HomeMy WebLinkAboutTrans 2013-04-23 Item 2A - Briefing - Allentown Area Relating to Burlington Northern Santa Fe (BNSF) RailroadTO:
FROM:
DATE:
SUBJECT:
City of Tukwila
Jim Haggerton, Mayor
MEMORANDUM
Transportation Committee
Kimberly Matej, Government Relations Manager
April 16, 2013
Preparation of Scope of Work Relating to Allentown and the BNSF Intermodal Facility
— Information Only
Committee Chair Kruller has requested that as information only, the Transportation Committee
receive a briefing on the item below which was discussed and approved by the Community Affairs &
Parks on Monday, April 8. Additionally, a copy of the Meeting Report Summary from the BNSF
Intermodal Hub Yard Task Force dated April 10, 2000, prepared by Cooper Consulting Company has
been provided for Committee reference.
Previous Memo submitted and presented to the Community Affairs & Parks Committee on 04/8/13
ISSUE
For several years, the City has been working with the Allentown community on issues regarding the
impacts of Burlington Northern Santa Fe's (BNSF) South Seattle Intermodal Facility located in the
neighborhood. After meetings with representatives from the City's Congressional delegation, local
community members, and BNSF representatives, staff is recommending and seeking Committee
approval to move forward with creating a scope of work to be utilized in identifying a consultant who
can conduct and present a data-driven report of findings quantifying the effects of the Intermodal
Facility onto the Allentown community.
BACKGROUND
The BNSF South Seattle Intermodal Facility located in Allentown became fully operational in 1970. In
1989, the Allentown neighborhood was annexed by the City of Tukwila. This annexation finally
provided this previously unincorporated area a voice within a full-service city. In January 2000, an ad-
hoc committee (Burlington Northern Intermodal Task Force) was established to consider alternative
truck access routes into the Intermodal Facility. The Task Force recommended four alternative routes
for consideration, and presented a Meeting Report Summary, which Copper Consulting Company
prepared on April 10, 2000. More recently, over the past few years, the City has met and
corresponded with BNSF representatives in an effort to build a foundation for sustainable and
cooperative relationships between the Intermodal Facility and its residential neighbors. Efforts to
address concerns have included discussions, meetings and correspondence with community
representatives, BNSF representatives and Federal legislators.
DISCUSSION
Pending Committee approval, City staff will continue to work with the community to ensure that a
scope of work represents a fair assessment of concerns that can be further assessed through
consultant research. The scope of work will also include a task requesting identification of possible
mitigation in response to documented effects.
Staff has inquired if BNSF would be interested in sharing the cost of a consultant, as well as
participating in consultant selection. This invitation has been extended in a continued effort between
the City and BNSF to work in a collaborative manner to address community concerns regarding
quality of life issues that have been expressed by Allentown residents as a result of the Intermodal
Facility location.
1
Information Only: BNSF Scope of Work page 2
Funding was not identified in the 2013-2014 Biennial Budget to address this issue; therefore, funding
for a consultant will require a year-end budget adjustment. Based on the length of time that this has
been a community conoern, as well as Council's interest in addressing these concerns, staff
recommends Council consider a year-end adjustment aliowing staff the opportunity to identify funding
for a consultant. Initial estimates suggest that a consultant would cost between $50,000 — $80,000.
RECOMMENDATION.
Staff has recommended to Mayor Haggerton, and he concurs that it is in the best interest of the City
and the residents of Allentown to move forward with creating a scope of work in order to identify
impacts of and potential mitigation opportunities relating to the BNSF Intermodal Facility.
2
75
MEETING REPORT SUMMARY
of the
BURLINGTON NORTHERN SANTA RAILROAD
INTERMODAL HUB YARD TASK FORCE
for the
CITY OF TUKWILA
Presented to:
Mr. James F. Morrow, Director
City of Tukwila, Washington
Department of Public Works
Tukwila City Hall
6200 Southcenter Blvd
Tukwila, Washington 98199
Prepared by:
Hal B. H. Cooper, Jr.
Consulting Engineer
Cooper Consulting Company
11715 N.E. 145th Street
Kirkland, Washington 98034
April 10, 2000
3
SUMMARY
A detailed evaluation has been conducted of the available alternative solutions for improving the
heavy truck access for improving the heavy truck access into the BNSF Railroad South Seattle
intermodal yard hub center in the Allentown area of the City of Tukwila. An ad -hoc task force
was established by the Mayor of the City of Tukwila whose charge was to identify, evaluate,
prioritize and recommend possible solutions to improving the truck access into the BNSF
Railroad intermodal yard so as to reduce adverse community impacts. The criteria for identifying,
evaluating and recommending possible solutions were that they be technically feasible, financially
affordable, have a reasonable implementation timeframe, and be politically acceptable.
The Burlington Northern Task Force held a series of meetings to review the available information
regarding alternative truck access routes into the BNSF Railroad intermodal yard. The greatest
challenge the Task Force faced was to develop and recommend one or more possible solutions for
truck access into the BNSF Railroad intermodal yard. The goal of developing these possible
solutions would be to alleviate or eliminate the present adverse community impacts associated
with large scale movements of 600 to 800 heavy trucks per day along South 124th Street in the
Allentown area of Tukwila. These large -scale truck movements along South 124th Street are
through a residential neighborhood of modest homes close to a street, which was never designed
nor intended to be used by large numbers of heavy trucks on a regular basis.
The Burlington Northern Task Force identified 8 possible alternative routing solutions for
alleviating the problems associated with adverse community impacts resulting from large scale
truck movements through the Allentown area of Tukwila. These 8 alternative truck route
configurations to and from the BNSF Railroad intermodal yard were as follows. improve the
existing South 124`h Street rout build a new route along 56th Avenue South build a new
route along 48th Avenue South 4 build a new route along either Gateway Drive Sout build a
new route along Gateway Drive North b develop a new route along South 115`h Str _
develop a new route along East Marginal Way and South 112th Stree 8 build a new access route
along Airport Way South into the BNSF Railroad intermodal yard. Talternative entry options
for future truck access into the BNSF Railroad South Seattle intermodal yard in the Allentown
area of the City of Tukwila is illustrated in Figure A.
These 8 individual alternative routing solutions were developed with the twin objectives of
providing efficient truck access and minimizing adverse community and minimizing adverse
community impacts. The specific issues for which the 8 individual alternative route solutions
were to be evaluated included residential impacts, business income impacts, employment impacts,
environmental impacts, intersection impacts, traffic impacts, noise impacts, safety impacts, and
land acquisition needs. A summary of the evaluation matrix developed by the Burlington
Northern Task Force of the City of Tukwila is presented in Table A.
The estimated capital costs of each alternative routing solution were to be identified and broken
down in terms of land purchase costs, property displacement costs, construction costs, indirect
costs, and costs to private sector businesses, especially for the BNSF Railroad. The identification
of private sector costs was of particular importance because most Federal and State grants
available preclude the use of public funds for the benefit of private property.
4
Figure A'
ALTERNATIVE TRUCK ACCESS ROUTES INTO THE BURLINGTON NORTHERN SANTA FE
ALLENTOWN AREA OF TUKWILA BY THE AUTHOR
Scale of. Distance in Feet
RAILROAD INTERMODAL YARD IN THE
1
1 000 2,100
00 5, 100
Duwamis
River
SR 599
Freeway
SEATTLE 1,
TUKWILA
Airport Wa
Sout lai
SEATTLE
5 107 5l
5 11] 51
M101 NI
5 116 5l
$ Wallace 51
Inte
5 F# e
ALL NTO
5 122 51
S 124 51
BO
;South 124th Street
5 126 51
5 128 S1
TUKWILA
5
Table A
RESULTS OF THE COMPARATIVE ALTERNATIVE OPTION RANKING PROCESS BY THE BURLINGTON NORTHERN TASK
FORCE MEMBERS FOR THE INDIVIDUAL TRUCK ROUTES INTO THE BURLINGTON NORTHERN SANTA FE RAILROAD
SOUTH SEATTLE INTERMODAL YARD HUB CENTER IN THE ALLENTOWN AREA OF THE CITY OF TUKWILA
Evaluation Criteria
BNSF TASK FORCE OPTIONS EVALUATION
Options
Specific
Impact
Do Nothing
48th Ave S.
Gateway Drive
Gateway
Drive (B)
I. Marginal
Way (S 112th
St)
Airport
Way
Access
S I 15th St.
56th Ave S.
Improve
124th
Environmental Impact
n.a.
Red
Red
Red
Yellow
Yellow
Yellow
Red
Red
Residential Impacts
Red
Green
Red
Yellow
Green
Green
Red
Red
Red
Project Costs:
Facility Costs
0
$8.9 Mill.
$l1.3 Mill
$112 Mill$20.0
Mill.$12.2
M
$18.6 Mil
$14.3 Mil
$6.4 Mill
BNSF Costs
0
0
0
0
$3.5 Mill$3.5
M
$3.5 Mil
0
0
Land Acquisition
No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Loss of Business Income
No
Yes
Yes
Yes
No
No
Yes
No
No
Job Impnts
Green
Red
Yellow
Yellow
Yellow
Green
Green
Green
Green
ImpdsatIntemntim
Yellow
Red
Yellow
Yellow
Yellow
Green
Red
Red
Red
Noise Impacts
Red
Red
Red
Red
Yellow
Yellow
Red
Red
Red
Safety Impacts
Red
Red
Yellow
Yellow
Green
Yellow
Red
Red
Red
Traffic Patterns in the City
Red
Red
Yellow
Yellow
Yellow
Yellow
Red
Red
Red
Legal Issues
Impacts to BNSF Yard Ops
Cree
_-_ ii,
- - •
-
: •
: - •
- .
- •
- - .
Project Duration
No
Project Fmldhlg
n.a .
Green
Red
Red
• - •
R.
Red
r, - •
G Rn
4
The extensive evaluation by the Burlington Northern Task Force led to the recommendation of
four possible alternative route solutions of constructing new routes along Airport Way South,
East Marginal Way South with South 112th Street and Gateway Drive South, and improving the
South 124th Street entry. The estimated capital costs of the four alternative solutions ranged
between $6,450,000 (South 124th Street) and $23,500,000 (East Marginal Way South). The
highest ranked alternative was the Airport Way South route, which was the second highest cost
option because of its minimal adverse impacts. The lowest ranked alternative was the South 124th
Street improvements at $6,450,000 because of its continued use of a residential street. The other
four alternatives were all eliminated from further consideration, primarily because of perceived
excessive adverse community impacts. A summary of these comparative rankings for the
alternative truck access routes, into the BNSF intermodal yard, as listed in Table B.
The author made a separate analysis of the potential alternative solutions for improving truck
access into the BNSF Railroad intermodal yard. This analysis identified 12 alternative route
solutions for improving truck access into the BNSF Railroad intermodal yard. These 12
alternative solutions included the 8 options identified by the Burlington Northern Task Force plus
the Boeing Access Road at the north and along Interurban Avenue South between Gateway Drive
and 48" Avenue at the south. In addition, the author identified two alternative routes to the east
to connect with Martin Luther King Way South and the Interstate 5 freeway, which were not a
part of the other analyses. The comparative capital costs for all of these alternative solutions by
source for alternative truck access routes, as presented in Table C.
The analysis conducted by the author also recommended four route options of which three were
the same as by the Burlington Northern Task Force. These recommended alternative routes were
along Airport Way South and East Marginal Way South at the north end plus Gateway Drive
South at the south end. The fourth alternative route recommendation was different than by the
Burlington Northern Task Force in that the lowest capital cost but maximum community impact
improvement of the South 124th Street route was eliminated because trucks would still go through
the Allentown residential neighborhood to the BNSF intermodal yard.
In the place of the South 124th Street option was recommended a combined eastern route access
over the BNSF and Union Pacific Railroad tracks to connect with the Interstate 5 freeway and
Martin Luther King Way South, as illustrated in Figure B. This alternative route could be
considered as a rail-road grade separation which could make its eligible for FAST Corridor grade
separation project funding or under the TEA-21 Act funding programs. There would then only
need to be a 20 to 25 percent private funding requirement for the BNSF Railroad as this project
can then be considered as a freight mobility enhancement. In addition, it is possible that the
planned Sound Transit Central Link light rail transit alignment through Segment E in Tukwila
could go along the Interstate 5 freeway in coordination with the BNSF Railroad intermodal yard
roadway entry and exit ramps.
The estimated capital costs of the recommended alternatives by the author ranged between $11.85
million and $25.75 million in the medium cost range and between $16.90 and $32.25 million for
the maximum cost range, as listed in Table D. Those recommended alternative solutions which
involved a north end access to the BNSF Railroad intermodal yard all had higher estimated capital
costs because they required a complete reorientation of the existing yard configuration as well as
a bypass road around its western end. The advantages of the north end entry options into the
7
TABLE B
COMPARATIVE RANKINGS OF RECOMMENDED ALTERNATIVE ROUTING
SOLUTIONS FOR IMPROVING TRUCK ACCESS INTO THE BURLINGTON
NORTHERN SANTA FE RAILROAD SOUTH SEATTLE INTERMODAL YARD HUB
CENTER IN THE ALLENTOWN AREA OF THE CITY OF TUKWILA
Recommending
Source
Priority
Ranking
Solution
Number
Alternative
Description
Capital
Cost
$
Author Evaluation
1
2
Airport Way South
24,250,000
2
2
East Marginal Way
South 112th Street
25,750,000
3
9
Gateway Drive South
11,850,000
4
7
Interstate 5 Freeway
Martin Luther King Way
24,750,000
Burlington Northern
Task Force - Tukwila
1
1
Airport Way South
15,700,000
2
2
East Margirnal Way
South 112 Street
23,500,000
3
6
Gateway Drive South (A)
11,170,000
4
4
South 124'" Street
6,450,000
8
6
TABLE C
COMPARATIVE ESTIMATES OF CAPITAL COSTS FOR THE PROPOSED
ALTERNATIVE SOLUTIONS FOR IMPROVING TRUCK ACCESS INTO THE
BURLINGTON NORTHERN SANTA FE RAILROAD INTERMODAL YARD HUB
CENTER TERMINAL IN THE ALLENTOWN AREA OF THE CITY OF TUKWILA
Solution
Number
Alternative
Description
Harding
Lawson
Associates
Hanon &
Wilson
Consultants
City of
Tukwila
Estimates
Cooper
Revised
Estimates
1
Airport Way South
-
16,675,727
15,700,000
32,270,000
2
Boeing Access
Road
-
18,400,639
-
33,000,000
3
East Marginal Way
8,987,691
20,639,554
23,500,000
31,860,000
4
South 115`" Street
-
-
22,155,000
41,280,000
5
South 124`" Street
-
-
6,450,000
15,900,000
6
Martin Luther King
Way
-
-
-
36,190,000
7
Interstate 5
Freeway
-
-
-
26,795,000
8
Gateway Drive
North
-
8,752,457
11,255,000
23,310,000
9
Gateway Drive
South
6,785,981
7,275,067
11,170,000
16,880,000
10
Interurban Avenue
South
-
-
-
22,330,000
11
48th Avenue South
2,838,608
-
8,925,000
24,750,000
12
56`" Avenue South
-
-
14,330,000
27,105,000
Average Capital Cost
14,348,689
14,185,625
27,721,667
Dollar Reporting Basis
1998
1997
1999
2000
9
Figure B
7
PROPOSED ENTRY AND EXIT ROUTE CONFIGURATION INTO AND OUT OF THE BURLINGTON
NORTHERN SANTA FE RAILROAD SOUTH SEATTLE HUB CENTER INTERMODAL YARD WHICH
CONNECTS WITH THE,INTERSTATE 5 FREEWAY AND MARTIN LUTHER KING JR WAY SOUTH
WITH A NORTH TERMINAL ENTRY ACCESS FROM IRP0RT WAY SOUTH TO SOUTH SEATTLE
Airpor
ay Sou
• 111•••■••
SEATTLE
Interstate 5
Freeway.
TUKWILA
0 500 1,opo
; 'J e 41 1 1 e
Scale of Distahce-Feei-
••••••••
SEATTLE
.L. King Jr.
ay South
1
1
1
OMMMOSIMM. 1WW■MMO■■•••
TUKWILA
Av
So
.1k fimA
Future Entr :\ y‘tit
Ramp from 2no
Level'Facilitv,
Elevated
viaduct
Licht
Rail
North \
Entry
South 112th Street
City of Seattle
Electricity-Water
Utiltt=
aSat
rSotth
Residential Property
to be Acquired for
Bypas
East Marginal
Way South
Surface Light
Rail Line
Street
.L. King D
South
DU
NE
BNSF
J%Railroad
10
8
TABLE D
APPROXIMATE RANGES IN THE ESTIMATED CAPITAL COSTS OF THE
PROPOSED ALTERNATIVE SOLUTIONS FOR IMPROVING TRUCK
ROADWAY ACCESS INTO THE BURLINGTON NORTHERN SANTA FE
RAILROAD INTERMODAL YARD HUB CENTER TERMINAL IN THE
ALLENTOWN AREA OF THE CITY OF TUKWILA
Solution
Number
Alternative
Description
Minimum
Cost
$
Medium Cost
$
Maximum
Cost
Cost
Ranking
By Number
1
Airport Way
South
16,000,000
24,250,000
32,500,000
8
2
Boeing Access
Road
18,500,000
25,750,000
33,000,000
10
3
East Marginal
Way
20,600,000
23,500,000
32,5000,000
7
4
South 115`" Street
22,150,000
31,750,000
41,300,000
11
5
South 1241' Street
6,450,000
11,250,000
15,900,000
1
6
Martin Luther
King Way
27,500,000
32,000,000
36,200,000
12
7
Interstate 5
Freeway
22,500,000
24,750,000
26,800,000
9
8
Gateway Drive
North
8,750,000
16,250,000
23,310,000
3
9
Gateway Drive
South
6,800,000
11,850,000
16,900,000
2
10
Interurban
Avenue South
20,000,000
21,250,000
22,500,000
6
11
48`" Avenue
South
8,950,000
17,000,000
24,750,000
4
12
56`" Avenue
South
14,300,000
20,750,000
27,100,000
5
Average Capital Cost
14,842,667
19,312,500
27,721,667
11
9
BNSF Railroad intermodal yard was that they generally involved fewer adverse community
impacts as compared to those alternative solutions with southern end access.
It will be necessary to develop suitable financial package for whatever recommended option for
solving the BNSF Railroad intermodal yard is selected. The recommended and favored north end
access solutions may require a BNSF Railroad expense of up to $13 million unless alternative
financing means are utilized such as declaring the access ramp grade separations and using freight
mobility funding. An estimated capital cost breakdown by type of expense for the alternative
truck entry routes into the BNSF intermodal yard is illustrated in Figure C.
A large scale justification for major public sector funding from State and Federal government
sources can be developed based on the fact that there are substantial avoided costs resulting from
reduced highway maintenance costs along the Interstate 90-94 freeway intercity corridor of $19
million per year for the State of Washington alone, and $134 million per year across the entire 7
Northern Tier states between Seattle and Chicago. A breakdown of highway maintenance cost
savings across the Northern Tier States resulting from the intermodal diversion of these 660
trailers per day from road to rail using the BNSF intermodal yard is shown in Figure D.
Ultimately a combined expenditure of $20 to 40 million will be required by the public sector and
private sector separately or in a combination in order to enhance truck access into the BNSF
Railroad intermodal yard while reducing or alleviating the adverse community impacts associated
with these truck movements. It is possible that 70 to 75 percent of the total project cost could
come from public sector grants from the Federal and State governments with the BNSF Railroad
intermodal yard classed as being a past of the FAST Corridor project as an essential public facility
with the entry and exit ramps as a rail-road grade separation, as presented in Table E. It is
possible that the BNSF Railroad intermodal yard project could be financed by user fees of
approximately $10.00 to 11.50 per trailer in order to repay of the long term low interest loans or
tax exempt revenue bonds when based on a $40 million capital cost.
The intermodal diversion of truck traffic from the road to the rail via the BNSF Railroad
intermodal yard is expected to result in a total reduction in highway maintenance cost of $133
million per year across the 2,135 mile long route through the seven Northern Tier States. The
prorate savings in total highway maintenance costs are expected to be $19 million per year for the
305 mile section across the State of Washington alone. The various diesel full taxes plus excise
taxes and tire wear taxes paid by these trucks constitutes about 40 percent of these total roadway
maintenance costs. The net roadway maintenance cost increase which would result across the
seven Northern Tier States is estimated as $80 million per year if these trucks did not go by
railroad with $11 million per year for the State of Washington. These avoided costs to State
roadway maintenance costs can provide at least some justification for State and Federal
government expenditures to improve truck access to the BNSF intermodal yard in Tukwila.
12
Figure Q
COMPARISON OF THE ESTIMATED CAPITAL COSTS FOR THE PROPOSED ALTERNATIVE ROUTES FOR IMPROVED
TRUCK ACCESS INTO AND OUT OF THE BURLINGTON NORTHERN SANTA FE RAILROAD SOUTH SEATTLE HUB
CENTER INTERMODAL YARD TO REDUCE ADVERSE IMPACTS IN THE ALLENTOWN AREA OF THE CITY OF TUKWILA
ra-1 P
31.9
5.9
26.8
]Public Sector Funding
IIPrivate Sector Funds
Orr
Public- Private :SeCtor -
Funding Partnership
24.8,
7.1 a
rr
derr
Sol 1
Airport
Way
South
Sol 2 Sol 3 Sol 4 Sol 5 Sol 6 Sol 7 Sol 8
Boeing E. Marg 5 115th S 124th ML King IH 5 Gateway
Access Way South Street Street Way South Freeway Dr North
Road S 112th St Access Improvem IH 5 Fwy Onramps Access
Sol 9 Sol 10 Sol 11
Gateway Interurb 48th
Dr South an Avenue Avenue
Access South South
Sol 12
-56th
Avenue '-
South
Figure D
ESTIMATED AVOIDED HIGHWAY MAINTENANCE COST SAVINGS ACROSS THE NORTHERN TIER STATES AS
THE RESULT OF INTERMODAL DIVERSION OF DOMESTIC TRAILER AND CONTAINER SHIPMENTS FROM
ROAD TO RAIL FOR SHIPMENTS BETWEEN SEATTLE AND CHICAGO OR TWIN CITIES WHICH ORIGINATE
AND TERMINATE AT THE BURLINGTON NORTHERN SANTA FE RAILROAD INTERMODAL YARD IN TUKWILA
Washing o d o Montana
18.95
Data compiled based on
information develoed by
the Washington State
Department of Transpo
North Dakota
Minnesota sconsi
Total Mainten lce Need
Road Use Tax Reiniburse
inois
2.69 Mill
.27 Mill:
Externalized Vaintenance- 79.42 Mill:
Nonreimburseid from Tax -s
5.54
ation, Olympia, Washin
ton, 1998.(Ref. 11).
500
1,000
1;500
Distance from Tukwila in Miles
2,000
2,400
TABLE E
ESTIMATED CAPITAL COST OF THE COMBINED INTERSTATE 5 FREEWAY-MARTIN LUTHER KING WAY SOUTH EASTERN ACCESS AS A
PROPOSED RAILROAD GRADE SEPARATION INTO 'THE BURLINGTON NORTHERN SANTA FE RAILROAD SOUTH SEATTLE INTERMODAL
YARD IN CONJUNCTION VVITH THE POSSIBLE SOUND TRANSIT CENTRAL LINK LIGHT RAIL TRANSIT ALIGNMENT ALONG THE INTERSTATE
5 FREEWAY BETWEEN THE BOEING ACCESS ROAD AND THE SR599 FREEWAY
Cost
Category
Specific
Expense
Expense
Description
Unit Cost
$/unit
Cost
$
Funding
Source
Land Purchase
Purchase existing homes
Purchase 50 homes
$150.000/homo
7.500.000
TEA-21 Grant State
funds
ByponoRood
West bypass road along 44
Place South
Construct 4,000-foot road
as truck bypass
4.000/foot
(2 lanes)
16.000.000
TEA-21 Grant
State funds
Connecting Road
North entry road from Airport
Way South
Construct 1 ,750-foot road
as truck entry
4.000/hoot
(2 lanes)
7.000.000
BNSF railroad
State entry road
Sub-total Entry Roads:
23.000.000
Freeway Ramps
Grade Separation
Elevated road
Construct 1,600 ft. of
elevated viaducts
5.000/hJot
8'000.000
Fast corridor federal-
state
Surface road
Construct 200 ft. of surface
roadway
3.000/foot
600,000
Fast corridor federal-
state
Interchange points
Construct six ramp
interchange points
500.000/inL
3.000.000
Fast corridor federal-
state
Subtotal Ramps, Grade separation
11.800.000
Yard
Reconfiguration
Relocate entry gates and weigh
scales
Relocate gates and scales
from south to north end of
yard
6.500.000
5.550.000
BNSF Railroad
Subtotal Yard Reconfiguration
5.550.000
TOTAL AMOUNT:
47.600.0001'3
40.600.0002'3
1 Includes the Airport Way South entry route into the BNSF Railroad intermodal yard.
2 Excludes the Airport Way South ent mu�i��e8�FR�|n�i��o���.
o based nnPr�e/�funding a|buaUonu'by source aufollows:
Funding Organization No Airport Way Entry
BNSF Railroad
King County )
Federal Cbvemment
TOTAL
With Airport Way Entry
m
6,080,000 15.0 6,0E10,00 l2,8
7,500,000 18.5 7,500,000 15.8
7.560.000 18/6 7.560/000 15.9
19.460.000 47.9 26,460,000 55.O
40.600.000 100.0 47.600.000 100.0
Funding Type
Direct expense
Passthrough Grant
Grant (FAST )
Grant (TEA-21)