HomeMy WebLinkAboutCAP 2007-03-27 Item 2D - Agreement - Tukwila Pond Park Design with Robert W DrollTO:
MEMORANDUM
Mayor Steve Mullet
Community Affairs and Parks Committee
FROM: (4 Rick Still, Deputy Director of Parks and Recreation
DATE: March 21, 2007
SUBJECT: Tukwila Pond Park Authorize Consultant Agreement
Project Number 03 -PK -10 TUKPOND2007
Parks and Recreation Department
Bruce Fletcher, Director
ISSUE
Select a consultant to provide design services and for the Tukwila Pond Park development.
BACKGROUND
The Tukwila Urban Center Master Plan includes further development of the Tukwila Pond
Park. An informational report and conceptual design were completed and presented to the
City Council in 2006. Concurrently, there are two different design issues being performed for
the Tukwila Pond Park Project. A water quality feasibility study is being conducted by the
Department of Community Development. The Parks and Recreation Department is utilizing
the 2006 conceptual design to develop schematic designs and final plans and specifications
for the development of this park.
The attached proposal, dated March 16, 2007, is presented in two phases. The first phase
(written in black) is the scope of work for which we are seeking approval. Phase one will
provide wetland delineation, boundary and design survey, concept plan and cost estimate,
and enough detail drawings to obtain the required permits. The second phase (written in
gray) scope of work is for consultant services that need to be performed once funding is
acquired for development.
ACTION TAKEN
Three firms were short- listed from the City's consultant roster of firms that indicated they
provide expertise in landscape architecture, park design, wetland issues, boardwalk and trail
construction, wildlife enhancements and interpretive presentations, and are familiar with
public projects, funding and grant programs. All three firms were rated based on the
expertise and experience necessary to perform the work. Robert W. Droll, Landscape
Architect, P.S. was selected as the most qualified (see rating sheet attached).
A draft scope of Work and Fee Estimate are attached.
RECOMMENDATION
Approve the selection of Robert W. Droll, Landscape Architect, P.S., as the Tukwila Pond
Park development design consultant and authorize the Mayor to execute a contract with
Robert W. Droll, Landscape Architect, P.S. in the amount of $90,820.00.
Attachments: Map, Rating Sheet, Consultant Agreement, Scope of Work, Fee Estimate.
cc: City Administrator
Director of Parks Recreation
Tukwila Pond Park 300ft
Site Location Map
Landscape Architecture
Park Design
Wetland Issues
Boardwalk Trail Design
Public Projects, Funding
Grant Programs
Public Involvement
Public Presentations
TOTALS
CONSULTANT SELECTION
2007 TUKWILA POND PARK DEVELOPMENT PROJECT
Wildlife Enhancements
Interpretive Presentations
Score consultant 1 to 4, with 1 being highest and 4 being lowest.
Lowest score is consultant ranked highest.
Hough Beck Adolfson Robert W. Droll
Baird Inc. Associates, INC. Landscape Architect
1 1
2 2
2 3
3 2
2 3
2 2
12 13
Attachment A
Tukwila Pond Trail Tukwila Parks Recreation
Scope of Services
3/16/2007
Tukwila Pond Trail Boardwalk
City of Tukwila Parks and Recreation Department
Scope of Work
This assignment includes the Schematic and Final Design services work to be performed by Robert W.
Droll, Landscape Architect, PS and Project Team (hereinafter collectively, RWD) for the City of
Tukwila, Washington on Tukwila Pond Trail Boardwalk. RWD will serve as consultant to Tukwila in
the capacity of Park Planner/Landscape Architect and will prepare Bid Documents. The goal of the
project is to implement a new Loop Trail and Boardwalk around Tukwila Pond.
Basis of Proposal
This Scope of Services and Fee Proposal are based upon discussions and information provided by the
Tukwila Parks and Recreation Department, site visits and documentation review.
Scope of Services
RWD proposes the following Scope of Services to accomplish the work necessary for the preparation of
Tukwila Pond Trail Boardwalk (hereinafter the "Trail
Phase 1
I Task 1 Schematic Design -35% Submittal
Task 1.01 Site Visit
RWD will visit site with Client, wetland biologists and survey crew.
Task 1.02 Wetland Delineation
Conduct wetland delineation, category rating and report in compliance with City of Tukwila Critical
Areas Ordinance.
Task 1.03 Boundary and Design Survey
Conduct topographical fieldwork necessary to generate mapping of one foot contours, spot elevations,
trees, six inches and larger, and other planimetric features. Survey will include bathymetric survey of
pond from shoreline to fifty feet into pond. Show Boundary Survey as provided by Tukwila. Prepare
mapping in ACAD format.
Task 1.04 Concept Plan Cost Estimate
RWD will prepare Concept Plan illustrating type, size and location of main loop trail and boardwalk
and spur connections. RWD will provide Estimate of Probable Cost based upon measured quantities.
Task 1.05 PreSubmission Conference w/ Tukwila
RWD will prepare PreSubmission Conference application and attend PreSub Conference.
Robert W. Droll, Landscape Architect, PS, 4405 7" Avenue, Lacey, WA, SE, 98503, 360.456.3813, bob@rwdroll.com 1
Attachment A
Tukwila Pond Trail Tukwila Parks Recreation
I Task 2 Permit Processing
Tasks 2.01 Layout and Grading Plan
Layout and Grading Plan will be prepared by RWD defining horizontal and vertical relationships of
proposed Trail and Site improvements. Horizontal definition of proposed improvements will be
achieved by dimensioning from coordinates derived from Design Survey. Grading will be defined by
contours and spot elevations that will be relative to vertical datum.
Task 2.02 Boardwalk Plan Details
Boardwalk Plan will define the horizontal and vertical alignment of Boardwalk, which anticipated to
be located over the water in locations where there is insufficient public property to locate the trail in
an upland area. RWD will provide all details and calculations to comply local codes, ADA
regulations and International Building Code.
Task 2.03 SEPA JARPA Permitting, Biological Assessment
RWD will prepare SEPA and Site Plan Approval and JARPA applications and respond to inquiries
and follow up on permits. RWD will prepare Biological Assessment.
Task 2.04 Illustrative Plan
Prepare one each color illustrative site plan, floor plan and two elevations for Client's use in public
meetings. Color will be applied to In- Process drawings (3 sheets maximum): no separate
drawings /sketches will be prepared specifically for Illustrative drawings.
Task 2.05 Public Presentation of Tukwila Pond Trail
RWD will prepare for and attend a public presentation of project.
Task 4,02 Demolition and Temporary Erosion Sedimentation Control Plan
RWD will prepare plan indicatine. the existin site features that shall be demolished, abandoned
salvaged and retained as well as ti e location of erosion control measures.
3/16/2007
I Task 3 Project Management
Task 3.01 Project Management
Manage the contractual elements, scheduling, billing and timing of project. Manage the coordination
of consultants and the execution of the Project Schedule. Communicate and coordinate with Client.
Phase 2
I Task 4 Design Development -60% Submittal
Task 4.01 Title Sheet
Title Sheet with 1 t t it Map, General ti tes. Legen. Abbreviations, i_
Ci:(ia1•L li Shee ;�L'�liti?3L•:YtCli "'t 1. t ;t, list City
Council Members and Parks Department Staff.
Tasks 4.03 Layout and Grading Plan
3 and will prepared t i horizontal ai.d �;radinti Plan .i";ll be 1.tei�a:• =�:d 1",,, RWD n;�riraittal and vertical relationships of
proposed Trail and Site improvements. horizontal definition of proposed improvements will be
proposed
by dimensioning from coordinates derived from Design Survey. Grading will be defined hss
contours and spot elevations that will he relative to vertical datum.
Robert W. Droll, Landscape Architect, PS, 4405 7` Avenue, Lacey, WA, SE, 98503, 360.456.3813, bob@nvdroll.com 2
Attachment A
Tukwila Pond Trail Tukwila Parks Recreation
Task 4.04 Boardwalk Plan Details
Boardwalk Plan will define, the horizontal and vertical alianment of Boardwalk. which anticipated /c
be located over the water in locations where there is insufficient public p1 operty to locite the trail in
an upland area. RWD will provide all details and calculations to comply local codes_ ADA
regulations and International Building Code.
Task 4.05 Site Details
Prepare details for project oiic improvements.
Tasks 4.06 Estimate of Probable Costs
RWD will provide Estimate of Probable Cost based upon measured cuantities. RWD will organize
Estimate by Trail Segment vu allow Client to render Phasing decisions i[necessary. Estimate will
include all Project Development Costs including consultant costs, construction administration,
mobilization, bonds. contingencies, taws, projected construction year cost escalation (if neeessar
taxes and all identified costs associated with this proiect's development.
Task 4.07 Review with Stu[[
Review Plans with Staff.
Task 5 Final Design 90% Submittal
Tasks 5.01-5.06 are the same Tasks as 4.01-4.06 except Work will he at a 90% eomp(odonhr6.
Task 5.07 Specifications
Prepare Technical Specifications, Sections 1-16. in Construction Specification institute tCSI) fc,
Task 5.08 Review with Staff
Review Plans with Staff.
Task 5.09 Building Permit Application Processing
FOND will submit and process Building Pennit applications.
Task 5.10 Quality Review
K\YD will retain a Construction Manager to review a set of hjd documents.
3/16/2007
Task 6 Con/rurtDwxumrom— lUO% Submittal
Tasks 6.0/-6.07 arc the same Tasks ox5.0i'5,07 except Work v ill howtu 1OU% completion level
and ready for Advertising and Bidding.
Task 6.08 Assemble Deliver Contract Documents
RWD will assemble Technical Specifications and Plans in .pdf format and forward to Client.
Robert m Droll, Landscape Architect, PS, 7 Avenue, Lacey, WA, SE, n�360.456.3mx.bobr&rwdroll.com 3
Attachment A
Tukwila Pond Trail Tukwila Parks Recreation
Task 7 Project Management
Task 5.01 Project Management
j x the coordination
the contractual elements, scheduling. scheduling. L�ill;� and f11 ?l�s of project. '��c the t: C >ittf::..:;';7
of consultants and the execution of the Project Schedule. Communicate and coordinate with Client.
I Task 8 Bidding Negotiations,
Task 10.01 Pre -Bid Conference
RIND will attend Pre -Bid Conference and prepare Addenda. it necessary..
I Task 9 Construction Administration
t g will ti. t 1 time following Tasks i:l 1?c tleg ti�t.;_ at t ?a ti i2e a: 3idi,'slc, if requested by Client.
Task 9.01
Task 9.02
Task 9.03
Pre Construction Conference
Submittal Review
Construction Observation
3/16/2007
Additional Services, Excluded Services
Specific items that are not within the scope of work/services include, but are not limited to, the following:
Traffic studies
Stormwater Drainage studies /design
Demand analysis /economic modeling
Legal Descriptions of easements, Rights -of -Ways, etc.
Hydrology /Water Quality Studies, Environmental Studies
Geotechnical Investigation, Recommendations, and Material Testing.
Construction Staking
Mitigation Design
Permit Fees
Wildlife and Archaeological investigations
Web -site preparation and hosting, visual impact analysis, photo simulations, perspective character
sketches
Tree valuation, noise studies, air quality studies
Boundary Survey
Public Presentations, Neighborhood meetings, Hearing Examiner meetings, etc. other than in those
identified in scope.
Professional Fee
Professional Fees to accomplish the Scope of Services as shown in Attachment B. RWD will perform the
Scope of Services on a Time Materials, Not Exceed Basis. Direct Expenses are reimbursable.
Client's Responsibilities
Client shall provide the following information or services as required for performance of the work. RWD
assumes no responsibility for the accuracy of such information or services and shall not be liable for
errors and omissions therein. Should RWD be required to provide services in obtaining or coordinating
compilation of this information, such services shall be charged as Additional Services.
Robert W. Droll, Landscape Architect, PS, 4405 7 Avenue, Lacey, WA, SE, 98503, 360.456.3813, bob rixdroll.com 4
Attachment A
Tukwila Pond Trail Tukwila Parks Recreation
Provide Title Report
Provide space for Public Meeting
Provide Division 00 and City Bidding information
Advertise for Bid, Award, Bid Tabulation, etc.
Existing as-built site engineering and utility base information.
Provide aerial photos.
3/16/2007
Robert W. Droll, Landscape Architect, PS, 4405 7 Avenue, Lacey, WA, SE, 98503, 360.456.3813, bob'rr�rwdroll.com 5
3 -16 -07
Tukwila Pond Interpretive Trail
City of Tukwila, WA
Project Scope of Work Fee
Tasks
Phase 1
1.00 Schematic Design 35% Submittal
1.01 Site Visit 1,600.00 8 920.00 8 680.00
1.02 Wetland Delineation 6,800.00 4 460.00 4 340.00 6,000.00
1.03 Boundary and Design Survey 30,260.00 8 920.00 4 340.00
1.04 Concept Plan Cost Estimate 9,740.00 16 1,840.00 40 3,400.00
1.05 PreSubmission Conference w/ Tukwila 970.00 4 460.00 6 510.00
Task Total 49,370.00
2.00 Permit Submittal Processing 55%
2.01 Layout/Grading Plans 2,276.66
,270.00 2 230.00 24 2,040.00
2.02 Boardwalk Plan and Details 5,090.00 2 230.00 16 1,360.00
SEPA and JARPA Permitting /Processing,
2.03 Biological Assessment 21,680.00 40 4,600.00 48 4,080.00
2.04 Illustrative Plan 920.00 8 920.00
Tasks Subtotal
Direct Expenses (plots, phone, reproduction,
mail, travel)
Subconsultant Administration
1 Professional Services Fee Total
Total
Attachment B
83,720.00 11,500.00
1,500.00
5,600.00
90,820.00I
Wetland biological
RWD Delineation Assessment Survey Electrical Structural
ine
Bob Droll /Project The Coot Watershed Larson MC
Manager Land. Tech Ill Clerical Company Company Associates BCE Squared
hours: total :hours total hours: total total total total total i total
2.05 Public Presentation of Tukwila Pond Trail 920.00 8 920.00
as tal o 30,880.00
3.00 Meetings Project Coordination
Project Management via phone, tax, email
3.01 etc 3,470.00 24 2,760.00 2 170.00 12 540.00
a'� sks Total 3,470.00
13,000.00
29,000.00
3,000.00 1,500.00
3,500.00
12,750.00 540.00 6,000.00 13,000.00 29,000.00 3,000.00 5,000.00
Robert W. Droll, Landscape Architect, PS 360.456.3813
3 -16 -07
Tukwila Pond Interpretive Trail
City of Tukwila, WA
Project Scope of Work Fee
Tasks Total
Phase 2
_4.00 Design Development 160 Submittal
4.01 Title Sheet
4.02 Demolition TESC Plan
4.03 Layout/Grading Plans
4.04 B an
oardwalk Plan d Details
4.05 Site Details
4.06 Estimate of Probable Costs
4.07 Review with Staff
Task Total
5.00 Final Design 90% Submittal
5.01 Title Sheet
5.02 Demolition TESC Plan
5.03 Layout/Grading Plan
5.04 Boardwalk Plan and Details
5.05 Site Details
5.06 Estimate of Probable Costs
5.07 Specifications Division 1 -16
5.08 Review with Staff
5.09 Building Permit Application /Processing
5.10 Quality Review
Task Total
6.00 Bid Documents -100% Submittal
6.01 Title Sheet
6.02 Demolition TESC Plan
6.03 Layout/Grading Plan
6.04 Boardwalk Plan and Details
6.05 Site Details
6.06 Estimate of Probable Costs
6.07 Specifications Division 1 -16
6.08 Assemble Deliver Contract Documents
Task Total
7.00 Meetings I Project Coordination
7.01 Project Management via phone, fax, email, etc
Task Total
8.00 Bidding, Negotiations
Task Total
9.00 Construction Services
9.01 Pre Construction Conference
9.02 Construction Observation
9.03 Punchlist and Final Walk -Thru
Task Total
Phase 2
Not in this Scope
of Work
Tasks Subtotal
Direct Expenses (plots, phone, reproduction, mail, travel)
Subconsultant Administration
!Professional Services Fee Total
Attachment B
Robert W. Droll, Landscape Architect, PS 360.456.3813