ITEM INFORMATION
CAS NUMBER: 04-012 I ORIGINAL AGENDA DATE: 2/2/04
AGENDA ITEM TITLE Tukwila International Blvd Phase 2 3 Scope and Budget Alternatives
CATEGORY Discussion Motion Resolution Ordinance Bid Award Public Hearing Other
Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date 11122/04
SPONSOR Council El Mayor Adm Svcs DCD El Finance Fire Legal P&R Police PTV
SPONSOR'S The City has received additional federal grant funds and working with WSDOT to receive
SUMMARY state funds from the "nickel package The new scope of work with these funds include
undergrounding, illumination and sidewalks. Question is to design the roadway with full
10' sidewalks (6' concrete 4' planter) for the length of the project or reduce to 8'
sidewalk sections with no planters where necessary.
REVIEWED BY COW Mtg. CA &P Cmte El F &S Cmte Transportation Cmte
El Utilities Cmte Arts Comm. Parks Comm. Planning Comm.
DATE: 11/8/04
RECOMMENDATIONS:
SPONSOR /ADMIN. Provide direction on desired scope of project
CommirrEE Recommend 8' sections forward to COW for discussion
COST IMPACT FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED CITY FUNDS REQUIRED
$16.15 million $16.2 million $2,430,000
Fund Source: 104.02 Commercial Streets (page 44 45, 2005 CIP)
Comments: City Funds also includes $225, 000 from 412 Surface Water for the High Flow Bypass (pg 125 Prpsd 2005 CIP)
MTG. DATE I RECORD OF COUNCIL ACTION
Complete roadway from S 138 St north to Sabey development
Budget restrictions limited scope to not include undergrounding
11/22/04 1
MTG. DATE I ATTACHMENTS
11/22/04 Information Memo dated November 3, 2004
Spreadsheets on Scope and Budget Alternatives
Transportation Committee Meeting Minutes from November 8, 2004
. INFORMATION MEMO
To:
From:
Date:
Subject:
Mayor Mullet
Public Works Director
N ovemberJ, 2004
TukwilaInternational Blvd - Phases 2 & 3 (S 116 tb St toS 138tb St)
Scope, and Budget Alternatives
Project No. 95..RW03
ISSUE
Present scope' alternatives based on updated funding and ,potential funding, from WSDOT.
BACKGROUND
This project was presented to the Transportation Committee in February 2003 where project
limits were discussed. Thereslllting consensus was the preference to camplete roadway
improvements from the ,north limit of Phase 1 (S 13Stb St) to' as far north as possible with the
available funding (just north of the Sabeydevelapment). This would eliminate having a "gap"
in, improvements where" Phase' 3 is currently identified.
In January 2004, scope and budget alternatives were presented to the City Council for
discussion regarding the available budget (at that time) campared with the estimated
canstruction costs. far three different alternatives (see attached spreadsheet). The Council
provided directionontheir preferred scope items. Staff has since prepared 30% design plans
that have been reviewed by .a Value, Engineering team.
The, City ,has subsequently applied for and received additianal federal grant funds for
constructian of the praject. Staff is also warking with WSDOT to transfer state funds to the
City's project from a "Nickel Package"praject that is identified within the City's project
limits .
KPO, Inc., is under contract with the City to design Phase 2 of T .I.B. improvements. They
have developed revised scope and budget alternatives far the project limits fram S 13Stb St to S
116tb 8t based on the currently anticipated funding scenario. The estimated casts with
descriptions of included and excluded scope items are shown in an attached spreadsheet.
ANALYSIS
All alternatives are based on the same project limits from S 13Stb St to S 116tb St. The new
scopes and estimated costs are based on: 1) the original information developed within the
design report including the scope items desired from input by the City Council and 2) the
current secured funding and the anticipated state funds. The description shown for each
funding alternative identifies both 'included and excluded scope items for that particular
alternative.
Mayor Muliet
Page 2
November 3, 2004
RECOMMENDATION
Discuss the alternatives presented and provide direction to staff on desired scope items in
order to proceed with final design of improvements.
Funding Source
Preliminary Engineering.
State Transportation Improvem.entBoard
Federal Hwy TEA-21.Grant
State DOT Funds
Construction
State Transportation Impr()vement Board
Federal Hwy TEA-21 Grant
State "Nickel Package" Funds
TukwilaCityRevenue{104&412 Funds)
Total
Total
$ 660,000.00
440,000.00
400,000.00
$1,500,000.00
$4,200,000.00
6,681,008.00
2,900,000.00
2,430,000.00
$16,211,008.00
attachments:SCQpe and Budget Alternatives (from November 2004)
Scope and Budget Alternatives (from January 2004)
(P:ProjeclS\A- RW & RS ProjeclS\9SRW03 TIB2\Memo phase 2 AIlS - Round 2)
New $400,000
New $2,995,020
New $2,900,000
Tukwila International Boulevard Phase II and III
Phase 2 and 3
South 139th Street to South 116th Street
Scope and Budget Alternatives November 2004
Tukwila International Boulevard Phase II and III Phase 2 and 3
South 139th Street to South 116th Street
Scope and Budget Alternatives December 12, 2003
"
Transportation Committee
November 8, 2004
Present:
JoanlIernandez, Chair; Pam Carter, Joe Duffie
Pat Brodin, Robin Tischmak, Jim Morrow, Kevin Fuhrer, Alan Doerschel, Frank
Iriarte, Gail Labanara, Lucy Lauterbach
1. Interurban Avenue South Design Thecityhas received a $396,000 federal grant for funding
the design of road improvements on Intemrban Avenue S. from 143rd to Fort Dent "Vay. After
interviewing five of the fourteen firms that were interested, staff chose KPG by a wide margin.
They scored higher than other companies on every rating criterion. The design and engineering
costs of $434,710.24 are within the, project budget, although Joan noticed that in the CIP there is
not money for constmctionuntil after 2010. She asked if the design work being done now would
still be useful if construction didn't occur until that many years ahead, and Jim assured her it
wQuld;The Comrpitteeapproved the scope of work that was included.. Authorize mayor to
si2'llcontract with KPG for design services for Interurban.
2. SouthcenterParkwav Extension Supplement David Evans already has a $35l ,000 contract
to design the extension of South center Parkway to the south city limits. Additional design work
is needed for thesewerline from Minkler to S. 200th and the additional 1,400 feet of roadway to
reach the city'ssouthernboundary,soa supplement to the contract has been prepared. Segale did
some preliminary designwork on the sewer, but the majority of design still remains to be done.
A supplement has beennegotiated in the amount of $70,615, and is within budget. Advertising
for construction is included in the work. Jim said the City cannot afford to build the road or
sewer withoutbonds;iand we couldn't pay the bond payments with()ut assistance from the TVS
project. Pam pointed outthat the only reason forthe sewer project is to serve the TVS project.
The seWer money is within the S. 180th Street project in the CIP. Recommend authorizin!!
mavortosi2'n sUODlement for extension.
.~
3. TukwilalnternationalBoulevard (TIB) Phases 2 and 3 of the TIB project were previously
discussed in late 200Jandearly 2004, but there was not enough money to do both phases, so the
southern section thatwould continue the previous improvements north, had been chosen. Since
the first oftheyeartheCjtyhas received more funding, and is now able to do both phases, if
some savings are found. The Committee considered the$16.5m and $16.15m versions and
recommended the $16.15 million dollar version, and also considered other savings that could be
made if necessary. Move discussion to CO\V,
4. Cascade View Park Cascade View Community,Park constmction is complete, and the city is
ready to release theretainage of the contractor. Though the contract was largely done in 2003,
there were a number of landscape issues that have remained open. Those are now resolved, and
the.proj~ct can be closedouLJoan asked what the $8,571.20 cost overruns were for and ....vas
informed they were partly for gravel, asphalt and the sidewalk extension. Recommend Droiect
accentance and release of retainage to consent agenda of a Regular Meeting.
.~::-