HomeMy WebLinkAboutTIS 2024-05-21 Item 2H - Resolution - 2025-2030 Transportation Improvement ProgramCity of Tukwila Thomas McLeod, Mayor INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Services Committee FROM: Hari Ponnekanti, Public Works Director / City Engineer BY: Cyndy Knighton, Senior Program Manager CC: Mayor McLeod DATE: May 17, 2024 SUBJECT: Resolution for Six -Year Transportation Improvement Program (2025 - 2030) ISSUE Approve a Resolution adopting the annual update of the Six -Year Transportation Improvement Program for 2025 - 2030. BACKGROUND The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of Washington (RCW) 35.77.010. The TIP is adopted by resolution after a public hearing at the local agency level and incorporated into regional and state TIPs. The TIP is primarily a financial planning document for projects competing for grants. Any project submitted for federal grant funding must be included in the local, regional, and state adopted TIPs. The TIP is a rolling plan showing various funding sources: grants, developer, and local funds. Projects "roll" as funds or stages occur (design report, final design, and construction). Tukwila's Six Year TIP and the Capital Improvement Program (CIP) list many of the same transportation - related projects. The TIP generally lists only those transportation -related projects planned within the next six years that are deemed regionally significant or that have grant funding awarded or expected. ANALYSIS The attached spreadsheet is the "Draft" 2025 - 2030 TIP and was created by modifying the 2024 - 2029 TIP to add or remove projects and adjust project costs. No prioritization was assigned, and the list of projects is presented in alphabetical order. Prioritization of projects is reflected in the current CIP. No projects were removed. Six new projects were added, all but one fully funded with recently awarded grants. Added: Funding Source 42nd Avenue S Bikeway 100% Grant Funded (Sound Transit) Boeing Access Road Overlay 100% Grant Funded (Federal) Interurban Avenue S Overlay 100% Grant Funded (Federal) Orillia Road S Overlay 100% Grant Funded (Federal) S Ryan Way City, private, and potential grants Southcenter Blvd Bikeway and Ped Xing Upgrades 100% Grant Funded (Sound Transit) FINANCIAL IMPACT None. RECOMMENDATION Council is being asked to approve the Resolution for the 2025 - 2030 Six -Year Transportation Improvement Program and consider this item at a Public Hearing at the June 10, 2024, Committee of the Whole and subsequent June 17, 2024, Regular Meeting. ATTACHMENTS: • Draft Resolution • Draft 2025-2030 TIP Summary • 2025-2030 Draft Transportation Improvement Program • Current Adopted 2024-2029 TIP 115 DRAFT A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR TRANSPORTATION IMPROVEMENT PROGRAM (2025- 2030), AND DIRECTING THE SAME TO BE FILED WITH THE STATE SECRETARY OF TRANSPORTATION AND THE TRANSPORTATION IMPROVEMENT BOARD. WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the City Council of the City of Tukwila has previously adopted a Transportation Improvement Program and thereafter periodically modified said Transportation Improvement Program by resolution; and WHEREAS, the City Council has reviewed the work accomplished under said program, determined current and future City street and arterial needs and, based upon these findings, has prepared a Six -Year Transportation Improvement Program for the ensuing six calendar years (2025-2030); and WHEREAS, on June 10, 2024, a public hearing was held regarding the City's Six - Year Transportation Improvement Program; NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, HEREBY RESOLVES AS FOLLOWS: Section 1. Program Adopted. A Six -Year Transportation Improvement Program for the calendar years 2025 to 2030, attached hereto as Exhibit A, is hereby adopted. Section 2. Filing of Program. The City Clerk is hereby authorized and directed to file a copy of this resolution, together with the exhibit attached hereto, with the Secretary of Transportation and the Transportation Improvement Board of the State of Washington 116 PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at a Regular Meeting thereof this day of , 2024. ATTEST/AUTHENTICATED: Andy Youn, CMC, City Clerk Mohamed Abdi, Council President APPROVED AS TO FORM BY: Filed with the City Clerk: Passed by the City Council: Resolution Number: Office of the City Attorney Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2025 to 2030 117 DRAFT 2025 - 2030 TIP SUMMARY 2023-2028 CIP Sheet PROJECT TITLE Project Costs in Thousands of Dollars Funding Sources Unsecured 2025 2026 2027 2028 2029 2030 TOTAL Federal State/TIB City/Local Grant City* 9 42nd Avenue S Bridge Replacement 200 1,800 19,000 10,000 0 0 31,000 13,500 18,400 1,000 1,400 NEW 42nd Avenue S Bikeway 55 295 0 0 0 0 350 1,895 500 1,895 500 5 46th Avenue Safe Routes to School 0 250 75 2,070 0 0 2,395 2,060 520 2,060 410 10 Allentown Truck Reroute Project 10 0 0 0 0 0 10 10 14 ADA Improvements 100 100 100 100 100 100 600 600 600 20 APE/Minkler Blvd Intersection 220 1,800 0 0 0 0 2,020 1,440 580 1,440 360 22 APE/Industry Drive Intersection 0 170 1,750 0 0 0 1,920 1,530 390 1,530 220 13 Annual Bridge Inspections and Repairs 215 220 230 235 240 240 1,380 1,380 1,380 12 Annual Overlay and Repair Program 2,500 2,500 2,500 2,500 2,500 2,500 15,000 15,000 15,000 15 Annual Traffic Signal Program 130 130 130 150 160 160 860 860 860 NEW Boeing Access Road Overlay 564 3,426 0 0 0 0 3,990 3,990 - 25 E Marginal Way S (BAR - S 112th St) 0 0 250 900 3,000 0 4,150 2,300 1,850 2,300 1,850 NEW Interurban Avenue S Overlay 0 397 4,561 0 0 0 4,958 4,958 - Keeping South King County Moving with TDM 235 260 260 260 130 0 1,145 1,880 840 6 Macadam Road S Complete Streets Project 0 0 300 200 3,100 0 3,600 3,240 360 3,240 360 NEW Orillia Road S Overlay 0 105 1,204 0 0 0 1,309 1,309 18 S 119th St Pedestrian Bridge Painting 0 200 0 0 0 0 200 200 200 23 S 133rd St/SR 599 Southbound Intersection 0 0 0 0 550 2,700 3,250 1,620 1,630 1,620 1,630 21 S 144th St Bridge Sidewalks 0 579 2,690 0 0 0 3,269 2,802 467 2,302 388 4 S 152nd Street Safe Routes to School 350 4,225 0 0 0 0 4,575 2,140 2,435 2,140 2,085 NEW S Ryan Way (pending planning level estimate) 400 900 9,200 0 0 0 10,500 8,080 2,420 8,080 2,420 - South King County Regional TDM 130 130 159 159 159 159 896 1,000 106 50 636 NEW Southcenter Blvd Bikeway and Ped Xing Upgrade: 65 325 0 0 0 0 390 390 19 Southcenter Blvd/65th Avenue S Signal 1,182 0 0 0 0 0 1,182 280 187 - PROJECTS REVISED FROM 2024-2029 TIP 47 47 47 47 47 45 280 94 TOTAL 6,403 17,859 42,456 16,621 9,986 5,904 99,229 27,559 45,065 30,642 29,670 28,263 PROJECTS REVISED FROM 2024-2029 TIP New 42nd Avenue S Bikeway Boeing Access Road Overlay Interurban Avenue S Overlay Orillia Road S Overlay S Ryan Way Southcenter Blvd Bikeway and Ped Xing Upgrades Deleted/Completed: none * Unsecured City funding includes all funds necessary outside of the current biennial budget cycle May 14, 2024 118 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title Amendment ___A Resolution No. Improvement Type c — ,� Total Length Environmental Type RW Required D. Road Name or Number m 0 E. Begin & End Termini w. o. F. Project Description G. Structure ID c a N 05 / 1037(004) TUK-62 06/10/24 6/17/24 11 0.100 DCE No 42nd Ave S Bridge Replacement N 42nd Ave S over the Duwamish River Interurban Ave S to Northern end of bridge Replace the existing 42nd Ave S steel truss bridge. The replacement will require preliminary engineer design, right-of-way, and construction phases. The new structure will meet current road and bridge design standards. The replacement structure configuration will be two through -lanes, possibly a turn pocket, and include sidewalks. Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fe• . Funds St and Code State Funds Local Funds Total Funds S PE 2025 STBG 1, 0 1,000,000 2,500,000 P RW 2026 0 MAW 1,400,000 0 1,400,000 S CN 2027 BR 600,000 MAW 17,000,000 0 29,000,000 jlli s 1 , '00 18,400,000 1,000,000 32,900,000 Expenditure Schedule Phase 1st 2nd 3r 4th 5th & 6th PE 200,000 400,000 0 0 0 RW 0 1,400,000 0 0 0 CN 0 0 19,000,000 10,000,000 0 Totals 200,000 1,800,000 19,000,000 10,000,000 0 Report Date: May 14, 2024 Page1 119 ANL 111171 v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m c. c Q. Amendment ___A Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-15812 42nd Avenue S Bikeway 42nd Avenue S Southcenter Blvd to S 150th Street Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and Southcenter Blvd. On the west side of the street, add striped southbound bike lane between Southcenter Blvd and S 150th St. On the east side of the street, add striped bike lane between Southcenter Blvd and S 151st St. Remove on -street parking to widen the sidewalk on the east side of the street between S 151 st St and S 150th St, creating a shared path; add shared lane markings to the roadway I‘L) 06/10/24 6/17/24 N 28 C G P S T W No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code al Fun and Code State Funds Local Funds Total Funds S PE 2025 0 0 55,000 55,000 S CN 2026 0 0 295,000 295,000 s 0 0 350,000 350,000 Expenditure Schedule 2ndN4th5th 295,0 0 0 & 6th 0 0 Phase 1st PE 55,000000 CN 0 Totals55,000295,0 Report Date: May 14, 2024 Page 2 120 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m 0. c Q. Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 19 WA-11113 46th Avenue Safe Routes to School 46th Avenue S S 150th Street to S 144th Street Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S, including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised crosswalk across S 144th Street with RRFB. 06/10/24 6/17/24 N 05 0.370 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federa Fund Code State Funds Local Funds Total Funds P PE 2026 0 SRTS 170,000 80,000 250,000 P RW 2026 RTS 65,000 10,000 75,000 P CN 2028 SRTS 1,660,000 410,000 2,070,000 Tota� 0 1,895,000 500,000 2,395,000 Expenditure Schedule Phase 1st 2nd 4th5th & 6th PE 0 25{!1* 0 0 0 RW 0 0 75,000 0 0 CN 0 0 0 2,070,000 0 Totals 0 250,000 75,000 2,070,000 0 Report Date: May 14, 2024 Page 3 121 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c a Amendment ___A Resolution No. Improvement Type c ,� c� o. N Total Length Environmental Type RW Required 00 WA05409 Allentown Truck Reroute Project to Study alternatives for truck access to reroute outside of residential neighborhood. _ 06/10/24 6/17/24 N 18 EIS No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Funds Local Funds Total Funds S PL 2025 Vilate 0 600,000 600,000 Totals jill10 0 600,000 600,000 Expenditure Schedule V Phase 1st 2nd 3r 4th 5th & 6th PL 10,000 0 0 0 0 Totals 10,000 0 0 Report Date: May 14, 2024 Page 4 122 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m �. c a Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 00 WA-05405 Americans with Disabilities Act (ADA) Improvements Various locations to Design and construct ADA compliant upgrades to City infrastructure in conjunction with a City developed plan. 06/10/24 6/17/24 N 06 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S ALL 2025 0 0 600,000 600,000 Totals 0 0 600,000 600,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 100,000 100,00 0 100,000 200,000 Totals 100,000 10 100, 100,000 200,000 v Report Date: May 14, 2024 Page 5 123 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m 0. c a Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. co Total Length Environmental Type RW Required 16 WA-07746 Andover Park E/Minkler Blvd Intersection Andover Park E Minkler Blvd to Construct left turn lanes on Andover Park East and reconstruct traffic signal 06/10/24 6/17/24 N 03 C G O P S TW No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S PE 2025 0 0 200,000 200,000 S RW 2025 0 0 20,000 20,000 P CN 2026 TIB 1,440,000 360,000 1,800,000 Totals 0 1,440,000 580,000 2,020,000 Expenditure Schedule Phase 1st 2nd ' 4th 5th & 6th PE 200,000 0 0 0 RW 20,000 0 0 0 0 CN 0 1,800,000 0 0 0 Totals 220,000 1,800,000 0 0 0 Report Date: May 14, 2024 Page 6 124 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m �. c Q. Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 04 WA-15107 Andover Park East/Industry Dr Intersection Andover Park E Industry Drive to Design and construct traffic signal with Andover Park East left turn lanes and crosswalks. 06/10/24 6/17/24 N 03 P 0.100 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds P PE 2026 0 0 150,000 150,000 P RW 2026 0 0 20,000 20,000 P CN 2027 TIB 1,530,000 220,000 1,750,000 Totals 0 1,530,000 390,000 1,920,000 Expenditure Schedule Phase 1st 2nd 4 4RW 4th 5th & 6th PE 0 150,1. 0 0 0 0 20,000 0 0 0 CN 0 0 1,750,000 0 0 Totals 0 170,000 1,750,000 0 0 Report Date: May 14, 2024 Page 7 125 ANL 1117, v�rasr�ingti n state Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c Q. Amendment ___A Resolution No. Improvement Type c ,� o Q. N Total Length Environmental Type RW Required 14 WA-03731 Annual Bridge Inspections and Repairs Various City Street to Perform load ratings and bi-annual inspections as well as construct necessary repairs and maintenance 06/10/24 6/17/24 N 06 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S ALL 2025 0 0 1,380,000 1,380,000 Totals 0 0 1,380,000 1,380,000 Expenditure Schedule Phase lst 2nd 3rd 4th 5th & 6th ALL 215,000 220,00 0 235,000 480,000 Totals 215,000 22 230, 235,000 480,000 v Report Date: May 14, 2024 Page 8 126 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m �. c Q. Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 16 WA-03733 Annual Overlay and Repair Program Various City Streets to Repair, rehabilitate, and overlay City streets as needed in an annual program 06/10/24 6/17/24 N 06 C G O P S TW No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S ALL 2025 0 0 15,000,000 15,000,000 Totals 0 0 15,000,000 15,000,000 Expenditure Schedule Phase lst 2nd 3rd 4th 5th & 6th ALL 2,500,000 2,500,00 2, 0 2,500,000 5,000,000 Totals 2,500,000 2,50 2,500, 2,500,000 5,000,000 v Report Date: May 14, 2024 Page 9 127 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c Q. Amendment ___A Resolution No. Improvement Type c — ,� 0 o. N Total Length Environmental Type RW Required 00 WA-15104 Annual Traffic Signal Program Varies to Design and construct traffic signal upgrades and repairs of signals that exceed routine maintenance work;loop replacement, head replacement, and controllers. Replace direct bury cable for existing lighting system. 06/10/24 6/17/24 N 44 P No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federa Fund Code State Funds Local Funds Total Funds S ALL 2025 0 0 860,000 860,000 Totals 1 0 860,000 860,000 Expenditure Schedule Phase 1st 2nd d 4th 5th & 6th ALL 130,000 130, 15 150,000 320,000 Totals 130,000 130, 150,000 150,000 320,000 Report Date: May 14, 2024 Page10 128 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m �. c Q. Amendment ___A Resolution No. Improvement Type c ,.. °a 0E. N Total Length Environmental Type RW Required 03 TUK-68 Boeing Access Road Overlay Boeing Access Road East Marginal Way S to Martin Luther King Jr Way S Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF railway. 06/10/24 6/17/24 N 05 0.560 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S PE 2025 NHPP 0 0 0 564,000 S CN 2026 NHPP 3,42 0 0 0 3,426,000 Totals 3 0 0 3,990,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PE 564,000 0 0 ALL 0 3,426, 0 0 0 Totals 564,000 3,426,000 0 0 0 Report Date: May 14, 2024 Page11 129 ANL 1117, v�rasr�ingIi n state Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m �. c Q. Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 04 WA-15109 E Marginal Way S (BAR - S 112 St) E Marginal Way S Boeing Access Road to S 112th St Design and construct curb, gutter, drainage, lighting, turn lanes, and traffic control. 06/10/24 6/17/24 N 03 C G O P S TW 0.270 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds P PE 2027 0 0 350,000 350,000 P RW 2028 0 TIB 500,000 300,000 800,000 P CN 2029 TIB 1,800,000 1,200,000 3,000,000 Totals 0 2,300,000 1,850,000 4,150,000 Expenditure Schedule Phase 1st 2nd ' 4th 5th & 6th PE 0 250,000 100,000 0 RW 0 0 0 800,000 0 CN 0 0 0 0 3,000,000 Totals 0 0 250,000 900,000 3,000,000 Report Date: May 14, 2024 Page12 130 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m 0. c a Amendment ___A Resolution No. Improvement Type c ,.. °a 0E. N Total Length Environmental Type RW Required 03 TUK-66 Interurban Avenue S Overlay Interurban Avenue S E Marginal Way S to S 143rd Street Complete pavement repairs, overlay, and curb and gutter repair. _ 06/10/24 6/17/24 N 05 2.250 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds ate d - State Funds Local Funds Total Funds S PE 2026 NHPP '00 0 0 397,000 S CN 2027 NHPP 4,56 0 0 0 4,561,000 Totals 4,9 10 0 0 4,958,000 Expenditure Schedule Phase 1st 2nd d 4th 5th & 6th PE 0 397,0 0 0 ALL 0 561,000 0 0 Totals 0 397,00 ,561,000 0 0 Report Date: May 14, 2024 Page 13 131 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c Q. Amendment ___A Resolution No. Improvement Type c — ,� 0 o. co Total Length Environmental Type RW Required 00 TUK-63 Keeping South King County Moving with TDM South King County Various to Various This project will help people access sustainable transportation options that reduce drive -alone travel and traffic congestion in South King County. TDM programming and services will be provided to residents, workers, visitors, employers, property managers, and students in Tukwila and the partnering jurisdictions of Burien, Des Moines, Kent, Renton, and SeaTac. The program will target those willing and able to try sustainable modes of transportation at activity centers (community hubs, commercial areas, business parks, multifamily housing complexes, and educational institutions). Examples of activity centers include the Tukwila International Boulevard District, Southcenter, and Sea-Tac Airport. The TDM Program will work in partnership with transit agencies, nonprofits, employers, and community organizations to reach priority populations through trusted channels. The project aims to reduce 542,997 vehicle trips and 8,093,549 vehicle miles traveled. 06/10/24 6/17/24 N 44 0.000 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Fun State Fund Code State Funds Local Funds Total Funds S ALL 2025 0 WSDOT 672,000 0 672,000 S ALL 2025 0 OTHER 168,000 0 168,000 P ALL 2025 0 WSDOT 832,000 0 832,000 P ALL 2025 0 OTHER 208,000 0 208,000 Totals 0 1,880,000 0 1,880,000 Expenditure Schedule Phase lst 2nd 3rd 4th 5th & 6th ALL 235,000 260,000 260,000 260,000 130,000 Totals 235,000 260,000 260,000 260,000 130,000 Report Date: May 14, 2024 Page14 132 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c Q. Amendment ___A Resolution No. Improvement Type c — ,� 0 o. N Total Length Environmental Type RW Required 17 WA-11110 Macadam Rd S Complete Streets Project Macadam Road S 150th Street to S 144th Street Design and construction of a complete street on Macadam Road. Road widening and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of the roadway. Includes illumination, curb, and storm drainage. 06/10/24 6/17/24 N 04 0.350 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federa Fund Code State Funds Local Funds Total Funds P PE 2027 0 P ike Program 350,000 50,000 400,000 P RW 2028 Pe e Program 90,000 10,000 100,000 P CN 2029 /Bike Program 2,800,000 300,000 3,100,000 Tota 0 3,240,000 360,000 3,600,000 Expenditure Schedule Phase 1st 2nd {IS. 4th 5th & 6th PE 0 300,000 100,000 0 RW 0 0 0 100,000 0 CN 0 0 0 0 3,100,000 Totals 0 0 300,000 200,000 3,100,000 Report Date: May 14, 2024 Page15 133 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m -,. c Q. Amendment ___A Resolution No. Improvement Type c ,� o o. N Total Length Environmental Type RW Required 03 TUK-67 Orillia Road South Overlay Orillia Road S S 188th Street to S 204th Street Complete pavement repairs; overlay; and curb and gutter, sidewalk, and guardrail repair. 06/10/24 6/17/24 N 05 0.750 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S PE 2026 NHPP 0 0 0 105,000 S CN 2027 NHPP 1,20 0 0 0 1,204,000 Totals 1 0 0 1,309,000 Expenditure Schedule Phase lst 2nd 4th 5th & 6th PE 0 10 0 0 ALL 0 ,204,000 0 0 Totals 0 105,000 1,204,000 0 0 Report Date: May 14, 2024 Page16 134 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c Q. Amendment ___A Resolution No. Improvement Type c — ,� 0 o. N Total Length Environmental Type RW Required 00 WA13494 S 119th St Pedestrian Bridge Painting S 119th Street Bridge West bank Duwamish River to East bank Duwamish River Ongoing maintenance of the S 119th Street Pedestrian Bridge in the Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance needed. 06/10/24 6/17/24 N 06 0.040 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federa Fund Code State Funds Local Funds Total Funds P CN 2026 0 0 200,000 200,000 Totals 1 0 200,000 200,000 Expenditure Schedule Phase 1st 2nd d 4th 5th & 6th CN 0 200, 0 0 Totals 0 200, 0 0 0 Report Date: May 14, 2024 Page17 135 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m 0. c Q. Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 03 WA-15108 S 133 St/SR599 Southbound Intersection S 133rd Street SR 599 SB Ramp to Design and construct intersection improvements, which could include a new traffic signal or a roundabout, lighting, pedestrian facilities, and drainage. 06/10/24 6/17/24 N 03 C G O P S TW 0.100 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede nds ` - Fund Code State Funds Local Funds Total Funds P PE 2028 0 0 400,000 400,000 P RW 2028 0 150,000 150,000 P CN 2029 0 TIB 1,620,000 1,080,000 2,700,000 TIONNI 0 1,620,000 1,630,000 3,250,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 400,000 0 RW 0 0 0 150,000 0 CN 0 0 0 0 2,700,000 Totals 0 0 0 550,000 2,700,000 Report Date: May 14, 2024 Page18 136 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Begin & End Termini F. Project Description G. Structure ID m �. c a Amendment ___A Resolution No. Improvement Type c ,� - °a 0E. N Total Length Environmental Type RW Required 19 WA-11112 S 152nd Street Safe Routes to School S 152nd Street Tukwila International Blvd to 42nd Avenue S Design and construct curb, gutter and sidewalks on both sides including widening pavement width by 3 feet to construct on -street parking lane on north side of street. 06/10/24 6/17/24 N 05 0.300 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S PE 2025 0 0 250,000 250,000 S RW 2025 0 0 100,000 100,000 P CN 2026 ke Program 2,140,000 2,085,000 4,225,000 Totals 0 2,140,000 2,435,000 4,575,000 Expenditure Schedule Phase 1st 2nd ' 4th 5th & 6th PE 250,000 0 0 0 RW 100,000 0 0 0 0 CN 0 4,225,000 0 0 0 Totals 350,000 4,225,000 0 0 0 Report Date: May 14, 2024 Page19 137 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c a Amendment ___A Resolution No. Improvement Type c — ,� 0 o. N Total Length Environmental Type RW Required 04 WA-15829 S Ryan Way SR 900 to 51 st Ave S Resurface and rechannel S Ryan Way to improve failing pavement and improve safety. Add pedestrian and bicycle facilities where appropriate. Signalize intersection with 47th Avenue S to accommodate future growth and improve safety. 06/10/24 6/17/24 N 06 C G P S T W 0.500 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede nds - - Fund Code State Funds Local Funds Total Funds P PE 2025 0 TIB 780,000 520,000 1,300,000 P CN 2027 TIB 7,300, 000 1,900,000 9,200,000 Totals 0 8,080,000 2,420,000 10,500,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PE400,00090IO ,00 0 CN0,200,0000 0 Totals400,000900,00,200,000 0 0 Report Date: May 14, 2024 Page 20 138 ANL 1117, v�rasr�ingIi n state Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c a Amendment ___A Resolution No. Improvement Type c — ,Z 0 o. N Total Length Environmental Type RW Required 05 TUK-65 South 144th Street Bridge Sidewalks S 144th Street Bridge 51 st Ave S to 53rd Ave S The project entails replacing approximately 320 feet of raised bridge deck on the S 144th street bridge with 6-foot-wide sidewalks, which will be separated from the traffic lanes by a crash tested barrier and a pedestrian railing. Sharrows will also be added to the traffic lanes for bicycle traffic. 06/10/24 6/17/24 N 28 0.060 DCE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede ' nds Fund Code State Funds Local Funds Total Funds S PE 2026 STBG(UL) 50J0 0 78,035 578,035 P CN 2027 SRTS 2,302,000 388,000 2,690,000 Totals 00,000 2,302,000 466,035 3,268,035 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PE 0 57Ilk)0 0 0 CN 0 ,690,000 0 0 Totals0 578,03,690,000 0 0 Report Date: May 14, 2024 Page 21 139 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title Road Name or Number Begin & End Termini m 0. Amendment ___A Resolution No. Improvement Type c ,Q.D. - °a 0E. Total Length Environmental Type RW Required F. Project Description G. Structure ID c a N 00 TUK-64 06/10/24 6/17/24 24 0.000 No South King County TDM N South King County N/A to N/A This project will provide TDM programming and services at selected activity centers in Tukwila and partnering South King County jurisdictions. Activity centers include community hubs, commercial areas, business parks, multifamily housing complexes, and educational institutions. For example, places such as Tukwila International Boulevard District, Southcenter, and Sea-Tac Airport. By providing transportation resources and incentives, the project will encourage people to choose sustainable transportation options that reduce drive -alone travel and traffic congestion in South King County. TDM services will be provided to residents, commuters, and visitors, targeting those willing and able to try sustainable modes of transportation. The program will work in partnership with partner agencies, nonprofits, employers, an community organizations. Funding Status Phase Phase Start Year (YYYY) Federal Fund Co al F State Fund Code State Funds Local Funds Total Funds S PL 2025 CMAQ 4 67 OTHER 20,164 50,000 519,731 P PL 2027 CMAQ 550,000 OTHER 85,838 0 635,838 To 999,567 106,002 50,000 1,155,569 Expenditure Schedule Nr Phase 1st 2nd 3rd 4th 5th & 6th PL 129,933 129,933 158,960 158,960 317,909 Totals 129,933 129,933 158,960 158,960 317,909 Report Date: May 14, 2024 Page 22 140 ANL 111171 v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m c. c A Amendment ___A Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 WA-15813 Southcenter Blvd Bikeway and Pedestrian Crossing Upgrades Southcenter Boulevard International Boulevard to 42nd Avenue S Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half - mile of Tukwila International Boulevard Station (TIES). Re-channelize to 11 ft general purpose lanes to accommodate separated (tuff curb and post) bike lanes. Tighten intersection with 40th Ave S to shorten crossing distance. Add bike channelization and upgrade to high -visibility crosswalk markings at Southcenter Blvd/TIBS station entrance and Southcenter Blvd/42nd Ave S intersections. I‘L)P 06/10/24 6/17/24 N 28 C G P S T W No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code al Fun and Code State Funds Local Funds Total Funds S PE 2025 0 0 65,000 65,000 S CN 2026 0 0 325,000 325,000 s 0 0 390,000 390,000 Expenditure Schedule 2ndN4th5th 325,0 0 0 & 6th 0 0 Phase 1st PE 65,000000 CN 0 Totals65,000325,0 Report Date: May 14, 2024 Page 23 141 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m w. c Q. Amendment ___A Resolution No. Improvement Type c ,� o o. N Total Length Environmental Type RW Required 04 WA-13495 Southcenter Blvd/65th Avenue S Signal Southcenter Boulevard 65th Avenue S to Design and construct a new traffic signal at the Southcenter Boulevard/65th Avenue S intersection to improve level of service and safety. 06/10/24 6/17/24 N 21 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F nd Code State Funds Local Funds Total Funds S CN 2025 0 TIB 782,090 400,000 1,182,090 Totals 0 782,090 400,000 1,182,090 Expenditure Schedule Phase lst 2nd 3rd 4th 5th & 6th CN 1,182,000 0 0 0 Totals 1,182,000 0 0 v Report Date: May 14, 2024 Page 24 142 ANL 1117, ViastungIi n state Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2025 to 2030 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title Amendment ___A Resolution No. Improvement Type c — ,Z Total Length Environmental Type RW Required D. Road Name or Number m 0 E. Begin & End Termini -,. o. F. Project Description G. Structure ID c Q. co 00 WA-13491 06/10/24 6/17/24 44 0.000 No Transportation Demand Management Implementation to N Provision of TDM services to Commute Trip Reduction -affected employment sites. Facilitate employer reporting and records associated with biennial CTR survey. Engage CTR employment sites with opportunities for improvement and remain connected via technical meetings with other CTR jurisdictional representatives. Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede nds - Fund Code State Funds Local Funds Total Funds S ALL 2025 0 SDOT 93,300 0 93,300 P ALL 2027 SDOT 186,600 0 186,600 Totals 0 279,900 0 279,900 Expenditure Schedule Phase lst 2nd 3r 4th 5th & 6th ALL 46,650 46,6 46,650 46,650 93,300 Totals 46,650 46,650 46,650 46,650 93,300 Mineral Funds State Funds Local Funds Total Funds Grand Totals for Tukwila 25,256,567 45,994,992 31,461,035 102,712,594 Report Date: May 14, 2024 Page 25 143 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID v �. to Resolution No. Amendment Adopted Improvement Type c ot % C) o. N Total Length Environmental Type RW Required 05 / 1037(004) 42nd Ave S Bridge Replacement 42nd Ave S over the Duwamish River Interurban Ave S to Northern end of bridge Replace the existing 42nd Ave S steel truss bridge. T replacement w preliminary engineer design, right-of-way, and constru n phase Th structure will meet current road and bridge design stan . T pla structure configuration will be two through -lanes, possibly cket, a sidewalks. equire ew ens TUK-62 e R 06/12/23 06/26/23 N 11 0.100 DCE No Funding Status Phase Phase Start Year (YYYY) Fed Co Funds State F e St s Local Funds Total Funds S PE 2024 TBG ) 1,5r A Mr 1,100,000 2,600,000 S RW 2024 ^, i 13,500 100,000 S CN 2024 BR 1 ,• - e 17,00i 100 0 28,913,500 To a s 13,500,001 , 00,0i1 1,113,500 31,613,500 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 800,000 0 0 0 0 RW 100,000 0 0 0 0 CN 0 15,636,500 13,500,000 0 0 Totals 900,000 15,636,500 13,500,000 0 0 Report Date: May 04, 2023 Page 1 144 1117, ViastungIi n state Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID 1 �. to Amendment Adopted Resolution No. Improvement Type c ot , C) o. N Total Length Environmental Type RW Required 19 46th Avenue Safe Routes to School 46th Avenue S S 150th Street to S 144th Street Design and construct curb, gutter and sidewalk on the including curb bulb -out at the SE corner of 46th Avenu crosswalk across S 144th Street with RRFB. st side of 46th /S 144th e WA-1111:06/12/23 enue S, ith rail R 06/26/23 N 05 0.370 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P9 PE 2024 90,000 270,000 P RW 20242 10020,000240,000 P CN2025 9 7801,•' 6� '�0 7TS 410,000 2,070,000 taps _ 6�00 520,000 2,580,000 v ■ v v Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 270,000 0 0 0 0 RW 240,000 0 0 0 0 CN 0 2,070,000 0 0 0 Totals 510,000 2,070,000 0 0 0 Report Date: May 04, 2023 Page 2 145 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID m �'. t Amendment Adopted ,:, `D o E o Z P Improvement Type C C) a N Total Length Environmental Type RW Required 00 Allentown Truck Reroute Project to Study alternatives for truck access to reroute outside esidential neig rhood. WA05409 06/12/23 1::0 1::0 06/26/23 18 EIS No Funding , ` , ` ` , . Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PL 2024 0 0 600,000 600,000 - To AIIIMIII AP 600,000 600,000 Expenditure Schedule Phase 1st 2nd _ zy 5 6th PL 600,000 p Totals 600,000 0 0 Report Date: May 04, 2023 Page 3 146 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type % c Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. Q. F. Project Description G. Structure ID to N 00 WA-05405 06/12/23 06/26/23 06 No Americans with Disabilities Act (ADA) Improvements Various locations to Design and construct ADA compliant upgrades to City with a City developed plan. rastructure in 1111 junction IR IR N Funding w — _ m _ - _ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2024 0 0 435,000 435,000 ^ ^ A ^ ^ 435,000 435,000 Expenditure Schedule Phase 1st 24 d & 6th ALL 50,000 ,00 50,00 0,0 1 Totals 50,000 50,000 50,000 50,000 100,000 Report Date: May 04, 2023 Page 4 147 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type C % Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. Q. F. Project Description G. Structure ID to N 16 WA-07746 06/12/23 06/26/23 03 C G O P S No TW Andover Park E/Minkler Blvd Intersection Andover Park E Minkler Blvd to Construct left turn lanes on Andover Park East and re struct tray si I IR IR N Funding — _ m _ - Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2025 0 0 134,000 134,000 S RW 2025 I 10,000 10,000 P CN 202611 IA III 1,570,000 1,570,000 , - 1,714,000 1,714,000 Expenditure Schedule r • r r Phase 1st 2nd 3rd 4th 5th & 6th PE 0 134,000 0 0 0 RW 0 10,000 0 0 0 CN 0 0 1,570,000 0 0 Totals 0 144,000 1,570,000 0 0 Report Date: May 04, 2023 Page 5 148 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type C , Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. o. F. Project Description G. Structure ID to N 04 WA-15107 06/12/23 06/26/23 03 P 0.100 Yes Andover Park East/Industry Dr Intersection Andover Park E Industry Drive to Design and construct traffic signal with Andover Park crosswalks. t left turn lane if nd IR IR N Funding — _ m _ - Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2025 0 0 75,000 75,000 S RW 2025 1 10,000 10,000 P CN 202611 IA III 657,000 657,000 , - 742,000 742,000 Expenditure Schedule r • r r Phase 1st 2nd 3rd 4th 5th & 6th PE 0 75,000 0 0 0 RW 0 10,000 0 0 0 CN 0 0 657,000 0 0 Totals 0 85,000 657,000 0 0 Report Date: May 04, 2023 Page 6 149 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID v �. to Amendment Adopted Resolution No. Improvement Type c ot % C) o. N Total Length Environmental Type RW Required 14 Annual Bridge Inspections and Repairs Various City Street to Perform load ratings and bi-annual inspections as well repairs and maintenance construct nec if ary WA-03731 06/12/23 IR IR 06/26/23 N 06 No Funding — _ m _ - Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2024 0 0 1,345,000 1,345,000 ^ ^ A ^ ^ 1,345,000 1,345,000 Expenditure Schedule Phase 1st 24 d & 6th ALL 205,000 220,00 0,0 4 ,00 Totals 205,000 215,000 220,000 230,000 475,000 Report Date: May 04, 2023 Page 7 150 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type C % Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. Q. F. Project Description G. Structure ID to N 16 WA-03733 06/12/23 06/26/23 06 C G O P S No TW Annual Overlay and Repair Program Various City Streets to Repair, rehabilitate, and overlay City streets as neede an annuipr m Funding — _ m _ - Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2024 0 0 8,850,000 8,850,000 ^ ^ A ^ ^ 8,850,000 8,850,000 Expenditure Schedule Phase 1st 24 d & 6th ALL 1,400,000 ,00 , 0,0 3,1 ,400,00 Totals 1,400,000 1,400,000 1,400,000 1,500,000 3,150,000 Report Date: May 04, 2023 Page 8 151 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID v �. to Adopted Amendment Resolution No. Improvement Type c ot % C) o. N Total Length Environmental Type RW Required 00 WA-15104 Annual Traffic Signal Program Varies to Design and construct traffic signal upgrades and repai of signals that eed routine maintenance work;loop replacement, head rep ment, a o Ilers. Replace direct bury cable for existing lighting system. 06/12/23 06/26/23 44 P No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2024 1,040,000 1,040,000 el taps n A n n el% 1,040,000 1,040,000 Expenditure Schedule ZI= 4.1 Phase 1st 21 ALL 130,000 130,000 130,000 150,000 300,000 Totals 130,000 130,000 130,000 150,000 300,000 Report Date: May 04, 2023 Page 9 152 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type C % Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. o. F. Project Description G. Structure ID to N 04 WA-15109 06/12/23 06/26/23 03 C G O P S 0.270 Yes TW E Marginal Way S (BAR - S 112 St) E Marginal Way S Boeing Access Road to S 112th St Design and construct curb, gutter, drainage, lighting, t lanes, antra control. IR IR N Funding — _ m _ - Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2025 0 0 288,000 288,000 P RW 2029 1 - 281 420,000 700,000 P CN 2029 IA IBIII • 7 111 1,460,000 2,430,000 , - 1,250, 2,168,000 3,418,000 Expenditure Schedule r • r r Phase 1st 2nd 3rd 4th 5th & 6th PE 0 50,000 0 0 170,000 RW 0 0 0 0 700,000 CN 0 0 0 0 2,430,000 Totals 0 50,000 0 0 3,300,000 Report Date: May 04, 2023 Page10 153 ANL 111171 v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 1 �. to Adopted Amendment Resolution No. Improvement Type c ot , C) o. N Total Length Environmental Type RW Required 00 TUK-63 Keeping South King County Moving with TDM South King County Various to Various This project will help people access sustainable transation options t reduce drive -alone travel and traffic congestion in South King , unty. TD pro mming and services will be provided to residents, workers, visi . ern. ' rs, ert managers, and students in Tukwila and the partnering juri . of Buri R Moines, Kent, Renton, and SeaTac. The program will target those willing and able to try sustainable modes of transportation at activity centers (community hubs, commercial areas, business parks, multifamily housing complexes, and educational institutions). Examples of activity centers include the Tukwila International Boulevard District, Southcenter, and Sea-Tac Airport. The TDM Pr ill fler with transit agencies, nonprofits, employers, and com ity o npriority populations through trusted channels. The project aim r97 vehicle trips and 8,093,549 vehicle miles traveled.ono() 06/12/23 06/26/23 N 44 0.000 No Funding ` v ` ' ,_ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2024 0 WSDOT 672,000 0 672,000 S ALL 2024 0 OTHER 168,000 0 168,000 Totals 0 840,000 0 840,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 210,000 105,000 0 0 0 Totals 210,000 105,000 0 0 0 Report Date: May 04, 2023 Page 11 154 1117, ViastungIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID v �. to Amendment Adopted Resolution No. Improvement Type c ot % C) o. N Total Length Environmental Type RW Required 17 Macadam Rd S Complete Streets Project Macadam Road S 150th Street to S 144th Street Design and construction of a complete street on Maca and rechannelization to add 5-foot bike lanes and 5-fo the roadway. Includes illumination, curb, and storm drai m Road. Road idewalks b WA-1111( ening sides o R 06/12/23 06/26/23 N 04 0.350 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2024 am 50,000 400,000 P RW 2024 Ped/B Prog 9 �00 10,000 100,000 P CN 2025Ped/Bike 9Ped/Bik 9 Pr m2350S 80k '.0 300,000 3,100,000 24�00 360,000 3,600,000 v ■ v v Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 400,000 0 0 0 0 RW 100,000 0 0 0 0 CN 0 3,100,000 0 0 0 Totals 500,000 3,100,000 0 0 0 Report Date: May 04, 2023 Page12 155 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID v �. to Amendment Adopted Resolution No. Improvement Type c ot % C) o. N Total Length Environmental Type RW Required 00 S 119th St Pedestrian Bridge Painting S 119th Street West bank Duwamish River to East bank Duwamish R. Ongoing maintenance of the S 119th Street Pedestria Allentown/Duwamish neighborhoods. Painting of bridg needed. ridge in the outstan WA-13494 ntenanc R 06/12/23 06/26/23 N 06 0.040 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2024 200,000 200,000 el taps n A n n filo%200,000 200,000 Expenditure Schedule ‘01.111 4.1 Phase 1st 2 CN 0 200,000 0 0 Totals 0 200,000 0 0 0 Report Date: May 04, 2023 Page13 156 ANL 1117, v�rasr�ingIi n state Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Resolution No. Amendment Adopted Improvement Type c % Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. o. F. Project Description G. Structure ID to N 03 WA-15108 06/12/23 06/26/23 03 C G O P S 0.100 Yes TW S 133 St/SR599 Southbound Intersection S 133rd Street SR 599 SB Ramp to Design and construct intersection improvements, whic signal or a roundabout, lighting, pedestrian facilities, and drainage. ould inclu a w traffic R R N Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2028 I 1 300,000 300,000 P RW 2028 iI , i 50,000 50,000 P CN 2029 I 2,070,000 2,070,000 1 W &IrW 2,420,000 2,420,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 300,000 RW 0 0 0 0 50,000 CN 0 0 0 0 2,070,000 Totals 0 0 0 0 2,420,000 Report Date: May 04, 2023 Page14 157 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID m �'. Amendment Adopted XI `D o o Z P Improvement Type C , n a co Total Length Environmental Type RW Required 17 S 144th St Bridge Sidewalks S 144th Street 51 st Ave S to 53rd Ave S Widen existing sidewalks on bridge over 1-5 between t Ave S and 53 Ave S WA03782 06/12/23 1::0 IZI 06/26/23 28 0.250 CE No Funding , ` , ` ` , . Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2026 STBG(UL) 500,000 0 79,000 579,000 P CN 2025 2,302,0 38,000 2,690,000 ei taps ^ 2,80 ^ ^ 0� 467,000 3,269,000 Expenditure Schedule Phase PE 1st 0 CN 0 Totals 0 2 1Z ZikAa 579,000 0 0 0 2,690,000 0 0 579,000 2,690,000 0 Report Date: May 04, 2023 Page15 158 ANL 1117, v�rasr�ingti n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type % C Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. o. F. Project Description G. Structure ID to N 19 WA-1111 ' 06/12/23 06/26/23 05 0.300 No S 152nd Street Safe Routes to School S 152nd Street Tukwila International Blvd to 42nd Avenue S Design and construct curb, gutter and sidewalks on b pavement width by 3 feet to construct on -street parkin sides including ne on nob si idening of street Funding — _ m _ - Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2024 0 TIB 3,200,000 815,000 4,015,000 ^ ^ A ^ 01.4k2020% 815,000 4,015,000 Expenditure Schedule Phase 1st 2nki) d kii)& 6th CN 4,015,000 Totals 4,015,000 0 0 0 0 Report Date: May 04, 2023 Page16 159 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID v �. to Adopted Amendment Resolution No. Improvement Type c ot % C) o. N Total Length Environmental Type RW Required 00 TUK-64 South King County TDM South King County N/A to N/A This project will provide TDM programming and servic at selected act y center in Tukwila and partnering South King County jurisdicti . Activity to include community hubs, commercial areas, business parks, m mil sin le R and educational institutions. For example, places such as nterna Boulevard District, Southcenter, and Sea-Tac Airport. By providing transportation resources and incentives, the project will encourage people to choose sustainable transportation options that reduce drive -alone travel and traffic congestion in South King County. TDM services will be provided to residents, commuters, and visitors, targeting those willingand able tosustainable mode port e 9 9try program will work in partnership with partner agencies onpro loye a re) A community organizations. 06/12/23 nnn 06/26/23 N 24 0.000 No Funding Status Phase Phase Start Year (YYYY) Fe CoAG unds State a Local Funds Total Funds S PL 2024 CMAQ 450,000 OTHER 55,232 15,000 520,232 Totals 450,000 55,232 15,000 520,232 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PL 260,116 0 0 0 0 Totals 260,116 0 0 0 0 Report Date: May 04, 2023 Page17 160 ANL 1117, v�rasr�ingIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title B. STIP ID Amendment Adopted Resolution No. Improvement Type % c ot Total Length Environmental Type RW Required D. Road Name or Number v C) E. Begin & End Termini �. o. F. Project Description G. Structure ID to N 04 WA-13495 06/12/23 06/26/23 21 No Southcenter Blvd/65th Avenue S Signal Southcenter Boulevard 65th Avenue S to Design and construct a new traffic signal at the South S intersection to improve level of service and safety. ter Boulevard/ IIII h Avenu IR IR N Funding w — _ m _ - _ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2024 0 0 200,000 200,000 P CN 2025 er) 500,000 A eo 1,000,000 taps n A in 700,000 1,200,000 Expenditure Schedule Phase 1st PE 100,000 0 0 0 0 CN 1,000,000 0 0 0 0 Totals 1,100,000 0 0 0 0 Report Date: May 04, 2023 Page 18 161 ANL 1117, ViastungIi n State Department ot Transportation Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2024 to 2029 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID v �. to Amendment Adopted Resolution No. Improvement Type % c ot C) o. N Total Length Environmental Type RW Required 00 Transportation Demand Management Implementation to Provision of TDM services to Commute Trip Reductio Facilitate employer reporting and records associated Engage CTR employment sites with opportunities for i connected via technical meetings with other CTR jurisdict WA-13491 06/12/23 ected employIvey. biennial R nt sites.RR em nd in resenta 06/26/23 N 44 0.000 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F9unds State Fund Code State Funds Local Funds Total Funds S ALL 2024 O 8' 0 88,526 P ALL 20259 WSDOT 4 0 46,650 taps 135, 0 135,176 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 46,650 46,650 0 0 0 Totals 46,650 46,650 0 0 0 Federal Funds State Funds Local Funds Total Funds Grand Totals for Tukwila 16,752,000 28,280,408 23,504,500 68,536,908 Report Date: May 04, 2023 Page19 162