HomeMy WebLinkAboutTrans 2014-02-10 Item 2B - Change Orders #1-2 - Tukwila Urban Center Transit Center / Andover Park West Widening with Puget Sound EnergyTO:
FROM:
BY: Cyndy Knighton, Senior Program Manager
DATE: February 7, 2014
SUBJECT: Tukwila Urban Center — Transit Center and Andover Park West Widening
Puget Sound Energy — Facility Relocation Agreement, Contract No. 13 -121
Change Order Nos. 1 & 2
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
Mayor Haggerton
Transportation Committee
Bob Giberson, Public Works Directo L.
ISSUE
Approve two change orders to the Utility Relocation Agreement between the City of Tukwila and Puget Sound Energy
(PSE).
BACKGROUND
In July of 2013 a Facility Relocation Agreement was executed between PSE and the City. This agreement defined the
roles and financial responsibilities for relocation of two underground vaults and two above ground switches in
association with the TUC Transit Center and Andover Park W Widening Projects. The two switches are on the
Westfield Southcenter Mall property and are therefore the financial responsibility of the City. The two underground
vaults straddled the right -of -way line along the Mall frontage and therefore the relocation costs to move them out from
the right -of -way are shared between Tukwila and PSE.
A cost estimate was included for the relocation work and the Facility Relocation Agreement capped Tukwila costs at
$738,400.00 (which included a 10% contingency), absent a mutually agreed upon change order or amendment.
DISCUSSION
PSE has completed relocating the northern vault along Andover Park W, referred to as V10, and the two above ground
switches. The relocation costs have exceeded the original cost estimate partially due to excessive dewatering of the
vaults, extensive traffic control, changes in field conditions, and additional property restoration. The additional property
restoration was a result of PSE construction occurring prior to the City's construction project, The PSE estimate
assumed that the utility relocation work would occur in conjunction with the City's project and that PSE's restoration
costs would be minimal. Relocation of the southern vault, known as V12, will be completed after the City's contractor,
Road Construction Northwest, removes the Firestone canopy structure.
FINANCIAL IMPACT
The total amount for Change Order No. 1 is $54,215.09, of which Tukwila is responsible for 71 % or $38,492.71
Change Order No. 2 is $37,422.09 and the City is responsible for 100 %. The total of the two change orders is
$91,637.18 and Tukwila's portion of the costs is $75,914.80. The change orders are currently within the total project
budget of $738,400, but the final PSE relocation costs for the second vault are not known at this time. There is a
potential overrun of the utility relocation budget of $55,733, if the cost estimate for the V12 work is accurate. Any cost
overruns exceeding the City's responsibility of $738,400 will be paid from the Project's construction contingency.
RECOMMENDATION
Council is being asked to approve Change Order Nos. 1 and 2 in the amount of $75,914.80 to Contract No. 13 -121
with PSE for the TUC Transit Center Utility Relocation and consider this item on the Consent Agenda at the February
18, 2014 Regular Meeting.
Attachments: Summary Table
Change Order Nos. 1 and 2
W:\PW EngIPROJECTSW- RW & RS Projects\Transit Center (90610402)1Constructionl #.200 - Correspondence1005 - Utility & Interlocal CoordinationlINFO MEMO PSE Ag CO #1 RRT gl 02- 07- 14.docx
15
PSE Electrical Vault Relocation Costs
Change Order Summary
Item
V10
V12
SWITCHES
Total
Actual
Estimate (Incl. CO #1)
Estimate Actual
Actual
Estimate (Incl. CO #2)
Estimate Actual
Materials
Construction
Engineering &Management
Right of Way
Overhead (18 %)
$55,163.57 $60,680.00
$177,065.77 $213,451.00
$19,673.97', $23,717.00
$0.00', $0.00
$45,342.601 $53,613.00
$63,345.56
$131,578.05',
$14,619.78
$0.00',
$37,717.81
$100,435.20'', $60,680.00
$107,846.22', $172,168.00
$11,982.91 $19,130.00
$0.00, $0.00
$39,647.58 $45,356.00
$218,944.33 $121,360.00
$416,490.04 $385,619.00
$46,276.66 $42,847.00
$0.00'', $0.00
$122,707.99', $98,969.00
Utility Relocation Total (Tukwila
PSE Costs)
$297,245.91 $351,461.00
$247,261.20 n/a
$259,911.91 $297,334.00
$804,419.02; $648,795.00
Tukwila Costs
Tukwila @ 71%
Tukwila @ 81%
Tukwila @ 100%
Budgeted $738,400.00
Tukwila Total Amount
$211,044.60 $249,537.31
$200,281.57 n/a
$259,911.91 $297,334.00
$671,238.08 $546,871.31
Tukwila Change Order Amount
$38,492.71
$37,422.09
$75,914.80
Remaining Budget
$191,528.69
Potential Overrun @ Completion
$55,732.51
PUGET SOUND ENERGY
CHANGE ORDER V10
To: City of Tukwila Date: 11/18/2013
Project Number: 101080841
Attn: Cyndy Knighton Project Manager: GRENNER
Project: TUKWILA - Andover Park W P.I
Description of work:
This change order is for the costs in excess of the original estimate provided in "Exhibit C" of the
relocation agreement between the City of Tukwila and Puget Sound Energy. The excess costs
associated with this portion of the relocation work were, but not limited to, 1)Dewatering of vaults.
2)Traffic control and pedestrian safety. 3)Wire crew performing night time cutover for commercial
customers and rerouting unknown service cables out of existing vault V10 that were undocumented
and unreferenced on the original estimate.
Item
Amount Comments
Estimate
Materials $ 55,164
Construction $ 177,066
Engineering & Management $ 19,674
Right of Way $ -
Overhead $ 45,343
Estimate Total $ 297,246
Actual
Materials $ 60,680
Construction $ 213,451
Engineering & Management $ 23,717
Right of Way $ -
Overhead $ 53,613
Actual Total $ 351,460
Change Order Total $ 54,214
Allocation of Change Order Total
Company 29% $ 15,722
Govemment Entity 71% $ 38,492
Change Order Total
Note: This change order will be effective only when signed by both parties:
Puget Sound Energy City of Tukwila
Signed: Signed:
Title: Title:
Date: Date:
(Please sign and return one copy)
3591 7 -04 Puget Sound Energy PO Box 90868 Bellevue, WA 98009 -0868
$ 54,214
PUGET SOUND ENERGY
a subsidiary of PUGET ENERGY
17
PUGET SOUND ENERGY
CHANGE ORDER SWITCHES
To: City of Tukwila Date: 11/18/2013
Project Number: 101080841
Attn: Cyndy Knighton Project Manager: GRENNER
Project: TUKWILA - Andover Park W P.I
Description of work:
This change order is for the costs in excess of the original estimate provided in "Exhibit C" of the
relocation agreement between the City of Tukwila and Puget Sound Energy. The bulk of the "excess
costs" associated with this portion of the relocation work were, but not limited to 1)Dewatering of
vaults. 2)Traffic control and additional pedestrian safety implemented near the bus transit center.
3)Additional shoring, due to the unstable nature of the soil. 4)Additional resoration that was mutually
agreed to by the City and Westfield property management.
Item
Amount Comments
Estimate
Materials $ 100,435
Construction $ 107,846
Engineering & Management $ 11,983
Right of Way $ -
Overhead $ 39,648
Estimate Total $ 259,912
Actual
Materials $ 60,680
Construction $ 172,168
Engineering & Management $ 19,130
Right of Way $ -
Overhead $ 45,356
Actual Total $ 297,334
Change Order Total $ 37,422
Allocation of Change Order Total
Company 0% $
Government Entity 100% $ 37,422
Change Order Total
$ 37,422
Note: This change order will be effective only when signed by both parties:
Puget Sound Energy City of Tukwila
Signed: Signed:
Title: Title:
Date: Date:
(Please sign and return one copy)