HomeMy WebLinkAboutCOW 2009-08-24 Item 4A - Bid Award - Ro-Con Equipment Specialist for Storm Lift Station #18 Improvements for $294,610CAS NUMBER. 09-117 SPONSOR'S SUMMARY MTG DATE 08/24/09 08/24/09 MTG DATE 08/24/09 08/24/09 0 I I i Meeting Date 08/24/09 CATEGORY Discussion Motion Mtg Date 08/24/09 Mtg Date COUNCIL AGENDA SYNOPSIS Prepared by JM Resolution Mtg Date Initials 1 Mayor's review ITEM INFORMATION Fund Source: 412.02 SURFACE WATER (PG. 148, 2009 CIP) Comments Council review ORIGINAL AGENDA DATE: AUGUST 24, 2009 AGENDA ITEM TITLE Bid Award for Storm Lift Station No. 18 Improvements RECORD OF COUNCIL ACTION ATTACHMENTS Informational Memorandum dated 08/12/09 (revised after TC) Bid Tabulation 2009 CIP Sheet Page 148 Minutes from the Transportation Committee meeting of 08/17/09 ITEM No SP 3 Ordinance Bid Award Public Hearing Other Mtg Date Mtg Date 08/24/09 Mtg Date Mtg Date SPONSOR Council Mayor Adm Svcs DCD Finance Fire Legal P&R Police PTV The Storm Lift Station No. 18 Improvement Project will replace the existing single 8" pump with two 10" pumps to increase pumping capacity and provide a secondary backup pump. The project was advertised for bids on July 29 and August 5, 2009 and nine bids were opened on August 12 with the low bid of $294,610.00 from Ro -Con Equipment Specialist, Inc. Ro -Con's references were checked and found to be satisfactory Council is requested to award the bid to Ro -Con Equipment Specialist, Inc. for $294,610.00. REVIEWED BY COW Mtg CA &P Cmte F &S Cmte Transportation Cmte Utihties Cmte Arts Comm. Parks Comm. Planning Comm. DA "1'E. 08/17/09 RECOMMENDATIONS. SPONSOR /ADMIN Public Works CoMMI Unanimous Approval, Forward to Committee of the Whole Special COST IMPACT FUND SOURCE EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $294,610.00 $300,000.00 $0.00 ISSUE City of Tukwila INFORMATIONAL MEMORANDUM TO Mayor Haggerton TRANSPORTATION COMMITTEE FROM Public Works Director DATE August 12, 2009 SUBJECT Storm Lift Station No. 18 Improvements Project No 07 -DRO3 BID AWARD Award the bid for construction of Storm Lift Station No 18 Improvements BUDGET AND BID SUMMARY (All amounts include sales tax.) Bid Results Estimate Budg Construction 294,610.00 373,118 63 300,000 00 Contingency (20 58.922.00 74.623.73 0.00 Total 353.532.00 447142.36 300.000.00 *Any overage amount will come from the Surface Water Fund's ending fund balance. RECOMMENDATION The Council is being asked to award the construction of the Storm Lift Station No 18 Improvements to Ro -Con Equipment Specialist, Inc. in the amount of $294,610 00 for consideration at the August 24, 2009 Committee of the Whole meeting and the Special Meeting immediately following the C 0 W that same night. Attachments: Bid Tabulations CIP Sheet W:1PW Eng \PROJECTSW- DR Projects \07 -DRO3 (Storm Lift Station No. 18 Improvements) \Design \Info Memo Bid Award.doc Jim Haggerton, Mayor BACKGROUND This project will upgrade Storm Lift Station No 18 by replacing the existing single 8" pump with two 10" pumps, replacing the wet well, adding a control structure and constructing an electrical control building These improvements will require the acquisition of additional right -of -way and will provide a secondary backup pump, increased pumping capacity and automatic operation The project was advertised for bids on July 29 and August 5, 2009 Nine bids were received and opened on August 12, 2009 and the bids were checked and tabulated Ro -Con Equipment Specialist, Inc. is the low bidder with a base bid of $294,610 00 The engineer's estimate was $373,118 63 ANALYSIS The bids were reviewed and tabulated No errors were found Ro -Con Equipment Specialist, Inc's references were checked and found to be satisfactory Owner: City of Tukwila Project: Allentown Storm Water Pump Station Engineers: PACE Engineers, Inc. ITEM NO. ITEM OR TASK DESCRIPTION ROADWAY 1 6" HMA 1/2" with 6" CSTC Base 2 3" HMA 1/2" with 2" CSTC Base I 3 Crushed Surfacing Top Course 4 Shoulder Gravel TRAFFIC CONTROL DEVICES 5 Traffic Control Devices ROADSIDE DEVELOPMENT I 6 Property Restoration 7 Plantings 8 10 -Foot Chain Link Gate 9 Cedar Fence STORM DRAINAGE 10 Mobilization 11 Temporary Water Polution /Erosion Control 12 Resolution of Utility Conflicts 13 Traffic Control Labor (Min. $35 /hr) 14 Contractor- Supplied Surveying and Staking 15 Potholing 16 Storm Water Pump Station I 17 72 -inch Diameter Discharge Manhole 118 CMU Building 1 19 10" DI Pipe and Fittings 1 20 12" DI Pipe and Fittings 121 Removal and Disposal of Existing 84" Pump Station 22 Removal and Salvage of Existing Controls 23 10" R.S. Gate Valve and Valve Box 24 Bank Run Gravel 1 25 36" DI Pipe 1 26 Electncal 27 Trench Shoring and Safety Sales Tax included Unit and Lump Sum prices per Rule 171 Bid Tab 8- 12- 09.x1s QUANTITY NO. UNIT UNIT UNITS PRICE COST 125 SY 860.00 57.500.00 $58.00 97.250.00 8110.00 813.750,00 675.00 09,375.00 068.00 011,000.00 $90.00 011.250.00 076.00 $9,500.00 25 SY 532.00 $800.00 $50.00 01,250.00 I 0300.00 97,500.00 060.00 51.500,00 097.00 52,425.00 $45.00 51.125.00 038.00 $950.00 70 TN 028.00 01.960.00 530.00 $2,100.00 $55.00 03.850.00 $30.00 82,100.00 $26.00 91.820.00 $20.00 51.400,00 536.00 02,520.00 50 TN 028.00 51.400.00 530.00 01.500,00 $65.00 53,250.00 530.00 01.500,00 I $26.00 01,300.00 030.00 01.500,00 537.00 01,850.00 1 FA 10 EA 1 LS 70 LF LS LS 1 FA 400 Hour 1 LS FA LS LS LS LS LS LS 1 LS 2 EA 150 TN 1 LS LS LS LS 54,500.00 94,500.00 95,000,00 55.000,00 '1 5600.00 5600,00 02.500.00 92.500,00 51.150,00 Subtotals UNIT PRICE COST BID TABULATION RO -CON EQUIPMENT SPEC. 1 EBENAL GENERAL- INC. NORDIC CONSTRUCTION. INC SCI INFRASTRUCTURE. LLC CONSTRUCTION INC UNIT UNIT UNIT UNIT UNIT UNIT UNIT PRICE COST PRICE_ COST j PRICE COST PRICE COST PRICE COST PRICE COST PRICE COST $5.000.00 55.000,00 55,000.00 55.000,00 05,000.00 $5,000.00 $5.000.00 05,000,00 05.000,00 55,000.00 05.000,00 55,000.00 55.000,00 55,000.00 I 85.000,00 $5,000.00 q $5.000.00 55.000,00 5450.00 $4.500.00 $500.00 05.000,00 $200.00 02.000,00 0200.00 02.000,00 $92.00 5920.00 5130.00 51,300.00 5335,00 $3.350.00 I 0350.00 53.500,00 p $250.00 52,500,00 91,800.00 01,800.00 $2,000.00 52.000,00 51,000.00 01,000,00 $1.200.00 01,200.00 01,900.00 $1.900.00 51.700,00 $1.700.00 81.700,00 01.700,00 I 51.700.00 51,700.00 II $1.200.00 01.200.00 $35.00 02,450.00 $30.00 52.100.00 535.00 02,450.00 550.00 $3.500.00 I 539.00 82,730,00 030,00 02.100.00 530.00 02.100,00 I 030,00 $2.100.00 528.00 $1.960.00 56,000,00 06,000,00 030,000.00 530,000.00 $8,000.00 $8.000.00 016,500.00 016,500.00 $29,600.00 029,600,00 51,000.00 01,000,00 05.000,00 55,000,00 01.500,00 91,500.00 02.500.00 $2,500.00 528.800.00 828;800,00 010,000.00 910,000.00 510.000,00 010.000,00 510,000.00 910,000.00 010,500.00 010,000.00 010,000.00 910,000,00 538.00 $15,200.00 545.00 018.000.00 542.00 916,800.00 I 540,00 516,000.00 1 $46.00 018,400.00 53,200.00 03200,00 05,000.00 05,000.00 82.000,00 02,000.00 05,000.00 05,000.00 02.600,00 52.600.00 55,000,00 $5,000.00 05,000.00 05,000,00 55.000.00 05.000,00 $5.000.00 05,000.00 05.000,00 05,000.00 559,500.00 559.500.00 596.000.00 096,000,00 0135.000.00 0135,000,00 0110.000,00 5110.000.00 $115,800.00 $115.800.00 022,500.00 522.500.00 06,200.00 56,200.00 $44.000.00 944.000.00 065,000.00 065,500.00 $18.500.00 018.500.00 $24.000.00 024.000.00 040,000.00 540,000.00 030,000.00 $30,000.00 950,000.00 $50,000.00 048,800.00 048.800.00 012,500,00 $12.500.00 010,000.00 010,000.00 07,000.00 07,000.00 I 96,500.00 $6.500.00 $15.300.00 015,300.00 04.200,00 04.200,00 02,000,00 92.000,00 $4.200.00 $4,200.00 95.200,00 05,200.00 52.900,00 62,900.00 $12.000.00 512,000.00 030,000.00 030.000,00 58.000,00 98,000.00 $9,000.00 $9.000.00 015.300,00 015,300.00 54,000.00 04,000,00 05.005.00 $5,000.00 I 51.000.00 $1,000.00 $3.000.00 $3.000.00 $14.100.00 014,100.00 52,500.00 05.000,00 51.250.00 52,500,00 I 02,000.00 04,000,00 $2.300.00 $4,600.00 52,630.00 95,260.00 $26.00 53,900.00 $20.00 $3,000.00 I 0135.00 $20,250.00 030,00 $4.500.00 926,00 93,900.00 02,700.00 02,700.00 525.000.00 025,000.00 I 017.000.00 017,000.00 I 915,000,00 015.000.00 022.000,00 522.000,00 056.000.00 556,000.00 556,000,00 556,000.00 960,000.00 060.000.00 I 950.000,00 050.000.00 058.000.00 958.000,00 018.000.00 018,000.00 91,000.00 $1,000.00 93,000,00 03.000.00 910,000,00 010,000.00 09,000.00 $9,000.00 0294,610.00 0380,900.00 0416,150.00 0416,475.00 $451,505.00 Bid Dale: 08/12/2009 Bid Time: 11:00 a.m. Job No. 08671.00 GARY HARPER R. L ALIA COMPANY I ONSTRUCT COMPANY LLC VLS CONSTRUCTION CO. 7 REALM INC. 5100.00 $12,500.00 I 078,00 09.750,00 5170.00 54,250,00 I 070.00 51,750.00 $30.00 52,100.00 028,00 01,960.00 $20.00 51,000.00 528.00 51,400.00 81,150.00 52,000.00 02,000.00 02.000.00 02.000,00 I 05.000,00 05.000,00 I $3,500.00 03,500.00 020,000.00 020.000.00 051.000,00 051.000.00 940,000.00 040,000.00 560,000.00 560.000,00 51,000,00 91,000.00 $5.000.00 05,000.00 016.000.00 016,000.00 03.500,00 $3.500.00 910,000.00 010,000.00 010.000,00 $10,000.00 010.000,00 $10,000.00 I 010.000,00 010.000.00 542.00 516.800,00 038.00 015,200.00 $40.00 016,000.00 I 042,00 016.800.00 51.600.00 01.600,00 05.000.00 05.000,00 51.600.00 01.600,00 I 05.000.00 55,000,00 05.000.00 05.000.00 05,000.00 05,000.00 i 05,000.00 05,000,00 I $5.000.00 55,000.00 0219.000.00 5219,000.00 0173,000.00 0173.000.00 $130.000.00 0130.000,00 I $230.000.00 0230.000.00 07,000,00 07,000.00 569.000.00 069.000.00 050,000.00 $50.000.00 540,000.00 $40.000.00 040.000,00 040.000,00 1 $40,000.00 940,000.00 $45,000.00 045.000.00 050,000.00 950,000,00 010.000,00 $10,000.00 510.000,00 010.000.00 012.000.00 012,000,00 03,500.00 03,500,00 910,000.00 $10.000.00 94,000.00 04,000.00 I 99.000.00 $9,000.00 93.500.00 03,500,00 910.000.00 010.000,00 $25,000.00 $25,000.00 015.000.00 015,000,00 015,000.00 $15.000.00 02,500.00 02.500,00 55.000.00 05.000,00 52.500.00 02,500.00 03.000.00 03,000,00 $5.000.00 010.000,00 $3.000.00 06.000,00 $3.300.00 06,600.00 07.500,00 915,000.00 $20.00 03,000.00 $21.00 $3,150.00 $30.00 $4,500.00 016.00 02.400.00 05.000.00 05.000,00 010.000.00 910,000.00 918,000.00 018.000,00 $12.500.00 012,500.00 050,000.00 050.000.00 051,000.00 951,000.00 952,500.00 852,500.00 $55.000.00 055,000.00 010,000,00 010.000.00 I 010,000,00 010,000.00 $62.000.00 062,000.00 93.000.00 93,000.00 $458,275.00 0526,320.00 9532,850.00 $562,220.00 TOTAL BID I 0294,610.00 9380,900.00 $416,150.00 5416,475.00 0451,505 DD $458,275.00 $526,320.00 I 9532,850.00 0562,220.00 08/13/2009 CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2009 to 2014 PROJECT Storm Lift Station No. 18 Improvements LINE ITEM 412.02.594.38 .36 PROJECT NO 07 -DRO3 DESCRIPTION Conduct an assessment of Storm Lift Station No. 18 to determine repairs or upgrades that may be needed. Since its installation in 1997 the Allentown area has seen an increase in redevelopment, infill, and expansion JUSTIFICATION of the City's drainage system. In addition, the station only has one pump and must be manually activated during the flood season. Flooding may result in the event of a power or pump failure. STATUS. MAINT IMPACT Manually operating of flood gates and emergency responses will be decreased. COMMENT FINANCIAL Through Estimated (in $000's) 2007 2008 2009 2010 2011 2012 2013 2014 BEYOND TOTAL EXPENSES Design 10 60 70 Land (R/W) 0 Const. Mgmt. 50 50 Construction 300 300 TOTAL EXPENSES 0 10 410 0 0 0 0 0 0 420 FUND SOURCES Awarded Grant Proposed Grant Mitigation Actual Mitigation Expected City Oper Revenue TOTAL SOURCES 0 10 410 0 0 10 410 0 0 0 0 0 0 420 0 420 0 Project Location 2009 2014 Capital Improvement Program 0 0 0 0 148 0 0 0 0 TRANSPORTATION COMMITTEE Meeting Minutes August 17, 2009 5 00 p m. Conference Room 1 PRESENT Councilmembers: De' Sean Quinn, Chair; Joan Hernandez (filling in for Dennis Robertson) and Verna Griffin Staff: Jim Morrow, Frank Iriarte, Bob Giberson, Cyndy Knighton, Ryan Larson, Gail Labanara, Derek Speck and Kimberly Matej Guests: Jeremy Eide CALL TO ORDER. Committee Chair Quinn called the meeting to order at 5 p.m. L PRESENTATIONS No presentations. City of Tukwila Transportation Committee II. BUSINESS AGENDA A. Allentown Storm Water Lift Station Staff is seeking full Council approval to award a bid for the construction of Storm Water Lift Station No 18 (also referred to as Allentown Storm Water Pump Station) Improvements to Ro -Con Equipment Specialist, Inc in the amount of $294,610 Under usual circumstances, this item would be discussed in the Utilities Committee; however, time constraints associated with. anticipated increased river flows and potential flooding from the Howard Hanson Dam and normal Council processes delayed by a 5 Monday (August 31) would delay construction to late September Utilities Committee Chair Kathy Hougardy is aware of these issues and has approved the item to be heard as a Transportation Agenda item. Improvements to the Lift Station will include replacing a single 8 -inch pump with two 10 -inch pumps and will improve pumping capacity and automatic operation. Ro -Con Equipment Specialist, Inc. has not worked on City projects previously; however, their references were found to be satisfactory The item came in under the Engineer's Estimate, but with contingency is over budget. Any overruns will be taken from the Surface Water Fund's ending fund balance. Committee members suggested in consideration of time (saving of approximately four weeks), this item move forward the August 24 COW for discussion and the subsequent Special Meeting on the same date. UNANIMOUS APPROVAL. FORWARD TO AUGUST 24 COW FOR DISCUSSION B Tukwila Urban Center Access Project (Klickitat) Schedule for Formation of a Local Improvement District As an Information Only item, staff is reviewing the proposed schedule for the formation of a Local Improvement District (LID) for the Tukwila Urban Center Access Project (Klickitat) Without a LID, funding for the project will be incomplete and over $8 million of awarded project grants will become ineligible for use. Committee members emphasized the need to oversaturate areas that will receive notification mailings regarding the LID formation in order to increase outreach potential. Additionally, Committee Chair Quinn requested that staff attend the August 24 COW to notify Council of this proposed schedule. FORWARD TO AUGUST 24 COW FOR BRIEFING