Loading...
HomeMy WebLinkAboutTrans 2012-03-05 Item 2D - Discussion - Tukwila Urban Center / Andover Park West Widening ProjectsCity of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Transportation Committee FROM: Bob Giberson, Public Works Director DATE: March 2, 2012 SUBJECT. TUC Transit Center and Andover Park West Widening Projects Project Nos. 90610402, 98810404, 99840105 Design Update ISSUE A presentation of the combined Tukwila Urban Center Transit Center and Andover Park West Roadway Widening Project prior to a property owner presentation on March 7, 2012. BACKGROUND In February 2006, IBI Group was retained by the City to begin the design of the Tukwila Urban Center Transit Center on Andover Park W. The Transit Center's Concept Plan was completed in December 2006. Due to the overlapping design needs of the Transit Center and the Andover Park W widening project (98810404), the two projects were combined under the IBI Group contract. The water main project (99840105) was also added to the IBI Group's design contract. The 30% design for the projects was completed in 2011 and work progresses toward the completion of 60% design. DISCUSSION Prior to completing the draft 60% plan set, the design team would like to get input from Council and affected property owners on remaining design issues. A Stakeholder meeting is scheduled for Wednesday, March 7, 2012 to present the status of the design and open up discussions with property owners and businesses along Andover Park West. A similar presentation will be made to the Transportation Committee on Monday, March 5, 2012 in advance of the Stakeholder meeting. The design team will present information on the status of the design, identify design issues needing direction or concurrence, and share the current schedule. RECOMMENDATION For information and discussion only. No formal action is required. wApw eng \projects\a- rw rs projects \90610402 transit center\info memo transit center apw widening update on design.docz 11