HomeMy WebLinkAboutTrans 2013-10-15 Item 2B - Update - 2013 Work Plan: Transportation CommitteeTO:
City of Tukwila
Jinn Haggerton, Mayor
Department of Public Works Bob Giberson, P.E., Director
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
BY: Robin Tischmak, City Engineer
DATE: October 11, 2013
SUBJECT: 2013 Transportation Work Plan
ISSUE
Updated information includes anticipated schedules for the list of 2013 funded transportation projects
and anticipated items which may be brought forward to the Transportation Committee.
DISCUSSION
Public Works discussed the 2013 work program at the January 15, 2013 and March 26, 2013
Transportation Committee meetings. Anticipated schedules and potential committee agenda items will
be presented, as well as direction from the committee regarding preferences or requests on how
agenda items are included.
* An asterisk indicates items approved as Transportation Committee Goals
Second Quarter
1. TUC Access (Klickitat) — Final LID Assessment Roll (Complete)
2. Annual Bridge Inspections — Award contract(s) for inspections and repair project(s) (Complete)
3. Transportation Improvement Program (TIP) — Council adoption (Complete)
4. 42nd Ave S Safety Rail Along River — Guardrail analysis (Complete)
Third Quarter
1. *CIP Project Review Policy (Complete)
2. Boeing Access Road Bridge Rehabilitation — Approve design contract (Complete)
3. Overlay & Repair - E Marginal Way — Approve design contract (Complete); Award construction
contract
4. ADA Improvements — Approve design contract (Complete); award construction contract
5. Safe Routes to Schools (Cascade and Thorndyke) — Approve contracts for design; award
construction bid for Cascade View Elementary trail
6. TUC Transit Center & Andover Park W (Tukwila Pkwy to Strander Blvd) — Award construction
bid
7. Interurban Ave S (S 143rd St to Ft Dent Way) — Approve design contract (Complete); Award
construction contract
8. 2013 Overlay & Repair — Award construction contract; approve 2014 design contract
9. Traffic Impact Fee Intersection Improvement Projects (5) — Approve contracts for design:
a. Andover Park E/Industry Dr
b. Andover Park E/Minkler Blvd
c. W Valley Hwy /S 156thSt
d. S 133rd St/SR 599
e. Macadam Rd S /144th St
10. Tukwila Urban Center Access (Klickitat) — Project Closeout (Complete)
11. Southcenter Parkway Extension - Project Closeout (Complete)
W: \PW Eng \OTHER \Robin Tischmak \InfoMemo 2013 (2nd Revision) TC WorkProgram & Goals - sb.docx
3
INFORMATIONAL MEMO
Page 2
12. School Zone Issues
13. Traffic Impact Fees
Fourth Quarter
1. *Public Safety Oriented Sidewalk Policy
2. *Tukwila International Boulevard Corridor Improvements
3. *Apprenticeship Policy
4. 42nd Ave S — Phase III (Southcenter Blvd to S 160th St) — Continue /complete design; present
periodic status updates and /or present issues that may need Council input or direction
5. TUC Pedestrian /Bicycle Bridge — Finish design; submit grant applications
6. Transportation Element of Comprehensive Plan — Adopt Comprehensive Plan
Other Transportation Issues
1. SCATBd Agendas (Each meeting)
2. BNSF Freight Mobility Issues (COW Item)
RECOMMENDATION
Information only.
W: \PW Eng \OTHER \Robin Tischmak \InfoMemo 2013 (2nd Revision) TC WorkProgram & Goals- sb.docx
4