HomeMy WebLinkAboutPark 2014-04-23 Item 4A - Project UpdatePARKS &. RECREATION
GOOD HEALTHY FUN
CURRENT PROJECTS
1
2
3
PARKS COMMISSION
PROJECT UPDATE
Restroom Counters Replacement at the Clubhouse
Researching equipment, materials, and options for work to be completed.
Target Completion Date: Spring 2014
Project Stage: Investigating materials and options
Project Budget: $10,000
Duwamish Hill Preserve (DHP)
Consultant Agreement signed, Kickoff held on site with consultant team, Design Open House scheduled for
May 15th to begin design and public input process.
Target Completion Date: On -going
Project Stage: Consultant Agreement Signed /Design work beginning
Project Budget: $900K
Ft Dent Parking Lot Repair Work
Received 90% plans for overlay work in areas of parking lot at Ft. Dent Park
Target Completion Date: 2014 Summer
Project Stage: 90% Plans
Project Budget: $250K
5