HomeMy WebLinkAboutTrans 2013-09-24 Item 2D - Grant Acceptance - Tukwila Urban Center Pedestrian-Bicycle Bridge from State Regional Mobility GrantTO:
Cit of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
Peggy McCarthy, Finance Director
DATE: September 20, 2013
SUBJECT: Tukwila Urban Center— Pedestrian /Bicycle Bridge
Project No. 90510403
Acceptance of State Regional Mobility Grant
ISSUE
City acceptance of a State Regional Mobility grant in the amount of $6,870,000 awarded to the Tukwila Urban Center (TUC) Pedestrian/
Bicycle Bridge over the Green River Project.
BACKGROUND
In October 2012, Council authorized staff to submit a grant application to the Washington State Department of Transportation Regional
Mobility program for right -of -way acquisition and construction of the TUC Pedestrian /Bicycle Bridge. This grant application was
successful and funds have been incorporated directly into the Washington State biennial budget. According to CIP Policy, staff must
obtain approval from the full Council before accepting grants.
Design is underway with full design and permitting expected to be completed by March 2014. Right -of -way acquisition can take a year to
acquire and the City could start on this process soon. Construction is currently anticipated to be over an 18 -24 month period to
coordinate with fish windows and other restrictions associated with working over the Green River.
The Transportation Committee asked staff at the June 25 and August 27 meetings to return to Committee with a funding proposal for
park impact fees. The Proposed 2014 CIP sheet (attached) shows the revised expected park impact fees of $35,000 for 2013 and
$55,000 for 2014 and 2015 and a Interfund loan from the Water Fund for $665,000.
DISCUSSION
The Regional Mobility Grant Program requires a local match of at least 20% of the total cost of the project from direct contributions. City
funds, park impact fees and future grants may be used as match, as well as staff salaries and past expenditures, including previously
awarded grants for the design work. The Regional Mobility Grant is a 4 -year award over two state biennial budgets. The award for the
2013 -2015 biennium is $4.6M and the continuing award into the 2015 -2017 biennium is for $2.2M. This is very similar to the awarded
grant for the Transit Center Project from the same agency.
FISCAL IMPACT
Attached is a new draft of the 2014 CIP page 12 which still has
the $145,000 shown from Park Impact Fees in 2013, 2014, and
2015. The Park Impact Fee ordinance is based on up to
$1,600,000 to be utilized for the Pedestrian Bridge Project. To
make up the difference for lower than expected Park Impact
Fees, staff is proposing to issue General Obligation bonds for the
City match in the estimated amount of $1,662,000. As future Park
Impact Fees come in, they will help pay off the debt service. Staff
will return with more information as the project progresses and is
closer to construction with firmer cost estimates.
Phase
Design
Right of Way
Construction
Total
Amount
$1,633,833
$1,100,000
$7,485,000
$10,218,833
Funding Source
Awarded Grants
General Fund
Park Impact Fee
Regional Mobility
General Fund
Park Impact Fee
Regional Mobility
General Fund
Park Impact Fee
Total
Amount
$1,496,833
102,000
35,000
$870,000
175,000
55,000
$6,000,000
1,430,000
55,000
$10,218,833
RECOMMENDATION
Council is being asked to formally accept the State's Regional Mobility Grant for the Tukwila Urban Center Pedestrian /Bicycle Bridge
Project in the amount of $6,870,000 and consider this item at the October 14, 2013 Committee of the Whole and subsequent October 21,
2013 Regular Meeting.
Attachments Funding Options with Advantages & Disadvantages.
May 28, 2013 E -mail Notification of Award
Excerpt from the 2013 -2015 LEAP Transportation Document (ESSB 5024p
Draft 2014 CIP page 12
W:IPW Eng'sPROJECTSW- RW & RS Projects\TUC Ped Bicycle Bndge (90510403)) Grantsttnfo Memo - Grant Acceptance -rev 9 -20 -13 gl.docx
141
Pedestrian Bridge
Financing Options - Advantages & Disadvantages
Options
Term
Effect on General Fund
Option Advantages
Option Disadvantages
1
External
Debt
-- Issue general obligation
(GO) debt;
-- Pay debt service with park
impact fees
- -To the extent park impact
fees fall short of GO debt
service, establish an interfund
loan with the General Fund;
-- Pay back interfund loan
from future park impact fees
20
To the extent impact fees fall
short of GO debt service
(estimated at $127K -$133K
annually), General Fund would
fund shortfall with an interfund
loan; payback would occur
through future park impact
fees; no permanent general
fund impact
1. No long -term financial impact on
General Fund.
2. Debt issuance could be combined
with the 2014 general obligation bond
issuance planned for other arterial
street projects potentially reducing
financing costs.
1. Reduces debt capacity; capacity at 12-
31 -12 was $42M
2. Until debt service is paid off, limits
funding for other park impact fee
projects, ie Tukwila Pond
2
External
Debt
-- Issue private placement
bond, ie Cashmere Bank, or
obtain bank loan
-- Pay debt service with park
impact fees
10
To the extent impact fees fall
short of debt service
(estimated at $211K annually),
General Fund would fund
shortfall with an interfund
loan; payback would occur
through future park impact
fees; no permanent general
fund impact
1. Shorter repayment period
compared with GO debt option
lowering total interest cost
1. Higher annual debt service due to
shorter repayment term requiring
greater commitment of General Fund
resources for the interfund loan
2. Reduces debt capacity; capacity at 12-
31 -12 was $42M
3. Until debt service is paid off, limits
funding for other park impact fee
projects, ie Tukwila Pond
3
Internal
Debt
-- Issue Interfund loan from
General Fund to Arterial
Street fund;
-- Pay debt service with park
impact fees
10
Temporary use of General
Fund resources;
payback over 10 years
1. Internal lending rate is lower than
market thus lowering project interest
cost
2. Interest earnings from lending
activity remains with the City.
3. Debt is not considered in City's debt
limits.
1. Commits General Fund resources to a
greater extent than external lending
options
2. Until interfund loan is paid off, limits
funding for other park impact fee
projects, ie Tukwila Pond
4
Pay from
General
Fund
-- Pay from General Fund
reserves
na
General Fund permanent cash
outflow
1. Elimination of interest costs reduces
total project cost
2. No impact on City's debt limits
3. Future park impact fees available
for other projects, ie. Tukwila Pond
1. Use of General Fund resources
reduces funds available for other
projects, reserves or other purposes
Cyndy Knighton
From: Eldridge, Mark <EldridM @wsdot.wa.gov>
Sent: Tuesday, May 28, 2013 11:33 AM
To: Morrison, David; Dong, Jonathan; Kirk McKinley; Cyndy Knighton;
dianas @kitsaptransit.com; Barb Hunter (bhunter @piercetransit.org); Overby, Monica;
Wolterink, Lisa; Otterstrom, Karl; Howell, Gordon; Marcia Smith
(msmith @skagittransit.org); steve.wall @ci.ridgefield.wa.us; Heffernan, Peter;
(melissa.cauley @commtrans.org); Kathryn Rasmussen; DBloom @intercitytransit.com;
(BHolman @intercitytransit.com); 'dorinda.costa @seattle.gov'
(dorinda.costa @seattle.gov); Chuck Green (ChuckG @c - tran.org); julies @c- tran.org; Kelly
Hayden (khayden @piercetransit.org); 'Barb Savary' (savary@islandtransit.org);
madams @piercetransit.org; (kmcmullen @bft.org); Suing, Troy; Futrell, Kevin
(Kevin.Futrell @yakimawa.gov); dc1 @bft.org; AFreeman @intercitytransit.com; Martha
Rose; Dale O'Brien; (marciaC @ridewta.com) (marciaC @ridewta.com)
Cc: Rutledge, Nicole; Eldridge, Mark
Subject: Regional Mobility Grant Projects for 2013 -2015
Welcome!
You're receiving this email because your project(s) has been selected for funding by the Washington State Legislature for
the 2013 -2015 biennium. It's been almost a year since the call for new project went out and a lot of energy has been
expended getting to this point, well done!
Now that the project list is complete WSDOT staff will be preparing contracts for each new project. We will also be
preparing contract amendments for the continuing projects. I anticipate they will be ready and in your hands by the end
of June.
So what happens next? I have a few helpful hints and reminders to pass along:
• Please review your project schedule and make sure it's up to date. If it isn't, then please send me a revised page
by June 10th
• Please review your planned expenditures by quarter. If that needs to be updated, then please have that to me
by June 10th
• Any expenditure made on the project before June 30, 2013 can be counted towards your match requirement,
but not eligible for reimbursement.
• For four year projects make sure your scope of work will get you to the minimum milestones for continued
funding in 2015 -2017 biennium. The grant application guide describes the minimum milestones.
• Starting July 1, 2013 any eligible project expense is eligible for reimbursement regardless when the contract is
signed.
• A project Performance Measurement Plan (PMP) is required to be reviewed and approved by WSDOT before a
reimbursement request will be processed and check cut. There are examples of past project PMP's on the
Regional Mobility web page copying is encouraged. Janice Heimann will help you prepare the PMP and will also
be the one reviewing and approving. As you may recall Janice is the person you sent your Year 1 and Year 4 VT
and VMT reduction to in Step 1 of the grant application process. HelmannJ@wsdot.wa.gov 206 - 464 -1284. You
can start on this now and beat the rush.
• The project scope you included in your grant application is what we expect you to build or provide. If the
project scope must change for some reason you must contact me immediately.
• If you're project cost comes in 10% lower than you anticipated you must contact me immediately.
1
143
• When you do send us a reimbursement request please make sure its painfully easy for us to track the
expenditures. Some of the reimbursement request are several inches thick and we don't know what numbers
your taking from where. Please use highlighter, sticky notes, a spreadsheet anything to help us follow the rabbit
trail. It will get done faster and you won't get a phone call from us.
• The supporting documentation you send should add up to the total expenses on the reimbursement form (we
will send each grantee a custom Reimbursement Request form).
• A project that has more than 20% local match can bill the grant at 100 %. A project that has 20% local match
must bill the grant at 80% of the eligible expenses.
• Please use the Regional Mobility Grant funds early, because you don't have to deal with reappropriation
requests and accruals. This will make all our lives easier, but if you can't that's fine too.
• A grantee must bill the grant at least quarterly. Someplace it says a grantee can't bill more than once a month,
but I say bill as often as you need to. The caveat is, please make sure it's for a reasonable amount ($2,000 or
more), because they take time to process and we don't have as many staff as we used to.
The first and most important thing I do as grant manager is to help you complete your project on time, on budget, and in
scope. The other less glamorous thing deals with accountability and reporting.
Call us any time you have questions. We will do everything we can to help you! I plan to schedule a meetings with each
of you over the next few months, because I want us to get to know each other, and you're projects in more detail.
Mark Eldridge
Regional Mobility Grant Program Manager
Park and Ride Lot Program Manager
360 - 705 -7273
2
144
LEAP Transportation Document 2013-2 as developed April 23, 2013
ALL PROJECTS
Public Transportation (V)
(Dollais in Thousands)
-- Fund Source -- Total
Bin Project Leg Dist "[PA Nckl Othr 2011-13 2013-15 2015.17 2017-19 2019.21 2021-23 2023 + (incl. Prior)
016 20130031 'Island, Skagit and Whatcom Transits, Tri County 0.31 0 0 0 0 2.300 0 0 0 0 0 2,300
Connector
017 20130100- City of Tukwila, Urban Center Pedestrian Bridge 11 . 0 . 0 liili 0 4,600 7.270 0 0 0 0 6.870
Contingency (Unfunded) Regional Mobility Grants 0 24,409 10,353 0 0 0 0 34,762
001 20130019 Sound Transit. Tacoma Trestle Replacement & 27 0 0 0 0 7.000 0 0 0 0 0 7,000
Capacity Improvements
002-- 20130101 Kitsap Transit, SR 305-1nterchange- 23 . 0- ...7_ 0 , 1326 ,0.- .-- 0• - -0 . 0...-
Improvements at Suquamish Way Park an
003 20130101 King County Metro, Northgate Transit Center 43 0 0 0 0 1.187 2.313 0 0 0 0 3,500
Redevelopment
004 20130104 Spokane Transit, West Plains Transit Center 06, 07 0 0 0 0 1,600 0.400 0 0 0 0 8,000
005 20130105 King County Metro, Madison Street Corridor 43 0 0 0 0 2.440 1,640 0 0 (1 0 4,080
006 20130026 City of Mukilteo, Mukilteo Multimodal 21 E1 El VI 0 1.000 (1 0 0 0 0 1.000
Pedestrian Bridge Project
007 20130106 City of Kenmore, SR 522 West A (61st Ave NE 46 0 0 0 0 5,202 0 0 0 0 0 5,202
10 65111 Ave NE
008 20130108 City of Langley, Port of South Whidbey Park and 10.21 0 0 2) 0 2.634 0 0 0 0 0 2.634
Ride facility with Sunda
009 20130110 Clallam Transit. Kitchen DickiHighwav 101 24 0 0 0 0 300 0 0 0 0 0 300
Park and Ride
010 20130112 Jefferson Transit, Jefferson Healthcare Transit 24 0 0 [2 0 160 0 0 0 0 (1 160
Bus Pullout and Shelter
011 20130113 River Cities Transit, Transit Service 19 0 0 Eil 0 560 0 0 0 0 0 560
Improvements
ES SB 5024 Striking Amendment
Version: 131 EGR AR
Page 36 of 47
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2014 to 2019
PROJECT: Tukwila Urban Center - Pedestrian /Bicycle Bridge Project No. 90510403
DESCRIPTION: Construct a new pedestrian /bicycle bridge over the Green River.
JUSTIFICATION: Pedestrian /bicycle connection between Tukwila's Urban Center and commuter rail /Amtrak station.
Supports local and regional goals and policies regarding land use and transportation in Urban Center.
Pedestrian System Report identified the optimal location for bridge crossing to be south of the Best
STATUS: Western Hotel. Type, Size, and Location Report was completed in 2011. Council approved a design of
a twin -tied arch bridge with no accommodation for a future bridge crossing over West Valley Highway.
MAINT. IMPACT: To be determined.
Design grants: State Enhancement for $190k & $500k, Transit Oriented Development (TOD) planning grant
COMMENT: of $55k, and Federal CMAQ grant of $751 K. WSDOT Regional Mobility construction grant of $6.870M.
Project is on Park Impact Fee list with funding of $2 million with an 80 %/20% split for $1.6M. A City Bond
issue will be used for the City match.
FINANCIAL Through Estimated
in $000's
2012 2013 2014
2015 2016 2017 2018 2019 BEYOND TOTAL
EXPENSES
Design
585
748
300
1,633
Land (R/W)
1,100
1,100
Const. Mgmt.
1,000
1,000
Construction
6,485
6,485
TOTAL EXPENSES
585
748
1,400
7,485
0
0
0
0
0
10,218
FUND SOURCES
Awarded Grant
540
713
243
1,496
Awarded Reg Mobility
870
6,000
6,870
Park Impact Fees
35
55
55
145
Bond
1,662
1,662
City Oper. Revenue
45
0
(1,430)
1,430
0
0
0
0
0
45
TOTAL SOURCES
585
748
1,400
7,485
0
0
0
0
0
10,218
2014 - 2019 Capital Improvement Program
12
146