TO: Tukwila City Council
FROM: Steve Goldblatt
PMQA Consultant
RE: Public Safety Plan
November update
With almost all significant Council actions on the Plan's components accomplished, my ac-
tive advising role will end soon. I will monitor ongoing project updates, and alert Council of
any pending issues or action items. This final monthly report focuses on recent and upcom-
ing Council actions. To follow construction progress, see SOJ's Construction Management
Monthly Report in Council's first regular meeting packet each month.
Fire Station 52 final MACC
The final MACC amendment to approve Lydig's full scope of construction —including
the Fire Dept. administrative space build -out —was discussed and forwarded at COW
12 November for approval by Council 18 November.
Public works shops master plan
On 4 November, Council approved (1) the first phase of SHKS's master plan and seis-
mic retrofitting of the Heiser building to house George Long Shops and (2) interim im-
provements to Minkler Shops.
Public works shops design services
Public Works presented a design consulting amendment to SHKS's contract for renova-
tion of the Heiser building to Transportation & Infrastructure 19 November for possi-
ble Council approval 2 December.
Professional services
On 4 November, Public Safety moved to Council's 18 November consent agenda
amendments to (1) Mayes Testing Engineers for Fire Station 52 services and added
Justice Center scope, and (2) SoundEarth Strategies for added Justice Center scope.
LEGEND
• Meeting target
Proceeding as planned.
Caution advised
Steps needed to meet target.
Correction needed
Steps needed to attempt recovery.
Not meeting target
No recovery plan in place.