HomeMy WebLinkAboutCOW 2009-06-08 Item 4F - Bid Award - Green River Construction for 2009 Small Drainage Program for $571,186.50 COUNCIL AGENDA SYNOPSIS c 1LA i
Initials ITEM NO.
:4 S. 1 Meeting Date 1 Prepared by 1 Mayor's review 1 Council review
f 9 1 06/08/09 1 JM, A4 1 (L /y r
9OB 1 06/15/09 I JM 1 4
U I
1 1 1 1
I L i R-
ITEM INFORMATION
CAS NUMBER: 09-081 I ORIGINAL AGENDA DATE: JUNE 8, 2009
AGENDA Bid Award for 2009 Small Drainage Program
CATEGORY Discussion Motion Resolution Ordinance Bid Award Public Hearing Other
Mtg Date 06/08/09 Mtg Date Mtg Date Mtg Date Mtg Date 06/15/09 Mtg Date Mtg Date
SPONSOR Council Mayor El Adm Svcs DCD Finance Fire Legal P&R Police PIYI
SPONSOR'S The Small Drainage Program was advertised for bids on May 7 and 14, 2009 for four base
SUMMARY bid items and two additive items. The lowest bidder is determined by the base bid amount.
Five bids were received and opened on May 22, 2009. The low base bid of $486,351.50
was from Green River Construction. Green River Construction also submitted a proposal of
$84,835.00 for the two additive items. Green River Construction has successfully worked
for the City in the past and Council is requested to award the base bid and two additives.
REVIEWED BY COW Mtg. CA &P Cmte F &S Cmte Transportation Cmte
Utilities Cmte Arts Comm. Parks Comm. Planning Comm.
DATE: 05/27/09
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works
COMMITTEE Unanimous Approval; Forward to Committee of the Whole
C OST IMPACT FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$571,186.50 $800,000.00 $0.00
Fund Source: 412.02 SURFACE WATER (PG. 146 147, 2009 CIP)
Comments:
MTG. DATE RECORD OF COUNCIL ACTION
06/08/09
I
06/15/09
I
MTG. DATE ATTACHMENTS
06/08/09 Informational Memorandum dated 05/22/09
Vicinity map
Bid Tabulation
CIP Sheets Pages 146 147, 2009 CIP
Minutes from the Utilities Committee meeting of 05/27/09
06/15/09
-i
.t f i t of Tukwila
3 plc.. f ��'T`.7
4 9 Jim Haggerton, Mayor
f_=9Q INFORMATIONAL MEMORANDUM
TO: Mayor Haggerton
UTILITIES COMMITTEE
FROM: Public Works Director o-___.
DATE: May 22, 2009
SUBJECT: 2009 Small Drainage Program
Project No. 09 -DR01
BID AWARD
ISSUE
Award the bid for construction of the 2009 Small Drainage Program.
BACKGROUND
This project will provide drainage improvements at six locations listed on Page 2 of this memo.
The project was advertised for bids on May 7 and 14, 2009 for four base bid items and two additive
items. The specific basis of award which determines the lowest bidder is the base bid amount for the
four base projects. Five bids were received and opened on May 22, 2009. The bids were checked,
corrected, and tabulated. Green River Construction is the low bidder with a base bid of
$486,351.50. The engineer's base bid estimate was $675,225.
ANALYSIS
The bids were reviewed and tabulated. One error was found and corrected in the base bids. Green
River Construction has successfully worked for the City on past projects. Since favorable bids were
received, the two additive items can be awarded and constructed within budget.
BUDGET AND BID SUMMARY (All amounts include sales tax.)
Bid Results Estimate Budget
Construction (Base Bid) $486,351.50 $675,225.00
Additive Items 1,2 84.835.00 122.205.00
Subtotal $571,186.50 $797,430.00
SDP (2009,2010) Construction Budget (pg 146) $600,000.00
Private Storm Budget (pg 147) 200,000.00
Contingency (15 85.677.98 119.614.50 0.00
Total $656.864.48 $917.044.50 $800.000 -00
*Includes construction funds from the Private Storm System Adoption Program for project No. 4
RECOMMENDATION
The Council is being asked to award the construction of the 2009 Small Drainage Program including
two Additive Alternates to Green River Construction in the amount of $571,186.50 for consideration
at the June 8, 2009 Committee of the Whole meeting and subsequent June 15, 2009 Regular
Meeting.
Attachments: Project Location Map
Bid Tabulations
CIP Sheets Annual Small Drainage Program and Private Storm System Adoption
W 1PW E.- rg'PROJECTS■A- DR Projeast0S -DRO i (2009 SDP)1Into Memo Bid Award 2009 SOP dad
INFORMATIONAL MEMO
Page 2
The 2009 Small Drainaae Program includes:
Site 1) South 146 Street
Site 2) South 133 Street
Site 2A) South 131 Place (Additive Item No. 1)
Site 3) West Marginal Place
Site 4) 33 Avenue South to 34 Avenue South (Private Storm System Adoption Project)
Site 5) South 143` Street Outfall (Additive Item No. 2)
2009 Small Drainaae Program Bid Results
Base Bide Schedule A $486,351.50
Additive Item No. 1 $80,835.00
Additive Item No. 2 4,000.00
Total $486.351.50 $84.835.00 $571.186.50
WW1 Eng1PROJECTSV+- DR Pr*otsle9 -DROI (2009 SDP)inio Memo Bid Award 2009 SCP.doc
2009 Annual Neighborhood Drainage Program
Map
11.11, Li IT
LL -11.6rz I f
yr rfig 1.." 5 6' yip
J 1r F
ig T6 '64 gig:2: g
Lk
I
I 11-
LU
Eim 71-,
CITY OF TUKWILA CAPITAL. PROJECT SUMMARY
2009 to 2014
PROJECT: Annual Small Drainage Program
LINE ITEM: 412.02.594.38 .09 PROJECT NO. Varies
DESCRIPTION: Select, design, and construct small drainage projects throughout the City.
JUSTIFICATION: Provide drainage corrections for existing /ongoing drainage problems throughout the City, including culvert
replacements, drain extensions, and pavement upgrades.
STATUS: Annual program is taken from Small Drainage Project List.
MAINT. IMPACT: Reduces maintenance.
COMMENT: Ongoing project, only one year actuals shown in first column. Construction expenses may occur over two
calendar years.
FINANCIAL Through Estimated
(in $000's) 2007 2008 2009 2010 2011 2012 2013 2014 BEYOND TOTAL
EXPENSES
Design 114 60 60 60 60 60 60 80 80 634
Land (R/W) 0
Const. Mgmt. 8 40 40 40 40 40 40 50 50 348
Construction 657 300 300 300 300 300 300 370 370 3,197
TOTAL EXPENSES 779 400 400 400 400 400 400 500 500 4,179
FUND SOURCES
Awarded Grant 0
Proposed Grant 0
Mitigation Actual 0
Mitigation Expected 0
Utility Revenue 779 400 400 400 400 400 400 500 500 4,179
TOTAL SOURCES 779 400 400 400 400 400 400 500 500 4,179
Project Location: _°°1
Entire System
JO'
G
L 1 ra
r 't a I ri
1 I
I 1
r AD
1
GIS
2009 2014 Capital Improvement Program 146
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2009 to 2014
PROJECT: Private Storm System Adoption and Rehabilitation Program
LINE ITEM: 412.02.594.38. .30 PROJECT NO. 06 -DRO3
DESCRIPTION: Adopt and repair existing piped private systems throughout the City that convey public stormwater.
JUSTIFICATION: Numerous private drainage systems exist that connect to the City's system. Failure of these private
systems may lead to flooding and property loss that would be the City's responsibility.
STATUS: Maintenance has surveyed existing private systems and developed a list of 25 sites that need to be
adopted and repaired. Some of these storm drain pipes are located under structures.
MAINT. IMPACT: Additional storm systems will require additional maintenance, however the City will have a more reliable
system and rerouting the existing sites will improve maintenance access.
COMMENT: In 2007, coordinated 3 projects with the Small Drainage Program. Over the next two years, these projects will also
be combined with the Small Drainage Program.
FINANCIAL Through Estimated
(in $000's) 2007 2008 2009 2010 2011 2012 2013 2014 BEYOND TOTAL
EXPENSES
Design 38 30 155 223
Land (R/W) 0
Const. Mgmt. 45 25 70
Construction 200 275 475
TOTAL EXPENSES 38 30 400 300 0 0 0 0 0 768
FUND SOURCES
Awarded Grant 0
Proposed Grant 0
Mitigation Actual 0
Mitigation Expected 0
City Oper. Revenue 38 30 400 300 0 0 0 0 0 768
TOTAL SOURCES 38 30 400 300 0 0 0 0 0 768
Project Location: ,J
Entire System
I r_j
ED i
r f ..0--
go
2009 2014 Capital Improvement Program 147
Utilities Committee Minutes Mav 27, 2009 Pace 2
D. 2009 Small Drainage Program Bid Award
Staff is seeking full Council approval to award a bid in the amount of $571,186.50 to Green River
Construction for the 2009 Small Drainage Program including two Additive Alternates.
This annual program constructs drainage projects throughout the City that are too large for completion by
City staff but smaller than the average capital improvement project. This year the Small Drainage
Program will construct four base bid and two additive items for a total of six project locations. Each year,
projects considered for this program are reprioritized based on such things as need, expense, time on the
list, etc. Highest priority projects are designed and constructed within annual budget limitations.
The City has worked successfully with Green River Construction on past project. Committee Chair
Hougardy inquired to the project contingency amount of 15% based on other projects which are
usually 10 Staff stated that there is no set contingency; the percentage is often determined by
project complexity and the current bidding climate. Although this is an annual program, staff is
utilizing a portion of the 2010 budget to increase the outreach of this year's program. Funding is still
available in the budget for projects in 2010. UNANIMOUS APPROVAL. FORWARD TO JUNE
8 COW FOR DISCUSSION.
III. MISCELLANEOUS
Meeting adjourned at 5:32 p.m.
Next meeting: Tuesday, June 9, 2009 5:00 p.m. Conf. Room No. 1.
l
Committee Chair Approval
Mi;•rde; rf:; Reviewed by GL.