HomeMy WebLinkAboutCOW 2010-03-22 Item 4E - Contract Supplement #9 - Tukwila Urban Center Access (Klickitat) with HNTB for $533,816CAS NUMBER 10-032
C,\ i I GORY
SPONSOR
SPONSOR'S
SUMMARY
MTG. DATE
1 03/22/10
04/05/10
MTG. DATE
03/22/10
04/05/10
1
I�
Meeting Date
03/22/10
04/05/10
Discussion Motion n Resolution
Mtg Date 03/22/10 Mtg Date 04/05/10 Mtg Date
Council n Ma n Adm Svc:r DCD
COUNCIL AGENDA SYNOPSIS
Prepared by
CK
CK
ITEM INFORMATION
ORIGINALAGENDADATE: MARCH 22, 2010
AG1:ND,\ I'1'i rvr TITLE' Tukwila Urban Center Access (Klickitat) Project
Design Supplement No. 9 with HNTB
n CA &P Cmte
n Arts Comm.
Mtg Date
n Finance
Initials
Mayor', review
F &S Cmte
n Parks Comm.
Ordinance n Bid Award Public Hearing Other
Mtg Date Mtg Date Mtg Date
Pi Fire ❑Legal P&R Police ®PW
The design of the Tukwila Urban Center Access (Klickitat) Project has a number of
outstanding issues requiring this additional Supplement No. 9 with HNTB. This supplement
covers all of the WSDOT changes along with updated environmental standards. The
construction timeline for the project will now be two years. Council is being asked to
approve Supplement No. 9 for $533,816.00 with HNTB.
RI!\'II D BY n COW Mtg. Transportation Cmte
Utilities Cmte
DATE: 03/15/10
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works
COMMITTER Unanimous Approval; Forward to Committee of the Whole Special
COST IMPACT FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED
$533,816.00 $3,851,000.00
Fund Source: 104 ARTERIAL STREETS (PAGE 15, 2010 CIP)
Comments: Additional design funding will come from the LID,
RECORD OF COUNCIL ACTION
ATTACHMENTS
Informational Memorandum dated 3/10/10 (revised after 3/15 TC)
Project Schedule
HNTB Supplement No. 9
Minutes from the Transportation Committee meeting of 03/15/10
n Planning Comm.
ITEM No.
SPE 3
APPROPRIATION REQUIRED
$109,000.00
94
TO:
City of Tukwila
Mayor Haggerton
Transportation Committee
FROM: Public Works Director
DATE: March 10, 2010
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
SUBJECT: Tukwila Urban Center Access (Klickitat) Proiect
Project No. 84 -RW19, Contract No. 05 -071
Supplemental Agreement No. 9
ISSUE
Approve Supplemental Agreement No. 9 to the HNTB contract #05 -071 for final design and final bid documents
associated with the Tukwila Urban Center Access (Klickitat) Project.
BACKGROUND
The design of the Tukwila Urban Access Project halted at the 100% shelf -ready design in May of 2007, pending
completion of other tasks. At the time it was shelved, there were a number of outstanding issues requiring
resolution before the project design efforts could resume. Those issues included: WSDOT approvals, design of the
buttonhook ramp, right of way (ROW) acquisition, property coordination and associated design efforts, construction
phasing and formation of the Local Improvement District.
The Supplemental Agreement #8, approved at the end of 2009, was for the work necessary to complete the project
design, assuming no major redesign efforts, as well as coordination with WSDOT to determine the final design
changes being required by the state. The extent of the design changes to be required by WSDOT was unknown at
the time Supplement #8 was prepared and certain assumptions were made that only minimal re- design would be
required.
Early on in the project, staff coordinated closely with WSDOT to establish design standards and review and
approval authority. In late 2005 through early 2006, discussions between Tukwila and WSDOT staff concluded with
a decision to shift the limited access line to the west side of the project. By doing this change, the vast majority of
the project would be designed to city standards and not reviewed by or subject to WSDOT design standards or
approval. City staff submitted the request and appropriate drawing to have the limited access line moved to
WSDOT HQ in late 2006. A minor change was requested and the revised drawing was re- submitted. With the
understanding that the design standards and approvals were established, the City proceeded to complete the
project design using City design standards.
From the time the limited access revision request was submitted in 2006, WSDOT was unresponsive on the issue
until March 2009. At that time, WSDOT rescinded all agreements and decisions made prior and informed staff that
the project would now be required to be designed to full WSDOT standards.
DISCUSSION
As the impacts to the design (already at 100% shelf- ready) would be significant, requiring nearly a full re- design of
the project and significantly more ROW, staff began the long process of trying to convince WSDOT to stand by the
original agreements. When it became apparent that WSDOT would not honor the earlier agreements, staff
attempted to negotiate lesser design standards. WSDOT remains firm in requiring changes to the project design to
accommodate large trucks through the project. To some extent, WSDOT has expressed willingness to consider
less than full freeway standards which will allow the project to be built within the existing ROW and not require a full
re- design of large elements such as the wall placement. All of this has resulted in additional design and permitting
work not originally anticipated. Of the entire supplemental scope and fee, approximately $243,000 is associated
purely with the WSDOT required design changes. The rest of the work effort includes all the final design and
coordination work still necessary as well as updating of some environmental documentation that is required
because standards have changed since the project was shelved in 2007.
W:1PW Eng\OId P drivelCyndy \KlickitatlINFOMATION MEMO Supplement #9 Final PS &E 3- 10- 10.doc
95
INFORMATIONAL MEMO
Page 2
WSDOT has agreed to pursue turning back the portion of Southcenter Parkway ROW which is under state
ownership in exchange for the City agreeing to move the Limited Access line to the east, encompassing the full
width of the project. The change in limited access includes a portion of the right -of -way acquired from Westfield. In
normal situations, WSDOT would have to acquire the limited access rights by purchasing them from the City.
Should the ROW turn back be approved by FHWA, any future changes made by Tukwila on Southcenter Parkway
would not require WSDOT approval, provided that no impact to limited access was made or federal or state monies
were involved.
Staff is requesting the Council consider this supplement on the March 22 COW meeting followed that same
evening with a Special Meeting for approval. Timing is critical to keep the project moving forward to a bid opening
this year and the three week delay following normal procedures would be a significant negative impact to the
project schedule.
Fiscal Impact: Approximately $400,000 is budgeted in the 2010 CIP. The additional monies will come out of the
LID. No WSDOT funds are included in the overall funding package.
RECOMMENDATION
Approve Supplement #9 with HNTB for final design and PS &E work in the amount of $533,816 consider this item at
the March 22, 2010 COW followed by a Special Meeting that same evening.
Attachment: Project Schedule
Scope of Work and Fee for Supplemental Agreement No. 9
9 6 W:1PW Eng\OId P drive \Cyndy \KlickitatlINFOMATION MEMO Supplement #9 Final PS &E 3- 10- 10.doc
Complete
Date
5/7/07
5/24/07
7/16/09
8/17/09
8/24/09
8/25/09
8/28/09
9/3/09
9/4/09
9/8/09
9/14/09
9/2
10/2/09
10/5/09
10/26/09
11/2/09
11/9/09
11/16/09
12/23/09 5/16/10
2/12/10
2/22/10
3/5/10
3/31/10- 4/21/10
3/31/10-4/21/10
3/31/10-4/21/10
5/3/10-6/8/10
5/17/10- 6/10/10
6/17/10- 7/8/10
7/8/10
7/19/10- 7/26/10
7/30/10
Aug. Nov. 2010
November 17, 2010
January 2011
July 2011
W:1PW Eng101d P drive\Cyndy\Klickitat\Project Schedule Council Packet.doc
Tukwila Urban Center Access (Klickitat)
Project Schedule
Description
Environmental Approval: ECS Accepted by FHWA
Design Substantial Completion: 100% Shelf -Ready Plans completed
Right -of -Way: Possession and Use Agreement from Legacy Partners
Transportation Committee: LID schedule and steps
Committee of the Whole: LID Schedule and Process
WSDOT: ROW certification, limited access revision, channelization plans
Open House: For property owners, businesses and tenants
Open House: For property owners, businesses and tenants
Notification to Property Owners For Public Hearing on Resolution to Form LID
Transportation Committee: Resolution of Intent to Form LID
Committee of the Whole: Resolution of Intent to Form LID
Regular Council: Public Hearing Adoption of Resolution of Intent to Form LID
Notification to Property Owners For Public Hearing on Ordinance to Form LID
Transportation Committee: Revised Resolution of intent to Form LID
COW Regular Council: Public Hearing Adoption of Resolution of Intent to
Form LID (revised)
Transportation Committee: Revised Ordinance to Form LID
Committee of the Whole: Ordinance to Form LID
Regular Council: Public Hearing Adoption of Ordinance Forming LID #33
Finalize PS &E Documents
WSDOT: Submit for Channelization Plan approval
Right -of -Way: Recorded acquisition and easements from Doubletree Legacy
WSDOT: Comments on Channelization Plan
WSDOT: ROW Certification Process
WSDOT: Revised Channelization Plan Approval Process
WSDOT: Project Analysis (deviations) Approval Process
WSDOT: Updated Storm Water Report Approval Process
WSDOT: 100% PS &E Approval Process
Advertise for Construction Bid: 3 week time period (required by federal funds)
Bids Due with Bid Opening
Transportation Committee, City Council (C.O.W. and Regular): Award of Contract
Notice to Proceed to successful bidder
Construction of project
Roadway open to traffic, close down of construction until 2011
Construction of project resumes
Completion of construction, roadway open to traffic
97
98
Washington State
71- Department of Transportation
Supplemental Agreement
Number 9
Original Agreement Number
Project Number
Project Title
Klickitat/Southcenter Parkway Access
Improvement Project
Description of Work
Final Design Services
By: HNTB Corporation
James E. Thomson, Vice President
Date
DOT Form 140 -063 EF
Revised 9/2005
05 -071
84 -RW19
Organization and Address Phone:
City of Tukwila
Public Works Department
6300 Southcenter Blvd., Suite #100
Tukwila, WA 98188
206 -431 -3665
Execution Date
New Maximum Amount Payable
The Local Agency of Tukwila desires to supplement the agreement entered into with HNTB Corporation and
executed on April 6, 2005 and identified as Agreement No. 05 -071. All provisions in the Agreement remain in
effect except as expressly modified by this supplement. The changes to the Agreement are described as follows:
11
Completion Date
June 30, 2010
$3,960,214
Section I1, SCOPE OF WORK, shall be amended as follows:
The scope of work for this project is supplemented as detailed in the attached Exhibit A, and by
this reference made part of the Agreement.
I1
Section IV, TIME FOR BEGINNING AND COMPLETION, shall be amended as follows:
All work under this Agreement shall be completed by the date shown in the heading of this
Supplemental Agreement Number 9 under Completion Date.
111
Section V, PAYMENT, shall be amended as follows:
Compensation due to Consultant for work performed or services rendered for this project is
supplemented as detailed in the attached Exhibit B, and by this reference made part of this
Agreement.
If you concur with this Supplemental Agreement and agree to the changes as stated above, please sign in the
appropriate spaces below and return to this office for final action.
By: City of Tukwila
Approving Authority Signature
Date
Page 1 of 2
99
No 6 Supp• N 7 Supp• NO.8
No 4lSupp•;,; °.5 Supp
$o.7 $147,387
No. 2 SupP' No. 3' SuPP.
$4,500
$63,3
O
Original Sapp N 1 SuPP $14,759 $0 $0,
i 0
Agreement 1
$17 X 200 $G
$1,956,680
$1,168,322 $3 426,398
mount $0 $3,27
Total A t $0 4
Authorized $0 70,311 $3,27,811
$50,000 202 $3,206,961$3,2 1
Management $3,192,
e Fund $3,192,
Resew $3,175,0
Amount $1,218,322
Maximum
Payabl
9 TOTAL No.
533,816
3 910,2
Total Amount
Authorized $0 $50,000
Management
Reserve Fun d 14 $8,960,214
Maximum Amount $3,960,2
Payable
Page 2of2
Scope of Work
Final Design /PS &E
Tukwila Urban Access Improvement Project
Contract 05 -071
Supplement 9
February, 2010
INT
101
102
Tukwila Urban Access Improvement Project Page i
TABLE OF CONTENTS
I. SUPPLEMENT PURPOSE 1
II. DESIGN CRITERIA 2
III. PROJECT SCHEDULE 3
IV. ITEMS AND SERVICES TO BE FURNISHED BY THE CITY 4
V. ABBREVIATIONS 4
VI. PROJECT DOCUMENTATION 5
VII. WORK TASKS 5
TASK 21.1 PROJECT MANAGEMENT 7
Task 21.1.1 Issues Resolution 7
Task 21.1.2 Measure Project Requirements 7
Task 21.1.3 Measure Budget Conformance 8
Task 21.1.4 Develop Schedule and Measure Conformance 8
Task 21.1.5 Communicate Progress 8
Task 21.1.6 Lead the Project CONSULTANT Team 8
Task 21.1.7 Manage Quality 8
Task 21.1.8 Manage Change 9
TASK 21.2 RIGHT OF WAY 10
Task 21.2.1 Right of Way Legal Descriptions and Easements 10
Task 21.2.2 Right of Way Plans 10
TASK 21.3 PERMITTING 10
TASK 21.4.0
Task 21.4.1
Task 21.4.2
Task 21.4.3
Task 21.4.4
Task 21.4.5
Task 21.4.6
Task 21.4.7
Task 21.4.8
TASK 21.5
Task 21.5.1
Task 21.5.2
ROADWAY 11
Roadway and Channelization Design 11
Signals and Interconnect 12
Illumination 12
Site Preparation 13
Traffic Control Plans 13
Detour Plans 14
Signing 15
Landscape Design and Architectural Treatments 15
DRAINAGE AND TESC 16
Stormwater Report 18
Drainage Plans and Details 18
c: \docume -1 \cyndy- 1.tuk\locals -1\ temp \xpgrpwise\ exhibit_ a_scope_of_work_supp_9_v1
Printed 03/09/2010
CNINTB
Tukwila Urban Access Improvement Project
Page ii
Task 21.5.3 TESC Plans and Details 19
TASK 21.6 STRUCTURES (BRIDGES /WALLS) 20
Task 21.6.1 Bridges and Walls 20
TASK 21.7 SURVEYING 20
Task 21.7.1 Field Survey for Design 20
TASK 21.8 UTILITIES 21
Task 21.8.1 Coordination with utilities 21
Task 21.8.2 Utility Design 22
TASK 21,9 SPECIAL PROVISIONS
TASK 21.10
TASK 21.11
TASK 21.12
TASK 21.13
DEVELOPMENT OF QUANTITIES AND COST ESTIMATE
100% AND AD -READY CONTRACT PLAN SHEETS
CONSTRUCTION SCHEDULE
ASSISTANCE DURING BID PERIOD 24
c \docume 1\cyndy -1.tuk \locals -1 \temp \xpgrpwise\ exhibit_ a_scope_of_work_supp_9_v10.docx
Printed 03/09/2010
22
23
23
23
MINTB
103
104
Tukwila Urban Access Improvement Project Page 1
During the term of this Agreement, the engineering CONSULTANT (CONSULTANT) shall
perform professional services for the CITYfinal design and assistance during bid period in
connection with the:
Tukwila Urban Access Improvement:
Klickitat Drive /Southcenter Parkway Area Project
This document shall be used to plan, conduct and complete the work on the project.
1. SUPPLEMENT PURPOSE
The design and PS &E of the Tukwila Urban Access Improvement Project was shelved at the
100% design in May of 2007. The purpose of this supplement is to finalize the project
specifically: 1) complete the work not completed at the time the project was shelved; 2) update
the shelved design to reflect changes in standards and specifications, and 3) design and
incorporate revisions required to meet WSDOT design approval requirements. Specific items to
be addressed in finalizing the design and PS &E from May 2007 include:
Design work at McDonald's entrance and parking.
Design work on Doubletree and Legacy properties.
Address the removal and re- setting of private business monument signs on the project.
(These are located on the Doubletree and Legacy properties)
Confirm final paving limits between disciplines.
Updates to project specifications and cost estimates.
Structural analysis and design of overhead sign supports
Maintenance of Traffic and Construction Phasing and Staging plans.
Design updates to reflect changed conditions in project area.
Coordination with property owners adjacent to the project to convey the current design
which has new curb, gutter, sidewalk, driveway and storm sewer reconstruction on the
west side of the project.
WSDOT Design Documentation with the exception of Channelization Plans for approval
and Deviations.
WSDOT review and approval of all work to take place within limited access or WSDOT
right of way (ROW).
WSDOT review and approval of signing plans.
Design changes at the south buttonhook ramp to accommodate a WB -67 design vehicle
and related potential impacts to, drainage design, plans, grading, removals, erosion
control and site preparation plans for project.
Revisions to Stormwater Report as a result of WSDOT changes and changes in criteria.
In addition, at the time this scope was developed for the City of Tukwila, WSDOT and the HNTB
design team coordinated to develop design modifications to accommodate a WB -67 design
vehicle. The WB -67 design vehicle is a change over the original project assumption of a WB -50
design vehicle. This change in design vehicle has resulted in changes to the shelved project
design which are used as the basis of redesign. These changes reflect modifications resulting
from meetings between the City, WSDOT and the CONSULTANT on November 3 2009 and
December 2n 2009. Any subsequent changes will require this scope of work to be revised.
c: \docume- 1\cyndy -1.tuk \locals -1\ temp \xpgrpwise \exhibit_a_scope_of work_supp_9_v10 docx
Printed 03/09/2010
CINTB
Tukwila Urban Access Improvement Project Page 2
Elimination and reduction of landscape islands at the intersection of Klickitat Drive and
Southcenter Parkway.
Widening of the southwest quadrant of the Klickitat Drive and Southcenter Parkway
intersection resulting in additional impervious area, modifications to the intersection curb
radius, ADA ramp modifications, relocation of existing traffic signal, controller cabinet,
conduit, pavement markings, additional grading, changes to site preparation plans.
Traffic signal timing /synchronization modifications.
Relocation of traffic signal pole Type III at Sta. 16 +08.
Crosswalk modifications.
Modifications to traffic island at the north buttonhook reduce island size and associated
landscaping.
Addition of a fillet on the north bridge abutment providing a cantilever to accommodate
wider truck turning movements.
Extension of c -curb on Southcenter Parkway.
South buttonhook ramp work.
North buttonhook ramp work.
Adjustments to the northbound lanes of Southcenter Parkway between Strander Blvd and
Klickitat Drive.
II. DESIGN CRITERIA
Documents developed as part of this scope of work will be in accordance with the latest edition
and amendments to the following documents, as of the date the AGREEMENT is signed.
Changes in any design standards or requirements after work has begun may result in the need for
Extra Work.
City of Tukwila Publications:
a. Year 2004 Comprehensive Plan
b. City of Tukwila Development Guidelines and Design and Construction Standards, 2003
WSDOT Publications:
a. Standard Specifications for Road, Bridge and Municipal Construction, English edition
(2010) (M41 -10)
b. Standard Plans for Road, Bridge and Municipal Construction, English edition (M21 -01)
c. Design Manual, (M22 -01)
d. Hydraulic Manual, (M23 -03)
e. Plans Preparation Manual, (M22 -31)
f. Bridge Design Manual, (M23 -50)
g. Amendments and General Special Provisions
h. Standard Item Table
c:\docume -1 \cyndy -1. tuk \locals- 15lemp \xpgrpwise\ exhibit _a_scope_of_work_supp_9_v10 docx
Printed 03/09/2010
105
106
Tukwila Urban Access Improvement Project Page 3
i. Traffic Manual, (M51 -02)
j. Highway Runoff Manual, (M31 -16)
k. Utilities Manual, (M22 -87)
1. Local Agency Guidelines, (M36- 63(PA))
m. Environmental Procedures Manual, (M31 -11)
American Association of State Highway and Transportation Officials (AASHTO) Publications:
a. A Policy on Geometric Design of Highways and Streets, 5 Edition (2004)
b. Standard Specifications for Highway Bridges, Seventeenth Edition, (2002)
c. Highway Design and Operational Practices Related to Highway Safety, (1997)
U.S. Department of Transportation (USDOT) Publications:
a. Manual of Uniform Traffic Control Devices for Streets and Highways, 2003
b. Highway Capacity Manual
Other Publications /Design Guides:
a. National Electrical Code
b. Standards of the American Waterworks Association
c. Book of American Society for Testing and Materials Standards
d. American Public Works Association standards
e. Americans With Disabilities Act (ADA)
f. General Electric's ALADAN program (Illumination design)
III. PROJECT SCHEDULE
The preliminary project schedule will be developed upon notice to proceed.
The duration of the reviews by the CITY, and by others, will be given in the project schedule.
Mutually agreeable changes to the project schedule, whether initiated by the CITY or
CONSULTANT, may be the basis for adjustments in the project budget.
c• \docume -1 \cyndy -1.tuk \locals -1\ temp \xpgrpwise \exhibit_a_scope_of work_supp_9_v10.docx
Printed 03/09/2010
CINTB
Tukwila Urban Access Improvement Project Page 4
IV, ITEMS AND SERVICES TO BE FURNISHED BY THE CITY
The CITY will provide the following items and services to the CONSULTANT that will facilitate
the preparation of the documents for work within the limits of the PROJECT. The
CONSULTANT is entitled to rely on the accuracy and completeness of this and other data
furnished and represented by the CITY and others, including but not limited to, survey and traffic
data.
The City will be responsible for leading WSDOT coordination, permitting, preparation of
agreements and private property coordination.
Reviews of CONSULTANT submittals at the mutually agreed upon times set forth in the
project schedule and the consolidation of all review comments by others onto one review
set prior to return to the CONSULTANT.
Lighting requirements and design criteria per City of Tukwila Department of Community
Development (DCD) requirements, if available.
CITY will prepare and provide documents for rights -of -entry upon all lands necessary for
the performance of the design work including official notices to property owners and
agencies.
Arrangements for the public meetings, including meeting place, announcements, etc.
The CITY will be responsible for public involvement and information for the PROJECT.
Payment of all review and /or permit fees.
Computer generated files supplied by the CITY will be in AutoCAD, and in a format
compatible with the CONSULTANT's hardware /software. Any reformatting or
reconfiguration or hardware /software purchase necessary to make the supplied files
compatible will be considered Extra Work.
V. ABBREVIATIONS
The following abbreviations are referred to throughout this scope of work:
AASHTO American Association of State Highway and Transportation Officials
BDM WSDOT Bridge Design Manual
DCE Documented Categorical Exemption
DFW Washington State Department of Fish and Wildlife
DNR Washington State Department of Natural Resources
DOE Washington State Department of Ecology
ESA Endangered Species Act
c:\docume -1 \cyndy -1. tuk \locals -1 temp\ xpgrpwise\ exhibd_a_scope_of_work_supp_9_v 10 -docx
Printed 03/09/2010
:'INTB
107
108
Tukwila Urban Access Improvement Project Page 5
FEMA Federal Emergency Management Agency
FHWA Federal Highway Administration
LOS Level of service
NEPA National Environmental Projection Act
NMFS National Marine Fisheries Service
NPDES National Pollutant Discharge Elimination System
NRHP National Register of Historic Places
ROW Right -of -way
PS &E Plans, specifications, and estimates
SEPA State Environmental Protection Act
TDM Transportation Demand Management
TS &L Type, Size and Location
WSDOT Washington State Department of Transportation
USFWS United States Fish and Wildlife Service
VI. PROJECT DOCUMENTATION
The documents listed as "Deliverables" in the Work Tasks, Section IX of this scope of work, and
other exhibits or presentations for the work covered by this AGREEMENT and associated
supplements, if necessary, will be furnished by the CONSULTANT to the CITY upon completion
of the various tasks of work. Whether the documents are submitted in electronic media or in hard
copy, any use of the materials on another project or on extensions of this project beyond the use
for which they were intended, or any modification of the materials or conversion of the materials
to an alternate system or format will be without liability or legal exposure to CONSULTANT.
The CITY will assume all risks associated with such use, modifications, or conversions. The
CONSULTANT may remove from the electronic materials delivered to the CITY, all references
to the CONSULTANT involvement and will retain a tangible copy of the materials delivered to
the CITY which will govern the interpretation of the materials and the information recorded.
Electronic files are considered working files only; the CONSULTANT is not required to maintain
electronic files beyond 90 days after the project final billing, and makes no warranty as to the
viability of electronic files beyond 90 days from date of transmittal.
VII. WORK TASKS
General Assunntions:
The level of effort for each phase and task of work is limited to the amount of labor and
expenses indicated in Exhibit C. These costs are itemized in Exhibit C to aid in project
c: \docume- 1\cyndy- 1.luk\ locals -1\ temp \xpgrpwise \exhibil_a_scope_of work_supp_9_v10.docx
Printed 03/09/2010
:aI N'A'B
Tukwila Urban Access Improvement Project Page 6
tracking purposes only. The budget may be transferred between tasks, provided the total
contracted amount is not exceeded. Additional services beyond these limits will be
considered Extra Work.
Subsurface investigation and remedial action associated with hazardous wastes located within
the project limits are not within this scope of services. No hazardous, dangerous, or
contaminated soil /ground water is anticipated on or within the project limits. Should any of
these materials be encountered, it will be considered Extra Work.
The analyses, design, plans, specifications, and estimate performed or prepared as part of the
PROJECT will be in English units. Metric units will not be used on this PROJECT.
The plans will be prepared in accordance with City of Tukwila drafting standards, with
WSDOT /APWA standards being the default standards to follow.
The project contract documents will be reviewed once by WSDOT and once by the City of
Tukwila. The review will be of the revised 100% PS &E.
Electronic files of PS &E contract documents will be delivered to the CITY in AutoCAD
format (latest version) at the conclusion of Supplement 9. Preparation of the record drawings
(as- builts) will be the responsibility of the CITY.
c \docume-1 \cyndy-1 tuk\ locals -1\ temp1xpgrpwise \exhibil_a_scope_of_work_supp_9 v10.docx
Printed 03/09/2010
:INTB
109
110
Tukwila Urban Access Improvement Project Page 7
TASK 21.1 PROJECT MANAGEMENT
In this task are described those services necessary to plan, perform, and control the various
elements of the project so that the needs and expectations of the CITY and other project
stakeholders will be met or exceeded.
Assunwtions:
To accurately establish and manage the total project budget, the CITY will provide to the
CONSULTANT their anticipated administrative costs through construction. The
CONSULTANT shall generate the estimated right -of -way acquisition costs.
The CONSULTANT's Project Manager and /or deputy Project Manager will meet with the
CITY's Project Manager on a weekly basis throughout the completion of the project.
The CONSULTANT shall submit monthly invoices with a written summary of project progress
to -date and activities expected for the next month.
The workplan components developed in Phase 1 of the project will be used as the guidelines for
performing the work in this supplement. Issues may arise that are beyond the provisions of this
scope of work. Flexibility will be maintained in the workplan to address these urgent project
issues; however, the reallocation of resources may result in justification for Extra Work.
Internal project team coordination meetings will be held weekly between NTP and completion of
final PS &E. These meetings will be in addition to the coordination meetings held with the CITY,
but budgeted as part of the specific work tasks, separate from Task 1 Project Management.
Task 21.1.1 Issues Resolution
In accordance with the Change Management Plan, this task may involve:
Identifying and assessing a given issue relative to schedule, budget, resources,
and risk.
Initiating the appropriate action(s) by assigning the issue to specific team
member(s) for resolution using the Communication Plan provisions as a
guideline.
Monitors the issue resolution progress.
Providing assurance for the timely resolution of issues.
Adjusting the project work plan components as required.
The level of effort associated with each individual issue is contained within the appropriate
task(s) available to the team member(s) responsible for its resolution.
Task 21.1.2 Measure Project Requirements
Maintain the focus of the team members on satisfying the project purpose, objectives, and scope
of work. Monitor and confirm that the technical aspects of the project are being performed and
c: \docume -1 \cyndy -1 tuk \locals -1l temp \xpgrpwise\ exhibit _a_scope_of_work_supp_9_v 10. docx
Printed 03/09/2010
CI NTB
Tukwila Urban Access improvement Project Page 8
prepared in compliance with the CITY's expectations. Verify that the information generated on
the project is being filed.
Task 21.1.3 Measure Budget Conformance
On a weekly basis, monitor the budget. Monitor the planned versus actual rate of expenditure for
each element, and identify trends, taking corrective actions if necessary by implementing the
applicable provisions of the Change Management Plan.
Task 21.1.4 Develop Schedule and Measure Conformance
This task will begin with the development of a project schedule. The schedule will incorporate
all tasks documented in this scope of work. The task shall also include monitoring and updating
the Project Schedule on a monthly basis or as needed to determine potential i►npacts of proposed
changes. Adjust the durations, predecessor relationships, constraints, linkages, deliverable
descriptions and dates, reviews, percent completes, milestones, critical path, and task completion
dates to reflect the current status of the project and the revisions made to the work breakdown
structure.
Task 21.1.5 Communicate Progress
Conduct ongoing, proactive, responsive communications with the CITY staff involved in the
direction and execution of the project. Coordinate the schedule of the reviews to be performed by
the CITY. Prepare and submit a monthly progress report that will include identification of work
performed in the previous month's schedule, measures for mitigating schedule slippage and
identification and discussion of potential problems that may arise. Prepare meeting minutes if
necessary and distribute to attendees.
Task 21.1.6 Lead the Project CONSULTANT Team
Provide direction to the project CONSULTANT team. Conduct project coordination meetings as
required with appropriate task leaders. Monitor the planned versus actual rate of expenditure for
each task and take corrective actions if necessary. Collect from each task leader, the percent
complete as measured by how much work is left to be accomplished on a task by task basis.
Maintain a high exposure to the project team of the issues to be resolved and their potential
impacts to the measures of success for the project.
Task 21.1.7 Manage Quality
The Quality Assurance manager shall implement the processes described in the Quality
Management Plan to meet the project objectives established by the stakeholders. Perform
continual Quality Planning to reaffirm which quality standards are relevant and how they are to
be satisfied. Verify that Quality Control has been provided for each technical specialty to
evaluate the overall project performance on a regular basis and to build confidence that the
project will satisfy the current quality standards for the design, drawings, specifications, and cost
estimates. Confirm that specific project results are being monitored by each technical specialty
through Quality Control activities to determine if they are in compliance with the quality
standards and, if not, that potential solutions to eliminate the cause(s) of unsatisfactory
performance have been identified and implemented. Facilitate the identification and assignment
of appropriate senior reviewers for each technical specialty. Confirm that the current Quality
Control activities are clearly indicated in the Project Schedule.
c. \docume -1 \cyndy -1.tuk \locals -1 temp \xpgrpwi se\ exhibit_ a_scope_of_work_supp_9_v10.docx
Printed 03/09/2010
:1NTB
111
112
Tukwila Urban Access Improvement Project Page 9
Task 21.1.8 Manage Change
The CONSULTANT's Project Manager will monitor scope adherence to identify potential
changes. The Project Manager will work with CONSULTANT team technical specialty staff to
track and document potential changes and, if necessary, complete Project Change Records for
endorsement from the City of Tukwila. Following are the specific efforts included in this task:
1. Identify, Analyze Develop Change Strategies. Orchestrate the Change Management
Plan by logging and tracking potential changes identified from any source (Step 1);
facilitating the analysis of the change and determination of its impacts (Step 2), and
facilitating the development of a response strategy (Step 3). The specific activities
associated with completing Steps 2 3 on a given potential change will be largely the
responsibility of each technical specialty staff.
2. Identify Analyze Risk of Change. Identify and analyze the likelihood of the potential
change introducing risk into the project. Characterize the risk to the extent possible and
outline control measures for minimizing its negative effects.
3. Change Authorization. Communicate the proposed strategy(s) to resolve the change and
make appropriate revisions as necessary to gain endorsement for the change (Step 4).
Obtain a written change authorization from the CITY, by the City Public Works Director,
and from the CONSULTANT, by its Project Manager, as representatives of the project
stakeholders.
4. Workplan Revisions. Prior to undertaking the work as a result of the change, revise the
project workplan (Step 5) to avoid misunderstandings, discontent, and poor project
performance. Monitor the implementation of the change using the standard project tools
and techniques.
c: \docume -1 \cyndy -1.luk \locals -1 \temp \xpgrpwise\ exhibit _a_scope_ot_work_supp_9_v 10.docx
Printed 03/09/2010
yINTB
Tukwila Urban Access Improvement Project Page 10
TASK 21.2 RIGHT OF WAY
Task 21.2.1 Right of Way Legal Descriptions and Easements
The CONSULTANT shall review right of way and easements by referring to the public record
and drawings to ensure that any changes that have taken place since the project was shelved have
been properly recorded. In addition, the CONSULTANT shall ensure that easements previously
prepared have been recorded and are shown on the right of way plans.
Assumptions:
The CONSULTANT assumes there will be recent recorded easements and right of way
legal descriptions encumbering adjoining private property that may affect the project.
The CONSULTANT shall review any record documents found and add the changes to
the right of way plans.
The CONSULTANT anticipates there to be a need for new descriptions to be written for
additional acquisitions. The CONSULTANT shall prepare up to six legal descriptions as
directed.
The Limited Access line will be moved east, to the back of the proposed curb and gutter
along Southcenter Parkway and the north and south limits of the Limited Access will not
change.
A Turnback agreement will be prepared between the City of Tukwila and WSDOT to
turn existing ROW and maintenance activities from WSDOT to the City of Tukwila. The
limits of this Turnback will be from new the Limited Access line located at the east curb
and gutter line along Southcenter Parkway to the west side of Walls 1 and Wall 3.
Deliverables:
The CONSULTANT shall provide an AutoCAD file depicting legal descriptions, in the project
coordinates showing the calculated locations.
Task 21.2.2 Right of Way Plans
Assumptions:
The CONSULTANT shall prepare ROW plans compliant with WSDOT format and
criteria depicting the centerline, right of way lines, easement lines, parcels, owner
information and acquisition areas.
Deliverables:
Submittal of revised 100% Right of Way Plans
Written to response to revised 100% submittal comments.
Ad -ready submittal of Right of Way Plans.
TASK 21.3 PERMITTING
Asscunu,tions:
c.\docume -1 \cyndy -1. tuk \locals -1 temp \xpgrpwise\ exhibit _a_scope_of_work_supp_9_v 10.docx
Printed 03/09/2010
b'LNTB
113
114
Tukwila Urban Access Improvement Project Page 11
The City will be responsible for all permitting efforts. No work by the CONSULTANT will
be performed.
TASK 21.4.0 ROADWAY
Task 21.4.1 Roadway and Channelization Design
The CONSULTANT shall update and complete channelization, sidewalk and curb areas impacted
by redevelopment or design criteria changes since the project was put on the shelf in May 2007.
These areas include but are not limited to: The northern curb line and amenities on Strander
Blvd, McDonalds frontage, Doubletree Hotel and adjacent office building property, and any areas
impacted by new proposed storm sewer changes. The CONSULTANT's efforts will include the
following:
Assumvtioiis:
Design revisions to accommodate development activity not listed above will be
considered extra work.
The buttonhook ramp design and other changes brought about by meetings with WSDOT
will be prepared to a 100% PS &E design level and submitted with the revised 100%
PS &E submittal and final ad -ready PS &E submittal; no other submittals will be made.
Deliverables:
Definition of the limits of excavation versus pavement removals and update of
quantity calculations if necessary.
Addition of pay items as required for Removal of Extruded Curb, Type C Curb
Channelization, Concrete Barriers, and Adjustment of Storm Drainage
Structures.
Design for temporary access for Mc Donald's entrance that allows use of parking
lot and drive thru factilities.
The proposed Impact Attenuators need to be re- evaluated against new AASHTO
design guidance. Review of standard item names and standard plan references
and make necessary adjustments to PS &E for these changes.
Ensure project connects properly with adjacent developments since project was
shelved. Verify that contract documents cover the removal and re- setting of the
private business monument signs on the project. These are located at the
Doubletree and Southcenter Place properties. Meet with other design disciplines
to finalize and adjust final revised paving limits.
Impacts associated with revisions agreed to during the WSDOT coordination
meetings on November 3` 2009 and December 2 2009
As part of this task the CONSULTANT shall complete the buttonhook ramp
design that was previously developed to approximately 30% design level along
with all other changes as a result of WSDOT coordination. The
CONSULTANT's work will include completing the horizontal and vertical
layout design, channelization, paving design and signing design.
Design deviations, evaluate upgrades and design justifications as described in the
memo from the CONSULTANT to CITY dated January 7, 2010 will be approved
by WSDOT. If not approved, additional related work required by the
CONSULTANT will be considered Extra Work.
cldocume -1 \cyndy 1.luk\ locals 1\ temp\ xpgrpwise \exhibit_a_scope_of_work_supp_9 v10.docx
Printed 03/09/2010
CINTB
Tukwila Urban Access improvement Project Page 12
Submittal of revised 100% roadway and channelization Plans, Specifications and
Estimate.
Written response to revised 100% submittal comments.
Ad -ready submittal of roadway and channelization Plans, Specifications and Estimate.
Task 21.4.2 Signals and Interconnect
The CONSULTANT shall update the final design and plans, specifications, and estimates for
traffic signal installations since the project was put on the shelf in May 2007 along with changes
resulting from WSDOT coordination. This task will include the design of signal interconnect
between the new or modified signalized intersections listed below.
Southcenter Parkway and Doubletree /McDonald's entrance
Southcenter Parkway and Strander Blvd
Southcenter Parkway and Klickitat Drive
Southcenter Parkway and Nordstrom entrance
Assail-lotions:
Signal interconnect to be designed and constructed as part of this project will terminate at
project limits on Southcenter Parkway.
Video surveillance cameras will not be included in this project.
Vehicle detection will be carried out using the Vantage video image vehicle detection
system systems.
Communication to support signal coordination will not extend beyond the limits of the
project.
The City of Tukwila will provide coordination of design activities, permits, and any other
projects that may affect the traffic signal systems design and installation.
Deliiverables:
Submittal of revised 100% Signals and ITS Plans, Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of Signals and ITS Plans, Specifications and Estimate.
Task 21.4.3 Illumination
The CONSULTANT shall update the illumination design including lighting calculations based on
changes since the project was shelved in May 2007. The following will be updated:
Review location of power vaults at north end of project and relocate if necessary
Power for lighting, sign lighting and ITS elements.
Review changes to channelization and illumination calculations
c \docume -1 \cyndy -1.tuk \locals -1\ temp xperpwiselexhibit _a_scope_of_work_supp_9 v10.docx
Printed 03/0912010
LINTB
115
116
Tukwila Urban Access Improvement Project Page 13
Update and coordinate with sign lighting design
Power sources will be identified.
Coordination with Puget Sound Energy for revised loads.
Voltage drop and load calculations.
Design will be prepared to meet WSDOT standards as modified by the City of Tukwila,
NEC, IES standards.
Assumptions:
Lighting calculations will use the AGI32 program to determine if additional lighting is
required in areas of roadway widening.
Luminaires will be relocated where required wiring and conduit will be installed
underground.
Deliverables:
Submittal of revised 100% Illumination Plans, Specifications and Estimate.
Written to response to the revised 100% submittal comments.
Ad -ready submittal of Illumination Plans, Specifications and Estimate.
Task 21.4.4 Site Preparation
The CONSULTANT shall develop updated design and PS &E (location, limits, type, details,
construction notes, calculations, and quantities) of the site preparation elements for the project to
a 100% review and Ad Ready level of completion based on any changes to design criteria or
standards resulting from shelving of the 100% submittal or from known changes resulting from
WSDOT coordination.
Deliverables:
Submittal of revised 100% site preparation Plans, Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of site preparation Plans, Specifications and Estimate.
Task 21.4.5 Traffic Control Plans
The CONSULTANT shall provide a specification for the contractor's use of CITY streets during
construction including the time periods during which construction work can occur.
Assumptions:
The CONTRACTOR shall develop traffic control plans to provide for the movement
of traffic between and through each work area during the course of construction, including
c. \docume- 1 \cyndy- 1.luk\ locals- 1l templxpgrpwise \exhibil_a_scope_ot work_supp_9_v10.docx
Printed 03/09/2010
`I N T B
Tukwila Urban Access Improvement Project Page 14
work zones, areas open to traffic, sequencing of work to required maintain traffic, and any
detours.
Traffic control plans developed for the 100% shelf submittal, May 2007 will be
provided to the contractor for information only.
Deliverables:
Submittal of revised 100% Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of Specifications and Estimate.
Task 21.4.6 Detour Plans
The CONSULTANT shall develop traffic detour plans based on the full closure construction
phasing and partial closure construction phasing identified above. The purpose of the traffic
detour plans is to establish detour routes to minimize disruption to traffic on adjacent facilities
during the closure of Southcenter Parkway.
The CONSULTANT team will conduct a single workshop to coordinate with various stakeholder
groups to develop the detour plans and strategies. Groups shall include:
Westfield Mall;
Tukwila Traffic Management Center staff.
King County Metro Transit Sewer
Emergency Services
Utilities
United State Postal Service (USPS) Regional Distributions, Freight Mobility
WSDOT
Detour plans developed will consider and include:
Traffic operations through the proposed detour routes
Identification of impacts to transit operations, and emergency service providers, and
mitigation of those impacts, if any.
Temporary signing and delineation
ASSU191ntions:
The project will be constructed under a full road closure as depicted in the 30% Design
Report and under a partial closure phase with the project being opened to traffic during
the seven week 2010-2011 construction moratorium period.
c: \docume -1 \cyndy -1. tuk \locals -1 temp \xpgrpwise\ exhibit _a_scope_ot_work_supp_9_v 10.docx
Printed 03/09/2010
N MTS
117
11
Tukwila Urban Access Improvement Project Page 15
CONSULTANT shall coordinate the detour plan and ramp closures with WSDOT, City
of Tukwila, property owners and other associated stakeholders.
Deliverables:
Submittal of revised 100% Detour Plans, Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of Detour Plans, Specifications and Estimate.
Task 21.4.7 Signing
The CONSULTANT shall finalize and update the design of overhead and street signs since the
project was shelved in May 2007. Design changes will have to be made to address addition of
the Buttonhook Ramp, development activity that has occurred in the area since project plans were
put on the shelf and other changes brought about through WSDOT coordination. Key elements of
work include:
Redesign of overhead signs and street signs
Perform structural analysis and design for overhead sign supports
Assumptions:
Work will incorporate changes to MUTCD requirements and design criteria as adopted,
as well as WSDOT std. plans and specs for signing that have occurred since the 2007
project shelf date.
Design and structural analysis will be required for 2 signs mounted to overpass structures.
Coordination with WSDOT will be necessary to complete the PS &E documents
WSDOT Bridge and Structures office will review signing structure design for signs
within WSDOT ROW.
Deliverables:
Submittal of revised 100% signing Plans, Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of signing Plans, Specifications and Estimate.
Task 21.4.8 Landscape Design and Architectural Treatments
The CONSULTANT shall update and complete the 100% shelf submittal urban design elements
including: pedestrian paving, wall finishes, barriers, pedestrian railings, street trees, slope and
accent plantings, irrigation, pedestrian street lighting, fencing and site furnishings based on
changes in criteria, changes in project area and design changes resulting from coordination with
WSDOT. This work also includes coordination with civil, structural, environmental and storm
water plan development.
Assumptions:
c: \docume -1 \cyndy -1. tuk \locals -1 temp \xpgrpwise\ exhibit _a_scope_ol_work_supp_ 10.docx
Printed 03/09/2010
C 'INTB
Tukwila Urban Access improvement Project Page 16
Artwork or coordination with artist is not included in the scope at this time
Deliverables:
Submittal of revised 100% Landscape and Architectural Plans, Specifications and
Esti mate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of Landscape and Architectural Plans, Specifications and Estimate.
TASK 2t5 DRAINAGE AND TESC
The CONSULTANT shall finalize and update the design for the drainage conveyance, detention
and Stormwater Report since the project was shelved in May 2007. Design changes will have to
be made to address the addition of the Buttonhook Ramp, WSDOT coordination, and other
development activity that has occurred in the area since project plans were put on the shelf. The
100% shelf Copy design will need to be updated to comply with current Washington State
Department of Ecology (DOE) design and permitting criteria. A drainage design review was
performed for the drainage system to identify possible opportunities to:
1) Modify the design to meet current standards.
2) Simplify the design (making it easier to construct in a shorter period of time).
3) Incorporate project changes that have been requested through WSDOT review.
The following Scope utilizes the concept identified in the February 2010 Drainage Design
Review and discussions with the City:
Assu,ni tions:
The following drainage and TESC assumptions apply:
The drainage design and calculations will comply with the 2008 WSDOT Highway
Runoff Manual within WSDOT ROW or Limited Access and the 2009 King County
Surface Water Design Manual in the City of Tukwila.
The Stormwater Report will follow WSDOT Northwest Region 2008 Highway Runoff
Manual Format.
This scope of work assumes changes to the roadway impervious areas for the additional
widening of the south "buttonhook" exit ramp and modifications resulting from WSDOT
channelization changes to accommodate WB -67 truck turning movements at Klickitat
Drive /Southcenter Parkway, which include, elimination of landscape islands,
rechannelization, added impervious area at southwest quadrant of the
Klickitat /Southcenter Parkway intersection.
Drainage updates will be based on the Drainage Design Review memorandum prepared
for the City of Tukwila in February 2010.
WSDOT will review and approve design elements within WSDOT Limited Access
and /or ROW.
c. \docume -1 \cyndy -1. tuk\locals-1\ temp \xpgrpwi se\ exhibit_ a_scope_of_work_supp_9_v10.docx
Printed 03/09/2010
119
120
Tukwila Urban Access Improvement Project Page 17
The drainage design approach for performing these revisions involves the following steps:
Meet with WSDOT and the City to discuss the drainage revision approach as a result of
changes in criteria and WSDOT revisions, submittal requirements, drainage report
format, and other WSDOT expectations.
Revise Threshold Discharge Areas according to roadway geometric changes.
Revise the drainage design criteria according to current King County Surface Water
Manual and the WSDOT Hydraulics Manual 2010, and Highway Runoff Manual 2008.
Revise the flow control detention vault design based on the Drainage Design Review
memorandum prepared for the City of Tukwila in February 2010.
Revise the water quality approach based on the Drainage Design Review memorandum
prepared for the City of Tukwila in February 2010.
Revise the conveyance system tributary areas, inlet spacing calculations, gutter spread
calculations, and conveyance calculations.
Revise the vault details.
Revise the control structure details.
Provide emergency bypass conveyance around the vaults.
Update plans, profiles, details, quantities, and specifications.
This work also involves removing the structure notes from the plans. Updating the
structure notes plans involves a significant effort. This change proposes to document the
approximate quantities in the specifications for the contractor to base a Lump Sum fee for
the drainage construction.
Update the drainage Technical Information Report
Update the Temporary Erosion and Sediment Control (TESC) Report
Submit the drainage and TESC report along with the revised plans and "original"
responses to WSDOT comments. Please note the responses to the original WSDOT
comments will be revised to accommodate current design issues.
This Scope assumes WSDOT will review the plans for 4 weeks (standard review time) and
the consultant will provide response to comments and attend one comment resolution meeting
with the City and WSDOT. Following the response to comments meeting, the Consultant will
update the design according to comment responses, submit for final review and request
drainage design approval.
c. \docume- 1\cyndy -1.tuk \locals- 1\temp \xpgrpwise\ exhibit _a_scope_of_work_supp_9_v10 docx
Printed 03/09/2010
C°I NTB
Tukwila Urban Access improvement Project Page 18
This Scope assumes a final review meeting will be held with WSDOT and the City to discuss
minor design elements and responses and revisions to be incorporated into the Ad Ready
PS &E submittal.
Task 21.5.1 Stormwater Report
This report will address changes in criteria since shelving of project, unresolved issues prior to
shelving, and modifications to impervious areas as a result of changes made during WSDOT
coordination of channelization plans in addition to updates agreed upon by the City as
documented in the Drainage Design Review Memorandum, February 2010. The report will
update the stormwater system design including analyses for modification to drainage basin
impervious areas, inlet spacing /locations, sag inlet capacity analysis, pipe sizing, and detention
and water quality treatment vault sizing. Sections of the existing Stormwater Report submitted to
WSDOT in 2005 will be incorporated wherever possible.
The CONSULTANT shall update and submit one draft and one final Type A Stormwater Report
with TESC narrative for approval to the City of Tukwila for review and approval by WSDOT. It
is assumed that the City and WSDOT will perform concurrent reviews of the Stormwater Report.
This report shall include a summary and description of both pre- and post developed conditions
along with calculations for both the collection /conveyance systems, flow control and quality
control systems. The report shall address flow control and runoff treatment requirements along
with a map and table identifying and summarizing the affected drainage basins and how much
new /replaced impervious surface will be constructed within each basin. The memo shall include
narrative, calculations, basin maps, stormwater /drainage plans, and figures.
Deliverables:
Report will be prepared according to WSDOT Northwest Regional Highway Runoff
Manual format.
I Draft Stormwater Report submitted with updated plans and calculations (electronic
PDF and 3 hard copies) to the City of Tukwila for concurrent review by the City and
WSDOT.
Responses to WSDOT and City of Tukwila comments on 1 draft Stormwater Report
(comment form electronic PDF)
Final Stormwater Report submitted with updated plans and calculations (electronic PDF
and 3 hard copies)
Task 21.5.2 Drainage Plans and Details
This element of work includes updating the storm drainage plans according to City of Tukwila
Public Works Department Development Guidelines and Design Construction Standards Revision
1 (2005) and the WSDOT 2008 HRM.
Update plan view pipe network
Update catch basin types, sizes, and locations
Update pipe sizes, callouts, and water quality facility locations
Update control structure details
Update detention and treatment vault details
c \docume- 1 \cyndy -1.tuk \locals -1 \temp \xpgrpwise \exhibit a_scope_of_work_supp_9_v10 docx
Printed 03/09/2010
I NTB
121
122
Tukwila Urban Access Improvement Project Page 19
Update profiles
Update utility crossings and checking for water and sewer conflicts
Updating wall conflicts
Update oil water separator details
Evaluate and update discharges into WSDOT right -of -way for method of construction
(i.e. bore and jacking).
Evaluate the existing WSDOT pond system for flow control and treatment capacity.
Deliverables:
Submittal of revised 100% Drainage Plans, Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of Drainage Plans, Specifications and Estimate
Task 21.5.3 TESC Plans and Details
The purpose of this task is to update TESC Plans and Details. This element of work includes
updating the TESC plans according to City of Tukwila Public Works Department Development
Guidelines and Design Construction Standards Revision 1 (2005) and the WSDOT 2008 HRM.
Deliverables:
Submittal of revised 100% TESC Plans, Specifications and Estimate.
Written response to revised 100% submittal comments.
Ad -ready submittal of TESC Plans, Specifications and Estimate
c: \docume -1 \cyndy -1. tuk \locals -1 temp \xpgrpwise\ exhibit_ a_scope_of_work_supp_9_v
Printed 03/09/2010
CIINTB
Tukwila Urban Access improvement Project Page 20
TASK 21.6 STRUCTURES (BRIDGES/WALLS)
Task 21.6.1 Bridges and Walls
The CONSULANT shall update and complete the project structural design since the project was
shelved in 2007. The structures include the single span cast -in -place slab bridge and foundations,
soldier pile retaining walls, structural earth retaining walls, cast -in -place retaining walls, moment
slabs, traffic barriers, light pole foundations, sign supports and stairs. Specific tasks to be carried
out include:
Review 100% shelf submittal and update plans.
Review 100% shelf specifications and update to current WSDOT Specifications and
Special Provisions.
Design changes for accommodation of WB -67 design vehicle
o Re- design of north end of CIP bridge and abutment
o Design of drilled shaft and column for signal pole foundation.
o Wall at SW corner of Klickitat Drive and Southcenter Parkway
Review and update the structural cost estimate quantities. Update unit prices and estimate
backup data for the current construction year.
Conduct interdisciplinary review and update PS &E.
Perform design checks and quality control on all revisions to the 100% shelf submittal.
Assemble 100% PS &E package for delivery to client.
Review, respond to and incorporate as appropriate review comments made on the
revised 100% Submittal.
Perform QC on the Ad -Ready PS &E Submittal
Assemble Final Ad -Ready package for delivery to client.
Project Closeout.
Assumptions:
6 -1 hour design team coordination meetings
6 -1 hour design meetings
Deliverables.
Submittal of revised 100% structures Plans, Specifications and Estimate.
Written response to revised 100% submittal comments.
Ad -ready submittal of structures Plans, Specifications and Estimate
TASK 21.7 SURVEYING
Task 21.7.1 Field Survey for Design
A ssunwtions:
The Consultant shall provide supplemental field survey for the following areas: 1) the north end
where the City of Seattle /City of Tukwila water intertie is located; 2) the changes to the north side
of Strander Blvd.: 3) the McDonalds parking lot and frontage to Southcenter Pkwy.; 4) The
bridge and abutment structure of Klickitat Dr.
in these areas:
c \docume -1 \cyndy -1. tuk \locals -1\ temp \xpgrpwise\ exhibit_ a_scope_of_work_supp_9_v10.docx
Printed 03/09/2010
:INT
123
124
Tukwila Urban Access Improvement Project Page 21
The surface features will be resurveyed and incorporated into the existing base map.
Utilities will be located only in the intertie area.
Deliverables:
The CONSULTANT shall provide a complete revised base drawing where the old
features have been removed and the current features added.
TASK 21.8 UTILITIES
Task 21.8.1 Coordination with utilities
In the previous phases the CONSULTANT coordinated with the utility agencies /private
companies and for this work will continue to do so. The utility companies that the
CONSULTANT included time to coordinate with are as follows:
Olympic Pipe Line
Qwest
King County Metro
City of Tukwila Water Dept.
PSE (gas power)
Assumvtions:
The CONSULTANT shall continue to coordinate and meet with the private utility companies and
utility agencies listed above to let them know how their facilities will be impacted. This will
include sharing project design drawings and survey base map data and information.
The CONSULTANT shall share design drawings with the utility companies and agencies
as needed to assist the utility companies with their planning and design.
The design of the private utility relocation such as PSE and Qwest facilities will be done
by those companies. The CONSULTANT will review the private utility design and
provide comments to the private utility.
Interpretation of any franchise agreements, up- dating, modifying or negotiating
agreements will be done by the City.
If the existing utilities (water sanitary sewer) are shown on the survey and are located
in the right of way have to be relocated and the CONSULTANT has included design for
that relocation to be done in kind. The CONSULTANT has not included any time to
coordinate with any local businesses or private companies as far as up- grading existing
utilities.
The CONSULTANT has not included any time to coordinate with utilities that have been
installed within the last 2 years or since the May 2007 100% Shelf submittal other than
improvements to the utilities owned by the companies listed above such as PSE.
Deliverables:
c. \docume- 1\cyndy- 1.tuk\ locals -1\ temp\ xpgrpwise \exhibit_a_scope_of_work_supp_ v10.docx
Printed 03/09/2010
CINTB
Tukwila Urban Access Improvement Project Page 22
The CONSULTANT shall document meetings with utility companies.
Task 21.8.2 Utility Design
The CONSULTANT shall complete and update the utility design to reflect changes since the
project was shelved in 2007.
Assumptions:
For the new water system the CONSULTANT has coordinated with the City of Tukwila
Fire Dept. for the water system fire protection requirements. It is assumed that the design
is still valid and meets the Fire Dept. requirements.
The water system design as last submitted still meets the City requirements as far as
alignment and sizing. The CONSULTANT has not included time for any new alignments
and either up sizing or down sizing the system.
The previous survey limits did not include SPU and City of Tukwila facilities at the north
end of the project in the vicinity opposite Bahama Breeze Restaurant. This proposed
scope of work will include survey for those items so the new water connection in that
area will be coordinated with the existing facilities.
The CONSULTANT shall include coordination with the other proposed new utilities
such as storm drain and signals if those designs are revised.
The CONSULTANT shall include coordination with the new utilities and improvements
from the mall new construction and new businesses and improvements along Strander
Blvd. This work includes time to adjust the existing new water main alignment due to
new utilities serving the mall or businesses based upon as -built data from the
developers /property owners, as available.
Deliverables:
Submittal of revised 100% utility Plans, Specifications and Estimate.
Written to response to revised 100% submittal comments.
Ad -ready submittal of utility Plans, Specifications and Estimate
TASK 21.9 SPECIAL PROVISIONS
The CONSULTANT shall update and complete project Special Provisions and assemble the
contract provisions for reviews and advertisement based on changes in criteria resulting from the
project being shelved and changes resulting from WSDOT coordination. The CONSULTANT
shall review the WSDOT Local Agency and APWA General Special Provisions, GSP's and
update those that are applicable.
Assumptions:
c \docume 1\cyndy -1.tuk \locals -1\ temp \xpgrpwise\exhibit_a_scope_of work_ supp_9_v10.docx
Printed 03/09/2010
NNTB
125
126
Tukwila Urban Access Improvement Project Page 23
The development of Special Provisions specific to the proposed project elements that
supplement or revise Tukwila's Standard Specifications and General Special Provisions
are addressed in Tasks 2, 4, 5 6 and 8.
Deliverables:
Deliverables are addressed in Tasks 2, 4, 5, 6 and 8.
TASK 21.10 DEVELOPMENT OF QUANTITIES AND COST
ESTIMATE
The CONSULTANT shall update and complete the Engineer's Estimate of Probable Construction
Cost, with an itemized list in tabular form describing specification section, item, and quantity,
estimated unit costs and estimated total. This estimate will be based on the 100% PS&E shelf
copy estimate developed for the May 2007 submittal and the update of the cost estimate
developed for Supplement 8.
The costs shown in the estimate represent an estimate of probable costs prepared in good faith
with reasonable care. HNTB has no control over the costs of construction labor, materials or
equipment, nor over competitive bidding or negotiating methods and does not make any
commitment or assume any duty to assure that bids or negotiated prices will not vary from this
estimate.
Deliverables:
100% and Ad -ready submittals of Engineer's Estimate of Probable Construction Cost.
TASK 2t11 100% AND AD -READY CONTRACT PLAN
SHEETS
Consultant shall prepare ad -ready plans with supporting design calculations. Format for plans
will be ink or equivalent, on City of Tukwila title /border, 22 -inch x 34 -inch size sheets. The
scales to be used, the lettering and the general delineation of the plans will be such as will provide
legible reproduction at full. scale, or when reproduced at one quarter the original area (50 percent
reduction). The Consultant shall also provide electronic files of the ad -ready plans. This task
shall include the update of the following sheets as needed for the 100% and Ad ready submittals:
Title and vicinity
Index
Legend
General Notes
Deliverables:
100% and Ad -ready submittal of contract plan sheets.
TASK 21.12 CONSTRUCTION SCHEDULE
The CONSULTANT shall update the construction schedule prepared in Supplement 8.
c: \docume \cyndy- 1.luk\locals -1\ temp \xpgrpwise \exhibit_a_scope_of work_supp_9 v10.docx
Printed 03/09/2010
Tukwila Urban Access improvement Project Page 24
Assumptions:
It is assumed that construction will be completed in two construction seasons.
The Construction schedule will be consistent with the City's construction moratorium.
Deliverables:
Draft and Final Construction schedules using Microsoft Projects software.
TASK 21.13 ASSISTANCE DURING BID PERIOD
The CONSULTANT shall attend a pre -bid meeting for the project. Attendance at the Pre -Bid
Meeting shall include up to two (2) CONSULTANT attendees to present information and provide
clarification. No information provided at the Pre -Bid Meeting shall supersede the contract
documents. Bidder questions raised during the Pre -Bid Meeting will be documented.
Effort by the CONSULTANT under this task will be complete at the date of bid opening.
c: \docume -1 \cyndy -1.tuk \locals -1\ temp \xpgrpwise \exhibil_a_scope_of work_supp_9_v10 docx
Printed 03/09/2010
CINTB
127
128
Staff Classification Hours Rate Total Cost
Principal 12 $269.34 $3,232
Project Manager 274 $186.65 $51,141
Sr. Engineering Manager 16 $158.38 $2,534
Sr. Architectural Manager 32 $175.43 $5,614
Senior Project Engineer 666 $150.67 $100,348
Project Engineer 60 $137.12 $8,227
Design Engineer /Traffic Engineer 827 $90.87 $75,150
Landscape Architect 160 $92.97 $14,876
Sr. Technician 453 $96.48 $43,704
Project Administrator 68 $113.06 $7,688
Admin. Asst. /Clerical 14 $67.74 $948
REIMBURSEABLE COSTS
SUBCONSULTANT COSTS
r
1
Exhibit B -1
HNTB Corporation
Consultant Fee Determination
Summary Sheet (Lump Sum)
Tukwila Urban Center Access Project: Klickitat /Southcenter Parkway
Supplement No. 9 Final Design
LABOR COSTS
Total Hours 2582
TOTAL LABOR COSTS $313,4621
Local Travel (Mileage /Parking): $500
Reproduction: $2,500
Other: $250
TOTAL REIMBURSEABLE COSTS $3,250
HDR Engineering, Inc. $132,8491
PACE Engineers, Inc. $84,2541
TOTAL FEE $533,8161
HNTB Corporation
05 -071, Supplement No. 9
C: \DOCU ME-1 \CYN DY -1.TU K \LOCALS -1 \Temp\XPg rpwise\ Supp_9_Exhibits_B_ &_C_split_v10
Page 1 of 2
129
13
Exhibit B -4
Summary of Hours All Firms
Tukwila Urban Center Access Project: Klickitat /Southcenter Parkway
Supplement No. 9 Final Design
HNTB J HDR J
Hours I Hours I
21.11 Project Management 1• 242.::,
21.1.111ssues Resolution I 10 6 1
21.1.21Project Requirements 1 20 4
21.1.31Budget Performance 1 80 4
21.1.4lSchedule Conformance 1 24
21.1.5lCommunicate Progress 1 32 22
21.1.61Consultant Team 1 40 32
21.1.7 /Manage Quality I 20 6
21.1.81Manage Change 16 4
1
21.21Right of Way 1... ,168
21.2.11Legal Descriptions Easements I 24
21.2.21/Right of Way Plans 1 144
1
'21.31 Permitting L
1 21.3.11NPDES Stormwater Permit for DOE
1
r 21.41 Roadway 816. l :990
1
21.4.1 I Roadway Design i 12 684
21.4.2 /Signals and ITS I 164
21.4.31Site Preparation I 128
21.4.41111umination 1 116
21.4.51Traffic Control Plans 1 36
21.4,61Detour plans 1 136
21.4.71Signing 1 28 306
21.4.8lLandscape Design Architectural Treatments 196
1
21.51Drainage'. '1' :•936
21.5,1lStormwater Report 1 360
21.5.2lDrainage Plans Details 1 460
21.5.31TESC Plans Details 1 116
1
21.61Structures I 360
21.6.1 (Bridges Walls 1 360 360
1
1', 21:71Surveying" 1„ :I 4 143
21.7.11 Field Survey for Design 1 4 143 147
1
21,8IUtifities 8 418.`
21.8.1 (Coordination w/ Utilitiies 4 40
21.8.21 Utility Design 4 378
1
21.91Special Provisions l' -76 .'•;76,
21.9.11Special Provisions 76 76
1
21.101Quantities and Cost Estimate •44? t: 7.',44'
21.10.1 (Quantities Cost Estimate 44 44
I
_''.21.1,11100% and Ad Ready Contract Plan Sheets 28.
21.11.11100% Ad Ready Contract Plan Sheets 28
1
;`21492:ICon'st iction�Sched'" lei ;r.r sk:. s v., :�:F• f,. ty 1..,
2 t .28
1.12.11Construction Schedule
28 I 28
1 1 I
21.13lAssistance During Bid Period I 40 I 1 12: 52'
21.13.1 (Assistance During Bid Period 1 40 1 12 52
1
1 Total Hours by Firm l 2,582 1 1,080
HNTB Corporation
05 -071, Supplement No. 9
\DOCUME -1 \CYNDY 1 .TUK\ LOCALS 1\ Temp \XPgrpwise \Supp_9_Exhibits B C_split_v10
PACE TOTAL
Hours Hours
I 16
I 24
30 1 114
24
1 54
72
26
20
759
24
144
'1,806'
696
164
128
116
36
136
334
196
936'
360
460
116
':'360
147.
426
44
382
"28
28
4,421
Exhibit C -1
HNTB Corporation
Consultant Fee Determination
Summary Sheet (Lump Sum)
Tukwila Urban Center Access Project: Klickitat /Southcenter Parkway
*Excerpt of Supplement No. 9, Final Design:
Amount of Extra Work Due to WSDOT Required Project Changes
LABOR COSTS
Staff Classification Hours Rate Total Cost
Principal 6 $269.34 $1,616
Project Manager 109 $186.65 $20,382
Sr. Engineering Manager 11 $158.38 $1,742
Sr. Architectural Manager 16 $175.43 $2,807
Senior Project Engineer 299 $150.67 $45,111
Project Engineer 30 $137.12 $4,114
Design Engineer /Traffic Engineer 400 $90.87 $36,348
Landscape Architect 128 $92.97 $11,901
Sr. Technician 218 $96.48 $21,032
Project Administrator 34 $113.06 $3,844
Admin. Asst. /Clerical 7 $67.74 $474
r
REIMBURSEABLE COSTS
Total Hours 1259
TOTAL LABOR COSTS $149,3711
Local Travel (Mileage /Parking): $100
Reproduction: $1,000
Other: $250
TOTAL REIMBURSEABLE COSTS $1,350
SUBCONSULTANT COSTS
HDR Engineering, Inc. $84,982!
PACE Engineers, Inc. $7,2751
TOTAL FEE $242,978!
HNTB Corporation
05 -071, Supplement No. 9
C \DOCUME -1 \CYNDY-1.TUK \LOCALS -1 Temp\ XPgrpwise\ Supp_9_Exhibits_B_ &_C_split_v10
131
Exhibit C -3
Summary of Hours All Firms
Tukwila Urban Center Access Project: Klickitat /Southcenter Parkway
Supplement No. 9 Final Design
*Excerpt of Supplement No. 9, Final Design:
Amount of Extra Work Due to WSDOT Required Project Changes
21.1 I Project Management
21.1.11Issues Resolution
21.1.21Project Requirements
21.1.31 Budget Performance
21.1.41Schedule Conformance
21.1.51Communicate Progress
21.1.61Consultant Team
21.1.71Manage Quality
21.1.81Manage Change
21.2IRight of Way
21.2.1 1 Legal Descriptions Easements
21.2.21Right of Way Plans
21.31Permitting .1.
21.3.11NPDES Stormwater Permit for DOE
21.41 Roadway
2.1.4.11Roadway Design
21.4.21Signals and ITS
21.4.3ISite Preparation
21.4.4) Illumination
21.4.51Traffic Control Plans
21.4.61Detour plans
21.4.7ISigning
21.4.8ILandscape Design Architectural Treatments
21.51Drainage
21.5.11Stormwater Report
21.5.21 Drainage Plans Details
21.5.31TESC Plans Details
21.61Structures
21.6.11Bridges Walls
'21.71Survejring
21.7.1 IField Survey for Design
21.81 Utilities
21.8.1 (Coordination w/ Utilitiies
21.8.21Utility Design'
21.91Special Provision
HNTB HDR
WSDOT WSDOT
121: 39
5 3
10 2
40 2
12
16 11
20 16
10 3
8 2
390
6
82
64
58
18
17
146
180
230
58
205
205
38
1663'`
479
184
HNTB Corporation
05 -071, Supplement No. 9
\DOCU ME -1 \CYNDY- -1.TUK \LOCALS -1 Temp\ XPgrpwise\ Supp_9_Exhibits_B_ &_C_split_v10
13
PACE
WSDOT
72:
72
12
TOTAL
WSDOT
8
12
42
12
27
36
13
10
:72
72
'1;053
485
82
64
58
18
200
146
468;
180
230
58
205:
205
'12'
12
38
Exhibit C -3
Summary of Hours All Firms
Tukwila Urban Center Access Project: Klickitat /Southcenter Parkway
Supplement No. 9 Final Design
*Excerpt of Supplement No. 9, Final Design:
Amount of Extra Work Due to WSDOT Required Project Changes
21.9.1 !Special Provisions
21:101Quantities. arid Cost Estimate
21.10 .1 !Quantities Cost Estimate
21.111100% and Ad Ready Contract Plan Sheets
21.11.11100% Ad Ready Contract Plan Sheets
2.1,:= 12:(Coi structionSchedule
21.12.1 !Construction Schedule
21.13jAssistance During Bid Period.
21.13.1 !Assistance During Bid Period
Total Hours by Firm'
HNTB HDR
WSDOT WSDOT
38
22
22
14'
14
1,259
702
HNTB Corporation
05 -071, Supplement No. 9
C: \DOCUME- 1 \CYNDY -1.TUK \LOCALS -1 Temp\ XPgrpwise\ Supp_9_Exhibits_B_ &_C_split_v10
PACE
WSDOT
84
TOTAL
WSDOT
38
:22
22
14.
14
2,044
133
134
TRANSPORTATION COMMITTEE
Meeting Minutes
March 15, 2010 5:00 p.m. Conference Room 1
CALL TO ORDER: The meeting was called to order at 5:01 p.m.
I. PRESENTATIONS
No presentations.
City of Tukwila
Transportation Committee
PRESENT
Councilmembers: Verna Seal, Chair; Joan Hernandez and De'Sean Quinn
Staff: Bob Giberson, Frank Iriarte, Robin Tischmak, Cyndy Knighton, Mike Ronda, Peter Lau,
Gail Labanara, and Steve Lancaster
11. BUSINESS AGENDA
A. Tukwila International Blvd Phases II III Construction Mamt Supplement #8 with KPG
Staff is seeking full Council approval for Supplement No. 8 with KPG, Inc. in the amount $181,903.40.
This supplement is for additional construction management by KPG and their sub consultants as the other
construction management firm, Harris and Associates, are not fulfilling their contract. This grant- funded
supplement will be covered by the anticipated savings from the under utilized Harris contract. The
supplement also covers adding a pedestrian access stairwell at the 37 Ave S road closure. UNANIMOUS
APPROVAL. FORWARD TO MARCH 22 COW FOR DISCUSSION.
B. Resolution Setting Street Vacation Public Hearing Date for 14403 51 Ave S
Staff is seeking full Council approval to set a Public Hearing date for the proposed street vacation at 14403
51" Ave S for April 26, 2010. A previous street vacation request was submitted in 2002, but a change in
ownership caused it to be dropped. The process for street vacations includes a resolution to set a Public
Hearing date, advertise and hold the Public Hearing, and then return to Committee and Council with the
ordinance that defines the street vacation's conditions and compensation ($27,000.00). UNANIMOUS
APPROVAL. FORWARD TO MARCH 22 COW FOR DISCUSSION.
C. Transportation Element Update to the Comprehensive Plan. Supplement No.1 with Fehr Peers
Staff is seeking full Council approval for Supplement No. 1 for Optional Task A with Fehr Peers. The
original contract was approved February 1, 2010 (see 1/19/10 TC minutes) and the EETP grant was
approved March 15, 2010 (see 3/1/10 TC minutes). The Fehr Peers supplement for $55,000.00 and
$14,500.00 of City staff time will be covered by the $69,500.00 EETP grant. The supplement will add
pedestrian and bike level of service analysis for arterial streets in the City as well as establish a multi -modal
transportation system. UNANIMOUS APPROVAL. FORWARD TO MARCH 22 COW FOR
DISCUSSION.
11 Tukwila Urban Center Access (Klickitatl. Supplement No. 9 with HNTB
Staff is seeking full Council approval for Supplement No. 9 with HNTB in the amount of $553,816.00. This
supplement will cover the design changes required by WSDOT. Staff is currently pursuing Letters of
Understanding with WSDOT for the final design, which may reduce the scope of work in this supplement.
The project schedule now shows a two -year construction timeline. There is $400,000 budgeted for
additional design, so remaining funds would come from the LID. Due to time constraints and WSDOT
negotiations, staff requests discussion and approval at the 3/22 C.O.W. and the Special meeting that same
night. UNANIMOUS APPROVAL. FORWARD TO MARCH 22 COW AND SPECIAL THAT SAME
NIGHT FOR DISCUSSION AND APPROVAL.
135