COUNCIL AGENDA SYNOPSIS
Meeting Date Prepared by
08/24/09 3M
Initials
Mayor's review
ITEM INFORMATION
Council rgview,
ORIGINAL AGENDA DATE. AUGUST 24, 2009
AGENDA ITEM TITLE Local Improvement District (LID) Formation Schedule for the
Tukwila Urban Center Access Project (Klickitat)
CATEGORY Discussion Motion Resolution Ordinance ❑Bid Award Public Hearing Other
Mtg Date 08/24/09 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date
SPONSOR Council Mayor Adm Svcs DCD Finance Fire Legal P&R Police PW
SPONSOR'S Forming a Local Improvement District (LID) involves many different steps that must be
SUMMARY taken in very specific order and adhere to very specific notification schedules. The
proposed schedule includes an Open House, Public Hearings for the Resolution stating the
Intent to Form a LID, followed by the Ordinance to Form the LID. Construction is still
scheduled to occur in one year with the road to be reopened on November 15, 2010.
REVIEWED BY COW Mtg CA &P Cmte F &S Cmte Transportation Cmte
Utilities Cmte Arts Comm. Parks Comm Planning Comm.
DATE. 08/17/09
RECOMMENDATIONS.
SPONSOR /ADMIN Public Works
COMMIUI E Unanimous Approval, Forward to Committee of the Whole
COST IMPACT FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
RECORD OF COUNCIL ACTION
ATTACHMENTS
Informational Memorandum dated 08/12/09 (formatting revised after TC)
LID Process Outline from Kenyon Disend, PLLC
Minutes from the Transportation Committee meeting of 08/17/09
ITEM NO
4, a,
City of Tukwila
TO Mayor Haggerton
Transportation Committee
FROM: Public Works Director
DATE. August 12, 2009
SUBJECT Tukwila Urban Center Access (Klickitatl Proiect
Project No. 84 -RW19
LID Formation Schedule
DISCUSSION
INFORMATIONAL MEMORANDUM
ISSUE
Proposed schedule and steps for the Local Improvement District (LID) formation
BACKGROUND
Jim Haggerton, Mayor
The history for the Tukwila Urban Center (TUC) Access (Klickitat) Project is quite extensive as it
has been ongoing for many years Specific to the financing, staff has aggressively pursued
grant funds in addition to other funding sources. in 2005, the Transportation Improvement Board
(TIB) informed the City that in order to be competitive for TIB grant funding, formation of a LID
was strongly recommended In response to the TIB, the City retained Macaulay Associates to
prepare a LID Feasibility Report, a Preliminary Special Benefit/Proportional Assessment Study,
and a Preliminary Assessment Roll Due to the City's demonstrated commitment to forming a
LID, Tukwila was successful in obtaining a $5 million grant from TIB The Preliminary
Assessment Roll is nearly complete and will be presented to the Council for action in
September
Throughout the preliminary engineering phase of the TUC Access project, the City has pursued
No- Protest Agreements from property owners as development has occurred These agreements
state that the property owner will not protest the formation of a LID for the TUC Access
(Klickitat) Project. The property owner can protest the Final Assessment Roll amount. No-
Protest Agreements have been signed by Westfield Mall, Wig Development, and La Pianta.
Forming a LID involves many different steps that must be taken in very specific order and
adhere to very specific notification schedules In 2006, the City retained Foster Pepper, PLLC
for Bond Counsel services The City Attorney's office, through Kenyon Disend staff, will be
providing Special Counsel services related to the LID formation A detailed schedule of steps
has been developed with the aid of the City's legal counsel team.
The proposed schedule includes an extra step not required to meet legal guidelines an Open
House for property owners, business owners, and tenants of the LID area. Although this
schedule does not show all the remaining steps necessary to get the project out to bid this fall,
this aggressive schedule shows the key milestones that must be met to form the LID Without
the LID, the funding package for the TUC Access project is incomplete Without the rest of the
funding in place so that the project can be advertised for construction, over $8 million in grants
which have already been awarded to this project will become unavailable for use. Grant funding
INFORMATIONAL MEMO
Page 2
agencies have been hit as hard as everyone else in this difficult economic climate and projects
unable to go to construction this year or next will have the funding cancelled and reassigned to
projects which can be built.
The proposed schedule, showing only key milestones, is shown below*
8/17/09
8/24/09
8/28/09
9/4/09
9/8/09
9/14/09
9/21/09
10/2/09
10/5/09
10/12/09
10/19/09
11/1/09-11/15/09
12/16/09-12/31/09
January 2010
Jan Feb 2010
Feb March 2010
March Nov 2010
11/15/10
RECOMMENDATION
Transportation Committee LID Schedule and Steps
Committee of the Whole LID Schedule and Steps
Open House For property owners businesses and tenants
Notification to Property Owners For Public Hearing on Resolution to Form LID
Transportation Committee Resolution of Intent to Form LID
Committee of the Whole Resolution of Intent to Form LID
Regular Council Public Hearing Adoption of Resolution of Intent to Form LID
Notification to Property Owners For Public Hearing on Ordinance to Form LID
Transportation Committee Ordinance to Form LID
Committee of the Whole Ordinance to Form LID
Regular Council: Public Hearing and Adoption of Ordinance to Form LID
Advertise for Construction Bid 4 week time period (3 weeks required by federal
funds 1 week extra for holiday)
Bids Due with Bid Opening
Transportation Committee Award of construction contract to successful bidder
City Council (C 0 W Regular) Award of construction contract
Notice to Proceed to successful bidder
Construction of project
Roadway open to traffic substantial completion of construction
Information only Transportation Committee requested that this item be forwarded to the August
24, 2009 Committee of the Whole to notify Council
W' \PW Eng \PROJECTS\A- RW RS Projects \84RW19 TUC Access (Klickitat) \INFO MEMO LID Formation Schedule 8 -12 -09 gl.doc
MICHAEL R. KENYON
BRUCE L. DISEND
SHELLEY M. KERSLAKE
SANDRA S MEADOWCROFT
CHRIS D BACHA
BOB C. STERBANK
KENYON DISEND, PLLC
THE MUNICIPAL LAW FIRM
11 FRONT STREET SOUTH
ISSAQUAH, WASHINGTON 98027 3820
WWW KENYONDISEND COM
(425) 392 7090 (206) 628 -9059
FAX (425) 392 7071
LID PROCESS OUTLINE
I. COMMENCEMENT PETITION METHOD OF FORMATION
1 Filing of a petition signed by owners of property aggregating a majority of
the area of the proposed Local Improvement District (LID) RCW 35 43 120
2. Certification of sufficiency of petition by the designated officer RCW
35 43 130
3 Designated person (usually Engineer) prepares cost estimate, assembles
other statutorily required information and certifies it to the council. RCW 35 43 130
II.
COMMENCEMENT RESOLUTION METHOD OF FORMATION
1 City Council adopts a resolution declaring its intention to form LID
RCW 35 43 130
a. Resolution declaring intent to form LID
b Minutes (or excerpts) of council meeting showing passage of such
resolution.
III. STEPS UNDER BOTH RESOLUTION AND PETITION METHODS OF
FORMATION
1 Determine whether LID formation is categorically exempt from
procedures of State Environmental Policy Act (SEPA), Chapter 43.21C RCW and
Chapter 197 -11 WAC If not categorically exempt, prepare and issue Environmental
Checklist and Determination of Non Significance (DNS) (or Environmental Impact
Statement (EIS)) before adopting ordinance creating LID and ordering improvements.
Environmental Checklist and DNS (or EIS)
2 If in response to a petition, adopt resolution fixing hearing on forming
LID If resolution method is being used, designated person prepares cost estimate,
F\APPS \CIV\TUKWILA \Other \LID Formation Outline.doc 1
SERVING WASHINGTON CITIES SINCE 1993
MARGARET J KING
KARI L. SAND
NOEL R. TREAT
STEVE I VICTOR
RENEE G. WALLS
SARA B SPRINGER
assembles other statutorily required information and certifies it to the council. RCW
35 43 130
3 The resolution must provide for a heanng on formation whether petition or
resolution method is used. RCW 35 43 130- 150, 35 43 125
4 Mail notice of hearing at least 15 days before the date fixed for hearing to
the owners as shown on the rolls of the County Assessor of all property (a) within the
proposed LID, and (b) outside of the proposed LID, when such property is required at the
time of notice to be connected to the proposed sewer or water facilities as a condition of
Federal Housing Administration loan qualification. RCW 35 43 150, 35 43.270 If state
owned property will be assessed, notice must be given by registered or certified mail at
least 30 days prior to hearing. RCW 79 44 040 Affidavit of mailing with form of
notices attached.
5 Publish resolution declaring intention or resolution fixing hearing on
forming LID in at least two consecutive issues of the official newspaper, the first
publication being at least 15 days prior to the hearing. RCW 35 43 140 Affidavit of
publication of both such publications.
6 Conduct hearing on formation of LID RCW 35 43 140
a. Minutes of council meeting, committee meeting, or proceedings
before hearing officer reflecting such hearing, including
recommendation of committee or hearing officer
b Resolution designating hearing examiner or committee, if
authorized.
7 Pass ordinance creating LID and ordering the improvement. RCW
35 43 070
a. Ordinance creating LID
b Minutes (or excerpts) of council meeting showing passage of such
ordinance
8 If SEPA review required for LID formation, give official notice of the date
and place for commencing an appeal under SEPA. RCW 43.21C 075(5), 43.21C 080;
WAC 197 -11- 680(5)
9 Publish ordinance creating LID in official newspaper
a. Affidavit of publication of formation ordinance.
F\APPS \CIV \TUKWILA \Other\LID Formation Outline.doc 2
10 Within 15 days after creation of LID, file ordinance creating LID,
boundary diagram of LID and preliminary assessment roll with City Treasurer
(sometimes referred to as Finance Director) Thereafter, City Treasurer should
immediately post the proposed assessment roll upon his or her index of local
improvement assessments RCW 35 50 005
11 If LID contains "farm and agricultural land" or "timber land" as defined in
RCW 84 34 310, file notice of foimation of LID with County Assessor and county
legislative body RCW 84 34 320
a. If LID does not contain such farm and agricultural land or timber
land, a certificate from the County Assessor to that effect; or
b If LID does contain such farm and agricultural land or timber land,
a certificate or receipt of fihng such notice.
12 County Assessor shall mail notice of formation of LID to owners of "farm
and agricultural land" or "timber land," as defined in RCW 84 34.310 RCW 84.34 320
a. Certificate or other evidence of mailing such notice.
13 Expiration of protest period for LID formed by resolution method 30 days
following passage of ordinance forming LID RCW 35 43 180
a. Clerk's or engineer's certificate of maximum percentage of protest
during that period.
14 Expiration of time limitation on litigation. No lawsuit may be maintained
challenging formation of the LID if not filed within 30 days after passage of the
formation ordinance (if initiated by petition) or after expiration of the 30 -day protest
period (if initiated by resolution) RCW 35 43 100
15 Authorize and publish call for bids for construction. RCW 35.22.620,
35.23.352, 35A.40.210, 35 43 190
a. Affidavit of publication of bid call
16 Receive bids
17 Accept best bid and award contract.
a. Minutes (or excerpts) of council meeting showing action on bids.
18 Authorize interim financing. RCW 35 45 130, 39 50 RCW
a. Ordinance authorizing interim financing.
F\APPS \CIV \TUKWILA \Other \LID Formation Outline.doc 3
b Minutes (or excerpts) of council meeting reflecting passage of such
ordinance
c Affidavit of publication of such ordinance
19 On completion of project, obtain necessary state clearances, accept work
and determine total cost. RCW 35 44 020, 60.28 040 (Dept. of Revenue), 51 12 050
(Dept. of Labor and Industries)
20 Engineer to prepare final assessment roll and file it with clerk.
21 Adopt resolution or motion setting time, date and place of assessment roll
hearing. RCW 35 44 070
a. Resolution.
b Minutes (or excerpts) of council meeting reflecting adoption of
such resolution or motion.
22 Mail notice of hearing to the owners of all property listed on the
assessment roll as those owners' names appear on the records of the County Treasurer at
least 15 days before date fixed for hearing. RCW 35 44 090
a. Affidavit or certificate of mailing with copy of notice attached.
23 Publish notice of hearing at least once a week for two consecutive weeks
in the official newspaper, the last publication being at least 15 days before the hearing
date RCW 35 44 090
a. Affidavit of such publication.
24 Conduct final assessment roll hearing, considering objections and
overruling them or modifying assessments. RCW 35 55 070, 35 44 100
a. Minutes of council meeting, committee meeting, or proceedings
before hearing officer reflecting such hearing, including
recommendation of committee or hearing officer
b Resolution designating hearing examiner or committee, if
authorized.
25 If any assessments are increased, set a new hearing and publish and mail
notice to those properties with increased assessments in the same manner as for the
original assessment roll hearing. RCW 35 44 120
F•\APPS \CIV\TUKWILA \Other \LID Formation Outline.doc 4
26 Pass ordinance confirming and levying assessments as finally approved.
RCW 35 44 100
a. Ordinance confirming assessment roll
b Minutes (or excerpts) of council meeting showing passage of such
ordinance.
27 Publish ordinance confirming assessments.
a. Affidavit of such publication.
28 In LID containing any "farm and agricultural land" or "timber land" as
defined in RCW 84 34.310, file notice with County Assessor, County legislative
authority and City Treasurer of adoption and confirmation of final assessment roll. RCW
84 34.320
29 Appeal period expires 10 days after the ordinance confirming assessment
roll becomes effective RCW 35 44 190 -.210
30 City Treasurer publishes in the official newspaper once a week for two
consecutive weeks, and (within 15 days after the first such publication) mails to all
property owners, notice that roll is filed for collection. RCW 35 49 010
a. Affidavit of such publications.
b Affidavit or certificate of such mailing with notice attached.
31 Prepayment period expires 30 days after first publication of Treasurer's
notice. RCW 35 49 010, 35 49 050
a. Treasurer's certification of amount of prepayment and balance of
unpaid assessments.
32 Sell bonds after expiration of prepayment period (bonds to be dated and
delivered no earlier than 20 days after conclusion of prepayment period) at public or
private sale. RCW 35 45 010, 35 45 040
33 Pass and publish bond ordinance authorizing sale.
a. Ordinance.
b Minutes (or excerpts) of council meeting reflecting passage of such
ordinance
c Affidavit of publication of such ordinance.
F•\APPS \CIV\TUKWILA \Other\LID Formation Outline.doc 5
TRANSPORTATION COMMITTEE
Meeting Minutes
August 17, 2009 5 00 p.m. Conference Room 1
City of Tukwila
a
Transportation Committee
PRESENT
Councilmembers De' Sean Quinn, Chair; Joan Hernandez (filling in for Dennis Robertson) and Verna Griffin
Staff: Jim Morrow, Frank Iriarte, Bob Giberson, Cyndy Knighton, Ryan Larson, Gail Labanara, Derek
Speck and Kimberly Matej
Guests. Jeremy Eide
CALL TO ORDER. Committee Chair Quinn called the meeting to order at 5 p.m.
I. PRESENTATIONS
No presentations.
H. BUSINESS AGENDA
A. Allentown Storm Water Lift Station
Staff is seeking full Council approval to award a bid for the construction of Storm Water Lift Station No 18
(also referred to as Allentown Storm Water Pump Station) Improvements to Ro -Con Equipment Specialist,
Inc in the amount of $294,610
Under usual circumstances, this item would be discussed in the Utilities Committee; however, time
constraints associated with. anticipated increased river flows and potential flooding from the Howard
Hanson Dam and normal Council processes delayed by a 5 Monday (August 31) would delay construction
to late September Utilities Committee Chair Kathy Hougardy is aware of these issues and has approved the
item to be heard as a Transportation Agenda item.
Improvements to the Lift Station will include replacing a single 8 -inch pump with two 10 -inch pumps and
will improve pumping capacity and automatic operation.
Ro -Con Equipment Specialist, Inc has not worked on City projects previously; however, their references
were found to be satisfactory The item came in under the Engineer's Estimate, but with contingency is over
budget. Any overruns will be taken from the Surface Water Fund's ending fund balance.
Committee members suggested in consideration of time (saving of approximately four weeks), this item
move forward the August 24 COW for discussion and the subsequent Special Meeting on the same date.
UNANIMOUS APPROVAL. FORWARD TO AUGUST 24 COW FOR DISCUSSION
B Tukwila Urban Center Access Proiect Klickitat) Schedule for Formation of a Local Improvement District
As an Information Only item, staff is reviewing the proposed schedule for the formation of a Local
Improvement District (LID) for the Tukwila Urban Center Access Project (Klickitat).
Without a LID, funding for the project will be incomplete and over $8 million of awarded project grants will
become ineligible for use.
Committee members emphasized the need to oversaturate areas that will receive notification mailings
regarding the LID formation in order to increase outreach potential. Additionally, Committee Chair Quinn
requested that staff attend the August 24 COW to notify Council of this proposed schedule. FORWARD
TO AUGUST 24 COW FOR BRIEFING