 Phase I design scheduled to begin Q3/Q4, 2019, after council approval.
Bidding and Construction
• Phases scheduled to begin in 2030.
m Landscape building to be demolished this summer after Council approval of demolition
0 See attached Budget Report
Schedule
ju|V2D19
~ Fire Station 52phase l(early vvork/fnundation") permit received
w Fire Station 53phase lLvdig contract amendment toCommittee and Council
• Fire Station 53 phase I (early vvork/foundations)construction begins
• Public Works masterp|anwith phasing presented tOCommittee and Council
175
August 2019
• Fire Station 52 phase 2 bidding
• Fire Station 52phase 2(bu1|dino) permit submitted
• Public Works phase 1contractor solicitation, if'council approves phase 2
Saptenmber2O19
~ Fire Station 52phase 2(bui|ding) permit issued
* Public Works phase l design begins, if council approves
C)ctober2019
0 Fire Station 52 Lyclig contract amendment to Public Safety Committee
November2019
• Fire Station 52|«digcontract amendment toCouncil
w Fire Station 52 phase 2construction begins
Decenmher2O3.9
0 Public Works Phase 1design complete
]anuary2O2D
0 Public Works Phase I construction begins
February2O20
0 Public Works Phase 1 construction continues
K8arch2O20
0 Public Works Phase 1 construction continues
PNay2D2O
* Fire Station 51Substantial Completion
* Public Works Move |n
Junm2O2O
0 Fire Station 51 Final completion
July 2020
0 Fire Station 51 move-in/occupancy
Septennber2O20
176
October 2020
• Justice Center move-in/occupancy
January 2021
• Fire Station 52 Substantial Completion
February/March 2021
Fire Station 52 move-in/occupancy
177
178
TU��||��U�||��A��TV���|
. ^^.^...`�. PUBLIC SAFETY PROJECTS
Justice Center
___
Construction Management Monthly Report
]Une 2019
Report Prepared by: Ethan Be07aU
Report Reviewed by: Justine Kim
Owners Representative: 3hielsOhletzJohnsen (SJI)
Architect: DLRGroup
Construction Progress:
* Completed demolition cfexisting asphalt paving and building foundations.
w Completed concrete pours for elevator pit and Area Abuilding footings.
• Continued earthwork and installation of underground stormwater system.
* Continued removal Vfcontaminated soils osencountered.
* Started installation oflight pole bases innorth parking lot.
• City fina(eddemo permits.
Upcoming Activities:
• Continue concrete pours for footings.
• Complete installation ofunderground stornnwatersystem.
• Start underground plumbing, electrical and water lines.
• First slab on grade pour (July 30).
• Start Vfsteel erection (August F).
Budget Status:
0 See overall TPSP budget summary updated monthly and included in monthly report package,
Change Order Status:
~ Change Order #1being prepared due tounforeseen conditions associated with contaminated soils,
anagency-directed change bySeattle City Light and anabandoned well.
Schedule Status:
0 See TPSPmaster project schedU|eupd8tedmnnthly and included inmonthly report package.
Critical Issues:
° Construction coordination with City 0fSeaTac'SMilitary Road Project 3t@rtingin|ateJune,
Tukwila Public Safety Plan -Justice Center -Monthly Report
1
179
4,,tAttainte,
Concrete Footings Poured at South Lot
446!;+0,1„,10;4‘4: •
er-P LittiTLAN„*.
:k'
0 4-04 rArT g
Concrete Footings Pourec
at South Lot
Tukwila Public Safety Plan - Justice Center - Monthly Report
180
Formwork for Footings at South Lot
Excavation for Undergrounc
WA+Ns's:.
Utilities at Sout
Lot
Tukwila Public Safety Plan - Justice Center - Monthly Report
3
181
Underground Stormwater System at South Lot
Light Pole Bases at North Lot
Tukwila Public Safety Plan - Justice Center - Monthly Report
182
TUKWILA PUBLIC SAFETY PROJECTS
Fire Station 51
SOJ
Construction Management Monthly Report
June 2019
Report Reviewed by: Justine Kim
Owner's Representative: Shiels Obletz Johnsen (SOJ)
Architect: Weinstein A+ U
GCCM: Lydig
Construction Progress:
• Started earthwork, heavy equipment onsite while footing excavation activities are ongoing.
• Sewer tie-in and grading activated ongoing.
• PSE trenching is complete.
• Brace frame footings are being formed.
First brace frame concrete pour occurred.
• Forming and rebar placement for continuous footing is ongoing.
Underground utility work is nearing completion.
Upcoming Activities:
Slab on grade completion late July.
• PSE temporary and permanent power installation to commence.
Budget Status:
• See overall TPSP budget summary updated monthly and included in monthly report package.
Change Order Status:
• No change orders issued in June
Schedule Status:
• See TPSP master project schedule updated monthly and included in monthly report package.
Critical Issues:
• None.
Tukwila Public Safety Plan - Justice Center- Monthly Report
183
Continuous Brace Footing Framing
Poured Footing
, „ " ' j ., "
''' '''''' -1',,' 4.: ', r
,•,e,,,,C4,0:9 e4,1. 44,0,,,,,Lf,,
• - , a , --.4' tv,m.,41q.ift:$07 ,1',414:4"1441;4'': , t4..".".4:Ft 4," , , 7 , , ,
, r
„,„„:"" ' ' ,„.„.„,;" 'rn
, .
"marat
Tukwila Public Safety Plan - Justice Center- Monthly Report
184
Undergrounc
Utility Installation
Tukwila Public Safety Plan - Justice Center - Monthly Report
3
185
186
TUKWILA PUBLIC SAFETY PLAN
FIRE STATION 51
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
FIRE STATION 52
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
JUSTICE CENTER
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
PUBLIC WORKS
A/E PROCUREMENT
MASTER SITE PLAN
DESIGN PHASE 1
BIDDING/CONSTRUCTION PHASE 1
MOVE-IN/OCCUPANCY PHASE 1
00
2016
2017
2018
2019
2020
11111111llLWllllllllll l
Ill
Ili
2021
PROJECT OM
A/E PROCUREMENT =
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY MI
City of Tukwila - Facilities Plan
TOTAL PROJECT
MONTHLY Budget Report
(REVISED Budgets; D-20 Plan Adopted by Counci )
Life to Date Costs
75 t0/9 (rerortr lerhve
IUA'(REP(MILVG 5(1//rR1
US77CE c1A7'ER
Iki,�nal/oul„n
Moro,/ rrunJrrc
Correia Reface,
Cnnaninrd Nagel
L7oln(.
1Rece 4 Comma
.nIIII, AWgel
c .nn c„npn,nn
A/E Services (bosh Design & CA)
Pennits/Fecs
Construction (Pre -Con, Consl & Tax)
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
Contingency for Site Contaminalion (soils,hasmat)
Land Acquisition
Contingency for Land Acquisition
S 3,278,125
5 700,000
$ 38,738,678
$ 2.112,639
$ 1,815.875
$ 6,507,731
$ -
$ 14,133,295
$ 1,250,000
$ 221,875
$ 50,000
$ (720,007)
$ (25.275)
5 266,721
$ (1,712,213)
$ 550,000
$ (422,733)
S 250,000
S 3,500,000
$ 750,000
$ 38,018,671
$ 2,087,364
$ 2,082,596
5 4,795,518
$ 550,000
$ 13,710,562
$ 1,500,000
5 3.173,129
$ 401,278
$ 38,018,670
5 565,287
$ 1.986,865
$ -
$ -
$ 13,709,987
$ 1,491,500
$ 2.371,453
$ 401,278
$ 3,388,688
$ 315,860
$ 1.030,002
S -
5 -
S 13,686,033
$ 1,491,500
5 801,676
$ -
$ 34,629,982
$ 249,427
$ 956,863
5 -
$ -
$ 23,954
S -
5 326,871
$ 348,722
$ 1
S 1,522,077
$ 95,731
$ 4,795,518
$ 550,000
$ 575
S 8,500
5 -
$
$ -
$ -
$ -
$ -
$ -
$
5
.. TOTAL.
5 68,536,343
5 (1511,632)
5 66,994,711
5 59,346,716
S 22,684,814
5 36,661,902
5 7,647,995
5 -
(%I UA'('11. REPORTING S U3131.I R F' -
FIRE e'T.IT1!%A'SI
Original Nn lee
/n+A„rl rrnrr.Jin
Curren, llnJ„n C'nn,nW+M Bldgrr
Nee. VogeC'nne
xen+nin';(Cnnnninrr! Nenm, n�NuJ;,,vy
Ci,uW C.,mp/.Tian
AIE Services (both Design & CA)
Land Acquisition
Permitsffees
Construction (Pre -Con, Consl & Tux)
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
5 1,070,000
$ -
$ 234,000
$ 9,396,000
$ 931,000
$ 526,000
$ 1.116,000
$ 322.781
$ -
$ 100,000
$ 1,315,046
5 (300,000)
$ (50,000)
$ 153,806
$ 1,392.761
$ -
S 334,000
$ 10,711,045
S 631,000
$ 476,000
5 1,269.806
S 1.280,609
$ -
5 151,812
5 10,711,045
$ 138,222
$ 363,412
$ -
$ 873,166
$ -
$ 136,024
S 99,273
S 88,429
$ 154,205
$ -
$ 407,443
$ -
$ 15,788
$ 10,611,773
$ 49.793
$ 209,207
S -
$ 112,172
$ -
$ 182,188
$ -
5 492,7713
5 112,388
$ 1.269,806
$ -
$ -
$ -
$ -
$
5 -
$
. .. ' TOTAL ""
5 13,273,000
5 1511,633
5 14,814,632
5 12,645,100
5 1,351,1)97
5 11,294,003
5 2,169532
$ -
CU[S\'CIL REPOR'1'L\'G.SL§1LMANY-
FIRE STATWA' 53
A/E Services (both Design & CA)
Land Acquisition
Permits/Fees
Construclion (Pre -Con, Contt & Tax)
Construction Related Costs (incl Bond)
PM Services (tact Other Professional Svcs)
Contingency (incl Construction & Project)
Original wd;,•r
5 1,415,000
$ 16,000
$ 353,000
$ 13,298,000
$ 1,398,000
$ 787,000
$ 1,343,000
Ind;,•., Trawler,
5 355,172
$ 9,160
$ 50,000
$ 469,000
$ (307,160)
$ (50,000)
$ 123,828
oaten, Bodge,
$ 1.770,172
$ 25,160
5 403,000
$ 13,767,000
$ 1,090,840
$ 737,000
5 1.466,828
C„mmuned linage
c�mnW, cn,,,
x,,,,ni„'c (1,,,,,,ur<e
xrn+„ini„a lr,nrsn
c.lmc'an,Pr.,ia„
S 1.622,653
$ 17,157
$ 78,332
$ 137,500
$ 400,853
$ 546,069
5 -
5 783,638
5 17,157
5 18,155
$ -
$ 20,489
$ 233,367
I S -
$ 839,015
$ -
5 60,177
$ 137,500
$ 380,364
$ 312,702
5 -
$ 147,519
$ 8,003
$ 324,668
$ 13,629,500
5 689,987
$ 190,931
5 1,466,828
$ -
5 -
$ -
$ -
$ -
$ -
S -
TOTAL
S 18,610,000
0 650,000
5 19,260,000
5 2,802,564
1 $ 1,07I,806
5 1,729,758
S 16,457,136
5 -
_
('IIUA'('11. REPORTINGSU3L3L1HI'-
FlltF..1'f I T'lU:\' 54
AlE Services (both Design&CA)
Land Acquisition
Permits/Fees
Construction (Pre -Con. Coral & Tax)
Construction Related Costs (tool Band)
PM Services (tact Other Professional Svcs)
Contingency (tact Construction & Projccl)
(Oo,,,,lAndae,
5 150,000
5 902,668
S 20,000
5 230,000
$ 50,000
5 107,500
$ 41,832
nnx„n rrnnyr,.
$ (17,005)
$ 31,206
$ (12,827)
5 (123,300)
$ (2,698)
5 (835)
$ 125.459
Cnrn,n Rickel
$ 132,995
5 933,874
$ 7,173
5 106,700
$ 47.302
$ 106,665
$ 167,291
Committed
5
S
$
5
$
$
S
Racer
Lifrro Dnre(L,n
Povnnin'g t5ounrill
IO x H111101
Cux nY('an,(Aian
r
132,995
933,875
2,173
106,760
42,302
106,665
-
5 131,495
$ 933,775
$ 2,173
$ 67,856
$ 22,798
$ 86,066
$ -
$ I,500
S 100
$ -
5 38,844
5 19,504
5 20,599
$ -
$ (0)
$ (I)
S 5,000
5 -
$ 5,000
5 -
$ 167.291
S
$
$ -
$ -
5 -
S -
$ -
" TOTAL . . .
$ 1502,000
5 -
5 1,502,000
5
1,324,710
5
1,24-1,163
5
80,547
S 177,290
S -
C!I(r:\'('/I. HF.P(1/7TL\'(i .CL'3L1/rlRI' -
PUBLIC WORKS
Reigned /6drrl
10.5.d trot.(,'
Carroll Rickel C'nnanilr.Jlla,fe.,
2Jr in Derr ('n,l.
INeII irr'x C'nn,minnl
Nnnnitin, Thwig Y
Ci,.(nr Cnn+p(.,inn
A/E Services (both Design & CA)
Lond Acquisition
Permits/Fecs
Construction (Pre -Con, Consl & Tax)
Construction Related Costs (incl Bond)
PM Services (inc) Other Professional Svcs)
Contingency (incl Construction & Project)
$ 767.385
5 22,000,046
I 110,000
S 4,950,000
$ 529,036
5 668,426
$ 975,107
$ 15,000
5 3,374,913
S (20,000)
5 (1,895,000)
$ (404,793)
$ (348.426)
$ (721,694)
I 782,385
$ 25,374,959
5 90,000
S 3,055,000
S 124,243
$ 320,000
5 253,413
$ 318,882
$ 25.347,193
S -
S -
$ 77,643
5 27'3,832
$ -
5 221,796
$ 25,344,993
S -
S -
$ 50,471
$ 152,685
$ -
$ 97,086
S 2,200
5 -
5 -
$ 27,172
S 127,147
$ -
$ 463,503
$ 27,766
$ 90,000
$ 3,055,000
S 46,600
$ 40,168
$ 253,413
S -
$ -
S -
S -
$ -
$ -
$ -
" TOTAL
$ 30,000,000
S -
5 30,000,000
S 26,02355015 25,769944
5 253,605
I 3976,150
5 -
190
City of Tukwila
BNB - Justice Center
WMBE/DBE Participation
Scopes of Work that you Intend to
Award to INMBEs
Sub/Supplier Name
Certification
City of
Seattle Self-
Identified
OMINBE
State
Certification
OMWBE
Federal
Certification
SCS
Approximate
Subcontract $
Amount
Demo and Abatement
Rhine Demo
192,995
Foundation, Structure,
Waterproofing
BNBuilders
$ 4,288,300
Earthwork and Utilities
IIliad
$ 4,874,410
Site Concrete
BNBuilders
720,000
Architectural Casework
BNBuilders
1,186,000
Exterior Siding
Northshore Exteriors
$ 1,760,000
Roofing Systems
Axiom
#1027
$ 583,020
Doors and Hardware
BNBuilders
1,577,000
Aluminum Systems
General Storefronts
855,688
Painting and Coatings
Halili
WBE
$ 219,450
Acoustical Assemblies
ADI
344,716
Insulation GWB Assemblies
Northwest Partition
2,149,000
Flooring Covering
Great Floors
486,296
Misc Specialties
BNBuilders
977,000
Window Coverings
Iris
47,269
Elevator
BNBuilders
$ 118,000
Fire Protection
Columbia Fire
#1599
287,890
Mechanical
Johansen Mech
$ 3,284,321
Electrical
Valley Electric
4,699,000
Paving and Striping
Lakeside Industries
$ 437,733
Irigation and Landscaping
RE Sides Landscaping
#1054
1,020,000
Total Amount Intended to be Performed by SCS to Date:
2,110,360
Scopes where the sub/supplier is not
yet determined or committeddo
When do you anticipate making a
selection?
Do YOU
anticipate
using a SCS
Is this a
Spread the
Work SCS
Can only a
Sole Source
the
work?
Approximate
Subcontract $
Amount
$ -
$
-
_
$
$ -
$
Total Amount Not Yet Committed to a Sub/Supplier:
-
Page 2/3
191
City of Tukwila
BNB - Justice Center
Updated 4.24.19
WMBE Participation
GC Contract Value
Award Amount:
2.9,098,0
00
2,153,460
Scopes of Work that you Intend to
Award to WMBEs
Sub/Supplier Name
Certification
Approximate
Subcontract $
Amount
City of
Seattle Self-
Certification
OMWBE State
Certification
OMWBE
Federal
Certification
SCS
Roofing Systems
Axiom
#1027
$ 583,020
Painting and Coatings
Halili
WBE
$ 219,450
Fire Protection
Columbia Fire
#1599
$ - 287,890
Irigation and Landscaping
RE Sides Landscaping
#1054
$ 1,020,000
$ 22,000
Temp Sanitation (NSS)
Construction Site Services
Waterproofing
Inland Waterproofing
WBE
$ 21,100
Outreach Coordinator
Darling Nava Consulting
M4F0026198
In Progress Participation:
$ 2,153,460
Percentage of Award Amount:
7/a
Scopes where the sub/supplier is not
yet determined or committed
When do you anticipate making a
selection?
Do you anticipate
using a SCS
Is this a
Spread the
Work SCS'
Can only a
Sole Source
do the
work?
Approximate
Subcontract $
Amount
$ -
$ -
$ -
$- -
$
$ -
$ _
Total Amount Not Yet Committed to a Sub/Supplier:
$ -
Page 2/3
192
Apprentice Utilization Plan
List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and
apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours.
Estimated information
Prime Contractor and all Subcontractors
JourneyHours
Labor Hours
Apprentice
Labor Hours
Total Labor
for
Project
Apprentice
Percentage
Number of
Apprentices
BNBuilders
472
16
488
3.28%
1
Ascendent, LLC
566
55
621
8.86%
3
Iliad, Inc
1,081
0
1,081
0.00%
0
Rhine
0
0
0
0.00%
TOTALS:
2,119
71
2,190
3.24%
Apprenticeship Utilization Requirement: 1 5%
4
Page 3/3
194
City of Tukwila
Gydig Construction Inc - Fire Station #51
WMBEMBE Partic'pation
Scopes of Work that you Intend to
Award to VVNIBEs
Sub/Supplier Name
Certification
Approximate
Subcontract $
Amount
City of Seattle
Self -Identified
OMWBE
Stat
. e
Certification
OMWBE
era
Fedl
Certification
S
CS
GREAT FLOORS, LLC
38,500
MASONS SUPPLY COMPANY
-
PROSTEEL, INC.
54,397
WEST WIND REINFORCING, LLC
$ 30,296
SPOKANE METALS, LLC
219,266
SCI INFRASTRUCTURE, LLC
854,000
ALASKA GLAZING INC. D/B/A FACADE TECH
298,628
MCKINSTRY CO.
1,243,566
LANDSOL LLC D/B/A KIRKLAND LANDCARE
262,451
SECURE A SITE INC
WBE-W
$ 299,000
CALIBER CONCRETE CONSTRUCTION, INC.
WBE-W
394,500
CASCADE CONSTRUCTION COMPANY, INC.
#2014
310,097
GK KNUTSON
523,500
Ben's Ever -Ready, Inc.
828
CHG BUILDING SYSTEMS INC
FBE/SBE/
VOSB
168,922
CONSURCO
37,900
METROPOLITAN APPLIANCE
$ 29,017
EMERALD FIRE, LLC
WBE-W
$ 49,750
NORTHSHORE EXTERIORS, INC.
263,900
DYNAMIC LAUNDRY SYSTEMS, INC.
5,677
INFINITI WINDOW COVERINGS
6,779
CRAWFORD DOOR COMPANY LLC
MWBE-W
$ 102,261
Simonet Woodwork Ltd.
146,110
INLAND WATERPROOFING SERVICES, LLC
WBE-W
4,100
Stanley Patrick Striping Co.
#1092
4,834,000
FAWCETT PAINTING, INC.
59,000
AXIOM DIVISION 7
#1027
217,945
Evergreen Construction Specialties
60,200
MILES SAND & GRAVEL
-
Construction Site Services
WBE-W
Keeney Office Supply
WBE-W
Darling Nava Consulting
MWBE
DBE/SBE
Total Amount Intended to be Performed by SCS to Date:
10,514,590
Scopes where the sub/supplier is not yet
determined or committed
When do you anticipate making a selection?
Do you
anticipate
using a SCS
Is this a
Spread the
Work SCS
Can only a
Sole Source
do the
work?
Approximate
Subcontract $
Amount
$ -
$_
$ -
$ _
$ -
$ _
$ -
$ -
$ -
Total Amount Not Yet Committed to a Sub/Supplier:
$ -
Page 2/3
195
LCJ - Fire Station #51
City of Tukwila
Updated: 5.23.19
WMBE Participation
GC Contract Value $ 10,514,590.00
Award Amount: $ 6,380,675.00
Scopes of Work that you Intend to
Award to WMBEsWBE
Sub/Supplier Name
Certification
Approximate
Subcontract $
Amount
City of Seattle Self-OMWBE
Certification
OM
State
Certification
Federal
Certification
SCS
SECURE A SITE INC
VI/BE-IN
299,000
CALIBER CONCRETE
WBE-W
394,500
CASCADECONSTRUCTION
#2014
310,097
CHG BUILDING SYSTEMS INC
FBE/SBENOSB
168,922
EMERALD FIRE,LLC
WBE-W
49,750
CRAWFORD DOOR COMPANY
MWBE-W
$ , 102 261
INLAND WATERPROOFING
WBE-W
4,100
Stanley Patrick Striping Co.
#1092
$ 4 834 000
. ,
AXIOM DIVISION 7
#1027
217, 945
Construction Site Services
WBE-VV
Keeney Office Supply
WBE-W
Darling Nava Consulting
MWBE
DBE/SBE
Total Amount Intended to be Performed by SCS to Date:
6,380,576
Percentage of Award Amount:
61%
Scopes where the sub/supplier is not
yet determined or committed
When do you anticipate making a selection?
Do you
anticipate
using a SCS
Is this a Spread the Work
SCS
Can only a
Sole Source
do the
work?
Approximate
Subcontract $
Amount
$-
$ _
$ -
Total Amount Not Yet Committed to a Sub/Supplier:
-
Page 2/3
196
Apprentice Utilization Plan
List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and
apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours.
Estimated information
Prime Contractor and all Subcontractors
Journey
Labor Hours
rentice App
Labor Hours
Total Labor
Hours for
Project
Apprentice
Percentage
Number of
Apprentices
Lyd ig Construction
TOTALS:
0
0
Apprenticeship Utilization Requirement:
0.00%
0
Page 3/3