ITEM INFORMATION
CAS NUMBER: 08-021 GRIGINAL AGENDA DATE: FEBRUARY 11, 2008
AGENDA ITEM TITLE Southcenter Blvd Water Main Replacement Project
Approval of Budget and Change Order No. 2 for $73,000.
CATEGORY Discussion Motion Resolution Ordinance I 1 BidArvard Public Hearing L] Other
Mtg Date 02/11/08 Mtg Date 02/19/08 Mtg Date Mt Date Alts Date Mtg Date Mtg Date:
!SPONSOR Council Major n _Adra Svcs DCD L Finance El Fire Legal P&R Police PIY/
SPONSOR'S This project replaced the water main from Grady Way to Tukwila Pkwy and required
SUMMARY crossing the Southcenter Blvd bridge. Crossing the bridge produced an increase in extra
labor, materials, equipment and contract time. Due to the overruns, a change order for
$73,000.00 is being presented which caused a $49,035.00 budget shortfall. Additional
water funds will be available from the water fund's ending fund balance and savings
from the Interurban Water Reuse project.
REVIE \OWED BY n COW Mtg. CA &P Cmte F &S Cmte Transportation Cmte
Utilities Cmte Arts Comm. Parks Comm. n Planning Comm.
DATE: 02/04/07
RECOMMENDATIONS:
SPONSOR /ADMIN. Authorize Mayor to sign Change Order No. 2.
COMMITTEE Unanimous approval, forward to COW.
COST IMPACT FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
980,000.00 $930,965.00 $49,035.00
Fund Source: 401.02 Water Fund
Comments.
MTG. DATE RECORD OF COUNCIL ACTION
I 02/11/08
02/19/08
MTG. DATE ATTACHMENTS
02/11/08 Information Memo dated February 6, 2008 (revised after UC)
Closeout Budget Analysis
2008 CIP page 81
Utilities Committee Meeting Minutes from February 4, 2008
02/19/08
INFORMATION MEMO
TO: Mayor Haggerton
FROM: Public Works Director
DATE: February 6, 2008
SUBJECT: Southcenter Boulevard Water Main Replacement Project
Project No. 98 -WT05, Contract No. 07 -054
Change Order No. 2 Final Settlement Budget Shortfall
ISSUE
Approval of Change Order No. 2 brings total final project cost over budget.
BACKGROUND
R.L. Alia Company overran the contract time by approximately 100 days and was initially
assessed liquidated damages of over 100,000. Subsequently, R.L. Alia filed a protest and
provided additional documentation and details demonstrating that, in a lawsuit, they may be able
to show that the plans were not clear enough to allow the bidder to plan for all the intricacies
required to install the new water main across the Southcenter Boulevard Bridge through existing
knockouts and penetrations without significant extra labor, matenals, equipment and contract
time.
Subsequently, the final settlement Change Order was negotiated in the amount of $73,000 to
compensate R.L. Alia Company for all additional direct labor, equipment and material costs. The
final total for the construction contract is estimated to be $871,200.
Due to the overruns in time, the base contract of $89,615 for construction management (CM) was
increased with Amendment 1 by $12,414 and Amendment 2 is pending at $6,771, for a CM total
of $108,800.
The attached closeout budget analysis shows that the expenditures exceed the budget amounts by
$49,035.
ANALYSIS
This final settlement Change Order is a fair and equitable complete compensation. Furthermore,
this settlement minimizes the risk of a protracted battle with a contractor and eliminates potential
litigation costs.
An upcoming agenda item for an interlocal agreement with King County Metro includes savings
of up to $110,000 for the City of Tukwila. King County will pay for the design and construction
if Tukwila agrees to pay for bidding and construction management. See page 81 of the 2008 CIP
for proposed savings.
RECOMMENDATION
Authorize the Mayor to sign Change Order No 2 for $73,000 and approve using ending water
fund balance due to savings in the Interurban Water Reuse project to pay for project budget
shortfall.
Attachments: Closeout Budget Analysis
2008 CIP page 81
P \PROJECTS\A- WT Projects\98wt05 Southcenter BlvaInfo Memo COR2 2 -06 -08 l;C budget paper gl.doc
Southcenter Blvd Water Main Replacement Project
98 -WTO5
Closeout Budget Analysis
Construction Award
Construction Bid Award $764,864
Construction 10% Contingency $76,486
Const. Mgmt Award $89,615
Total Award $930,965
Construction Expenditures
R.L. Alia base contract ($703,000 plus tax) $774,200
R.L. Alia C.O. #1 (conduits for Time Warner anc $24,000
R.L. Alia C.O. #2 (final settlement) $73,000
Total Construction $871,200
Construction Management Expenditures
Anchor Environmental base agreement $89,615
Anchor Environmental Supplement No. 1 $12,414
Anchor Environmental Supplement No. 2 $6,771
Total Const Mgmt $108,800
Total Expenditures $980,000
BUDGET SHORTFALL (49,035)
P' \PROJECTSW- WT Projects \98wt05 Southcenter Blvd \Closeout Budget
J
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2008 to 2013
PROJECT: Interurban Water Reuse
LINE ITEM: 401.02.594.34. .21 PROJECT NO. 92 -WTO6
DESCRIPTION: Develop water reuse along the Interurban corridor with Class A treated wastewater from the Eastside
Reclamation Facility for irrigation, sewer flushing, sweeping, dust control, and other non potable uses.
JUSTIFICATION: Using reclaimed water is an element of the Gity's Water Conservation Plan as well as the Cascade Water
Transmission and Supply Plan.
STATUS: King County Department of Natural Resources (KCDNR) and the City are currently completing the
assessment of crossing the river through an old 6° line in order to serve Baker Commodities.
MAINT. IMPACT: Future maintenance and operation of the new meters, tracking and preventing cross connections.
COMMENT: KC Dept of Natural Resources maintains and operates a distribution pipe from the Eastside (Renton)
Reclamation Facility to the golf course.
FINANCIAL Through Estimated
(in $000's) 2006 2007 2008 2009 2010 2011 2012 2013 BEYOND TOTAL
EXPENSES
Design 15 5 20
x
Land (R/W) 0
Const. Mgmt. 17 17
Construction 13 110 123
I. TOTAL EXPENSES 13 15 132 0 0 0 0 0 0 160
I FUND SOURCES
Awarded Grant 0
Proposed Grant 0
Mitigation Actual 0
Mitigation Expected 0
Utility Revenue 13 15 132 0 0 0 0 0 0 160
TOTAL SOURCES 13 15 132 0 0 0 0 0 0 160
i
f
F- Pro ject Location fi 1t-- ,I;
��sost� N
j] 4 f� 5 114 9 n
4,! u
L i.,..... lb 4 Iwo
''"I r ►�r� "IGIS
01111 TUkwI.
1 3,s4
1
81
Utilities Committee Minutes February 4. 2008 Paae 2
The City will enter into an agreement with Tellink LTD in the amount of $16,000, to conduct a needs
analysis, system audit, network infrastructure assessment and equipment identification for the a new
citywide telephone system. The funds will be taken from the 303 Fund. Council approval for the contract
is not required since the contract is less than $25,000. INFORMATION ONLY.
D. Southcenter Boulevard Water Main Change Order No. 2 Budvet Shortfall
Staff is seeking full Council approval to utilize the ending Water Fund budget to pay for a project
overrun in the Southcenter Boulevard Water Main Replacement Project.
Two reasons were identified for the over budget amount: 1. the design of the project was not
communicated in the best possible clear and definitive terms from the City to the contractor; and 2
inflation due to rising materials costs.
A''''' The project contractor, R.L. Alia, overran the stated contract time by approximately 100 days. They
could possibly prove that the extended time was due to reason number one as stated above In response
to assessed liquidated damages by the City and contractor expression of a potential lawsuit, staff
negotiated a settlement with the contractor rather than induce a lawsuit. The negotiation was to pay the
contractor for direct expenditures for labor and material as related to unclear terms of the project design.
The contractor's original claim started much higher than negotiated.
The project exceeded the budgeted amount by $45,000 The over budget amount will be taken from the
ending Water Fund balance. The Water Fund balance will experience a cost saving of approximately
$110,000 as a result of an interlocal agreement with King County Metro in the Interurban Water Reuse
project. UNANIMOUS APPROVAL. FORWARD TO FEBRUARY 11 COW FOR
DISCUSSSION.
E. Recvclin2 Program Grant Funds
Staff is seeking full Council approval for the Mayor to sign and enter into interlocal agreements with the
King County Solid Waste Division and the Washington Department of Ecology for grant funding during
2008 -2009 for the Tukwila Recycling Assistance Program.
The City is able to maintain and run the Tukwila Recycling Assistance Program through this grant
funding which cycles every two years. Monies are received through the Waste Reduction/Recycling
Grant (administered by King County) and the Coordinated Prevention Grant (administered by
Washington Department of Ecology).
The Tukwila Recycling Assistance Recycling Program began in the 1990's and is not supported by the
City's General Fund or subscriber based fees; the program is based solely on grant funding. The Program
includes residential as well as business based recycling opportunities and other special collection events
UNANIMOUS APPROVAL. FORWARD TO FEBRUARY 11 COW FOR DISCUSSION.