HomeMy WebLinkAboutFS 2012-11-06 Item 2A - Resolution - 2013-2014 Land Use Fee ScheduleCity of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
TO: Mayor Haggerton
Finance and Safety Committee
FROM: Jack Pace, DCD Director
BY: Nora Gierloff, Deputy DCD Director
DATE: October 30, 2012
SUBJECT: Proposed Land Use Fee Schedule for 2013 -2014
ISSUE
The Department of Community Development (DCD) has developed a revised land use fee schedule
that would reflect annual increases in the costs of providing development review services.
BACKGROUND
In 2010, the Council approved a hybrid fee approach that mixed fixed fees for straightforward
permits with a retainer and hourly fee system for more complex, less predictable permits. A
review of the hybrid system indicates that on some permit types (appeals, shoreline, tree, and
some special permission approvals) the retainer was rarely exceeded so the revenue generated
through hourly fee tracking did not justify the administrative cost.
Tukwila's current and proposed fees were compared to nearby cities, see Attachment A. Many
nearby cities divide their land use fees into fees attributed to the Planning division, engineering
(Public Works) and, in some cases, Fire. Five of the seven cities that were compared levy a
revision fee to capture additional revenue for complicated or excessively revised projects.
DISCUSSION
The 2013 -2014 fee schedule includes annual increases that reflect increases in the cost of
providing services due to City salary increases at 4% in 2012 and 2.9% in 2014. In order to
streamline administrative cost and effort we propose to change appeals, shoreline permits, tree
permits, and some special permission approvals from hourly billing permit types to fixed fees.
Tree permits are proposed to increase from $53 plus hourly fees to a $100 fixed fee. While this
will likely not cover the review time spent we have had a policy of keeping them affordable to
encourage compliance.
We would continue to pass through any hearing examiner and peer review fees related to a
permit on to the applicant. Once the new permit system is operational we will return to Council
with a proposal for a technology fee to recoup the capital investment in the system. A City -wide
approach to increased costs due to increased use of credit cards will be developed in 2013.
FINANCIAL IMPACT
Annual revisions to the City's land use fees allow us to continue to recover the costs to provide
this service.
INFORMATIONAL MEMO
Page 2
RECOMMENDATION
The Council is being asked to approve the resolution and place it on the consent agenda at the
November 19, 2012 Regular Meeting.
ATTACHMENTS
A Fee Comparison
B Resolution
ZADCD n Clerk'slFee ResolutionllnfoMemo F &S 11- 6- 12.doc
2
Boundary Line Adjustment
$1,536
$1,202
$334
$854
$590
$1,406
$1,264
$3,4502200(minor)
$450
$400
$3,320
Lot Consolidation
$2,361
$570
$1 139
$575
$5
$500
$3 791
UP io $13,818
$1 456
$173
$3,500
$328
$2,000
$1,300
$3
varies $350.8000
Permit Exemption Letter, Shoreline
$222
$183
Short Plat (2-4 lots)
$215
$3,497
$147
$4,791
($1,294
$3,750
25A0t, 3 meetings
$5,437
$2,251
$5,653
+22/lot
$10,100
$3,554
$1,400
$2,889
$665
$4,948
Short Plat (5 -9 lots)
$3
$5,941
$1,961
$2,000
$6,465
$2
$7,879
$76/lot
$11,100
$1,400
Subdivision Preliminary Plat (10+ lots)
$5,119
+50
$7,138
$2,019
$3,000
$120/1.13 meetings
$9,422
$7,436
$79/ acre
$8,171
$54not
$8,500
$4,000
$6,500
$6 -7000 +$1697/
Subdivision Final Plat (10+ lots)
$3,187
+30
$4,363
$1,176
$1,533
$slum
$1
$2,913
$7,813
$22/mt
$9,000
$1,500
$3,250
$1697/ let'
Binding Site Improvement Plan
$3,497
$5,368
$1,871)
$1,139
$62/1.1,2 meetings
$5,312
$1593 for m nor
$2,252
$6,264
+$22n.t
$12,500
+.10 /sf of lot area
$1,800
ann esi en is Development,
5
2 meetings
+so/.na
+.10 /s g
aoo units
Shoreline Permits
Substantial Development Permit average fee
$3,320
$2,361
$959
$1 139
$1 151
$3 791
UP io $13,818
$1 456
$3,500
$2,000
$3
varies $350.8000
Permit Exemption Letter, Shoreline
$222
$183
$39
$215
$147
$85
$325
$175
$150
Conditional Use Permit, Shoreline
$3,554
+HE
$2,889
$665
$1,139
$1,151
$5,8631
$1,681
1 $5,500
$2,000
When fees charged by other cities vary based on size or cost of project, the average of the potential fees is calculated.
Auburn Hearing Examiner Costs passed through to applicant
Federal Way Fees are divided into Planning, Fire and PW allocations. All are included.
Burien Charges development engineering fees at $77 /hr with fee estimate included. Extra planning staff time is billed at $77 /hr for special staff analysis. Professional services are billed to applicant at cost.
Des Moines Charges development engineer fees in addition to planner fees on all final plats (SP, SD, BSIP, PUD). Charges deviation and resubmittal fees.
Renton Charges $75 /hr for complicated, modified, large, technical projects at City's discretion beyond typical review.
SeaTac Charges development engineer fees in addition to planner fees. Both fees are shown on the table. Hearing examiner costs are not passed through to applicant.
1 +X) indicates hourly billing for hours logged over X +HE) indicates that Hearing Examiner costs will be passed through to the applicant
2 Includes Engineering review Fees
p
A RESOLUTION THE CITY COUNCIL THE CITY
TUKWILA, WASHINGTON, ADOPTING A LAND USE FEE
SCHEDULE AND REPEALING RESOLUTION NOS. 1722
AND 1768.
WHEREAS, the City intends to update land use permit fees on an annual basis with
any increases tied to growth in City expenses for providing land use services; and
WHEREAS, the City Council wishes to recover the City's costs for review and
processing of permit applications; and
WHEREAS, the City has adopted a biennial budget process; and
WHEREAS, the overall budgeted increase is 4% for 2013 and 2.9% for 2014;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Fee Schedule. Land use permit and processing fees will be charged
according to the following schedule:
Decision Type
2013
Feel
Retainer
2014
Fee/
Retainer
Plus
Hearing
Examiner
Fees
Plus
Review
Hours over
Retainer
Appeal
Type 1, 2 and 4 Decisions
$563
$579
SEPA MDNS Appeal
$563
$579
Impact Fees:
Fire
$563
$579
Parks
$563
$579
Transportation
$563
$579
WAWord Processing\ResolutionsIand Use Fee Schedule 10-31-12
NG:bjs Page 1 of 5
R
Decision Type
2013
Fee/
Retainer
2014
Fee/
Retainer
Plus
Hearing
Examiner
Fees
Plus
Review
Hours over
Retainer
Sign Permit (TMC Chapter 19)
Permanent
$231
$238
Temporary
$100
$104
Pole /Banner Initial Application
$231
$238
Special Event
$100
$104
Pole /Banner Annual Renewal
$50
$52
New Billboard
$563
$579
Master Sign Program —Admin
$2,070
$2,130
Master Sign Program —BAR
$3,314
$3,411
Appeal of Sign Code Decision
$563
$579
Design Review'; (TMC Section 18.60, 030)
Administrative
$2,130
$2,192
Public Hearing
$3,817
$3,927
Major Modification
$1,305
$1,343
Minor Modification
$593
$610
Variances, Special Permissions &Site Plan Review
Variances (TMC Section 18.72)
$2,692
$2,770
+HE
Parking Variance
(Type 3 —TMC Section 18.56.140)
$924
$950
+HE
Administrative Parking Variance
(Type 2 —TMC Section 18.56.140)
$563
$579
Environmentally Sensitive Areas Deviation,
Buffer Reduction (TMC Chapter 18.45)
$1,425
$1,466
hours
over 15
Reasonable Use Exception
(TMC Section 18.45.180)
$2,850
$2,932
+HE
hours
over 30
TSO Modification to Development Standard
(TMC Section 18.41.100)
$563
$579
Exception from Single Family Design Standard
(TMC Section 18.50.050)
$563
$579
Special Permission Cargo Container
(TMC Section 18.50.060)
$563
$579
Landscape Perimeter Averaging
(TMC Section 18.52.060)
$563
$579
Parking Standard for use not specified
(TMC Section 18.56. 100)
$47_5
$489
hours
over 5
Residential Parking Reduction
(TMC Section 18.56.065)
$563
$579
W: \Word Processing \Resolutions \Land Use Fee Schedule 10 -31 -12
NG:bjs Page 2 of 5
Decision Type
2013
Fee/
Retainer
2014
Fee/
Retainer
Plus
Hearing
Examiner
Fees
Plus
Review
Hours over
Retainer
Variances, Special Permissions Site Plan Review (continued)
Shared, covenant, Complementary Parking
Reduction (TMC Section 18.56.070)
$563
$579
Parking Lot Restriping (TMC Section 18.56.120)
$563
$579
Tree Permit and Exceptions (TMC Chapter 18.54)
$100
$103
Lot Creation and Consolidation
Boundary Line Adjustment (TMC Chapter 17.08)
$1,597
$1,644
Lot Consolidation (TMC Chapter 17.08)
$593
$610
Short Plat (2 4 lots) (TMC Chapter 17.12)
$3,637
$3,742
Short Plat (5 9 lots) (TMC Chapter 17.12)
$4,139
$4,259
Subdivision:
Preliminary Plat (10+ lots)
(TMC Section 17.14.020)
$4,750
$4,888
+HE
hours
over 50
Final Plat (10+ lots) (TMC Section 17.12.030)
$2,850
$2,932
hours
over 30
Binding Site Improvement Plan (TMC Chapter 17.16)
$3,637
$3,742
Planned Residential Development:
Administrative (TMC Section 18.46. 110)
$2,070
$2,130
Public Hearin (TMC Section 18.46. 110)
$4,750
$4,888
hours
over 50
Minor Modification (TMC Section 18.46.130)
$563
$579
Major Modification (TMC Section 18.46.130)
$2,310
$2,377
Wireless' Communication Facility (TMC Chapter 18. 58.050)
Minor (Type 1)
$563
$579
Administrative (Type 2)
$1,597
$1,644
Major or Height Waiver (Type 3)
$3,194
$3,286
+HE
SEPA Environmental
Checklist
$1,628
$1,675
SEPA EIS
$2,850
$2,932
hours
over 30
SEPA Planned Action
$563
$579
SEPA Addendum
$563
$579
Sensitive Area Master Plan Overlay
(TMC Section 18.45.160)
$4,750
$4,888
hours
over 50
W: \Word Processing \Resolutions\Land Use Fee Schedule 10 -31 -12
NG:bjs Page 3 of 5
Decision Type
2013
Fee/
Retainer
2014
Fee/
Retainer
Plus
Hearing
Examiner
Fees
Plus
Review
Hours over
Retainer
Shoreline P ermits
Substantial Development Permit:
(TMC Cha 18.44)
Project value: $5,000- 1 0,000
$1,125
$1,158
$10,001 50,000
$2,632
$2,709
$50,001 500,000
$4,198
$4,320
M ore than $500,000
$5,324
$5,
Permit Exemption Letter, Shorelin
$231
$238
Conditional Use Permit, Shoreline
(TMC Section 18.44.050)
$3,696
$3,803
+HE
Shore Tree Per (TMC Chapter 18.
$100
$103
Shoreline E nvironment R edesi nation
$2,850
$2,932
+hours
over 30
Noise V ariance (TMC Sect ion 8.22.120)
Type 1
$462
$475
Type II
$623
$641
Type III
$1,385
$1,425
+HE
Use Permits
Conditional Use Permit (TMC Section 18.64.020)
$3,696
$3,803
+HE
Unclassified Use Permit (TMC Chapter 18.66)
$4,750
$4,888
+hours
ov er 50
TSO Special Permission Use
(TMC Secti 18.41.060)
$924
$950
+HE
Co Plan Changes (TMC Chapter 18.84)
Rezone (Map Change)
$3,325
$3,421
hours
over 35
Comprehensive Plan Amendment
$3,800
$3,910
hours
over 40
Zoning Co T ext Amend
$4,319
$4,444
i
W: \Word Processing \Resolutions \Land Use Fee Schedule 10 -31 -12
NG:bjs
Page 4 of 5
Dec ision Type
2013
Fee/
Retainer
2014
Fee/
Retainer
Plus
Hearing
Examiner
Fees
Plus
Review
Hours over
Retainer
Misce llaneous Services and Charges
Development Agreement
$1,900
$1,955
hours
over 20
Code Interpretation (TMC Sect 18.90.
$332
$341
Zoning Verification Lett
$332
$341
Le al Lot Verification
$532
$548
Prea plication Meeting
$462
$475
M ailing Fee to Generate Labels, p project
$437
$449
Public Notice Mailing Fee per address for each
maili
$1
$1
For permits marked hours over...," the retainer covers the specified number of review hours.
Hours over this retainer will be charged at $95 in 2013 and $98 in 2014.
All peer review fees will be passed through to the applicant per TMC Section 18.50.200.
Section 2. Repealer. Resolution No. 1722 dated August 16, 2010, and resolution
No. 1768 dated May 21, 2012, are hereby repealed effective December 31, 2012.
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this day of 2012.
ATTEST /AUTHENTICATED
Christy O'Flaherty, MMC, City Clerk Verna Seal, Council President
Shelley M. Kerslake, City Attorney
WAWord Processing \Resolutions\Land Use Fee Schedule 10 -31 -12
NGbjs
Filed with the City Clerk:_
Passed by the City Council:
Resolution Number:
Page 5 of 5
N