HomeMy WebLinkAboutFS 2009-11-03 Item 2B - Discussion - Above Ground Fuel Tank InstallationsTo:
City of Tukwila Steven M. Mullet, Mayor
Fire Department Nicholas J. Olivas, Fire Chief
Mayor Haggerton
Finance Safety Committee
From: Battalion Chief Tomaso, Fire Marshal
Date: October 29, 2009
Subject: Above Ground Fuel Tank Installations
Issue: The Fire Department has been contacted by several businesses within the
potential flooding areas seeking the permit requirements to install standby power and fuel
tanks to sustain their businesses in the event of loss of electrical power during a flooding
event.
We have already approved several locations for the installation of Hesco Baskets to prevent
flooding of the buildings and they are now looking at providing power and sufficient fuel to
operate these essential facilities.
Background: The Tukwila Urban Center zoning does not allow above ground fuel tank
installations, TMC 16.16.040, however under TMC 16.16.080 (3) allows for exceptions.
Exceptions have historically been brought to Council as an informational item and if properly
screened from public view have been allowed.
Discussion: Given the nature of the potential flooding and power loss if flooding does
occur the installation of standby power systems with supplemental fuel tanks is a reasonable
approach for the businesses to ensure continuity of operations. The installations will meet all
applicable Fire and Mechanical Codes for installation; in addition we would ensure that there is
proper screening is installed, to limit the potential view by the public of the installation. I have
been in contact with Planning and Public Works to ensure any of their concerns are addressed
in the permitting process.
Recommendation: Allow the Fire Department the latitude to approve these standby
power systems and above ground fuel tank installations related to flood preparations without
bringing them to the Council as an informational item prior to issuing the permit. This will allow
a faster permit turnaround for the applicants seeking the installations. The approvals will be
granted for temporary installations until the Howard Hansen Dam issues are resolved.
The Fire Department will provide Finance and Safety a monthly update of installations that
have been approved for informational purposes.
Headquarters Station: 444 Andover Park East Tukwila, Washington 98188 Phone: 206 -575 -4404 Fax: 206 -575 -4439