HomeMy WebLinkAboutPark 2013-09-18 Item 4A - Project UpdatePARKS COMMISSION
PROJECT UPDATE
CURRENT PROJECTS
1
Tukwila Pool Capital Project
2
3
4
5
This project was officially closed out by the MPD Board last month. There are still some warrentee items being worked
through. The pool was closed from Sept. 1 through Sept. 8 for the Labor Day Holiday and warranty work. The scope of
work focused on replacing the pool re- circulation pump with a smaller motor and larger sized impeller to maintain the
required flow rates and prevent cavitation from continuing to happen. The showers and flooring also had work done
on them, some by staff and some by the contractor.
Target Completion Date: Project Closeout will be Summer 2013
Project Stage: Closeout
Project Budget: $1.7M
Restroom Counters Replacement at the Clubhouse
Looking at doing this Fall 2013 when the patronage slows down.
Target Completion Date: Fall 2013
Project Stage: Researching Products
Project Budget: $10,000
[Front Fountain Lighting Retrofit at the Clubhouse
Received quote and investigating options for this in conjunction with the CIP Budget.
Target Completion Date: Fall 2013
Project Stage: Research and Planning
Project Budget: $2,000 - $5,000
iDuwamish Hill Preserve (DHP)
Coordination continues with this project. Past Forward consulting was hired again to assist with grant writing,
education develepment and tribal relations. A second kiosk development meeting is scheduled for Oct. 1 with Miller
Hull, SvR Design, Forterra, City Staff, and Friends of the Hill. Phase 2 conceptual planning and preliminary work studies
is under way.
Target Completion Date: On -going
Project Stage: Testing for Phase 2 /Restoration /Maintenance
Project Budget: Multiple grants for this project
Disc Golf Course
No new info to report this month.
Target Completion Date: Unknown
Project Stage: Public Input Gathering
Project Budget: N/A right now
5
6
TUKWILA
PARKS & RECREATION
GOOD HEALTHY FUN
PARKS COMMISSION
PROJECT UPDATE
7
'Ft Dent Parking Lot Repair Work
This project will be coordinated with the Public Works Overlay Project in 2014 to attain better pricing. Staff are
working together between departments to foster this. The funding looks to be available to complete more work then
origianlly planned.
Target Completion Date: 2014
Project Stage: Scope Planning /Design
Project Budget: $TBD
Ft Dent Pedestrian Pathway Bridge Repair
No new update.
Target Completion Date: 2013
Project Stage: Design
Project Budget: $30,000