HomeMy WebLinkAboutUtilities 2013-11-18 Item 2A - Change Order #1 - 2013 Annual Sewer Repair Program with King Construction Company����JILA�gs oz City of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Utilities Committee FROM: Bob Giberson, Public Works Director BY: Mike Cusick, P.E., Program Manager DATE: November 15, 2013 SUBJECT: 2013 . Annual Sewer Repair Program Project No. 91340201, Contract No. 13 -134 Change Order No. 1 Approval ISSUE Approve Change Order No. 1 to Contract No. 13 -134 with King Construction Co., Inc. BACKGROUND King Construction Co., Inc was awarded the contract for installation of side sewers to 6532 and 6542 Southcenter Blvd on August 6, 2013. Work began on the side sewer installation on August 19, 2013. DISCUSSION 1. During the first day of work, King Construction Co., Inc. began excavating for the sewer line up the hill from old Macadam Rd. The contractor encountered buried boulders greater in size than one half cubic yard. The boulders and ledge rock were found in remaining trenching for the project. The contractor's schedule allowed for 4 working days for excavating and installation of piping. With the removal of the boulders, an additional 3 days was needed to complete the project. 2. The Contractor had to concrete encase a 10 -foot portion of the sewer because it passed under a water main with less than 18" of clearance. 3. The Contractor was required to rotate the soil pipe at the 6532 Southcenter Blvd's crawl space so that it would exit in the front yard. When the contractor was in the crawl space, he determined that instead of 1 point of connection to the existing septic tank, there were 3. The contractor's schedule allowed 1 working day for installation of piping in the crawl space of the house. The change in scope required an additional day to complete the connection to the house. FINANCIAL IMPACT Contingency was set at 10% or $4,905.60 for this side sewer project. The additional scope of work included the extra time and effort required to excavate the unforeseen rock; plus the costs for concrete encasing the sewer line and rotating of the soil pipe under the house at 6532 Southcenter Blvd. The funds to cover this change order will come from the 55th Ave S Sewer Repair Project as that project had $31,964.50 remaining from the original $55,000.00 budget and the project was completed with no change orders. RECOMMENDATION Approve Change Order No. 1 in the amount of $28,825.85, including sales tax, to Contract No. 13 -134 with King Construction Co., Inc, for installation of the side sewer to 6532 and 6542 Southcenter Blvd and consider this item at the November 25, 2013 Committee of the Whole and subsequent December 2, 2013 Regular Meeting, Attachments: Change Order No. 1 Photos showing large rocks found during excavation W: \PW Eng \ PROJECTS \A- SW Projects \2013 Annual Sewer Repair (91340201) \Desimone Side Sewer Installation \Info Memo KING CON Change Orderl- sb.doc 1 CITY OF TUKWILA CONTRACT CHANGE ORDER NO. 01 Sheet 1 of 2 DATE: 9/13/2013 BUDGET NO.: PROJECT NO.: 91340201 CONTRACT NO.: 13 -134 PROJECT NAME: 2013 ANNUAL SEWER REPAIR DESIMONE SIDE SEWER TO: BRAD KING You are hereby directed to make the herein described changes to the plans and specifications or do the following described work not included in the plans and specifications on this contract: NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and covenants; B. The rights of the "Owner" are not prejudiced; and C. All claims against the "Owner" which are incidental to or as a consequence of this change are waived. D The Contractor Must Submit all Field Overhead and Home Office Overhead rates for approval in advance of all Change Orders. CHANGE: See attached sheet detailing the required change There is no time extension with this Change Order. We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above and below. ACCEPTED: Date 9 -/k -13 Contractor /-1r.) By �� Title Pie-si.,-r- Original Contract (without tax) $ 44,800.00 APPROVED BY THE CITY OF TUKWILA Previous Change Order $ 0.00 Date This Change Order (without tax) $ 26,324.98 By Mayor REV. CONTRACT AMOUNT $ 71,124.98 ORIGINAL: City Clerk (1 of 2) Contractor (2 of 2) cc: Finance Department (w /encumbrance); Construction Inspector; Construction Engineer; file: 2 CONTRACT CHANGE ORDER NO. 01 CHANGE: Sheet 2 of 2 1. During the first day of work, King Construction began excavating for the sewer line up the hill from old Macadam Road. They encountered buried boulders greater than one half cubic yard in size. The boulders and ledge rock were found in remaining trenching for the project. The contractor's schedule allowed 4 working days for excavating and for installation of piping but the boulders and ledge rock added over 3 additional days of construction time required to complete the installation of the sewer line. 2. The Contractor had to concrete encase a 10 foot portion of the sewer because it passed under a water main with less than 18" of clearance required by the Washington State Department of Health. 3. The Contractor was required to rotate the soil pipe at the house at 6532 Southcenter Blvd. in the crawl space under the house so that it would exit in the front yard. When the contractor was under the house in the crawl space, he determined instead of one point of connection, there were three points of connection to the existing septic tank. These extra connections required about an additional days labor so the house would be connected to the sewer system. 4. Extend the contract with King Construction, Co. Inc. to December 1, 2013, so that Change Order No. 1 can be completed. 3 King Construction Co., Inc. August 12, 2013 Project: 2013 Annual Sewer Repair - 2 Side Sewer Installations City project #: 91340201 RE: This spreadsheet lists the T & M costs requested for the differing site condition at the project for rock excavation. The crew was directed to encase the side sewer pipe in concrete at the water main crossing. This spreadsheet also includes the invoiced cost of the concrete as this work was done at the same time as the rock excavation occurred. This spreadsheet includes the excess cost of hauling the rock spoils for disposal beyond the amount included in the bid for dirt spoils. There is no excess dump fees as we found a site that would accept the rock spoils for reuse. Labor: ST /OT Total Rate Extension Russ Taylor ST 26 26 $ 60.35 $ 1,569.10 Komatsu, PC 128UU -2, excavator OT 26 0 $ 81.78 $ - Rex Taylor ST 46 46 $ 59.21 $ 2,723.66 6x4 dump, 70,000 #, 12 -18cy, diesel OT 26 0 $ 80.06 $ - Bernie Montano ST 20 20 $ 59.21 $ 1,184.20 Komatsu PC 078 excavator OT 26 0 $ 80.06 $ - Pipe layer ST 21 21 $ 47.86 $ 1,005.06 Allied 1600 compactor w /swivel OT 26 26 $ 66.20 $ - Subtotal 29% markup Labor total $ 6,482.02 $ 1,879.79 $ 8,361.81 v Equipment: Date Inv. If Amount Hwy flatbed, diesel, 20,0008, 4x2 26 26 $ 29.80 $ 774.80 Komatsu, PC 128UU -2, excavator 26 26 $ 66.50 $ 1,729.00 8x4 dump,85,000 #,15 -18cy, diesel 46 46 $ 101.40 $ 4,664.40 6x4 dump, 70,000 #, 12 -18cy, diesel 26 26 $ 88.50 $ 2,301.00 4x2 dump, 25,0008, 5 -6cy, diesel 26 26 $ 41.80 $ 1,086.80 Komatsu PC 078 excavator 26 26 $ 44.00 $ 1,144.00 Okada OKB3048 breaker 4 4 $ 11.65 $ 46.60 Allied 1600 compactor w /swivel 26 26 $ 11.80 $ 306.80 Trench box, 6x8 26 26 $ 6.00 $ 156.00 Steel plate 8x10 26 26 $ 1.20 ' $ 31.20 Kent, E 208 breaker 26 26 $ 15.50 $ 403.00 Subtotal 21% markup Equipment total $ 12,643.60 $ 2,655.16 $ 15,298.76 r/ Materials & Misc. Date Inv. If Amount Staging area $ 203.88 Sanikan $ 15.87 HD Supply, DI pipe & fittings 08/21/2013 B364747 _ $ 1,234.20 Contractor stock, adt gaskets $ 31.02 Stoneway Concrete 08/21/2013 806140 $ 83.50 Subtotal 21% markup Material total Summary: Labor Equipment Material total Total $ 1,568.47 $ 329.38 $ 1,897.85 f/ $ 8,361.81 $ 15,298.76 $ 1,897.85 $ 25,558.41 4 King Construction Co., Inc. August 12, 2013 Project: 2013 Annual Sewer Repair - 2 Side Sewer Installations City project #: 91340201 The project required the contractor to turn the plumbing 180 degrees and to exit out the front of the house for connection to the new side sewer. It was discovered that not all of the active plumbing connected under the house. The kitchen and laundry exited under the footing and connected the septic tank. This spreadsheet tracks the additional labor, equipment and materials to connect the additional lines to the rotated plumbing line. Labor: ST /OT # # # # # # # ## # # # # # # # ## Total Rate Extension Bernie Montano ST 2 2 $ 59.21 $ 118.42 McLendon OT 0 $ 80.06 $ - Pipe layer ST 5 5 $ 47.86 $ 239.30 OT $ 66.20 $ - Subtotal 29% markup Labor total $ 357.72 $ 103.74 $ 461.46 Equipment: Hwy flatbed, diesel, 20,000 #, 4x2 2 5 7 $ 29.80 $ 208.60 Subtotal $ 208.60 21% markup $ 43.81 Equipment total $ 252.41 Materials & Misc. Date Inv. # Amount Lowes 08/27/2013 $ 2.04 McLendon 08/28/2013 $ 7.58 Lowes 08/28/2013 $ 33.94 Summary: Labor Equipment Material total Total 25T5-50• G// sit 2 Subtotal 21% markup Material total 43.56 9.15 52.71 $ 461.46 $ 252.41 $ 52.71 $ 766.57 ✓ 5 photo