Project Sponsor: Tukwila City of
Project Title: Nelsen Side Channel
Amendment Type:
Time Extension
Amendment Description:
23-024(c)
Amendment to Grant Agreement Council Approval N/A
Project Number: 22-1047 P
Amendment Number: 3
Pursuant to a request from Tukwila City of the Project Agreement identified above is amended
to extend the end date of this agreement.
The project period of 09/22/2022 to 12/15/2025 is extended to allow the contracting party
until 3/15/2027 to complete the project.
Agreement Terms
In all other respects the Agreement, to which this is an Amendment, and attachments thereto,
shall remain in full force and effect. In witness whereof the parties hereto have executed this
Amendment.
State of Washington
Recreation and Conservation Office
BY: rte,,,,,, ,,,,,,,
FOR Megan Duffy
TITLE: Director
DATE: 01/28/2026
Pre -approved as to form:
By: /S/
Assistant Attorney General
Signed by:
B9A92938616B424...
APPROVED AS TO FORM BY CITY ATTORNEY 1/28/26.
APPROVAL ON FILE.
SAL Project Time Extension Amendment
General Fund - Federal RCW 77.85, WAC 420
TIMEXTEN.RPT
Project Number:
Project Name:
Sponsor:
Project Manager:
Amendment Milestone Report
22-1047 P
Nelsen Side Channel
Tukwila City of
Kate McLaughlin
Amendment Number: 3
X
Milestone
Target ..Comments/Description
X
Project Start
09/22/2022
X
i
Progress Report Due
06/27/2023
X
i
Progress Report Due
09/15/2023
X
i
Progress Report Due
03/15/2024
X
i
Annual Project Billing Due
04/23/2024
X
i
Progress Report Due
12/02/2024
X
i
Progress Report Due
04/09/2025
X
Other
08/29/2025
If City is proceeding with design without
acquiring Nelsen Family Trust property,
will apply for time extension for design
work by this date.
X
i
Progress Report Due
10/09/2025
Data Gathering Started
11/30/2025
i
Progress Report Due
11/30/2025
i
Annual Project Billing Due
12/12/2025
Other
12/15/2025
City of Tukwila holds title to Nelsen
Family Trust Property via a recorded
deed (if proceeding with acqusition).
RFP Complete/Consultant Hired
01/05/2026
i
Progress Report Due
03/16/2026
i
Annual Project Billing Due
07/13/2026
i
Cultural Resources Complete
08/31/2026
Cultural resources survey and historic
structures documentation required prior
to ground disturbance, may proceed
concurrently with geotech/soils
investigations, see special condition
#1.
i
Progress Report Due
09/30/2026
Other
10/01/2026
Data Gathering Complete
i
Preliminary Design to RCO
02/15/2027
As described in RCO Manual 18, App
D-2
Final Report Due
03/12/2027
This is the RCO final report in PRISM
Final Billing Due
03/12/2027
i
Agreement End Date
03/15/2027
Project Closing. All expenditures must
be prior to this date.
AMILESTO.RPT January 14, 2026 Page:
Amendment Milestone Report
X = Milestone Complete
! = Critical Milestone
AMILESTO.RPT January 14, 2026 Page:
AMENDMENT APPROVAL FORM
Project #:
22-1047 Planning
Amendment #:
3 - Time Extension
Project Title:
Nelsen Side Channel
Project Sponsor:
Tukwila City of
Project Manager:
KateM
Primary Program:
Salmon Federal Projects
AMENDMENT DESCRIPTION:
The project period of 09/22/2022 to 12/15/2025 is extended to allow the contracting party until 3/15/2027 to complete the
project.
PROJECT SUMMARY:
Board Funded Date: 09/22/2022 Prior Time Extensions: 1 RCO Amount:
$300,000.00
Project Start Date: 09/22/2022 Other External Amendments: 1 Sponsor Match Amount:
$54,000.00
Original End Date: 09/30/2024 Sponsor Active Projects: 2 Total:
$354,000.00
Current End Date: 12/15/2025 Sponsor Completed Projects: 6 RCO Paid To Date (2%):
$5,957.36
Sponsor Not Completed Projects: 0 RCO Remaining (98%):
$294,042.64
Last Progress Report: 09/18/2025 Sponsor Dead Projects: 0 Last Billing Date:
04/23/2024
PROJECT AGREEMENT DESCRIPTION:
The City of Tukwila proposes to complete preliminary design and apply for permits for the Nelsen Side Channel restoration on
the Lower Green River. The future restoration project will create about one acre of rare off -channel rearing habitat and restore
another acre of riparian forest by setting back a levee and reconnecting the river with its historic channel to benefit threatened
juvenile Chinook salmon and other salmonids. The design will include off -channel habitat to provide forage opportunities and
refugia during the high flows of the early out -migration period: planting plan for the riparian and upland areas surrounding the
side channel, and along the mainstem of the Green River, restoring ecological function and providing critically needed shade;
large wood placement to provide food sources, wood recruitment and refuge for juvenile Chinook. This proposal is integrated
with the work of the City's non-profit partner, DirtCorps, who is restoring nearly an acre of shoreline upstream from the side
channel. The Nelsen Side Channel Project is among the projects listed in WRIA 9's Salmon Habitat Plan 2021 update.
PROJECT FUNDING (CURRENT):
Bien Fund Appn Reapp Ind Orig Bien Orig Appn Grant Activity SubActiv SO
Amount
25-27 057 D13 Reapp 23-25 D13 PSARP PROJ NZ
$200,000.00
25-27 001 P22 Reapp 21-23 P22 NMFS 2022 PROJ FED NZ
$100,000.00
AMENDAPPROVALFORM. RPT