Loading...
HomeMy WebLinkAboutPark 2012-11-20 Item 5A - Project UpdatePARKS COMMISSION PROJECT UPDATE November 2012 Tukwila Pool Capital Project McKinstry, the MPD's Energy Savings Company (ESCO), has begun work on the Energy Savings Performance Contracting (ESPC) Capital Project at the Tukwila Pool. The pool closed on Monday, November 5, 2012 for the work and will remain closed for three months to complete the work. We are estimating to re -open on Monday, February 4, 2013. Target Completion Date: Early February 2013 Project Stage: Construction Project Budget: $1.66M Pool Exterior Access Improvements In conjunction with the above mentioned project, new walkways and improved parking will provide better access to the facility from the parking lot to aid the disabled and elderly patrons. Bids for this project will be received on November 16th and then forwarded through the City Council process for Bid Award. Construction should begin in December 2012 and end by the end of January 2013. Target Completion Date: Weather Dependent (hoping for Fall 2012, but could be Spring 2013). Project Stage: Design Tukwila Pool Re -Roof In conjunction with the two above mentioned projects Re -roof the pool with a new solid membrane roofing product that will adhere right over the top of the existing tourch down roof. A thermal scan will be conducted checking for any leaks, none anticipated at this time. Bids for this project will be received on November 16th and then forwarded through the City Council process for Bid Award. Construction should begin spring 2013 and be completed by May 15, 2013. Target Completion Date: Weather Dependent (hoping for Fall 2012, but could be Spring 2013). Project Stage: Design Project Budget: $85,000 4 IRestroom Counters Replacement at Foster Golf Lin Replace existing (water damaged and failing) restroom counters with new solid surface product that cannot be water damaged. New fixtures will be included depending upon budget. May purchase this year and install next year due to the budget status. Target Completion Date: End of year 2012 Project Stage: Researching Products Project Budget: $10,000 5 JEnergy Efficiency Improvements at Foster A preliminary Energy Audit has been completed at the Clubouse listing potential areas that energy efficiencies can be obtained. We are working with an ESCO on this and will be applying for grant funding for this project through the Department of Commerce (same as the pool, different ESCO). If we move forward with this project it would mostly focus on occupancy sensors, lighting fixture replacements and a couple other similar things all electrical related in gs potential. Target Completion Date: June 2013 Project Stage: Preliminary Investigation of Feasibility Project Budget: Unknown but will be grant funded F,oJe t update 11-20 -12x1sv G KWILA 1 IAA I ,ATION PARKS COMMISSION PROJECT UPDATE November 2012 Tukwila Pool Capital Project McKinstry, the MPD's Energy Savings Company (ESCO), has begun work on the Energy Savings Performance Contracting (ESPC) Capital Project at the Tukwila Pool. The pool closed on Monday, November 5, 2012 for the work and will remain closed for three months to complete the work. We are estimating to re -open on Monday, February 4, 2013. Target Completion Date: Early February 2013 Project Stage: Construction Project Budget: $1.66M Pool Exterior Access Improvements In conjunction with the above mentioned project, new walkways and improved parking will provide better access to the facility from the parking lot to aid the disabled and elderly patrons. Bids for this project will be received on November 16th and then forwarded through the City Council process for Bid Award. Construction should begin in December 2012 and end by the end of January 2013. Target Completion Date: Weather Dependent (hoping for Fall 2012, but could be Spring 2013). Project Stage: Design Tukwila Pool Re -Roof In conjunction with the two above mentioned projects Re -roof the pool with a new solid membrane roofing product that will adhere right over the top of the existing tourch down roof. A thermal scan will be conducted checking for any leaks, none anticipated at this time. Bids for this project will be received on November 16th and then forwarded through the City Council process for Bid Award. Construction should begin spring 2013 and be completed by May 15, 2013. Target Completion Date: Weather Dependent (hoping for Fall 2012, but could be Spring 2013). Project Stage: Design Project Budget: $85,000 4 IRestroom Counters Replacement at Foster Golf Lin Replace existing (water damaged and failing) restroom counters with new solid surface product that cannot be water damaged. New fixtures will be included depending upon budget. May purchase this year and install next year due to the budget status. Target Completion Date: End of year 2012 Project Stage: Researching Products Project Budget: $10,000 5 JEnergy Efficiency Improvements at Foster A preliminary Energy Audit has been completed at the Clubouse listing potential areas that energy efficiencies can be obtained. We are working with an ESCO on this and will be applying for grant funding for this project through the Department of Commerce (same as the pool, different ESCO). If we move forward with this project it would mostly focus on occupancy sensors, lighting fixture replacements and a couple other similar things all electrical related in gs potential. Target Completion Date: June 2013 Project Stage: Preliminary Investigation of Feasibility Project Budget: Unknown but will be grant funded F,oJe t update 11-20 -12x1sv G to t4 PARKS RECREATION PARKS COMMISSION PROJECT UPDATE November 2012 Front Fountain Lighting Retrofit at Foster Golf Links This will hopefully be included in the above project but if not then it will be conducted by staff. The Scope includes renovating the existing ten light fixtures around the fountain in the parking lot to three more efficient fixtures that will provide safe lighting, less energy use, and less maintenance costs in both labor and supplies. Target Completion Date: June 2013 Project Stage: Design Project Budget: $2,000 $5,000 Duwamish Hill Preserve (DHP) This project /preserve entails it all, maintenance, restoration, testing, design, development, partnerships, volunteers, planning. DHP is currently in a mode of maintenanc of existing site improvements (Phase 1 construction and on- going restoration) and planning for Phase 2. Phase 2 is in the process of conducting tests to guide design of the site. Staff is meeting with Seattle City Light (SCL) next week to discuss the possiblity of them using DHP for some of their off -site mitigation (great benefit and fits right in for Phase 2). Once testing is completed then design will start and eventually construction projected for 2014 most likely. We've been working with EarthCorps to aid in the restoration and maintenance of the site too. $15,000 grant presentation to 4Culture for archaeological survey November 16, 2012 Target Completion Date: On -going Project Stage: Testing for Phase 2 /Restoration /Maintenance Project Budget: Unknown but lots grants for this project 8 9 Ft Dent Parking Lot Repair Work parking lot is in need of re- striping, some curb repair work, and an area of ashpalt patch repair by a storm drain. s is kind of a on -going maintenance project with the heavy use at this site. Target Completion Date: Fall 2012 Spring 2013 (weather dependent) Project Stage: Scope Planning /Design Project Budget: $15,000 $20,000 together to get this done as one project to save funds. Target Completion Date: Fall 2012 Spring 2013 (weather dependent) Project Stage: Design Project Budget: $30,000 Pedestrian Pathway Bridge Repair Ft Dent P &R staff are working with PW to make necessary concrete and asphalt repairs to the bridge over the river into Ft Dent Park. The pedestrian pathway needs attention and so does the roadway part so the depertments are working N.Je UPUa .1120 12A. G