HomeMy WebLinkAboutCOW 2020-09-14 Item 3I - Public Safety Plan - 90% Design Plan and Financing Options for Public Works Shop / Consensus to Proceed with Call for Bid ProcessITEM INFORMATION STAFF SPONSOR: HARI PONNEKANTI ORIGINAL AGENDA DATE: 09/14/20 AGENDA ITEM TITLE Public Safety Plan – Public Works Shop History and Budget - Parts 1 and 2, 90% Design, and Financing Update CATEGORY Discussion Motion Resolution Ordinance Bid Award Public Hearing Other Mtg Date 09/14/20 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date SPONSOR Council Mayor HR DCD Finance Fire TS P&R Police PW SPONSOR’S SUMMARY Staff to present the history and budget along with the 90% design and scope of work for Phase 1 tenant improvements and enhanced seismic upgrades to the new Public Works Shops located at 11210 Tukwila International Blvd. Project is within budget and on schedule. Staff also will review a new finance plan for the General Fund portion of the PW Shops budget. Council is being asked to reaffirm going out to bid for the tenant improvements with the expected bid approval to be presented to Council in November. REVIEWED BY Trans&Infrastructure CommunitySvs/Safety Finance Com Planning/Economic Dev. LTAC Arts Comm. Parks Comm. Planning Comm. DATE: 8/17/20 & 8/31/20 COMMITTEE CHAIR: DELOSTRINOS JOHNSON RECOMMENDATIONS: SPONSOR/ADMIN. Public Works Department COMMITTEE Forward to Committee of the Whole COST IMPACT / FUND SOURCE EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $ $ $ Fund Source: 306 FUND Comments: MTG. DATE RECORD OF COUNCIL ACTION 09/14/20 MTG. DATE ATTACHMENTS 09/14/20 Informational Memorandums dated 8/14/20 and 8/28/20 Financing and Budget Update 9/11/20 Masterplan Programming PowerPoint from 10/18/19 C.O.W. PowerPoint 90% design, cost estimate, schedule, and facilities graphics Facility Study Final Report – 12/14/15 and Public Safety Plan Fact Sheet - Sept. 2016 Minutes - Transportation and Infrastructure Committee meetings 8/17/20 & 8/31/20 COUNCIL AGENDA SYNOPSIS ----------------------------------Initials --------------------------------- ITEM NO. Meeting Date Prepared by Mayor’s review Council review 09/14/20 GL 3.I. 139 140 INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Hari Ponnekanti, Interim Public Works Director David Cline, City Administrator CC: Allan Ekberg, Mayor DATE: August 14, 2020 SUBJECT: Public Safety Plan Focus on Public Works Shop – Part 1 of 2 Issue This memo serves as a comprehensive effort to highlight the history of the Tukwila Public Safety Plan with a focus on the Public Works Shop. This memo is part one of a two-part process to provide background to the City Council in preparation for reviewing the bids in October 2020 for the Phase 1 Tenant Improvements of the Public Works Shop. This Part 1 memo is focused on the history and timeline of the Public Works Shop and will be discussed at the August 17 Transportation and Infrastructure Committee. The Part 2 memo will be focused on the budget, financing, options and other Council questions and will be presented at a possible special meeting of the Transportation and Infrastructure Committee between August 31 to September 11, or at its September 21 meeting. History and Timeline The need for a new, safe, and efficient Public Works Shop Facility has been recognized and studied for several years. This includes the 2007 Seismic Study of all City Facilities and the 2014 Facility Need Study. In 2016, City Council adopted the Public Safety Plan, which included a new combined Public Works Shop. The City secured a location in 2018, created a master plan in 2019, and is currently on track to go out to bid for tenant improvements in September 2020. Council review of the tenant improvements will be in October/November 2020 and construction is planned to be completed by August 2021. (Appendix A highlights these studies) It should be noted that a significant amount of history of the Public Safety Plan is preserved on the City’s website and is a resource that goes back to the initial facilities plan, which is at TukwilaWA.gov/PublicSafetyPlan. In addition, all of Council’s actions – and therefore staff reports and information that initiated them – are available at the City’s digital records center. Siting and Acquisition As a part of the deliberation on the Public Safety Plan, the Council created a Siting Advisory Committee in 2017 to provide input and advice on the siting of all of the Public Safety Plan projects. The Siting Advisory Committee included two Councilmembers, four residents, and the 141 Public Works Shops Part 1 of 2 Page 2 https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 08-17-2020/D. PW Shops/PW Shops History gl 08122020.docx Public Works Director. Selection criteria was created and used to evaluate options for sites and open houses were held. The current site was selected as the preferred alternative. The City began negotiations with the property owners and secured the current sites in 2018 and 2019. The City acquired Phase 1 sites, the Heiser and Lifestyle Landscape site in July 2019, and will be conveyed the Phase 2 site, the Amalfi/Temkin (UPS) site in November 2023 to allow the current tenant, UPS, to complete it lease. Funding The Public Works facility was originally funded at $30M as part of funding model commonly known as D-20.1. Half of the funds for the Public Works facility comes from the General Fund and the other half from the Enterprise Funds. The General Fund resources include land sales from the George Long, Longacres and Minkler Shops, and issuing councilmanic bonds (LTGO). King County Flood Control District is actively pursuing purchasing the George Long and Minkler Shops from the City. The current budget for the Public Works Shop is now $35.7 million. Council most recently updated the D-20 Model in November 2019 for the Public Works Shops Phase 1 plan and a contract for design of the Public Works Shops tenant improvements in December 2019. The $35.7M includes additional seismic improvements to the original Heiser building along with $500,000 specified for improvements to the Minkler facility. Masterplan In October 2018, the City Council approved a contract with SHKS Architects to create a masterplan for the Public Works Facilities to be located on the former Heiser and UPS properties the consulting services contract with SHKS Architects. From October of 2018 through September 2019, SHKS worked closely with the Public Works staff to create a preferred alternative for a comprehensive master plan. SHKS has formulated several phasing alternatives that starts with the tenant improvement scope of work for the Fleet and Facilities group to move into the Heiser building. In November 2019, the City demolished the former Landscape Building on site. This first phase of improvements to the former Heiser building includes all of the “must haves” identified by Fleet and Facility staff (such as floor drains, site lighting and locker rooms, as examples). This results in an opportunity for City of Tukwila to keep moving forward with the Public Works Department’s ultimate goal of relocating all departments on one single site, as different funding sources become available over the next decade or more. Phase 1 - Tenant Improvements & Seismic Upgrades for the Fleet and Facility Building In December 2019, the Council approved moving forward on Phase 1 of the Master Plan and appropriated an overall budget of $35.7 Million for the project and approved a design contract amendment with SKHS to move forward on design and construction of Phase 1. 142 Public Works Shops Part 1 of 2 Page 3 https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 08-17-2020/D. PW Shops/PW Shops History gl 08122020.docx The Phase I Tenant Improvement (TI) scope of work (seismic, building systems and functional upgrades) for the use of Heiser property for the Fleet and Facilities group and program on the current George Long Shop as well as the soils and equipment storage on the Longacres Site. This will allow the Fleets and Facilities group to relocate from the existing inefficient and seismically unsafe Long facility to a seismically updated facility with much more space for daily operations, not only for today’s workload, but also serve future capacity. Moving the Fleet and Facilities functions to the former Heiser building will be a significant improvement of the work environment for staff and enhance their ability to work efficiently, particularly for the Fleet division. After these uses have been relocated, the George Long Shops and Longacres Sites will be sold and used to finance the Public Safety Plan, including the Public Works Shop, per the Council adopted D20 Financing Model. Major Activities in 2020  Transportation and Infrastructure Committee regular monthly updates  Seattle City Light easement signed – January 2020  Contracts were approved for the following:  Removal of paint booths (work was completed in July 2020)  Geotech and other work on-site completed (work completed in spring 2020)  Install security fencing and gates (planned to be installed in fall 2020)  Minkler restrooms upgrade (modular facility planned for October 2020)  30% design update - March 2020  60% design update - June 2020  Permits were applied for Covered Storage and parking – June 2020  Tenant Improvement Building permit applied – August 2020 Next Steps The next major step includes a review of the budget in a Part 2 Memo currently planned for the next Transportation and Infrastructure Committee meeting. On September 21, 2020, Transportation and Infrastructure Committee is scheduled to review the 90% design update of the Fleet and Facility Building, which will include updated cost estimates. Public bid for construction of the tenant improvements will then be advertised. In October 2020, the Transportation and Infrastructure Committee is scheduled to review and approve the tenant improvement construction contract award, which then would be sent to a C.O.W. and Regular Council meeting in November 2020. Recommendation Discussion only. 143 Public Works Shops Part 1 of 2 Page 4 https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 08-17-2020/D. PW Shops/PW Shops History gl 08122020.docx Appendix A Facility Studies Over the past ten years, the City has numerous facility studies that have detailed the facility history, analysis, and provided recommendations for facility updates and replacements.  2007 Reed Middleton Report This report provided analysis and recommendations of the seismic concerns for all City facilities, including the Public Works buildings.  2014 Facility Need Study by Rice, Fergus, Miller This plan was the basis and foundation for Public Safety Plan. In four main phases it identified the current and future needs, a review of the current facilities, an analysis of how needs matched current facility, and a recommendation for meeting needs for all facilities, including Public Works buildings. It was during this time that the plan for a combined Public Works Shop was identified along with the size, program, and costs that led to the final Public Safety Plan. At this time, the estimated costs of a new facility, including land, was estimated at $30 million.  2016 Plan B Public Safety Plan This plan identified Public Works as one of the Public Safety facilities that would be addressed (along with Police and Fire) during this phase of implementing the Facility Need Study. The Council adopted the full Public Safety Plan and chose to finance the Public Works Shop facilities through General Fund and Utility funds rather than including them in the Public Bond vote.  Wagner Report In 2017, the City asked Wagner Architects to verify the actual space needs for a new Public Works facility, which originally was identified as needing up to 15 acres. The Wagner Report completed a quick survey of other Public Works facilities in the region and determined that an estimated 10 acres would most likely meet the current and future needs for Tukwila Public Works. This information was used during the siting process to narrow the selection of sites.  2018 Adopted D-20 Plan In June 2018, the Council adopted a financing and implementation plan for the Public Safety Plan, which has been updated as progress has been made. During this process, the new estimated cost of a Public Works facility was shown as an option, approximately $60 million for a new building and $45 million for a refurbished building, to include land costs. The option of staying within the original $30 million was what was adopted by the Council. Attachments: Slideshow photos from 10/28/19 Committee of the Whole 144 INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Hari Ponnekanti, Interim Public Works Director CC: Allan Ekberg, Mayor DATE: August 28, 2020 SUBJECT: Public Safety Plan Focus on Public Works Shop – Part 2 of 2 Issue This memo serves as a comprehensive effort to highlight the budget of the Tukwila Public Safety Plan with a focus on the Public Works Shop. This memo is Part 2 of a two-part process, providing background to the City Council in preparation for reviewing bids in October 2020 for the Phase 1 Tenant Improvements of the Public Works Shop. The Part 1 memo focused on the history and timeline of the Public Works Shop and was discussed at the August 17, 2020 Transportation and Infrastructure Committee meeting and is included as an attachment. The Part 2 memo is focused on the budget, financing, options, and other Council questions. Project Scope In October 2018, the City Council approved a contract with SHKS Architects to create a masterplan for the Public Works Facilities to be located on the former Heiser and UPS properties. From October 2018 through September 2019, SHKS worked closely with the Public Works staff to create a preferred option for a comprehensive master plan. SHKS has formulated several phasing plans that start with the tenant improvement and Seismic Upgrade scope of work for the Fleet and Facilities operations, facilitating their move into the Heiser building, in Fall 2021 of next year. In November 2019, the City began Phase 1 by demolishing the former Lifestyle Landscape Building on this site. • The Master Plan envisions the redevelopment of over 13 acres of land, which will serve the Public Works Department into the future with planned growth through the year 2045. • The Master Plan comprises roughly 66,000 sf of interior program space, roughly 58,000 sf of exterior program space, parking for 285 vehicles, and facilities for 67 employees. • The Public Works Shops First Phase of the Master Plan focuses on relocating the PW Fleet Maintenance and Facilities divisions from George Long Shops to the Heiser property after seismic retrofitting and upgrades. The First Phase will also include moving all the program elements from the George Long Shops, ( Police vehicle evidence storage, spoils for PW and Parks) as well as all the program elements from the Longacres site (spoils, materials, and large equipment storage, such as light poles and pipe). 145 Public Works Shops Part 2 of 2 Page 2 • The Public Works Final Phase will include the entire buildout of the Heiser and UPS sites. This first phase of improvements to the former Heiser building includes the safe, functional, forward looking and stewards of environment items identified by Fleet and Facility staff (such as floor drains, site lighting and locker rooms), and seismic improvements for life safety. City Public Works staff have been an integral collaborator in this portion of the Public Safety Plan’s design and implementation. Public Works staff have been working out of three facilities, all of which were not optimally designed for the work they house now, nor with an eye toward future needs. Relocating to the seismically improved Heiser building allows the City of Tukwila to make progress toward its ultimate goal of consolidating all of its Public Works functions on a single site as different funding sources become available over the next decade or more. Phase I - Tenant Improvements & Seismic Upgrades for the Fleet and Facility Building Phase I commenced in December 2019 with approval of the updated project budget and the design contract. The Phase I Tenant Improvement (TI) and Seismic Upgrade scope of work (seismic, building systems and functional upgrades) allows the Fleet and Facilities group’s use of the Heiser property, relocating activities from the George Long Shop and soils and equipment storage from the Longacres Site. This will enable the Fleet and Facilities group to operate more efficiently and safely. The seismically updated facility has much more space for daily operations, helping the department meet today’s workload and giving it future cap acity. This move will create a significant improvement of the work environment for staff, enhance their ability to work efficiently, and boost their morale particularly for the Fleet division. Some of the improvements to be included in this Tenant Improve ment and Seismic Upgrade project scope are: • The facility provides a safe environment for workers and visitors and improves employee health and wellness • The facility houses a collaborative Public Works Department with the capacity and flexibility to support the operations of tomorrow efficiently and effectively • The facility conveys the Department’s values to its customers and employees • The facility will exemplify environmental and regulatory standards for a sustainable future • Higher code required seismic retrofit for staff safety and building stability, allowing staff to start providing fleet services to the first responders including police, fire and other public works crews • All new HVAC equipment for better air quality and health, including vehicle exhaust system, welding exhaust system, and increased ventilation • New locker rooms with showers, additional handwash sinks and emergency shower and eye-wash fixtures to meet OSHA requirements • New LED lighting will be provided throughout the facility, designed to provide adequate light for vehicle maintenance functions • A new generator to provide back-up power in case of power outage 146 Public Works Shops Part 2 of 2 Page 3 • Trench drains and an Oil and Water separator to meet the National Pollutant Discharge Elimination System (NPDES) requirements • All automatic roll up doors for efficient operation • Covered spoils area to store material currently stored on Longacres property and which needs to be stored inside to meet the NPDES permit requirements • Some of the covered storage area can be used by the Streets crew and sewer utilities crew to free up space in current Minkler Shop facilities See attachment A2 for Phase 1 schematic. Project Schedule We have provided this committee 30% and 60% project updates on March 2 and June 15, 2020, respectively. The project is proceeding on the target schedule as shown in the previous estimates. SHKS has received the 90% design document. Project team is expecting to complete the bid documents and advertise for bids in September, which will result in reporting back to coun cil with the bid pricing sometime in late October or early November 2020 - See attached project schedule in Attachment A2. Construction is scheduled for 6-7 months once the contract is approved. This project is on time to the anticipated occupancy of the building scheduled for 2nd quarter of 2021. See attachment A2 for current Project Schedule . Project Funding The Public Works facility was originally funded at $30M as part of the Public Safety Plan funding model commonly known as D-20 and based on estimates derived during the pre- design phase. Half of the funds for the Public Works facility come s from the General Fund and the other half comes from the Enterprise Funds. The General Fund resources for the funding Public Safety Plan, including the Public Works Shops, are dependent on several other sources such as land sales from the George Long, Longacres and Minkler Shops, and the issuance of councilmanic bonds (LTGO). This funding plan has been shown throughout the Public Safety Plan approval process, the bond package’s public information materials and in subsequent long-term financial plans and City budgets. The King County Flood Control District is actively pursuing purchasing the George Long and Minkler Shops from the City. In December 2019, Council updated the D-20 Model for the Public Works Shops Phase 1 plan and approved a contract for design of the Public Works Shops tenant improvements and Seismic Upgrades. The updated budget for the Public Works Shop is now $35.7 million. The $35.7 million budget includes additional seismic improvements to the original Heiser building along with $500,000 for specified improvements to the Minkler facility. The transfer was approved at the November 11, 2019 Regular Council Meeting. A budgeted transfer of $1 million from the general fund to the arterial street fund was redirected to the PW Shops fund. 147 Public Works Shops Part 2 of 2 Page 4 Additionally, the 2020 budget was adopted with a $1.4 million surplus. The surplus was allocated to this project at the same time that Council redirected the $1 million transfer. The remaining balance of $450,000 was realized through debt service budget savings. Due to favorable interest rates in the bond market, coupled with the City’s upgrade in bond rating from AA to AA+, the City realized substantial savings in t otal debt service for both the PW Shops project and the Public Safety Plan projects (Justice Center, Fire Stations, and Fire Apparatus/Equipment. SHKS has received the 90% design document estimates and the project is within the currently approved budget. After these uses have been relocated, the George Long Shops and Longacres properties will be sold as part of the funding plan for Public Safety Plan, including the Public Works Shop, per the adopted D-20 Financing Model. Issues to be Addressed Shoreline The property just to the south of the Heiser building, commonly known as the former Riverside Residences, was purchased by King County for a mitigation effort. The County will develop this property into a side channel/wetland to assist migrating salmon in the Duwamish River. This project is expected to begin in April 2020. As part of the City’s workplan for the Public Works Shops, and concurrent with the design work that is underway, City staff ha ve been working with their consultants, the State’s Department of Ecology(DOE) and the City’s Department of Community Development (DCD) to ensure that the full extent of the City’s property can be leveraged as intended for the Public Works facility. City staff have anticipated that King County’s project will move the shoreline closer to the new Public Works facility and is Original Budget Current Budget Committed Budget Life to Date Costs Remain'g Committed Remaining Budget A/E Services (Design & CA)670,768$ 670,768$ 572,268$ 263,537$ 308,731$ 98,500$ Permits/Fees 130,000$ 130,000$ 20,730$ 20,730$ -$ 109,270$ Construction 6,715,000$ 6,715,000$ 308,055$ 185,743$ 122,313$ 6,406,945$ Construction (Tax)662,618$ 662,618$ 21,924$ 21,924$ -$ 640,694$ Construction Related Costs 378,186$ 378,186$ 200,643$ 148,378$ 52,266$ 177,543$ PM Services (incl Other Professional Svcs)350,000$ 350,000$ 280,545$ 177,282$ 103,263$ 69,455$ Contingency (incl Construction & Project)843,437$ 843,437$ -$ -$ -$ 843,437$ 9,750,009$ 9,750,009$ 1,404,165$ 817,593$ 586,572$ 8,345,843$ Previously Managed Svcs (Land,A/E,Bond,Demo) 25,949,992$ 25,949,992$ 25,949,265$ 25,949,265$ -$ 727$ 35,700,000$ 35,700,000$ 27,353,431$ 26,766,858$ 586,572$ 8,346,570$ COUNCIL REPORTING SUMMARY - PUBLIC WORKS TOTAL-COMBINED PROJECT SUBTOTAL-CURRENT MANAGED PROJECT 148 Public Works Shops Part 2 of 2 Page 5 managing potential implications of that change. In addition, because King County’s project will create new wetlands, other regulations may apply in the future. Near-term Council action will be updated on our conversations with DOE to ensure that the City’s project continues to move forward. This issue is time-sensitive and a delay in construction will have significant impacts to leverage the full extent of the City’s property and the overall masterplan. Next Steps There are several additional Committee and City Council meetings planned for further review, input, and review of options moving forward. September 14, 2020– COW - the information presented at Transportation and Infrastructure Committee on August 17th and 31st will be presented to the Committee of the Whole for information. This will include the Part 1 and 2 info memos providing the history, scope, budget and financing options. September 21, 2020 – T&I Committee review (if needed) November 2, 2020 – T&I – The Transportation and Infrastructure Committee is scheduled to review and approve the tenant improvement and seismic upgrade construction contract award, which then would be sent to the C.O.W. on November 9, 2020 and Regular Council meeting on November 16, 2020. There will also be additional updates to the Transportation and Infrastructure Committee and the Council on the shoreline and wetland related agreements and DOE responses. Financing Plan The Council’s approved budget for the $35.7 million Public Works Shop in 2020 includes a planned transfer from the General Fund to the Public Works Shops project of $2 .85 million. As mentioned earlier, this was originally adopted and planned for in November 2019 using a General Fund transfer from funds planned for the arterial street fund, surplus planned in 2020, and debt service savings. However, since this is a long-term capital project with an expected useful life of more than five years, it would be appropriate for the Council to finance these improvements rather than using a general fund transfer. The Council has already authorized financing, using LTGO bonds, for the initial $30 million of the Public Works Shop recognizing this fact. The reasons for financing this would include the following: - this is an appropriate capital project with a useful life of more than five years - excellent interest rates at this time (estimated to be around 1.5% or lower) - provides the Council more options for using general fund balances for other curre nt needs - the City has an excellent and upgraded bond rating, - allows the Council to stay on schedule and use the current good construction bidding environment. 149 Public Works Shops Part 2 of 2 Page 6 Total debt issuance costs would likely be approximately $50k. With a ten-year repayment schedule, total estimated interest costs would be roughly $216k, and result in an annual debt service obligation of $309k. A twenty-year repayment schedule would result in total interest costs of approximately $442k and an annual debt service obligation of $166k. Closing The current George Long facility was built in 1965. This project is very important to the residents of Tukwila who depend on Public Works employees as first responders for major disasters and emergencies. This Phase 1 Tenant Improvements and Se ismic Upgrade is a long-term investment for the future of the City as well as the Public Works Department, its employees, and the residents that we serve. It will make the department’s operations efficient, safe, and meet our City’s vision. Recommendation City staff and its consultants recommend allowing the project to go to bid and have a high degree of confidence in the current budget’s ability to provide for the project’s costs. This appears to be a favorable time to bid projects; estimators are utilizing a 0% cost inflation factor for the next six months. The administration recommends changing the funding plan from the general fund to a bond funded project. This is estimated to free up $2.85 million in general fund resources in 2020. Attachments A1 Masterplan programming Powerpoint Presentation from COW 10-18-19 A2 Powerpoint Presentation (90% design, cost estimate, schedule, past and future facilities graphics) A3 PW Memo Part 1 of 2 – Public Safety Plan A4 Facility Study Final Report – 12-14-15 and Public Safety Plan Fact Sheet - Sept. 2016 A5 http://www.tukwilawa.gov/wp -content/uploads/PW-Project-FS-Facilities-Study-12-14-15-Exec- Summary.pdf 150 City of Tukwila Allan Ekberg, Mayor INFORMATIONAL MEMORANDUM TO: Finance Committee FROM: Vicky Carlsen, Finance Director CC: Mayor Ekberg DATE: September 11, 2020 SUBJECT: Debt Capacity and Update Debt Service Obligations ISSUE Update the City’s current and projected debt capacity limits and provide an updated debt service requirements. BACKGROUND The amount of debt a city may incur is limited by the State constitution (Article VIII, Section 6) and individual statutes. Debt limits (also referred to as debt capacity) are based on total taxable property value (assessed value or AV). Per RCW 39.36.020, cities may issue non-voted debt up to 1.5% of total assessed value. Voted debt may not exceed the aggregate of 2.5% for general purposes, 2.5% for parks and open spaces and economic development, and 2.5% for utility purposes. While increases in assessed value have been as low as negative 2.18% to a high of 9.96%, since 2012, the average increase in assessed value has been 5.67%. Conservative estimates for assessed value in 2020 is 7.6 billion, which is a 4% growth over 2019 values. Growth in assessed value is derived from increases in existing property values as well as new construction. DISCUSSION Debt Capacity The chart on the next page shows historical debt capacity and assessed value as well as the change in AV each year. The chart also includes projected assessed value and the calculation for projected available debt capacity. Growth in AV has been calculated at a conservative 4% growth each year. The chart indicates that for fiscal year 2021, the City would have a debt capacity of $49 million available for non-voted debt. The chart does not include the proposed debt issue of $2.85 million to finance the general fund portion of the tenant improvements at the new Public Works Shops facility. 151 INFORMATIONAL MEMO Page 2 Without a Vote of the People Year LTGO Debt UTGO Debt Total Long- Term Debt Assessed Value %Change AV 1.5%2.5% Remaining Non-Voted Debt Capacity Remaining Total Debt Capacity 2012 25,884,632 - 25,884,632 4,649,191,308 -2.18% 69,737,870 116,229,783 43,853,238 90,345,151 2013 21,727,609 - 21,727,609 4,756,373,688 2.31% 71,345,605 118,909,342 49,617,996 97,181,733 2014 23,288,621 - 23,288,621 5,054,078,747 6.26% 75,811,181 126,351,969 52,522,560 103,063,348 2015 29,322,914 - 29,322,914 5,395,325,118 6.75% 80,929,877 134,883,128 51,606,963 105,560,214 2016 27,218,532 - 27,218,532 5,763,649,829 6.83% 86,454,747 144,091,246 59,236,215 116,872,714 2017 35,014,277 32,990,000 68,004,277 6,184,943,263 7.31% 92,774,149 154,623,582 57,759,872 86,619,305 2018 48,358,749 31,875,000 80,233,749 6,685,919,176 8.10% 100,288,788 167,147,979 51,930,039 86,914,230 2019 71,439,055 68,405,000 139,844,055 7,351,973,382 9.96% 110,279,601 183,799,335 38,840,546 43,955,280 2020 72,205,534 67,035,000 139,240,534 7,646,052,317 4.00% 114,690,785 191,151,308 42,485,251 51,910,774 2021 70,223,143 66,335,000 136,558,143 7,951,894,410 4.00% 119,278,416 198,797,360 49,055,273 62,239,217 2022 67,765,203 65,375,000 133,140,203 8,269,970,186 4.00% 124,049,553 206,749,255 56,284,350 73,609,052 2023 61,347,790 63,595,000 124,942,790 8,600,768,994 4.00% 129,011,535 215,019,225 67,663,745 90,076,435 2024 57,181,954 61,615,000 118,796,954 8,944,799,754 4.00% 134,171,996 223,619,994 76,990,042 104,823,040 2025 53,420,406 59,210,000 112,630,406 9,302,591,744 4.00% 139,538,876 232,564,794 86,118,470 119,934,388 2026 50,040,664 56,565,000 106,605,664 9,674,695,413 4.00% 145,120,431 241,867,385 95,079,767 135,261,721 2027 46,540,800 53,660,000 100,200,800 10,061,683,230 4.00% 150,925,248 251,542,081 104,384,448 151,341,281 2028 42,903,850 50,485,000 93,388,850 10,464,150,559 4.00% 156,962,258 261,603,764 114,058,408 168,214,914 2029 39,274,814 47,025,000 86,299,814 10,882,716,582 4.00% 163,240,749 272,067,915 123,965,935 185,768,101 2030 35,822,728 43,290,000 79,112,728 11,318,025,245 4.00% 169,770,379 282,950,631 133,947,651 203,837,903 2031 32,236,628 39,270,000 71,506,628 11,770,746,255 4.00% 176,561,194 294,268,656 144,324,566 222,762,028 2032 28,530,514 34,950,000 63,480,514 12,241,576,105 4.00% 183,623,642 306,039,403 155,093,128 242,558,889 2033 24,694,422 30,315,000 55,009,422 12,731,239,149 4.00% 190,968,587 318,280,979 166,274,165 263,271,557 2034 20,729,762 25,360,000 46,089,762 13,240,488,715 4.00% 198,607,331 331,012,218 177,877,569 284,922,456 2035 16,626,052 20,075,000 36,701,052 13,770,108,264 4.00% 206,551,624 344,252,707 189,925,572 307,551,655 2036 12,652,810 14,440,000 27,092,810 14,320,912,594 4.00% 214,813,689 358,022,815 202,160,879 330,930,005 2037 8,926,072 8,440,000 17,366,072 14,893,749,098 4.00% 223,406,236 372,343,727 214,480,164 354,977,655 2038 5,070,838 4,335,000 9,405,838 15,489,499,062 4.00% 232,342,486 387,237,477 227,271,648 377,831,639 2039 1,640,000 - 1,640,000 16,109,079,024 4.00% 241,636,185 402,726,976 239,996,185 401,086,976 2040 - - - 16,753,442,185 4.00% 251,301,633 418,836,055 251,301,633 418,836,055 2041 - - - 17,423,579,873 4.00% 261,353,698 435,589,497 261,353,698 435,589,497 2042 - - - 18,120,523,068 4.00% 271,807,846 453,013,077 271,807,846 453,013,077 2043 - - - 18,845,343,990 4.00% 282,680,160 471,133,600 282,680,160 471,133,600 With a Vote of the People Legal Debt Limit Voted debt cannot exceed the aggregate of: 2.5% for general purposes, 2.5% for parks and open spaces, & economic development, and 2.5% for utility purposes City of Tukwila Historical Debt Capacity with Pro jected Assessed Value and Projected Debt Capacity 152 INFORMATIONAL MEMO Page 3 Existing and Proposed General Obligation Long-term Debt The chart below provides annual debt service obligations by debt issue and includes an estimate for debt service requirements to finance the general fund portion of tenant improvements at the PW Shops facility. . Not all of the debt issues listed currently impact the general fund. - MPD loan is paid by the Tukwila Pool Metropolitan Park District. The City invoices the MPD for the amount due and uses the receipts to pay this debt obligation. The City budgets both the revenue as well as the expenditure. - SCORE debt is currently paid by SCORE on behalf of the owner cities. SCORE plans to continue this practice. - Debt for PW Shops is split between the general fund and the utility funds. The utility funds pay their fair share of the debt in lieu of rent. For comparison purposes, the chart also includes two columns (last two columns) comparing debt service obligations as budgeted during the 2019-2020 biennial budget process and proposed debt service obligations. With the exception of 2021 and 2039, total proposed debt service is less than what was proposed two years ago. When the City issued debt in 2019, the total debt service requirements were lower than originally budgeted due to a favorable bond market coupled with the City’s elevated bond rating of AA+. The City can issue $2.85 million in limited obligation debt and still realize a savings in almost every year from what was budgeted the last biennium. Fund 217 LTGO Refunding, 2011 Fund 218 LTGO, 2013 Fund 200 LTGO, 2014 Fund 200 LTGO, 2015 Fund 200 LTGO, 2017 Fund 200 LTGO, 2017 Refunded LOC Fund 208 LTGO, 2018 Fund 208 LTGO, 2019 Fund 212 LTGO Refunding, 2019 Fund 200 LTGO Refunding, 2020 New Debt - PSP PW Shops $4,620,000 Original Issue $1,000,000 Original issue $3,850,000 Original Issue $5,825,000 Original Issue $8,180,000 Original Issue $2,276,000 Original Issue $18,365,000 Original Issue $22,830,000 Original Issue $4,921,702 Original Issue $1,995,000 Original Issue $2,850,000 Planned Issue Arterial Street, KC Bridge MPD Loan Urban Renewal Interurban Avenue South & BAR Bridge 42nd and 53rd Sidewalks Urban Renewal - Refunded LOC PSP - PW Shops PSP and PW Shops SCORE SC Parkway Extension/HHD PW Shops General Fund Portion Total Existing and Planned General Obligation Debt 2019-2020 Budget Document Increase / (Decrease) 2021 546,300$ 113,130$ 264,774$ 387,775$ 553,500$ 63,728$ 804,200$ 805,300$ 376,895$ 515,736$ 309,000$ 4,740,337$ 4,582,465$ 157,872$ 2022 551,500 113,115 265,289 390,275 553,600 2,344,280 1,534,200 1,690,300 377,030 514,415 309,000 8,643,004 8,694,344 (51,340) 2023 545,900 - 264,859 392,475 558,400 - 1,532,700 1,691,050 376,876 513,029 309,000 6,184,289 6,226,109 (41,821) 2024 - - 264,571 389,375 557,750 - 1,534,450 1,689,550 376,914 516,579 309,000 5,638,189 5,671,459 (33,270) 2025 - - 265,483 391,125 556,800 - 1,534,200 1,690,800 377,126 - 309,000 5,124,534 5,145,342 (20,808) 2026 - - 264,455 387,575 555,550 - 1,531,950 1,689,550 376,861 - 309,000 5,114,941 5,137,452 (22,511) 2027 - - 264,273 391,050 554,000 - 1,532,700 1,690,800 377,054 - 309,000 5,118,878 5,140,135 (21,257) 2028 - - 263,909 392,050 557,150 - 1,531,200 1,689,300 376,693 - 309,000 5,119,301 5,142,598 (23,297) 2029 - - 263,360 387,750 554,850 - 1,532,450 1,688,750 376,741 - 309,000 5,112,901 5,136,847 (23,946) 2030 - - 262,628 388,300 557,250 - 1,536,200 1,687,150 377,151 - 309,000 5,117,679 5,142,733 (25,054) 2031 - - 262,713 388,550 554,200 - 1,533,000 1,689,500 376,910 - - 4,804,872 5,137,264 (332,392) 2032 - - 261,583 388,500 555,850 - 1,533,200 1,690,650 376,982 - - 4,806,765 5,137,862 (331,097) 2033 - - 261,269 388,150 557,050 - 1,531,600 1,690,600 376,866 - - 4,805,535 5,136,989 (331,454) 2034 - - 260,742 392,500 557,800 - 1,533,200 1,689,350 376,770 - - 4,810,362 5,143,581 (333,219) 2035 - - - 391,400 551,875 - 1,532,800 1,686,900 376,673 - - 4,539,648 4,875,638 (335,990) 2036 - - - - 555,625 - 1,535,400 1,688,250 377,040 - - 4,156,315 4,490,053 (333,738) 2037 - - - - 553,725 - 1,535,800 1,688,250 376,866 - - 4,154,641 4,488,164 (333,523) 2038 - - - - - - 1,534,000 1,686,900 376,813 - - 3,597,713 3,932,362 (334,649) 2039 - - - - - - - 1,689,200 - - - 1,689,200 422,085 1,267,115 Totals 1,643,700$ 226,245$ 3,689,907$ 5,846,850$ 9,444,975$ 2,408,008$ 26,873,250$ 31,212,150$ 6,784,261$ 2,059,758$ 3,090,000$ 93,279,104$ Comparison to 2019-2020 Budget Document Schedule of Budgeted General Obligation Long-Term Debt 153 INFORMATIONAL MEMO Page 4 Included as an attachment is the Schedule of Prior, Existing, and Future Anticipated Long-Term Debt Service. The chart does not include Local Improvement District #33 debt as those bonds are paid through assessments levied to property owners within the Local Improvement District area. The chart also does not include voter-approved debt as those obligations are funded through an excess property tax levy. RECOMMENDATION For information only. ATTACHMENT Schedule of Prior, Existing, and Future Anticipated Long-Term Debt Service 154 Section 3Column 1 Column 2 Column 3 Column 4 Column 5 Column 6 Column 7 Column 8 Column 9 Column 10 Column 11 Column 12 Column 13 Column 14 Column 15 Column 16 Column 17 Column 18 Column 19 Column 20 Column 21 Column 22 Column 23 Column 24New Debt - PSP PW Shops1999 2000 2003 2003R 2008R 2009 2010 2010R 2011R 2013 2014 2014A 2015 2017 2017 2018 2018 20182018 $6,000,000 Original Issue $382,900 Original Issue $10,000,000 Original Issue $2,551,600 Original Issue $6,277,500 Original Issue $4,195,000 Original Issue $6,180,000 Original Issue $6,898,800 Original issue $5,870,000 Original Issue $1,065,000 Original Issue $4,620,000 Original Issue $1,000,000 Original issue $3,850,000 Original Issue $2,250,000 Line of Credit $5,825,000 Original Issue $8,180,000 Original Issue $2,276,000 Original Issue $18,365,000 Original Issue $22,830,000 Original Issue $4,921,702 Original Issue $1,995,000 Original Issue $2,850,000 Planned Issue TCC, Fire Station #53City Hall Annex, Tukwila VillageSCORESC Parkway Extension/HHDValley ComArterial Street, KC BridgeMPD Loan2000512,385 26,875 834,343 - - - - - - - - - - - - - - - - - - 1,373,603 - 1,373,603 2001516,100 - 833,623 245,882 - - - - - - - - - - - - - - - - - 1,595,604 - 1,595,604 2002513,973 - 834,223 250,595 - - - - - - - - - - - - - - - - - 1,598,790 - 1,598,790 2003 516,173 - 834,148 250,963 49,871 - - - - - - - - - - - - - - - - 1,651,155 - 1,651,155 2004- - 832,873 250,067 272,026 489,676 - - - - - - - - - - - - - - - 1,844,642- 1,844,642 2005- - 830,535 250,812 272,026 489,900 - - - - - - - - - - - - - - - 1,843,273- 1,843,273 2006- - 832,105 250,877 272,026 486,900 - - - - - - - - - - - - - - - 1,841,908- 1,841,908 2007- - 832,305 250,839 272,026 488,500 - - - - - - - - - - - - - - - 1,843,670- 1,843,670 2008- - 831,305 250,479 272,026 489,500 - - - - - - - - - - - - - - - 1,843,310- 1,843,310 2009- - 488,948 190,104 533,323 489,900 324,800 - - - - - - - - - - - - - - 2,027,075- 2,027,075 2010- - - 193,200 585,949 489,700 816,000 - 199,222 230,186 - - - - - - - - - - - 2,514,257- 2,514,257 2011- - - - 584,881 488,900 815,400 - 586,225 171,790 - - - - - - - - - - - 2,647,196- 2,647,196 2012- - - - 718,375 487,500 809,000 91,791 584,425 232,910 166,964- - - - - - - - - - 3,090,965- 3,090,965 2013- - - - 3,379,788 490,500 737,000 430,157 584,075 204,880 167,975 113,130 - - - - - - - - - 6,107,504 - 6,107,504 2014- - - - - 488,250 812,000 429,815 583,425 229,280 547,675 113,130 - - - - - - - - - 3,203,574 - 3,203,574 2015- - - - - - 811,300 432,885 585,650 228,800 545,825 113,130 249,404 18,118 102,107 - - - - - - 3,087,218 - 3,087,218 2016- - - - - - 811,100 427,960 585,450 - 548,675 113,130 260,918 22,000 392,575 - - - - - - 3,161,808 - 3,161,808 2017- - - - - - 809,900 427,461 581,190 - 552,300 113,130 260,175 40,000 390,975 87,448 - - - - - 5,495,579 - 5,495,579 2018- - - - - - 809,100 428,288 575,152 - 549,250 113,130 260,775 2,290,000 389,225 556,850 61,970 239,026 - - - 3,982,767 - 3,982,767 2019- - - - - - 810,900 - 567,307 - 548,700 113,130 260,455 - 392,325 557,700 59,176 804,200 - - - 4,113,893 - 4,113,893 2020- - - - - - - - 61,591 - 545,300 113,130 264,990 - 390,125 558,250 59,176 804,200 890,304 376,749 11,224 4,075,038- 4,075,038 2021- - - - - - - - - - 546,300 113,130 264,774 - 387,775 553,500 63,728 804,200 805,300 376,895 515,736 4,431,337 309,000 4,740,337 2022- - - - - - - - - - 551,500 113,115 265,289 - 390,275 553,600 2,344,280 1,534,200 1,690,300 377,030 514,415 8,334,004 309,000 8,643,004 2023- - - - - - - - - - 545,900 - 264,859 - 392,475 558,400 - 1,532,700 1,691,050 376,876 513,029 5,875,289 309,000 6,184,289 2024- - - - - - - - - - - - 264,571 - 389,375 557,750 - 1,534,450 1,689,550 376,914 516,579 5,329,189 309,000 5,638,189 2025- - - - - - - - - - - - 265,483 - 391,125 556,800 - 1,534,200 1,690,800 377,126 - 4,815,534 309,000 5,124,534 2026- - - - - - - - - - - - 264,455 - 387,575 555,550 - 1,531,950 1,689,550 376,861 - 4,805,941 309,000 5,114,941 2027- - - - - - - - - - - - 264,273 - 391,050 554,000 - 1,532,700 1,690,800 377,054 - 4,809,878 309,000 5,118,878 2028- - - - - - - - - - - - 263,909 - 392,050 557,150 - 1,531,200 1,689,300 376,693 - 4,810,301 309,000 5,119,301 2029- - - - - - - - - - - - 263,360 - 387,750 554,850 - 1,532,450 1,688,750 376,741 - 4,803,901 309,000 5,112,901 2030- - - - - - - - - - - - 262,628 - 388,300 557,250 - 1,536,200 1,687,150 377,151 - 4,808,679 309,000 5,117,679 2031- - - - - - - - - - - - 262,713 - 388,550 554,200 - 1,533,000 1,689,500 376,910 - 4,804,872- 4,804,872 2032- - - - - - - - - - - - 261,583 - 388,500 555,850 - 1,533,200 1,690,650 376,982 - 4,806,765- 4,806,765 2033- - - - - - - - - - - - 261,269 - 388,150 557,050 - 1,531,600 1,690,600 376,866 - 4,805,535- 4,805,535 2034- - - - - - - - - - - - 260,742 - 392,500 557,800 - 1,533,200 1,689,350 376,770 - 4,810,362- 4,810,362 2035- - - - - - - - - - - - - - 391,400 551,875 - 1,532,800 1,686,900 376,673 - 4,539,648- 4,539,648 2036- - - - - - - - - - - - - - - 555,625 - 1,535,400 1,688,250 377,040 - 4,156,315- 4,156,315 2037- - - - - - - - - - - - - - - 553,725 - 1,535,800 1,688,250 376,866 - 4,154,641- 4,154,641 2038- - - - - - - - - - - - - - - - - 1,534,000 1,686,900 376,813 - 3,597,713- 3,597,713 2039- - - - - - - - - - - - - - - - - - 1,689,200 - - 1,689,200- 1,689,200 Totals-$ -$ -$ -$ -$ -$ 810,900$ -$ 628,898$ -$ 2,737,700$ 452,505$ 4,215,351$ -$ 6,629,300$ 10,560,925$ 2,526,360$ 28,481,650$ 32,102,454$ 7,161,009$ 2,070,982$ 98,378,034$ 3,090,000$ 101,468,034$ Total = Columns 22 and 23FacilitiesStreets / FacilitiesFacilitiesSouth Park Br, Art. St., Golf CourseSubtotal = Columns 1-21PW Shops General Fund Portion42nd and 53rd SidewalksUrban Renewal - Refunded LOCFund 218 LTGO, 2013Urban RenewalUrban RenewalInterurban Avenue South & BAR BridgeSC Parkway Extension/HHDPSP - PW ShopsPSP and PW ShopsSCOREFund 207 LTGO Bonds, 1999Section 1Fund 200 LTGO, 2017Fund 200 LTGO Refunding, 2020Fund 211 LTGO Refunding, 2008Fund 212 LTGO Bonds, 2009Fund 214 LTGO 2010Fund 216 LTGO Refunding, 2010Fund 217 LTGO Refunding, 2011Fund 200 LTGO, 2017 Refunded LOCFund 208 LTGO, 2018Fund 208 LTGO, 2019Fund 212 LTGO Refunding, 2019Existing General Obligation DebtFuture Anticipated General Obligation DebtSCHEDULE OF PRIOR, EXISTING, AND FUTURE ANTICIPATED LONG-TERM DEBT SERVICETotal Existing and Future General Obligation DebtTotal Existing GO DebtFund 208 LTGO Bonds, 2000Fund 209 LTGO Bonds, 2003Fund 210 LTGO Refunding, 2003Fund 200 LTGO, 2014Fund 200 LTGO, 2014 LOCFund 200 LTGO, 2015Section 2Fund 201 LTGO BondsFund 205 Special Assessment BondsW:\Budget\2021-2022 BUDGET\200_21GO Debt sched only OS Debt9/5/20203:20 PM155 156 | 1TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 SITE TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY SPU RIGHT OF WAY / S 112TH ST TUKWILA INTERNATIONAL BLVDLINK LIGHT RAILE MARG INAL WAY S DUWAMISH RIVER LANDSCAPE PARCELHEISER PARCEL SCL PARCELS UPS PARCEL N 157 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 2EAST MARGI NAL WAY SOUTHDUWAMISH RIVER WETLANDPROPOSED WETLAND BY KING COUNTY PROPERTY LINE P R O P E R T Y L I N E TUKWILA PUBLIC WORKS FACILITY: MASTER PLAN RECOMMENDATION - 3 PHASES DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING PHASE 1 HEISER RENOVATION | DEMOLISH LANDSCAPE + COFFEE SHOP | POLICE IMPOUND | SITE WORK | COVERED SPOILS GEORGE LONG SHOPS + LONG ACRES RELOCATES IN SPRING 2021 UPS SITE REMAINS OCCUPIED BY UPS THROUGH OCT 2023 MINKLER RELOCATES IN 2024 NEW FLEET MAINTENANCE SHOP, COVERED SPOILS, AND DECANT IN 2029 TO COMPLETE CONSOLIDATED PUBLIC WORKS FACILITY DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING PHASE 2 ADMIN + SHOPS BUILDING | COVERED MATERIAL STORAGE | INTERIOR + COVERED PARKING | POLICE IMPOUND | SITE WORK DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING PHASE 3 FLEET MAINTENANCE BUILDING | SITE WORK | DECANT + BRINE TANKS | COVERED STORAGE | SPOILS | SITE WORK SPOILS PREVIOUS OHWM (APPROXIMATED) 100' SHORELINE BUFFER (APPROXIMATED) 200' SHORELINE NON-BUFFER (APPROXIMATED) SOUTH 112TH STREET TUKWILA INTERNATIONAL BLVD EAST MARGI NAL WAY SOUTHDUWAMISH RIVER BULK BINS 3,150 SF FLEET MAINTENANCE 23,105 SF ADMIN + SHOPS 43,200 SF 22,690 SF FOOTPRINT FLEET MAINTENANCE PARKING PD YARD WETLANDPROPOSED WETLAND BY KING COUNTY PROPERTY LINE P R O P E R T Y L IN E SPOILS 9,765 SF DECANT 4,400 SF WASH RACK1,980 SFBRINE TANKSCOVERED STORAGE 11,630 SF SPOILS 8,265 SF UNCOVERED STORAGE 8,454 SF WASTE 770 SF STAFF PARKING ADMIN + VISITOR PARKING INTERIOR FLEET UNCOVERED STORAGE 1,880 SF ORGANICS BINS 3,090 SF UNCOVERED STORAGE 700 SF UNCOVERED STORAGE3,262 SFR 100' - 0" COVERED FLEET PARKING (44) 10x30 COVERED FLEET PARKING (45) 9x20 COVERED FLEET PARKING (14) 10x30, (4) 15x45 7/2/2019 12:51:45 PM1" = 60'-0"1 SITE PLAN - OPTION 2.2 PROGRAM ADMIN + SHOPS BLDG FLEET MAINTENANCE BLDG SPOILS BINS BULK BINS ORGANICS BINS DECANT BRINE TANKS COVERED STORAGE UNCOVERED STORAGE WASH RACK TOTAL PROVIDED AREA 43,200 SF 23,105 SF 18,800 SF 3,150 SF 3,090 SF 4,400 SF 1,060 SF 11,630 SF 14,295 SF 1,980 SF 124,710 SF OPTION 2.1 PROGRAM SUMMARY DELTA +1% +14% -4% +5% +3% +5% +6% +25% -2% +4% +4% REQUIRED AREA 42,860 SF 20,195 SF 19,500 SF 3,000 SF 3,000 SF 4,200 SF 1,000 SF 9,300 SF 14,595 SF 1,900 SF 119,550 SF PARKING AREA STAFF PARKING VISITOR + ACCESSIBLE PARKING INTERIOR FLEET PARKING 9X20 10X30 15X45 COVERED FLEET PARKING 9X20 10X30 15X45 UNCOVERED FLEET PARKING 9X20 10X30 15X45 FLEET MAINTENANCE PARKING PD IMPOUND YARD TOTAL PROVIDED STALLS 70 20 2 3 3 45 58 4 0 0 0 50 30 285 OPTION 2.1 PARKING DELTA +3 +10 0 0 0 0 +1 0 0 0 0 0 0 +14 REQUIRED STALLS 67 10 2 3 3 45 57 4 0 0 0 50 30 271 0 60'120'30'15' OPTION 2.2 PROGRAM SUMMARYOPTION 2.2 PARKING PREVIOUS OHWM (APPROXIMATED) 100' SHORELINE BUFFER (APPROXIMATED) 200' SHORELINE NON-BUFFER (APPROXIMATED) SOUTH 112TH STREET TUKWILA INTERNATIONAL BLVD EAST MARGI NAL WAY SOUTHDUWAMISH RIVER BULK BINS 3,150 SF ADMIN + SHOPS 43,200 SF 22,690 SF FOOTPRINT PD YARD WETLANDPROPOSED WETLAND BY KING COUNTY PROPERTY LINE P R O P E R T Y L I N E UNCOVERED STORAGE 8,454 SF STAFF PARKING ADMIN + VISITOR PARKING INTERIOR FLEET UNCOVERED STORAGE 1,880 SF ORGANICS BINS 3,090 SF UNCOVERED STORAGE 700 SF COVERED FLEET PARKING (44) 10x30 COVERED FLEET PARKING (45) 9x20 COVERED FLEET PARKING (14) 10x30, (4) 15x45 FLEET MAINTENANCE Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks 1" = 60'-0"10/24/2019 5:03:09 PMPD 2.8 TUKWILA PUBLIC WORKS 6/25/2019 PW AH FACILITY TEST-TO-FIT 11231 E MARGINAL WAY S TUKWILA, WA 98168 OPTION 2.2 PHASE 2 0 60'120'30'15' 1" = 60'-0"1 SITE PLAN - OPTION 2.2 - PHASE 2 UPS HEISER N N N158 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 3 Water Facilities FUNCTIONAL STEWARDS OF ENVIRONMENT EFFICIENT FORWARD LOOKING ADAPTABLE AWARD WINNING INDUSTRY LEADER SAFE PROUD TO GO TO WORK SUSTAINABLE RESILIENT BETTER SERVICE TO PUBLIC TECHNOLOGICALLY ADVANCED CUTTING EDGE WELCOMING TO PUBLIC Engineering Fleet Sewer/Surface Street TUKWILA PUBLIC WORKS FACILITY: GOALSTUKWILA PUBLIC WORKS FACILITY: GOAL SETTING EXERCISE - 4 PRIORITY GOALS 159 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 4 TUKWILA PUBLIC WORKS FACILITY: GOAL SETTING EXERCISE - GUIDING PRINCIPLES SAFE The facility provides a safe environment for workers and visitors and improves employee health and wellness. FUNCTIONAL The facility houses a collaborative Public Works Department with the capacity and flexibility to support the operations of tomorrow efficiently and effectively. FORWARD LOOKING The facility conveys the Department’s values to its customers and employees. It supports a long-term investment strategy to raise existing facility standards and plans for technological advancements that improve service to the public. STEWARDS OF THE ENVIRONMENT The facility will exemplify environmental and regulatory standards for a sustainable future. It promotes human and environmental health.160 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 5 0’50’ 100’ LONG ACRESGEORGE LONGMINKLER 0’50’ 100’ 0’50’ 100’1.0 ACRE GROSS ACTIVE SITE AREA2.2 ACRES GROSS ACTIVE SITE AREA2.3 ACRES GROSS ACTIVE SITE AREA TUKWILA PUBLIC WORKS FACILITY: ASSESSMENT - EXISTING PROGRAM ANALYSIS N N N 161 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 6 MINKLER GEORGE LONG LONG ACRES TUKWILA PUBLIC WORKS FACILITY: ASSESSMENT - EXISTING CONDITIONS162 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 7 AADDMMIINN ++ SSHHOOPPSS FFLLEEEETT MMNNTT CCOOVVEERREEDD FFLLEEEETT SSPPOOIILLSS BBUULLKK CCOOVVEERREEDD SSTTOORR UUNNCCOOVVEERREEDD SSTTOORRAAGGEE SSTTAAFFFF//VVIISSIITTOORR PPAARRKKIINNGG WWAASSHH RRAACCKK DDEECCAANNTT PPOOLLIICCEE IIMMPPOOUUNNDD FLEET MAINTENANCE ADMIN + SHOPS COVERED FLEET PARKING DECANT + BRINE WASH RACK SPOILS BULK BINS COVERED STORAGE UNCOVERED STORAGE STAFF/VISITOR PARKING POLICE IMPOUND SITE TUKWILA PUBLIC WORKS FACILITY: ASSESSMENT - CURRENT AND FUTURE PROGRAM ANALYSIS 10,760 SF 22,150 SF 14,050 SF 3,860 SF 0 SF 0 SF 13,260 SF 3,500 SF 3,620 SF 12,600 SF 6,250 SF 20,195 SF 42,860 SF 12,910 SF 29,310 SF 3,800 SF 1,900 SF 19,500 SF 4,800 SF 5,300 SF 14,000 SF 6,250 SF NEW EXISTING PROJECTED 2045 AREASEXISTING AREAS 30,116 SF 50,389 SFINTERIOR PROGRAM 96,253 SF 152,611 SFEXTERIOR PROGRAM DIFFERENCE: +56,358 SF INTERIOR PROGRAM EXTERIOR PROGRAM SITE/ CIRCULATION SITE/ CIRCULATION 225,222 SF66,487 SF TOTAL: 447,131 GSFTOTAL: 192,856 GSF 4.4 ACRES 10.3 ACRES 163 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 8 TUKWILA PUBLIC WORKS FACILITY: ASSESSMENT - NEW SITE ANALYSIS HEISER HEISER - OFFICE HEISER - OPEN SHOPS HEISER - OPEN SHOPS164 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 9 PROGRAM LEGEND ADMIN + SHOPS FLEET MAINTENANCE FLEET MAINTENANCE PARKING INTERIOR FLEET PARKING COVERED FLEET PARKING UNCOVERED FLEET PARKING DECANT + BRINE SPOILS COVERED STORAGE BULK BINS UNCOVERED STORAGE TUKWILA PUBLIC WORKS FACILITY: OPTIONS STUDY - FINAL MASTER PLAN PROVIDED NET PROGRAM AREA: 211,000 NSF REQUIRED NET PROGRAM AREA: 203,000 NSF PROGRAMMED GROSS AREA: ~470,000 GSF DEVELOPABLE SITE AREA: ~503,000 SF MEETS 2045 PROGRAM REQUIREMENTS MEETS GUIDING PRINCIPLES COST: $78,600,000* *per proposed phasing PROPERTY LINE P R O P E R T Y L IN E Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks 1" = 60'-0" PD 2.2 TUKWILA PUBLIC WORKS 6/25/2019 PW AH FACILITY TEST-TO-FIT 11231 E MARGINAL WAY S TUKWILA, WA 98168 OPTION 2.2 1" = 60'-0"1 SITE PLAN - OPTION 2.2 PROGRAM ADMIN + SHOPS BLDG FLEET MAINTENANCE BLDG SPOILS BINS BULK BINS ORGANICS BINS DECANT BRINE TANKS COVERED STORAGE UNCOVERED STORAGE WASH RACK TOTAL PROVIDED AREA 43,200 SF 23,105 SF 18,800 SF 3,150 SF 3,090 SF 4,400 SF 1,060 SF 11,630 SF 14,295 SF 1,980 SF 124,710 SF OPTION 2.1 PROGRAM SUMMARY DELTA +1% +14% -4% +5% +3% +5% +6% +25% -2% +4% +4% REQUIRED AREA 42,860 SF 20,195 SF 19,500 SF 3,000 SF 3,000 SF 4,200 SF 1,000 SF 9,300 SF 14,595 SF 1,900 SF 119,550 SF PARKING AREA STAFF PARKING VISITOR + ACCESSIBLE PARKING INTERIOR FLEET PARKING 9X20 10X30 15X45 COVERED FLEET PARKING 9X20 10X30 15X45 UNCOVERED FLEET PARKING 9X20 10X30 15X45 FLEET MAINTENANCE PARKING PD IMPOUND YARD PROVIDED STALLS 70 20 2 3 3 45 58 4 0 0 0 50 30 OPTION 2.1 PARKING DELTA +3 +10 0 0 0 0 +1 0 0 0 0 0 0 REQUIRED STALLS 67 10 2 3 3 45 57 4 0 0 0 50 30 0 60'120'30'15' OPTION 2.2 PROGRAM SUMMARYOPTION 2.2 PARKING ADMIN + SHOPS FLEET MAINTENANCE FLEET MAINTENANCE PARKING COVERED FLEET PARKING COVERED FLEET PARKING COVERED STORAGE SPOILS SPOILS INTERIOR FLEET ORGANIC BINS ORGANIC BINS COVERED FLEET PARKING DECANT + BRINE UNCOVERED STORAGE UNCOVERED STORAGE COVERED FLEET PARKING POLICE IMPOUND STAFF PARKING ADMIN + VISITOR PARKING UNCOVERED STORAGEWASH RACKUNCOVERED STORAGETUKWILA INTERNATIONAL BLVDSOUTH 112TH ST PROPOSED WETLAND BY KING COUNTY WETLAND 165 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 10TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | COMMITTEE OF THE WHOLE | 10 28 19TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | COMMITTEE OF THE WHOLE | 10 28 19 GEORGE LONG LONG ACRES MINKLER TUKWILA PUBLIC WORKS FACILITY: PHASING - CONSIDERATIONS HEISER + LANDSCAPE SITE AVAILABLE 2019 MINKLER 13,897 nsf 42,926 nsf 43,795 nsf GEORGE LONG 16,219 nsf 40,112 nsf 22,692 nsf LONG ACRES 0 sf 13,215 nsf 0 sf TOTAL 30,116 nsf 96,252 nsf 66,487 nsf 192,856 gsf INTERIOR EXTERIOR HEISER + LANDSCAPE 42,500 gsf 129,800 gsf SCL EASEMENT 0 sf 14,750 sf* TOTAL 42,500 gsf 144,550 gsf* 187,050 gsf* INTERIOR EXTERIOR EXISTING AREAS AVAILABLE AREAS 0’50’ 100’UPS SITE AVAILABLE OCT 20230’50’ 100’ 0’50’ 100’ 0’50’ 100’ CIRCULATION166 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 11 TUKWILA PUBLIC WORKS FACILITY: PHASING - MASTER PLAN DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING PHASE 1 HEISER RENOVATION | DEMOLISH LANDSCAPE + COFFEE SHOP | POLICE IMPOUND | SITE WORK | COVERED SPOILS DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING PHASE 2 ADMIN + SHOPS BUILDING | COVERED MATERIAL STORAGE | INTERIOR + COVERED PARKING | POLICE IMPOUND | SITE WORK DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING PHASE 3 FLEET MAINTENANCE BUILDING | SITE WORK | DECANT + BRINE TANKS | COVERED STORAGE | SPOILS | SITE WORK DEMOLITION RENOVATION LANDSCAPING NEW CONSTRUCTION SITE WORK UNCOVERED PARKING ROM - ESTIMATED COSTS - PHASE 1 CONSTRUCTION COSTS: $6,700,000 SOFT COSTS: $2,800,000 TOTAL PROJECT COST: $9,500,000 ANTICIPATED CONSTRUCTION START: MID - 2020 ROM - ESTIMATED COSTS - PHASE 2 CONSTRUCTION COSTS: $22,600,000 SOFT COSTS: $10,400,000 TOTAL PROJECT COST: $33,000,000 ANTICIPATED CONSTRUCTION START: OCT 2023 ROM - ESTIMATED COSTS - PHASE 3 CONSTRUCTION COSTS: $24,400,000 SOFT COSTS: $13,000,000 TOTAL PROJECT COST: $37,400,000 ANTICIPATED CONSTRUCTION START: OCT 2029 167 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 12TUKWILA INTERNATIONAL BLVD PROPERTY LINE Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks 1" = 30'-0" PD 2.3 TUKWILA PUBLIC WORKS 6/25/2019 Author Checker FACILITY TEST-TO-FIT 11231 E MARGINAL WAY S TUKWILA, WA 98168 OPT 2.2 - PH 1 EXTERIOR PROGRAM (FLEET & FACILITIES) UNCOVERED STORAGE UNCOVERED FLEET PARKING STAFF PARKING POLICE IMPOUND SUBTOTAL EXISTING AREA (GEORGE LONG) 1,695 SF 12,380 SF 8,610 SF 10,400 SF 33,085 SF PHASE 1 PROGRAM SUMMARY DELTA 0% 0% 0% 0% +0% PROVIDED AREA (HEISER) 1,695 SF 12,380 SF 4,355 SF 10,400 SF 28,830 SF EXTERIOR PROGRAM (WATER, SEWER, STREET) UNCOVERED STORAGE SPOILS/ORGANICS SUBTOTAL TOTAL EXISTING AREA (GEORGE LONG) 565 SF 7,900 SF 8,465 SF 57,770 SF DELTA 0% +5% +4% +4% PROVIDED AREA (HEISER) 6,290 SF 16,160 SF* 22,450 SF 73,925 SF EXISTING AREA (LONG ACRES) 5,655 SF 7,560 SF 13,215 SF 13,215 SF REQUIRED AREA 6,220 SF 15,460 SF 21,680 SF 71,130 SF REQUIRED AREA 1,695 SF 12,380 SF 4,355 SF 10,400 SF 28,830 SF EXISTING AREA (LONG ACRES) - - - - - PARKING (FLEET & FACILITIES) UNCOVERED FLEET 9x20 10x30 15x45 FLEET MAINTENANCE PARKING STAFF TOTAL EXISTING STALLS (GEORGE LONG) 6 9 1 35 26 77 DELTA +0 +0 +0 +0 +0 +0 PROVIDED STALLS (HEISER) 6 9 1 35 26 77 *PORTION OF SPOILS/ORGANICS PROVIDED INSIDE HEISER BUILDING, SEE SHEET PD1.2 INTERIOR PROGRAM (FLEET & FACILITIES) OFFICE HEALTH & WELLBEING (BREAKROOM / RECOVERY) MEETING SPACE SHOP OPERATIONS STORAGE BUILDING SUPPORT (LOCKER ROOM / BUILDING UTILITIES) SUBTOTAL EXISTING AREA (GEORGE LONG) 2,645 SF 780 SF 240 SF 8,110 SF 3,450 SF 995 SF 16,220 SF REQUIRED AREA 1,810 SF 900 SF 375 SF 10,695 SF 4,770 SF 2,070 SF 20,620 SF PROVIDED AREA (HEISER) 1,865 SF 905 SF 375 SF 11,760 SF 5,420 SF 2,320 SF 22,645 SF EXISTING AREA (LONG ACRES) - - - - - - - DELTA +3% +1% 0% +10% +14% +12% +10% 1" = 30'-0" SITE PLAN - OPTION 2.2 - PHASE 1 TUKWILA INTERNATIONAL BLVD STAFF PARKINGHEISER BUILDING POLICE IMPOUND VEHICLE ACCESS GATE VISITOR PARKINGUNCOVERED STORAGEVEHICLE ACCESS GATE VEHICLE ACCESS GATE WASH RACKBUILDING VEHICLE ACCESS STAFF PARKING FLEET PARKING UNCOVERED STORAGE SITE VEHICLE ACCESS SITE REGRADING SECURITY FENCING SPOILS UNCOVERED STORAGE SPOILS/ORGANIC MATERIALS UNCOVERED STORAGE FLEET MAINTENANCE PARKING EXTERIOR PROGRAM (FLEET & FACILITIES) UNCOVERED STORAGE UNCOVERED FLEET PARKING STAFF PARKING POLICE IMPOUND SUBTOTAL EXIST (GEOR PHASE 1 PROGRAM SUMMARY EXTERIOR PROGRAM (WATER, SEWER, STREET) UNCOVERED STORAGE SPOILS/ORGANICS SUBTOTAL TOTAL EXIST (GEOR PARKING (FLEET & FACILITIES) UNCOVERED FLEET 9x20 10x30 15x45 FLEET MAINTENANCE PARKING STAFF TOTAL EXIST (GE INTERIOR PROGRAM (FLEET & FACILITIES) OFFICE HEALTH & WELLBEING (BREAKROOM / RECOVERY) MEETING SPACE SHOP OPERATIONS STORAGE BUILDING SUPPORT (LOCKER ROOM / BUILDING UTILITIES) SUBTOTAL EXIST (GEOR FLEE T M A I N T E N A N C E SPOILS SPOILS COVERED STORAGE UNCOVERED STORAGEUNCOVERED STORAGEUNCOVERED STORAGE VEHI C L E M A I N T E N A N C E P A R K I N G WASH RACKUNCOVERED STORAGE POLICE IMPOUND TUKWILA INTERNATIONAL BLVDSOUTH 112TH ST TUKWILA PUBLIC WORKS FACILITY: PHASING - PHASE 1 SITE TEST-TO-FIT FACILITIESSPOILSESTIMATED CONSTRUCTION COST - $5,800,000 • HEISER BUILDING T.I. - $4.4 MILLION • PERMANENT SITE STRUCTURES - $1.5 MILLION • SITE IMPROVEMENTS - $800K ESTIMATED SOFT COSTS - $2,800,000 THESE COSTS ARE TYPICALLY PAID FOR BY THE OWNER AND ARE IN ADDITION TO THE CONTRACTOR’S COSTS. THESE COSTS INCLUDE: • A/E FEES- ARCHITECT AND CONSULTANTS UNDER THE ARCHITECT’S CONTRACT. (11.5%) • ENGINEERING FEES AND STUDIES - OTHER PROJECT SPECIFIC CONSULTANTS NOT UNDER THE • ARCHITECT’S CONTRACT (EX: ENVIRONMENTAL IMPACT, GEOTECH, SURVEY, LOCATION WORK, ETC). (3.5%) • PERMITS AND FEES- INCLUDES MUP, BUILDING PERMITS, FIRE DEPARTMENT REVIEW, ETC. (2%) • COMMISSIONING- THIRD PARTY SYSTEM COMMISSIONING. (1%) • WA STATE SALES TAX. (10%) • FURNITURE, FIXTURES AND EQUIPMENT ALLOWANCE. (1.5%) • OWNER’S CONTINGENCY. (10%) ESTIMATED TOTAL PROJECT COST - $9,500,000 NOTE: CONSTRUCTION COSTS AND SOFT COSTS WILL BE MORE ACCURATE ONCE DESIGN PROGRESSES168 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 13 VEHICLE ACCESS FLEET MAINTENANCE OFFICE + SUPPORT FACILITIES SHOPS FACILITIES STORAGE SPOILS/ORGANICS FLEX/OVERNIGHT PARKING - - Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks 1/16" = 1'-0"9/19/2019 1:15:08 PMPD 1.2 TUKWILA PUBLIC WORKS 6/25/2019 Author Checker FACILITY TEST-TO-FIT 11231 E MARGINAL WAY S TUKWILA, WA 98168 PHASE 1 FLOOR PLAN - GEORGE LONG 1/16" = 1'-0"1 FIRST FLOOR PLAN - HEISER BUILDING - OPTION 2 - PHASE 1 1/16" = 1'-0"2 SECOND FLOOR PLAN - HEISER BUILDING - OPTION 2 - PHASE 1 PROGRAM (FLEET & FACILITIES) OFFICE HEALTH & WELLBEING (BREAKROOM / RECOVERY) MEETING SPACE SHOP OPERATIONS STORAGE BUILDING SUPPORT (LOCKER ROOM / BUILDING UTILITIES) TOTAL EXISTING AREA (GEORGE LONG) 2,645 SF 780 SF 240 SF 8,110 SF 3,450 SF 995 SF 16,220 SF PHASE 1 PROGRAM SUMMARY DELTA +3% +1% 0% +10% +14% +12% +10% REQUIRED AREA 1,810 SF 900 SF 375 SF 10,695 SF 4,770 SF 2,070 SF 20,620 SF PROVIDED AREA (HEISER) 1,865 SF 905 SF 375 SF 11,760 SF 5,420 SF 2,320 SF 22,645 SF EXISTING AREA (LONG ACRES) - - - - - - - 0 2' 4' 8'20'16' VEHICLE ACCESS FLEET MAINTENANCE OFFICE + SUPPORT FACILITIES SHOPS FACILITIES STORAGE SPOILS/ORGANICS FLEX/OVERNIGHT PARKING - - Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks 1/16" = 1'-0"9/19/2019 1:15:08 PMPD 1.2 TUKWILA PUBLIC WORKS 6/25/2019 Author Checker FACILITY TEST-TO-FIT 11231 E MARGINAL WAY S TUKWILA, WA 98168 PHASE 1 FLOOR PLAN - GEORGE LONG 1/16" = 1'-0"1 FIRST FLOOR PLAN - HEISER BUILDING - OPTION 2 - PHASE 1 1/16" = 1'-0"2 SECOND FLOOR PLAN - HEISER BUILDING - OPTION 2 - PHASE 1 PROGRAM (FLEET & FACILITIES) OFFICE HEALTH & WELLBEING (BREAKROOM / RECOVERY) MEETING SPACE SHOP OPERATIONS STORAGE BUILDING SUPPORT (LOCKER ROOM / BUILDING UTILITIES) TOTAL EXISTING AREA (GEORGE LONG) 2,645 SF 780 SF 240 SF 8,110 SF 3,450 SF 995 SF 16,220 SF PHASE 1 PROGRAM SUMMARY DELTA +3% +1% 0% +10% +14% +12% +10% REQUIRED AREA 1,810 SF 900 SF 375 SF 10,695 SF 4,770 SF 2,070 SF 20,620 SF PROVIDED AREA (HEISER) 1,865 SF 905 SF 375 SF 11,760 SF 5,420 SF 2,320 SF 22,645 SF EXISTING AREA (LONG ACRES) - - - - - - - 0 2' 4' 8'20'16' VEHICLE BAYS VEHICLE BAY MAC MACHINE SHOP TIRE STORAGE TIRE SHOP FACILITIES STORAGE WELDING EQUIP MAINT. SHOP FACILITIES PARTS MEETING SPACE FLEET STORAGE COMPRESSOR BUILDING SUPPORT VEHICLE ACCESS FLEET MAINTENANCE OFFICE + SUPPORT FACILITIES SHOPS MOTORCYCLE BAY FACILITIES STORAGE SPOILS/ORGANICS BUILDING SUPPORTOFFICE HEALTH/WELLNESS OFFICE BUILDING SUPPORT FLEX/OVERNIGHT PARKING BUILDING SUPPORT 7/2/2019 12:51:44 PM1/16" = 1'-0"1 FIRST FLOOR PLAN - HEISER BUILDING - OPTION 2 - PHASE 1 1/16" = 1'-0"2 SECOND FLOOR PLAN - HEISER BUILDING - OPTION 2 - PHASE 1 VEHICLE BAYS VEHICLE BAYS VEHICLE BAYSVEHICLE BAYSMACHINE SHOP FLEETS PARTSFLEETS STORAGEMACHINE SHOPTIRE STORAGE TIRE SHOP WELDING SURPLUS PARTS FACILITIES STORAGE FACILITIES PARTS EQUIP MAINT. SHOP HEALTH / WELLNESS LOCKER ROOMSOFFICE OFFICE MEETING SPACE STORAGE LOCKER ROOMS SPOILS ORGANICS TUKWILA PUBLIC WORKS FACILITY: PHASING - PHASE 1 TEST-TO-FIT HEISER T.I. ESTIMATED CONSTRUCTION COST - $4.4 MILLION • SEISMIC UPGRADES • HVAC UPGRADES • REQUIRED REPAIRS (ROOF, WALLS) • LOCKER ROOMS/OFFICES/MEETING • SHOP BUILD OUT • FIRE PROTECTION MODIFICATIONS • PLUMBING UPGRADES NOTE: CONSTRUCTION COSTS AND SOFT COSTS WILL BE MORE ACCURATE ONCE DESIGN PROGRESSES TENANT IMPROVEMENT TO RELOCATE GEORGE LONG SHOPS INTO THE HEISER BUILDING 169 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 14 TUKWILA PUBLIC WORKS FACILITY: PHASE 1 TI - 60% DESIGN PROGRAM/PLAN DN J G C A E WELDING SHOP MACHINE SHOP TIRE SHOP TIRE STORAGE CUSTODIAL / FACILITIES STORAGE FLEET OFFICE FACILITIES / EQUIPMENT MAINT VEHICLE MAINTENANCE COMPRESSOR VM MAINT STORAGEFIRE RISERFLEET PARTS 525 SF 170 SF FILE STOR CUSTODIAL OFFICE LUNCH / LRG MTG ADMIN W RR / LOCKER M RR / LOCKER LAUNDRY FLEET PARTS FLEET PARTS 8,445 SF (PROPOSED) 5,865 SF (EXISTING) +2,580 SF [+44%] VEHICLE MAINTENANCE VEHICLE MAINTENANCE COPY FLEET FLEX SPACE 1,385 SF (PROPOSED) VEHICLE MAINTENANCE 18 SF (PROPOSED) 640 SF (PROPOSED) 335 SF (EXISTING) +305 SF [+91%] 1,915 SF (PROPOSED) 1,440 SF (EXISTING) +475 SF [+33%]1,060 SF (PROPOSED) 1,225 SF (EXISTING) -165 SF [-13%] 670 SF (PROPOSED) 400 SF (EXISTING) +270 SF [+68%] 920 SF (PROPOSED) 1,082 SF (EXISTING) -162 SF [-15%] 690 SF (PROPOSED) 450 SF (EXISTING) +240 SF [+53%] 450 SF (PROPOSED) 285 SF (EXISTING) +165 SF [+58%] 180 SF (PROPOSED) 170 SF (EXISTING) +10 SF [+6%]510 SF (PROPOSED) 240 SF (EXISTING) +270 SF [+113%] 325 SF (PROPOSED) 445 SF (EXISTING) -120 SF [-27%] 315 SF (PROPOSED) 240 SF (EXISTING) +75 SF [+31%] 120 SF (PROPOSED) 80 SF (EXISTING) +40 SF [+50%] 40 SF (PROPOSED) 50 SF (EXISTING) -10 SF [-20%] 85 SF (PROPOSED) 190 SF (EXISTING) -105 SF [-55%] 285 SF (PROPOSED) 475 SF (EXISTING) -190 SF [-40%] LOBBY 95 SF (PROPOSED) 95 SF (EXISTING) 0 SF [0%]49' - 5" +/-23' - 1" +/-26' - 3" +/-17' - 11" +/-116' - 7" +/-SEE NOTE TO LEFT SEE NOTE TO LEFT SEE NOTE TO RIGHT SEE NOTE TO LEFT FAC SUPER 116 SF (PROPOSED) 120 SF (EXISTING) -4 SF [-3%] FAC FOREMAN 75 SF (PROPOSED) (E) SHARED OFFICE FAC TECH / HEAD CUST 115 SF (PROPOSED) 200 SF (EXISTING) 85 SF [-43%] LAUNDRY 15 SF (PROPOSED) KEY EQUIP 30 SF (PROPOSED) 13121110987654321 C E 8.1 26' - 3" +/-221' - 10" +/- RECORD / FILE STORAGE MEZZANINE STORAGE 565 SF (PROPOSED) SURPLUS PARTS STORAGE 7' - 8" +/-20' - 2" +/-20' - 0" +/-20' - 0" +/-20' - 1" +/-20' - 1" +/-20' - 1" +/-30' - 3" +/-3' - 8" +/- 18' - 9" +/-20' - 1" +/-18' - 11" +/- 2' - 2" +/- 655 SF (PROPOSED) 1,152 SF (EXISTING) -497 SF [-43%] 720 SF (PROPOSED) 450 SF (EXISTING) +270 SF [+60%] GENDER NEUTRAL WC 45 SF (PROPOSED) 35 SF (EXISTING) +10 SF [+29%] VEHICLE ACCESS OFFICE + SUPPORT SHOPS STORAGE FLEETS & FACILITIES BUILDING PROGRAM SUMMARY PROPOSED AREA 15,053 SF 3,206 SF 2,630 SF 3,630 SF 24,519 SF EXISTING AREA (GEORGE LONG) 10,322 SF 2,345 SF 2,463 SF 1,744 SF 16,874 SF DELTA +4,731 SF [+46%] +861 SF [+37%] +167 SF [+7%] +1,886 SF [108%] +7,645 SF [+45%] FLEETS FACILITIES / CUSTODIAL SHARED (MEETING / LOCKER ROOM / MEZZANINE STORAGE) CIRCULATION / MECHANICAL TOTAL LEGEND CIRCULATION / MECHANICAL Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks NOT FOR CONSTRUCTIONAs indicated 5/1/2020 10:17:57 AMA2.7 TUKWILA PUBLIC WORKS 05/01/ 20 MF AH FLEETS & FACILITIES BUILDING 60% DESIGN 11210 TUKWILA INTERNATIONAL BLVD TUKWILA, WA 98168 PROGRAM COMPARISION FIRST FLOOR PLAN - PROGRAM AREA 3/32" = 1'-0"2 SECOND FLOOR PLAN - PROGRAM AREA WELDING SHOP MACHINE SHOP AINTENANCE COMPRESSOR VM MAINT STORAGE 525 SF 170 SF OSED) NG) 4%] VEHICLE MAINTENANCE 1,060 SF (PROPOSED) 1,225 SF (EXISTING) -165 SF [-13%] 670 SF (PROPOSED) 400 SF (EXISTING) +270 SF [+68%] SEE NOTE TO LEFT VEHICLE ACCESS OFFICE + SUPPORT SHOPS STORAGE FLEETS & FACILITIES BUILDING PROGRAM SUMMARY PROPOSED AREA 15,053 SF 3,206 SF 2,630 SF 3,630 SF 24,519 SF EXISTING AREA (GEORGE LONG) 10,322 SF 2,345 SF 2,463 SF 1,744 SF 16,874 SF FLEETS FACILITIES / CUSTODIAL SHARED (MEETING / LOCKER ROOM / MEZZANINE STORAGE) CIRCULATION / MECHANICAL TOTAL LEGEND CIRCULATION / MECHANICAL 0 16'8'1' 4'2'170 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 15 TUKWILA PUBLIC WORKS FACILITY: PHASE 1 TI - 90% DESIGN PROGRAM/PLAN DN J G C A E WELDING SHOP MACHINE SHOP TIRE SHOP TIRE STORAGE CUSTODIAL / FACILITIES STORAGE FLEET OFFICE FACILITIES / EQUIPMENT MAINT VEHICLE MAINTENANCE COMPRESSOR VM MAINT STORAGEFIRE RISERFLEET PARTS 525 SF 170 SF FILE STOR CUSTODIAL OFFICE LUNCH / LRG MTG ADMIN W RR / LOCKER M RR / LOCKER LAUNDRY FLEET PARTS FLEET PARTS 8,445 SF (PROPOSED) 5,865 SF (EXISTING) +2,580 SF [+44%] VEHICLE MAINTENANCE VEHICLE MAINTENANCE COPY FLEET FLEX SPACE 1,385 SF (PROPOSED) VEHICLE MAINTENANCE 18 SF (PROPOSED) 640 SF (PROPOSED) 335 SF (EXISTING) +305 SF [+91%] 1,915 SF (PROPOSED) 1,440 SF (EXISTING) +475 SF [+33%]1,060 SF (PROPOSED) 1,225 SF (EXISTING) -165 SF [-13%] 670 SF (PROPOSED) 400 SF (EXISTING) +270 SF [+68%] 920 SF (PROPOSED) 1,082 SF (EXISTING) -162 SF [-15%] 690 SF (PROPOSED) 450 SF (EXISTING) +240 SF [+53%] 450 SF (PROPOSED) 285 SF (EXISTING) +165 SF [+58%] 180 SF (PROPOSED) 170 SF (EXISTING) +10 SF [+6%]510 SF (PROPOSED) 240 SF (EXISTING) +270 SF [+113%] 325 SF (PROPOSED) 445 SF (EXISTING) -120 SF [-27%] 315 SF (PROPOSED) 240 SF (EXISTING) +75 SF [+31%] 120 SF (PROPOSED) 80 SF (EXISTING) +40 SF [+50%] 40 SF (PROPOSED) 50 SF (EXISTING) -10 SF [-20%] 85 SF (PROPOSED) 190 SF (EXISTING) -105 SF [-55%] 285 SF (PROPOSED) 475 SF (EXISTING) -190 SF [-40%] LOBBY 95 SF (PROPOSED) 95 SF (EXISTING) 0 SF [0%]49' - 5" +/-23' - 1" +/-26' - 3" +/-17' - 11" +/-116' - 7" +/-SEE NOTE TO LEFT SEE NOTE TO LEFT SEE NOTE TO RIGHT SEE NOTE TO LEFT FAC SUPER 116 SF (PROPOSED) 120 SF (EXISTING) -4 SF [-3%] FAC FOREMAN 75 SF (PROPOSED) (E) SHARED OFFICE FAC TECH / HEAD CUST 115 SF (PROPOSED) 200 SF (EXISTING) 85 SF [-43%] LAUNDRY 15 SF (PROPOSED) KEY EQUIP 30 SF (PROPOSED) 13121110987654321 C E 8.1 26' - 3" +/-221' - 10" +/- RECORD / FILE STORAGE MEZZANINE STORAGE 565 SF (PROPOSED) SURPLUS PARTS STORAGE 7' - 8" +/-20' - 2" +/-20' - 0" +/-20' - 0" +/-20' - 1" +/-20' - 1" +/-20' - 1" +/-30' - 3" +/-3' - 8" +/- 18' - 9" +/-20' - 1" +/-18' - 11" +/- 2' - 2" +/- 655 SF (PROPOSED) 1,152 SF (EXISTING) -497 SF [-43%] 720 SF (PROPOSED) 450 SF (EXISTING) +270 SF [+60%] GENDER NEUTRAL WC 45 SF (PROPOSED) 35 SF (EXISTING) +10 SF [+29%] VEHICLE ACCESS OFFICE + SUPPORT SHOPS STORAGE FLEETS & FACILITIES BUILDING PROGRAM SUMMARY PROPOSED AREA 15,053 SF 3,206 SF 2,630 SF 3,630 SF 24,519 SF EXISTING AREA (GEORGE LONG) 10,322 SF 2,345 SF 2,463 SF 1,744 SF 16,874 SF DELTA +4,731 SF [+46%] +861 SF [+37%] +167 SF [+7%] +1,886 SF [108%] +7,645 SF [+45%] FLEETS FACILITIES / CUSTODIAL SHARED (MEETING / LOCKER ROOM / MEZZANINE STORAGE) CIRCULATION / MECHANICAL TOTAL LEGEND CIRCULATION / MECHANICAL Date: Revisions: Drawn by: Checked: Scale: No.Date Remarks As indicated 8/26/2020 11:28:05 AMA2.7 TUKWILA PUBLIC WORKS 08/26/20 MF AH FLEET & FACILITIES BUILDING 100% DESIGN 11210 TUKWILA INTERNATIONAL BLVD TUKWILA, WA 98168 PROGRAM COMPARISION FIRST FLOOR PLAN - PROGRAM AREA 3/32" = 1'-0"2 SECOND FLOOR PLAN - PROGRAM AREA WELDING SHOP MACHINE SHOP AINTENANCE COMPRESSOR VM MAINT STORAGE 525 SF 170 SF OSED) NG) 4%] VEHICLE MAINTENANCE 1,060 SF (PROPOSED) 1,225 SF (EXISTING) -165 SF [-13%] 670 SF (PROPOSED) 400 SF (EXISTING) +270 SF [+68%] SEE NOTE TO LEFT VEHICLE ACCESS OFFICE + SUPPORT SHOPS STORAGE FLEETS & FACILITIES BUILDING PROGRAM SUMMARY PROPOSED AREA 15,053 SF 3,206 SF 2,630 SF 3,630 SF 24,519 SF EXISTING AREA (GEORGE LONG) 10,322 SF 2,345 SF 2,463 SF 1,744 SF 16,874 SF FLEETS FACILITIES / CUSTODIAL SHARED (MEETING / LOCKER ROOM / MEZZANINE STORAGE) CIRCULATION / MECHANICAL TOTAL LEGEND CIRCULATION / MECHANICAL 0 16'8'1' 4'2'171 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 16 TUKWILA PUBLIC WORKS FACILITY: PHASE 1 TI - LOCKER ROOM172 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 17 TUKWILA PUBLIC WORKS FACILITY: PHASE 1 TI - BREAK ROOM/CONFERENCE 173 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 18 TUKWILA PUBLIC WORKS FACILITY: : PHASE 1 TI - VEHICLE MAINTENANCE174 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY STUDY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 19 TUKWILA PUBLIC WORKS FACILITY: PHASE 1 TI - COST PLAN UPDATE Tukwila Public Works - Fleet Facilities BldgTukwila Public Works - Fleet Facilities BldgTukwila Public Works - Fleet Facilities BldgTukwila Public Works - Fleet Facilities Bldg 8/27/2020 Scope Description Budget Classification Construction Cost Cost Why Improved seismic performance, upgrades for occupant and environmental health & safety Cost $278,613 Why Improved operational efficiencies and security Cost $32,180 Why (E) below grade piping condition unknown, code required infrastructure Cost $43,010 Why (E) below grade lines in need of replacement Cost $596,160 Why Ensure building is fully functional and operational to support Emergency OperationsAlternate $4,928,268 $4,928,268 TI Project+ Seismic upgrades to existing building to meet Life Safety occupancy + HVAC upgrades, Vehicle Exhaust, Weld Exhaust, Controls + Plumbing, Trench Drains, Oil/Water separator, Emergency Eye/Shower + Interior Offices/Locker Rooms/Showers + Electrical: Fire alarm, lighting, outlets + Fire Protection 60% Design Requiredx Requiredx $278,613 Requiredx $32,180 Previously budgeted as "Operations and Maintenance" expense Requiredx $596,160 $43,010Base ScopeSANITARY SEWER+ Replace below slab sanitary sewer line from locker rooms to exterior 'Y' connection north of existing building below asphalt + Sawcut existing concrete slab, excavate, and pour back concrete Scope add/revision during design.RequiredWATER LINE REPLACE+ Provide new backflow preventer at water line entry + Provide overhead pipe from water service entry to reduce pressure valve in paint booth addition. + Provide new piping to hose bibs, abandon (e) below grade water pipes Scope add/revision during design.OVERHEAD DOORS+ Replace existing overhead doors in poor condition + Provide motorized openers at all OH doors Previously budgeted as "Operations and Maintenance" expense Scope Additionsx Construction Costs $5,878,230EMERGENCY GENERATOR+ Provde 450kw emergency generator to provide backup power for building operations 175 TUKWILA PUBLIC WORKS CONSOLIDATED FACILITY | TRANSPORTATION & INFRASTRUCTURE COMMITTEE | 08 31 2020 | 20 TUKWILA PUBLIC WORKS FACILITY: PHASE 1 TI - SCHEDULE ID Task Name Duration Start Finish 1 City of Tukwila Public Works Design Schedule 503 days Tue 10/8/19 Wed 10/13/21 2 Master Plan Presentation 40 days Tue 10/8/19 Fri 12/6/19 11 Owner Performed Work 174 days Mon 12/9/19 Fri 8/14/20 17 Design and Documentation 205 days Fri 12/6/19 Mon 9/28/20 46 Bidding 37 days Wed 9/23/20 Mon 11/16/20 54 Construction 149 days Mon 11/16/20 Tue 6/29/21 60 Closeout 75 days Wed 6/30/21 Wed 10/13/21 Design and Documentation Bidding Construction W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Aug 23, '20 Aug 30, '20 Sep 6, '20 Sep 13, '20 Sep 20, '20 Sep 27, '20 Oct 4, '20 Oct 11, '20 Oct 18, '20 Oct 25, '20 Nov 1, '20 Nov 8, '20 Nov 15, '20 Nov 22, '20 Nov 29, '20 Dec 6, '20 Dec 13, '20 Dec 20, '20 Dec 27, '20 Jan 3, '21 Jan 10, '21 Jan 17, '21 Jan 24, '21 Jan 31, '21 Feb 7, '21 Feb 14, '21 Feb 21, '21 Feb 28, '21 Mar 7, '21 Tukwila PW Consolidated Facility - Phase 1 Construction Closeout T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Mar 14, '21 Mar 21, '21 Mar 28, '21 Apr 4, '21 Apr 11, '21 Apr 18, '21 Apr 25, '21 May 2, '21 May 9, '21 May 16, '21 May 23, '21 May 30, '21 Jun 6, '21 Jun 13, '21 Jun 20, '21 Jun 27, '21 Jul 4, '21 Jul 11, '21 Jul 18, '21 Jul 25, '21 Aug 1, '21 Aug 8, '21 Aug 15, '21 Aug 22, '21 Aug 29, '21 Sep 5, '21 Sep 12, '21 Sep 19, '21 Sep 26, '21 Oct 3, '21 Oct 10, '21 Oct 17, '21 Oct 24, '21 Oct 31, '21 Nov 7, '21 Tukwila PW Consolidated Facility - Phase 1176 City of Tukwila Facilities Needs Assessment and Feasibility Study Phase 4 Steering Committee Recommendations December 14, 2015 Committee of the Whole 1177 2 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 Introduction 2 Tonight’s Presentation ►Process Refresher ►Phase 1 Refresher ►Phase 2 Refresher ►Phase 3 –Steering Committee Recommended Alternatives ►Phase 4 ►Steering Committee Recommended Funding and Phasing ►Community Outreach and Engagement ►What’s next?178 3 Process 3 Community Outreach and Engagement Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 179 4 Facility Space Needs 4 Phase 1 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 0 50,000 100,000 150,000 200,000 250,000 144,044 sq. ft. 205,237 sq. ft. 235,567 sq. ft. EXISTINGSPACE 2013 NEEDS 2040 NEEDS180 5 Assessment of Existing Facilities Phase 2 5 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 6300 Bldg TCCGolfMaint. Fire St #53George Long Minkler Shop Fire Stn #51 Fire Stn #52 Fire Stn #54 maintainremodel -12 -12 -12 +7 +5 +9 -13 -14 -15 Unsuitable condition Suitable condition +1 +5 +7 +9-12-13-14-15 rebuild City Hall 181 6 Steering Committee Recommended Alternatives Phase 3 6 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 Public Safety Building $25.5 M Police & Courts combined in a new location. City Shops Facility $26.2 M Both current shops demolished and new shops combined on a new location, either concurrently with or after the Public Safety Building City Hall Campus $18.1 M 6300 to be demolished and City Hall expanded on current location after move-in to new Public Safety Building. 20162018202020222024202620282030203220342036203820402019 move-in 2034 move-in 2036 move-in 2019 move-in 2022 move-in @ p G182 7 Steering Committee Recommended Funding and Financing Phase 4 7 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 183 8 Recommended Community Outreach ►Road Show TIBAC, COPCAB, Tukwila Rotary, Southcenter Rotary, Southwest King Chamber of Commerce, Tukwila Historical Society, Equity and Diversity Commission, Library Advisory Board, Arts Commission, Parks Commission and Sustain the Pool ►Other Draft Report and Summary on website Narrated video of Road Show on website and TukTV TukTV Tukwila, Your Community episode Reporter –City Pages E-Hazelnut Mailing Open House Social media Internal communications Phase 4 8 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015184 9 What’s next? Phase 4 9 NEXT STEP TARGET DATE Council review of Steering Committee Recommendations December 14, 2015 Public Outreach January/February 2016 Council Plan Adoption March 2016 Council Selection of Funding Program March 2016 Pursue Funding Program April 2016 Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015 185 1010 Questions? Facilities Needs Assessment and Feasibility Study STEERING COMMITTEE RECOMMENDATIONS December 14, 2015186 The City of Tukwila has developed the Public Safety Plan to address the needs of the City’s first responders. The Public Safety Plan consists of: • A voter-approved Public Safety Bond to pay for critical needs of first responders. • A consolidated shops facility, paid for through an equal contribution of existing General and Utility Funds. Public Safety Bond On the November 8, 2016 General Election ballot, the voters of Tukwila will be asked to approve a bond to pay for: • Replacement of three seismically-deficient fire stations (Stations 51, 52 and 54); • Guaranteed funding for fire equipment and apparatus – such as fire trucks and other life/safety tools – for the life of the 20-year bond; and • Construction of a Justice Center to house the Tukwila Police Department and Tukwila Municipal Court. Sixty percent of the votes cast must be in favor of the measure for it to pass. The Public Safety Bond would cost a homeowner $0.47 per $1,000 of assessed value. (Your home’s assessed value can be found on the King County Assessor’s home page.) As an example, for an owner of a home assessed at $250,000, the bond would cost an average of $116 per year (250 X $0.47). To calculate the cost per your assessed value, do the following computation: Consolidated Shops Facility Public Works provides critical first response to a variety of issues. When roads need to be closed, water mains break, and Police and Fire need help with emergencies, Public Works staff are who is called upon. Currently, the City shops are housed in two locations, both of which are in the flood plain and seismically unsafe. As such, the Public Safety Plan calls for the construction of a new, consolidated Public Works shops facility, paid for equally by the General Fund through efficiencies, as well as the Utility Funds within the existing rate structure. CITY OF TUKWILA Your average cost per year for the Public Safety Bond Assessed value 1,000Divided by = X X times $0.47 = About Tukwila’s Public Safety Plan 187 FREQUENTLY ASKED QUESTIONS Where can I get more information? Visit TukwilaWA.gov/PublicSafetyPlan to read more details about the plan. You can also email PublicSafetyPlan@TukwilaWA.gov with any questions. Tours of Tukwila’s public safety buildings can be scheduled by calling 206-433-1850. Why does the City need this Public Safety Plan? The City has been investigating how to ensure full funding for fire service in the City of Tukwila, as well as replacing the seismically unsound and inefficient public safety facilities that include three fire stations and the two Public Works shops. In the event of a major earthquake, flood or other disaster, it is critical that these first responders are able to deploy throughout the City. Additionally, these aging facilities were constructed at a time when the City had less than one-fifth of its current population and required significantly less services and employees to meet the community’s needs. Finally, modern standards and mandates have made the existing fire stations, City shops, Municipal Court and Police Department obsolete. What are the proposed levels of service in the public safety plan? The plan sustains the current level of services for Police, Fire and Public Works for the near term, and allows for growth over the life of the bond. For instance, additional fire apparatus is included in future years to address expected growth in the community. Facilities will be constructed in such a way that they can be easily and economically expanded when the need arises. What is the cost of the different components of the Public Safety Plan? Fire Station 51 ........................................$10 million Fire Station 52 ..........................................$5 million Fire Station 54 ..........................................$6 million Fire Equipment & Apparatus ...............$21 million Justice Center ........................................$26 million Consolidated City Shops......................$26 million Detailed cost breakdowns – including pricing information on land acquisition, engineering, construction, contingency and more – can be found at TukwilaWA.gov/PublicSafetyPlan. Who pays for the Public Safety Plan? The City will use equal contributions of existing General Fund and utility funds within the existing rate structure to pay for the cost associated with the consolidated Public Works shops. The Public Safety Bond will be paid by property owners and, just like the current breakdown of existing property taxes, more than 80% will be paid by commercial/industrial property owners. Home- owners will pay less than 20% of the overall cost of the bond. Why fund fire apparatus and equipment in the bond? Fire trucks and equipment are expensive and must be purchased on a regular schedule to provide the most benefit to the community and be outfitted with key technologies. Including these critical life/safety components in a public safety bond ensures they are fully-funded for twenty years and are not subject to downturns in the economy similar to what the region faced in 2008. The total cost of fire equipment and apparatus is $21 million over the next twenty years. The full purchase schedule can be found at TukwilaWA.gov/PublicSafetyPlan. Have locations been determined for these new public safety facilities? The only determination for the siting of a new facility is that we know that Fire Station 51 will move to a location at Southcenter Parkway & South 180th, per the Tukwila South Development Agreement. No other decisions have been made regarding siting of the other public safety facilities. The City will engage in a community siting process at the appropriate time. How is the Public Works Shops being funded? Half of the funding comes from the Water, Sewer and Surface Water funds, which must be spent on utility-related issues. These costs can be absorbed within the existing rate structure as reserves in the funds rise and other bonds from previous projects are paid back. Debt service payments for the shops represents less than 6% of all funds on an annual basis. The other half of the funding for the shops will come from the City’s General Fund, achieved through efficiencies and continuing today’s level of service. What guarantees are in place to ensure that the City will use this funding for what it says it will? State law RCW 84.52.056 restricts how voter-approved bonds can be spent. They can only be spent on what is included in the ballot. Should the City for some reason not need the full amount listed in the ballot title, the City Council has the ability to either not bond the full amount, or use any excess bond funds to payoff (redeem) the bonds early (before the maturity date). In addition, the City Council created a bond oversight committee that will assist the City Council in its oversight role. What role will the community have in the siting and design of these buildings? The City Council and Administration share a desire for robust public engagement around siting and design of the three fire stations, the Justice Center housing the Tukwila Police Department and Municipal Court, and the Public Works Shops. The City will create a community advisory council on siting and design, and hold meetings, charettes and other visioning events. 188 UPDATED: 12/08/15 City of Tukwila INVESTING IN TUKWILA: ESSENTIAL GOVERNMENT SERVICES FACILITIES PLAN 2015-2040 This Facilities Plan for Essential Government Services provides a roadmap for the City of Tukwila to build the necessary facilities to ensure long-term financial sustainability, optimize organizational efficiencies, and maximize public safety. The process was led by a Steering Committee comprised of community volunteers, City Council members, and City administrators, with architectural and public finance consulting support. The resulting plan is based on a robust facility needs assessment including an estimate of current and future facility needs and a defensible assessment of current facility condition and suitability. It includes a destination, that is, a planning-level description of the City’s facilities needs to 2040 as well as potential funding pathways the City can pursue. The report provides an important knowledge basis and flexible planning tools to help the City and the community move forward to address the facility needs for essential government services in a manner that reflects Tukwila’s vision and goals. PHASE 1: FACILITY SP ACE NEEDS Using contemporary space assumptions, Tukwila’s current essential government services need roughly 205,237 square feet of space to support efficient operations. This includes general office space, shops, fire stations, and public safety facilities. Using a conservative estimate of future population and employment growth, Tukwila is projected to need 235,567 square feet of space by 2040, with the greatest growth occurring in public safety, fire stations, and shops. Current facilities are undersized for current needs, and projected to be even more undersized in the future. FIGURE 1: TUKWILA SPACE NEEDS PHASE 2: ASSESSMENT OF EXISTING FACILITI ES The City’s existing facilities were evaluated by outside experts according to criteria established by the Steering Committee and staff, and reflecting the priorities set out in the City’s Strategic Plan. Based on the cumulative scores across the criteria the Steering Committee made recommendations on whether the facilities should be replaced, remodeled, or maintained for continued City use. FIGURE 2: FACILITY ASSESSMENT OF SUITABILITY RESULTS City Hall Unsuitable conditionSuitable condition+1 Golf Maintenance +5 Fire Station #53 +7 Tukwila Community Center +9 Fire Station #54 -12 Fire Station #52 6300 Building -13 Fire Station #51 -14 Minkler Shop -15 George Long Shop 189 Based on the cumulative scores across the criteria, the Parks and Golf Maintenance building, the Tukwila Community Center, and Fire Station #53 all had attributes and strengths that outweighed any deficiencies, making these facilities suitable for maintaining. Both shops (Minkler and George Long), the 6300 Building, and the other three Fire Stations all had deficiencies that outweighed their attributes, making these facilities candidates for demolition and replacement. City Hall had both deficiencies and attributes that balanced one another. The analysis demonstrated a number of significant deficiencies in City Hall’s design and systems, however the high quality of original construction, familiarity of the public with its location, and the distinctive architectural character led the Committee to recommend City Hall be remodeled rather than demolished and replaced. PHASE 3: RECOMMENDATIONS Alternatives were developed based on the condition and suitability of existing buildings, a study of the ideal adjacencies among workgroups, and additional criteria set forth in discussions with the public, City Council, the Steering Committee, and staff. The Steering Committee recommendations prioritize public safety functions early in the project phasing and keep City Hall functions at the existing site. Siting considerations are recommended to preserve the long-term ability for expansion. The Steering Committee also favors a schedule that is as quick as possible, provided effective managerial oversight and financial feasibility, to minimize risk associated with rising construction costs and interest rates FIGURE 3: PREFERRED ALTERNATIVE PHASE 4: FUNDING AND FINANCING The Plan represents a 25 year strategy for meeting the City’s facility needs for essential government services. The Plan offers funding and financing options, and is flexible enough to accommodate changes in city services and circumstances. Four funding and financing alternatives were explored for their overall impact to the City’s planned capital facility projects, impact on debt capacity, impacts to rate payers, and overall costs. The financial analysis demonstrates the need for debt to finance some or all of the major facility projects, and likely additional revenue generation to cover debt obligations. 63-20 financing is also a feasible option for the Public Safety Building or City Shops Facility. The final Plan provides a funding decision tree to guide the City’s implementation of this facilities plan. Staff recommend funding and financing this Facilities Plan through a mix of UTGO (voted) bonds for the public safety building, 63-20 financing for the city shops facility, and LTGO (councilmanic) bonds for the City Hall improvements. FIGURE 4: STEERING COMMITTEE RECOMMENDED FUNDING PLAN 190 Transportation & Infrastructure Committee Minutes .......................................................................................... August 17, 2020 D. Public Safety Plan – Public Works Shops History Committee members reviewed the history of the Public Works Shop project, including siting and acquisition, funding, master planning, and Council decision points. The Council approved moving forward on Phase 1 in December 2019, and staff intends to return with 90% design and cost estimates in September. The Committee will continue discussion of the project’s budget at a special meeting on August 31, 2020. Item(s) needing follow-up Links to listed PowerPoint presentations and reports, Update on D-20 Financing and sale of properties, Status of Minkler Shops Committee Recommendation Return to Committee. The meeting adjourned at 6:52 p.m. Committee Chair Approval Minutes by LH, reviewed by GL 191 City of Tukwila City Council Transportation & Infrastructure Committee Special Meeting Minutes August 31, 2020 – 5:30 p.m. – Electronic Meeting due to COVID-19 Emergency Councilmembers Present: Cynthia Delostrinos Johnson, Chair; Verna Seal, Kate Kruller Staff Present: Allan Ekberg, David Cline, Hari Ponnekanti, Vicky Carlsen, Tony Cullerton, Han Kirkland, Gail Labanara, Bryan Still, Garron Herdt, and Henry Ancira Guests: Adam Hutschreider, Justine Kim, Emily Moon, Steve Goldblatt, PMQA Chair Delostrinos Johnson called the meeting to order at 5:30 p.m. I. BUSINESS AGENDA A. Public Safety Plan – Public Works Shops Budget – Part 2 of 2 Staff asked Committee for reaffirmation of going-out-to-bid with the expected bid results received by the first week of November. Also discussed the approval process for the proposed finance plan and will forward Parts 1 and 2 to the 09/14/2020 Committee of the Whole. Committee reviewed the 90% design and scope for Phase 1 tenant improvements and seismic upgrades. Staff stated that the project is on budget, on schedule, and reaffirmed with the Committee that the project is set to go out to bid. The next decisions for the Council are to review the bids in late October or early November as well as determining the financing plan. Committee members requested a full a presentation of Parts 1 and 2 be presented to the full Council at the 9/14/2020 Committee of the Whole. The presentation would provide the full Council with an update on progress to date and financing options to prepare for the Council's decision in November on the tenant improvement contract and financing. Item(s) needing follow-up Committee requested that the Finance Director include in a memo on the City’s debt service schedule and the City’s current bond capacity for the 9/14/20 C.O.W. Committee Recommendation Forward presentation to C.O.W. on 9/14/20 for full Council discussion. The meeting adjourned at 6:32 p.m. CDJ Committee Chair Approval Minutes by HP, reviewed by GL 192