HomeMy WebLinkAboutCOW 2009-07-27 Item 5D - Contract Supplement #5 - Tukwila Urban Center Access (Klickitat) with HNTB for $63,350COUNCIL AGENDA SYNOPSIS
Meeting Date Prepared
07/27/09 7M
08/03/09 3M
b Mayor's review 1 Council review
Initials
ITEM INFORMATION
ITEM NO.
CAS NUMBER: 09-108
ORIGINAL AGENDA DATE: JULY 27, 2009
AGENDA ITEM TITLE Tukwila Urban Center Access Project (Klickitat)
Design Supplement No. 5 with HNTB
CATEGORY Discussion Motion Resolution Ordinance Bid Award Public Hearing Other
Mtg Date 07/27/09 Mtg Date 08/03/09 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date
SPONSOR Council Mayor Adm Svcs DCD Finance Fire L Legal P&R Police PW
SPONSOR'S The design of the Tukwila Urban Center Access Project (Klickitat) has a number of
SUMMARY outstanding issues requiring this additional Supplement No. 5 with HNTB. There are full
channelization plans needing WSDOT approval, new drainage requirements needing
Department of Ecology's approval as well as property coordination and LID support.
Council is being asked to approve Supplement No. 5 for $63,350.00 with HNTB.
REVIEWED BY COW Mtg. CA &P Cmte F &S Cmte Transportation Cmte
Utilities Cmte Arts Comm. Parks Comm. Planning Comm.
DA'Z'E: 07/20/09
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works
CoMMIF Unanimous Approval; Forward to Committee of the Whole
COST IMPACT FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$63,350.00 $60,000.00 $0.00
Fund Source: 104.02 ARTERIAL STREETS (PAGE 15, 2009 CIP)
Comments: Additional design funds will be used from the project's construction funds
MTG. DATE
07/27/09
08/03/09
MTG. DATE
07/27/09
08/03/09
RECORD OF COUNCIL ACTION
ATTACHMENTS
Informational Memorandum dated 07/15/09
HNTB Supplement No. 5
2009 CIP page 15
Minutes from the Transportation Committee meeting of 07/20/09
City of Tukwila
Mayor Haggerton
Transportation Committee
FROM: Public Works Directo
DATE: July 15, 2009
TO:
Attachments: Ag 05 -071 Supplemental Agreement No. 5
2009 CIP page 15
INFORMATIONAL MEMORANDUM
SUBJECT: Tukwila Urban Center Access Proiect (Klickitat)
Proiect No. 84 -RW19. Contract 05 -071 with HNTB
SupDlemental Agreement No. 5
W: \PW Eng \PROJECTS\A- RW RS Projects \84rw19 Klickitat_Sctr Pkwy_15 Access Rev \INFO MEMO HNTB Supp #5 7 -15 -09 gl.doc
Jim Haggerton, Mayor
ISSUE
Approve Supplemental Agreement No. 5 to the HNTB contract for additional design and permit work
associated with the Tukwila Urban Center Access Project (Klickitat).
BACKGROUND
The design of the Tukwila Urban Access Improvement Project has a number of outstanding issues
requiring resolution. These issues include:
WSDOT approvals Design of the buttonhook ramp
Property coordination and Construction phasing and staging
associated design efforts
ANALYSIS
Additional work is required to complete the design, permitting, Local Improvement District support
and final WSDOT approvals. WSDOT has informed us that they will require a full channelization plan
for approval and deviations of all design elements that do not meet WSDOT standards on
Southcenter Parkway and Klickitat Drive. Previously, WSDOT had verbally approved the use of
AASHTO standards, which is the typical minimum standard for City streets. WSDOT standards are
higher for freeways because highways are designed for higher speeds and volumes.
In addition, the Washington State Department of Ecology's drainage requirements have changed
and an assessment of the potential impacts to the project is needed. Supplement No. 5 will have
HNTB identify all remaining design work and permits needed to complete the design package for
advertisement and assist the City with coordination of design approvals for work within the State
rig ht -of -way.
There is currently $60,000 budgeted for design in 2009/2010. Additional design funds will be used
from the $20,662,000.00 construction funds if we rely on the current climate of favorable bids.
RECOMMENDATION
Approve Supplement No. 5 with HNTB for additional design and permitting services in the amount of
$63,350.00 and consider this item at the July 27, 2009 COW and the August 3, 2009 Regular
Meeting.
Ink
WI Washington State
Department of Transportation
Supplemental Agreement
Organization and Address Phone:
City of Tukwila
Number 5 Public Works Department
6300 Southcenter Blvd., Suite #100
Original Agreement Number Tukwila, WA 98188
05 -071 206 -431 -3665
Project Number Execution Date Completion Date
84 -RW19 April 6, 2005 December 31, 2009
Project Title New Maximum Amount Payable
Klickitat/Southcenter Parkway Access $3,270,311
Improvement Project
Description of Work
Final PS &E, including 60 90 and 100% design, and delivery of final documents for
construction advertisement.
The Local Agency of Tukwila desires to supplement the agreement entered into with HNTB Corporation and
executed on April 6, 2005 and identified as Agreement No. 05 -071. All provisions in the basic agreement remain in
effect except as expressly modified by this supplement. The changes to the agreement are described as follows:
I I
Section II, SCOPE OF WORK, shall be amended as follows:
The scope of work for this project is supplemented as detailed in the attached Exhibit A, and by
this reference made part of this Agreement.
I I
Section IV, TIME FOR BEGINNING AND COMPLETION, shall be amended as follows:
All work under this AGREEMENT shall be completed by the date shown in the heading of this
SUPPLEMENTAL AGREEMENT under completion date.
III
Section V, PAYMENT, shall be amended as follows:
Compensation due to Consultant for work performed or services rendered for this project is
supplemented as detailed in the attached Exhibit B, and by this reference made part of this
Agreement.
Original Supp. No. Supp. No. Supp. No. Supp. No. Supp. No.
Agreement 1 2 3 4 5 Total
Total Amount $1,168,322 $1,956,680 $17,200 $0 $14,759 $63,350 $3,220,311
Authorized
Management $50,000 $0 $0 $0 $0 $0 $50,000
Reserve Fund
Maximum Amount $1,218,322 $3,175,002 $3,192,202 $3,192,202 $3,206,961 $3,270,311 $3,270,311
Payable
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces
below and return to is office for final action.
By: HNTB orati
Date
DOT Form 140 -063 EF
Revised 9/2005
7 s
By: City of Tukwila
Approving Authority Signature
Date
EXHIBIT A -5
SCOPE OF WORK
TUKWILA ACCESS IMPROVEMENT PROJECT:
KLICKITAT DRIVE /SOUTHCENTER PARKWAY AREA
Supplemental Agreement Number 5
SUPPLEMENTAL AGREEMENT NUMBER 5
a1NTB
Exhibit A -5 Page 1 of 4
BACKGROUND
The design of the Tukwila Urban Access Improvement Project was shelved at the 100% design in
May of 2007. At the time it was shelved, there were a number of outstanding issues requiring
resolution once the project design efforts resumed. These issues include but are not limited to:
WSDOT approvals, design of the buttonhook ramp, property coordination and associated design
efforts, construction phasing and staging. In addition, the Washington State Depai linent of
Ecology's drainage requirements have changed and an assessment of the potential impacts to the
project is needed. To complete the project design and prepare an ad ready contract package the
City and the CONSULTANT have agreed upon a two stage approach to complete the design and
prepare an ad ready contract package. The first stage of this approach is reflected in the
following scope of work.
PURPOSE OF SUPPLEMENT #5
The purpose of Supplement #5 is to identify all remaining design work and permits needed to
complete the contract PS &E package for advertisement, and assist the City with coordination of
design approvals for work within the State right -of -way.
1.0 PROJECT MANAGEMENT
The CONSULTANT will provide overall project administration and management for 4 months;
the estimated duration of the coordination and assessment of potential design changes to the
project and initiation of the final PS &E preparation.
This effort includes the following tasks:
Minor updates to the current project cost estimate
Preparing and updating the project schedule as needed
Monthly budget status /forecast using Earned Value method
Monthly progress reports and invoices
Up to 4 bi- weekly project management team meetings, agendas, meeting summaries, at
Tukwila offices with up to 3 CONSULTANT staff
Up to 4 CONSULTANT team design meetings, with up to 5 staff, to coordinate work
between CONSULTANT staff
2.0 WSDOT DESIGN COORDINATION
Supplemental Agreement Number 5
NTB
The purpose of this task is to assist the City with coordination of WSDOT design approvals
required for the project. These approvals are in addition to existing Local Agency agreement
between the City of Tukwila and WSDOT and the deviation for the 2' shoulder currently under
review.
The CONSULTANT shall provide technical assistance to the City by responding to requests for
information regarding design issues, attending meetings (up to 4 with the City and WSDOT,
Exhibit A -5 Page 2 of 4
responding to WSDOT comments on the design, and supporting the City in the process for
deviation and limited access revision approvals.
3.0 REINITIATION OF PS &E COMPLETION
4.1 Assessment of Drainage Design Updates
INTB
This task includes determining an approach for the completion of PS &E based on changed
conditions and the findings of Supplement #5 Tasks 1 and 2. For budgeting purposes 128 hours
have been included. The remainder of work needed to complete the ad -ready PS &E will be
included in another supplemental agreement.
4.0 REQUIRED SERVICES CURRENTLY UNDER NEGOTIATION
The following tasks are required for completion of the plans and specifications. These additional
work items are under negotiation for scope and fee for a future supplemental agreement.
The purpose of this task is to assess the specific tasks required to update the drainage design
based the CONSULTANT's review of the design. The CONSULTANT's review of the design
will be based on changed project conditions and the addition of the current WSDOT buttonhook
ramp design. The CONSULTANT's review includes identifying impacts of revisions to the
drainage design on other project design elements including structures and walls.
4.2 DOE Coordination and Related Assessment of Drainage Impacts
The purpose of this task is to determine if the drainage design approach used in the existing
project design will be accepted by the DOE. The existing drainage design followed the 2004
Highway Runoff Manual (HRM). In a letter dated March 15, 2004 from DOE, projects designed
using the 2004 HRM were deemed compliant through the 2005 -2007 biennium. This task will be
accomplished through direct coordination with DOE during which the CONSULTANT shall seek
acceptance of the existing drainage design. If DOE does not accept the existing drainage design
approach, this task will assess the impacts on the drainage design and the rest of the project
design.
4.3 Status of Environmental Documents and Permits
The purpose of this task is to assess the status of environmental documentation and permits and
identify the impacts of both on the current drainage design.
The CONSULTANT shall prepare a permit matrix that identifies the permit name, permitting
agency, permit trigger, documentation required, anticipated timeline for permit approval, and
responsible project team member.
Supplemental Agreement Number 5
Exhibit A -5 Page 3 of 4
4.4 Design Completion
INTB
The design of the Tukwila Urban Access Improvement Project was shelved at the 100% design in
May of 2007. At the time it was shelved, there were a number of outstanding items requiring
completion once the project design efforts resumed. These include:
WSDOT approvals.
Permits.
Updates to project specifications.
Design of the buttonhook ramp and related potential impacts to Hydrology report,
drainage design, plans, grading, removals, erosion control and site preparation plans for
project.
Design work at McDonald's entrance and parking.
Maintenance of Traffic and Construction Phasing and Staging plans.
Design updates to reflect changed conditions in project area.
Coordination with property owners on the west side of project to convey the current
design which has new curb, gutter, sidewalk, driveway and storm sewer reconstruction on
the west side of the project
Address the removal and re- setting of private business monument signs on the project.
These are located on the Doubletree and Legacy properties.
Confirm final paving limits between disciplines.
Ensure thorough WSDOT review and approval of signing plans.
Ensure thorough WSDOT review of the roadway improvements adjacent to the northern
interstate ramp terminal where the project currently proposes to remove and replace the
median island.
The resolution of the above outstanding issues will allow the completion of the following
design elements of the project.
Permitting
Right of way
Roadway channelization
Signals and interconnect
Illumination
Maintenance of Traffic
Detour plans
Construction staging and phasing
Landscape design and architectural treatments
Signing
Drainage plans, profiles and details
Erosion and sediment control
Utility coordination
Earthwork
Bridge and other structures design
Supplemental Agreement Number 5
Exhibit A -5 Page 4 of 4
Exhibit B -5
Consultant Fee Determination Summary Sheet
(Negotiated Hourly Rates)
Klickitat /Southcenter Parkway Access Improvement Project
Supplemental Agreement No. 5
LABOR COSTS
Staff Classification Hours Rate Total Cost
Principal 2 $215.44 $431
Project Manager 92 $182.73 $16,811
Sr. Engineering Manager 68 $214.52 $14,587
Sr. Landscape Architect 8 $171.76 $1,374
Senior Project Engineer 8 $147.51 $1,180
Project Engineer 48 $134.25 $6,444
Design Engineer 8 $123.04 $984
Landscape Architect 8 $91.02 $728
Jr. Engineer 8 $80.73 $646
Sr. Technician 40 $96.74 $3,870
Project Administrator 32 $110.69 $3,542
Administrative Assistant 0 $66.32 $0
REIMBURSEABLE COSTS
SUBCONSULTANT COSTS
IROTAL COSTS
SUB -TOTAL LABOR COSTS
Travel:
Local Travel (Mileage, Parking) $500
Reproduction: $500
Other: $0
SUB -TOTAL REIMBURSEABLE COSTS $1,000
HDR Engineering, Inc.
PACE Engineers, Inc.
HNTB Corporation
322 $50,598
$9,0331
$2,7201
$63,35011
HNTB Corporation
Summary of Hours
Klickitat/Southcenter Parkway Access Improvement Project
Supplemental Agreement No. 5
Staff Cassifications
Design
Sr. Sr. Engineer/ HDR PACE
Project Engineering Landscape Sr. Project Project Traffic Landscape Jr. Sr. Project Admin. HNTB Subtotal Subtotal
Task Principal Manager Mgr. Architect Engineer Engineer Engineer Architect Engineer Technician Admin. Assist Subtotal Hours Hours TOTAL
Task1 •IProiectManagement "I'.. I I. I I. I.,,..•;.,..,I I" 1,.:., ..I I": 1. 1
I 1 21 481 401 1 1 1 1 1 I 1 241 1 114 341 0 148
Task 2 IWSDOT Design Coordination I 'I :....1, I I 1,, I I I 1, I I 1 1
I I 1 28 1 20 1 I I 40 1 I 1 1 32 1 I 1 120 01 0 120
Task 3 :Ilnitiation of PS &E Completion:...:.; 1:. I:, 1, I i.' I I L I I I 1.
I 1 161 81 81 81 81 81 81 81 81 81 1 88 241 16 128
I Total Hours by Classifications 21 921 681 81 81 481 81 81 81 401 321 q 3221 581 161 396
Klickitat /Southcenter Parkway Access Improvement Project
Supplemental Agreement No. 5
LABOR COSTS
Staff Classification
REIMBURSEABLE COSTS
Exhibit B -5
Consultant Fee Determination Summary Sheet
Exhibit B -5
Consultant I-ee Determination Summary Sheet
(Negotiated Hourly Rates)
HDR Engineering, Inc.
Hours Rate Total Cost'
Principal 0 $213.06 $0
Project Manager 24 $194.91 $4,678
Sr. Project Engineer 8 $129.68 $1,037
Project Engineer 12 $119.00 $1,428
Sr. Administrator 10 $107.93 $1,079
Administrator 4 $77.58 $310
SUBTOTAL LABOR COSTS 58 $8,5331
Travel (Mileage, Parking): $50
Reproduction: $300
Postage, Express Mail, Courier $10
Other: $140
SUBTOTAL REIMBURSEABLE COSTS $500
IITOTAL COSTS $9,03311
Task Principal
Task 1 •.1 Project Management
1
Task 2 IWSDOT Design Coordination I
I
Task 3 Ilnitiation of PS &E Completion
I
I Total hours by Classification
HDR Engineering, Inc.
Summary of Hours
Klickitat/Southcenter Parkway Access Improvement Project
Supplemental Agreement No. 5
01
Sr.
Project Sr. Project Project Administra Administra
Manager Engineer Engineer tor tor
1
16 41 101 4
8
24
8
81
81 121
I I
1
101 4
Staff Cassifications
01 0
01 0
01 01 0
HDR
Subbtotal
34
0
24
58
M
LABOR COSTS
Staff Classification
Senior Principal Surveyor
REIMBURSEABLE COSTS
IITOTAL COSTS
Exhibit B -5
Consultant Fee Determination Summary Sheet
(Negotiated Hourly Rates)
Klickitat /Southcenter Parkway Access Improvement Project
Supplemental Agreement No. 5
PACE Engineers, Inc.
Hours Rate Total Cost
16 $145.00 $2,320
Total Hours 16
TOTAL SALARY COSTS $2,3201
Travel (Mileage, Parking): $100
Reproduction: $100
Other: $200
TOTAL REIMBURSEABLE COSTS $400
Task
Task 1 (Project Management
Task.2 IWSDOT Design Coordination
Task 3 IInitiation of PS &E Completion
PACE Engineers, Inc.
Summary of Hours
Klickitat/Southcenter Parkway Access Improvement Project
Supplemental Agreement No. 5
Total hours by Classification
Staff Cassifications 1
Sr. Principal Surveyor
1 61
PACE
TOTAL
0
161 16
PROJECT: Tukwila Urban Center Access (Klickitat -S\C Pkwy Access Revision)
DESCRIPTION: Improve traffic flow on Southcenter Parkway, Klickitat Drive and Strander Boulevard by constructing an
underpass for the southbound lane on Southcenter Pkwy. Coordinate with WSDOT on 1 -5 on- ramps.
JUSTIFICATION: Provide needed future traffic capacity, safety improvements and reduce accidents.
STATUS: Design Report completed in 2005, design in 2006 2007, and LID formation to begin in 2008. Proposed
Southcenter Pkwy /Klickitat road closure for duration of construction will save a significant amount of costs.
MAINT. IMPACT: Overlay on a 10 -20 year cycle.
Project is on Impact Fee List. Federal funds for $3.1m. Assumes Mall mitigation of $1.5m with $611k cash and
COMMENT: $846k ROW, Boeing (Longacres) mitigation is $65k, ACME Bowling $115k. Construction grants; State TIB $5m,
Federal STP $3m, and State funds $250k. Local Improvement District (LID) is $11.8 million.
FINANCIAL Through Estimated
(in $000's) 2007 2008 2009 2010 2011 2012 2013 2014 BEYOND TOTAL
EXPENSES
Design 3,164 193 60 3,417
LID Expenses 113 27 80 220
Land(R/W) 2 854 992 1,848
Const. Mgmt. 2,818 2,818
Construction 20,662 20,662
TOTAL EXPENSES 3,279 1,074 1,132 23,480 0 0 0 0 0 28,965
FUND SOURCES
Awarded Fed Grant 974 3,000 3,974
Earmark future) 1,324 436 401 2,161
Awarded State Grant 5,250 5,250
LID 11,808 11,808
Mitigation Actual 183 1,601 1,784
ROW Donation 846 846
Impact Fees 331 331
City Oper. Revenue 798 (1,809) 731 3,091 0 0 0 0 0 2,811
TOTAL SOURCES 3,279 1,074 1,132 23,480 0 0 0 0 0 28,965
Project Location
2009 2014 Capital Improvement Program
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2009 to 2014
LINE ITEM: 104.02.595. .20 PROJECT NO. 84 -RW19
15
TRANSPORTATION COMMITTEE
Meeting Minutes
July 20, 2009 5:00 p.m. Conference Room 1
City of Tukwila
Transportation Committee
PRESENT
Councilmembers: De' Sean Quinn, Chair; Joan Hernandez (filling in for Dennis Robertson) and Verna Griffin
Staff: Bob Giberson, Cyndy Knighton, Jon Harrison, Gail Labanara and Kimberly Matej
Guests: Jeremy Eide
CALL TO ORDER: Committee Chair Quinn called the meeting to order at 5:00 p.m.
I. PRESENTATIONS
No presentations.
II. BUSINESS AGENDA
A. Tukwila Urban Center Access Proiect (Klickitat) HNTB Design Supplemental Aareement No. 5
Staff is seeking full Council approval for Supplemental Agreement No. 5 with HNTB Corporation in the
amount of $63,350 for additional design work and permitting associated with the Tukwila Urban Center
Access Project (Klickitat).
his project is returning to Committee after lying dormant since mid -2007 due to several issues regarding to
right -of -way acquisition, local improvement district formation and Washington State Department of
Transportation requirements. In 2007, the project design was considered to 100% shelf ready; however, now
that the project is ready to move forward again, HTNB's lead consultant and design engineer services are
needed to work through WSDOT and utilities coordination as well as the continued process of right -of -way
acquisition.
$60,000 has been identified for design services for this project in 2009. The additional $3,350 of funding for
the supplemental agreement will be taken from the project's 2010 construction funding. Construction
funding is anticipated to be under budget if the current bidding climate remains favorable.
Staff estimates that 90% of the work outlined in this supplemental agreement will be completed within 6 -8
weeks. Based on the interest of this project among Washington, D.C. constituents, Committee Chair Quinn
requested that staff provide an informational memo, when appropriate, that outlines timelines relative to
project grants, as well as when and if grant funds may be at risk. UNANIMOUS APPROVAL.
FORWARD TO JULY 27 COW FOR DISCUSSION.
III. MISCELLANEOUS
Meeting adjourned at 5:18 p.m.
Next meeting: Monday, August 3, 2009 5:00 p.m. Conference Room 1
Committee Chair Approval
Minutes by KAM.