HomeMy WebLinkAboutTrans 2013-12-10 Item 4C - Discussion - 2013 Transportation Committee GoalsTO•
City of Tukwila
Jim Haggerton, Mayor
Department of Public Works Bob Giberson, P.E., Director
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
BY: Robin Tischmak, City Engineer
DATE: December 6, 2013 (Revised from May 13, 2013)
SUBJECT: 2013 Transportation Work Plan
ISSUE
Updated information includes completed tasks for the list of 2013 funded transportation projects and
items that were included on the list, but were not brought forward to the Transportation Committee.
DISCUSSION
Public Works discussed the 2013 work program at the January 15th and May 14th, 2013 Transportation
Committee meetings. Anticipated schedules and potential committee agenda items were presented, as
well as direction from the committee regarding preferences or requests on how agenda items are to be
included.
* Indicates those items that were approved as Transportation Committee Goals.
Second Quarter
1. TUC Access (Klickitat) — Final LID Assessment Roll (Complete)
2. Annual Bridge Inspections — Award contract(s) for inspections and repair project(s) (Complete)
3. Transportation Improvement Program (TIP) — Council adoption (Complete)
4. 42nd Ave S Safety Rail Along River — Guardrail analysis (Complete)
Third Quarter
1. *CIP Project Review Policy (Complete)
2. Boeing Access Road Bridge Rehabilitation — Approve design contract (Complete)
3. Overlay & Repair - E Marginal Way — Approve design contract (Complete); award construction
contract (No program constructed in 2013)
4. ADA Improvements — Approve design contract (Complete); award construction contract
5. Safe Routes to Schools (Cascade and Thorndyke) — Approve contracts for design; award
construction bid for Cascade View Elementary trail (Design contract awarded)
6. TUC Transit Center & Andover Park W (Tukwila Pkwy to Strander Blvd) — Award construction bid
(Complete)
7. Interurban Ave S (S 143rd St to Ft Dent) — Approve design contract (Complete); award
construction contract (Will occur in 2014)
8. 2013 Overlay /Repair — Award construction contract; approve 2014 design contract (Complete)
9. Traffic Impact Fee Intersection Improvement Projects (5) — Approve contracts for design
i. Andover Park E /Industry Dr
ii. Andover Park E/Minkler Blvd
iii. W Valley Hwy /S 156th St
iv. S 133rd St/SR 599
v. Macadam Rd S/S 144 St
10. Tukwila Urban Center Access (Klickitat) — Project Closeout (Complete)
11. Southcenter Parkway Extension - Project Closeout (Complete)
C:\ Users \susan\AppData \Local \Microsoft \Windows \Temporary Internet Files \ Content .Outlook \360AGYOJ \InfoMemo 2013 (Revised 12 -4 -13) TC WorkProgram Goals.docx
5
INFORMATIONAL MEMO
Page 2
12. School Zone Issues
13. Traffic Impact Fees
Fourth Quarter
1. *Public Safety Oriented Sidewalk Policy
2. *Tukwila International Blvd Corridor Improvements
3. *Apprenticeship Policy
4. 42 "d Ave S — Phase III (Southcenter Blvd to S 160th St) — Continue /complete design; present
periodic status updates and /or present issues that may need Council input or direction
5. TUC Pedestrian /Bicycle Bridge — Finish design; submit grant applications
6. Transportation Element of Comp Plan — Adopt Comprehensive Plan
Other Transportation Issues
SCATBd Agendas (Each meeting)
BNSF Freight Mobility Issues (COW Item)
RECOMMENDATION
Information only.