HomeMy WebLinkAbout92-147 - City of Seattle - South 160th / 42nd Avenue / 51st Avenue Improvementsr•
A • C FILE # / ?'7
BATE lo?
INTERAGENCY COOPERATION AteEEMENT
THIS AGREEMENT, made and entered into on o" o/ 1992
between the City of Tukwila, (hereinafter called "Tukwila"),
and the City of Seattle, by and through its Water Department
(hereinafter called "Seattle").
WITNESSETH
WHEREAS, Tukwila proposes to proceed with a road
construction project outside the Seattle City limits,
commonly known as the South 160th Street, 42nd to 51st Ave.
S., Street Improvements, (hereinafter referred to as the
"Project"); and
WHEREAS, Seattle plans to provide encasement around an
existing 60" waterline near 43rd Ave. S. on the project site.
in accordance with all applicable laws, regulations, and
franchises; and
WHEREAS, Tukwila and Seattle both can achieve benefits
in the public's interest by utilizing Tukwila's construction
contractor(s) to perform certain work for Seattle during
construction of the Project, namely that the contractor
install 120 lineal feet of 60 -inch diameter pipe encasement
along the road rights-of-way from Sta. 52+90 to Sta. 54+10
(hereinafter referred to as the "Seattle Work"); and
NOW THEREFORE, it is hereby agreed as follows:
I. TERM OF AGREEMENT
This Agreement shall remain in full force and effect
until 30 days after final acceptance of the construction work
to be performed hereunder.
II. ADMINISTRATION OF AGREEMENT
Seattle's Superintendent of the Water Department and
Tukwila's Director of Public Works are responsible for
administering this Agreement.
III. PURPOSE
It is the purpose of this Agreement to realize cost
savings and other mutual public benefits by having the same
general construction contractor simultaneously perform
related work for both Tukwila and Seattle under one Tukwila
construction contract, and having Tukwila coordinate said
work.
IV. DESIGN
A. Seattle shall furnish to Tukwila reproducible
construction plans, specifications, and cost
estimates for the Seattle Work to be incorporated
into Tukwila's plans'and specifications for the
Project.
B. Tukwila shall notify Seattle of any changes that
must be made to Seattle's plans and specifications
to bring them into accordance with Tukwila
requirements, which changes shall be promptly made
by Seattle.
V. BIDDING
A. Tukwila shall incorporate Seattle's plans and
specifications into Tukwila's Contract and Bidding
Documents in such a manner as to allow, to the
fullest extent possible, identification of cost
allocations between the parties.
B. Following opening of construction bids on the
Project, Tukwila shall furnish Seattle with all the
bid prices for Seattle Work for Seattle's
consideration and approval. Within one week of
receiving the bid prices, Seattle shall notify
Tukwila in writing that Seattle_either approves of
or rejects the lowest bid for Seattle Work. Tukwila
shall not proceed with Seattle Work until Tukwila
has received approval from Seattle. If bids are
received that, in the estimation of Seattle were
not acceptable for the Seattle Work, that portion
of the work shall not be awarded.
VI. CONTRACT ADMINISTRATION
A. Tukwila shall provide the necessary engineering,
inspection, and administrative services necessary
for the execution of Seattle Work. In providing
such services, the Tukwila Public Works Director
may exercise all the powers and perform all the
duties vested by law.
B. Seattle shall furnish an inspector to observe
performance of Seattle Work. Seattle's inspector
may advise Tukwila of any deficiencies noted, but
shall not communicate directly with or interfere
with the contractor's performance. Tukwila shall
communicate to the Contractor all deficiences or
potential problems that Seattle's inspector or
other Seattle representatives have advised Tukwila
of.
C. Seattle shall notify Tukwila, in writing, of any
2
changes it wishes to make to the plans and
specifications that affect Seattle Work, which
changes shall be made, if feasible. Tukwila will
notify Seattle of any changes required by Tukwila
that substantially change the nature of Seattle
Work and will obtain Seattle's approval of such
changes.
VII. PAYMENT
A. Seattle shall reimburse Tukwila for all costs
reasonably incurred by Tukwila in performing the
Seattle Work, which costs shall include but not be
limited to:
1. The contract price, as adjusted by change
orders agreed to by Seattle, to perform the
Seattle Work;
2. Tukwila's internal costs (i.e., all
engineering, administrative, inspection
services costs, and all payroll additives)
directly attributable to Seattle Work.
B. All payments shall be due within 30 days of the
billing date, and when due shall accrue simple
interest at the rate of one percent per month, if
unpaid.
VIII.INDEMNIFICATION AND HOLD HARMLESS
Tukwila and Seattle each agrees to indemnify and hold
the other, its officers, agents, and employees harmless from
all claims arising out of the Seattle Work (including
demands, suits penalties, losses, damages or costs of any
kind whatsoever, including reasonable attorney fee), but only
to the extent that such a claim arises out of, or is caused
by, the indemnifying party's own negligence or that of its
officers, agents, or employees in performance of this
Agreement. In the event of concurrent negligence or fault
between Seattle and Tukwila, the obligations imposed under
this paragraph shall only extend to the degree of concurrent
negligence or fault.
IX. OTHER PROVISIONS
A. Tukwila shall retain ownership and usual
maintenance responsibility for the road and
sidewalk.
B. Seattle will use best efforts to secure, for its
own and Tukwila's benefit, a temporary construction
easement for Seattle Work.
3
C. This Agreement contains the entire written
agreement of the parties and supersedes all prior
discussions. This Agreement may be amended only in
writing, signed by both parties.
IN WITNESS HEREOF, the parties hereto have hereunto set
their hands and seals.
Date: L�-//1'07 Date: /,-,t/- yL
CITY OF TUKWILA, WASHINGTON
By:
ohn W. Rants
Mayor
APPROVED AS TO FORM:
By: ku-ke
City Attorney
City of Tukwila
Date: (�
4
By:
WATER DEPARTMENT,
C _ Y ! F EATTLE
obey P. Gronc ack
Superintendent of Water.