HomeMy WebLinkAboutTrans 2007-05-14 Item 3A - Contract Supplement #2 - Tukwila Urban Center Signal Interconnect and ITS with Siemens ITSTo: Mayor Mullet
From: Public Works Director
Date: May 7, 2007
Subject: Tukwila Urban Center Signal Interconnect and ITS
Traffic Operations Center Hardware and Software Integration
Project No. 88 -RW02, Contract No. 05 -085
Supplemental Agreement No. 2
ISSUE
Supplemental Agreement No. 2 has been negotiated with Siemens ITS for traffic operations software
integration services on the Tukwila Urban Center Signal Interconnect and ITS project for a fixed fee
not to exceed $136,274.
BACKGROUND
INFORMATION MEMO
Siemens ITS was selected in 2005 for design services on this project and we are quickly approaching
the end of the construction phase. The base contract amount with Siemens ITS under City Contract
No. 05 -085 was $285,877 for the preliminary engineering and final design phases. Supplemental
Agreement No. 1 for on -call construction management support and signal timing services was $93,325.
Siemens was asked to provide a supplemental agreement for the integration phase, as described in the
base contract as optional services. This supplement will provide the following for the Traffic
Operations Center:
System integration of all required hardware and software
System architecture development and testing
System graphics showing the urban center intersections
Signal timing installation, testing and verification
System documentation and training
ANALYSIS
Attachment III.A.
A supplemental agreement for Traffic Operations Center system integration services has been
negotiated for a fixed fee not to exceed $136,274. Budget is available in the construction phase.
RECOMMENDATION
Authorize the Mayor to sign Supplemental Agreement No. 2 with Siemens ITS in the amount of
$136,274.
BG:ad
attachment: Supplemental Agreement No. 2
(P:Projects\A- RW RS Projects'SSRWO2 Traf Sig Intrcnt\INFO MEMO SIEMENS CM Supplement No. 2)
2
SUPPLEMENTAL AGREEMENT
NO. 2
Agreement Number
05 -085
City Project Number
88 -RWO2
Project Title
Tukwila Urban Center Signal Interconnect and ITS
Project
Description of Work
Provide construction support services for this project.
The Local Agency of The City of Tukwila desires to supplement the agreement entered into with Siemens
Inc. and executed on 22 of July, 2005 and identified as Agreement No. 05 -085. All provisions in the
basic agreement remain in effect except as expressly modified by this supplement.
Section 1, SCOPE OF WORK, is hereby changed as set forth in EXHIBIT A-2, and by this reference
made a part of this supplement.
Section V, PAYMENT, shall be amended as follows:
By: SIEMENS ITS. By: Citv of Tukwila
Signature Date
Organization and Address
Siemens ITS
8004 Cameron Road
Austin, TX 78754
Attn: Paul Wilson
Phone
(512) 837 -8412
New Maximum Amount Payable
$529,599
The Maximum Total Amount Payable to the Consultant under this Agreement shall not exceed
the sum of the Amount Payable as set forth in EXHIBIT A -1 ($93,325) EXHIBIT A -2 ($136,274) and the
base contract ($285,877), for a total of $515,476.00
If you concur with this supplement and agree to the changes as stated above, please sign in the
appropriate spaces below and retum to this office for final action.
Signature Date
SIEMENS
.11allrbart- err deSrli lnffer
Scope of Work
Exhibit A -2
04/17/07
Table of Contents
Introduction 2
Task 9: Project Coordination with City of Tukwila 2
Task 10: Architecture Development and Implementation of an Integrated Traffic Management System 2
Task 10.1 System Architecture Report 2
Task 10.2 Procurement List of all TOC Hardware and Software 2
Task 10.3: System Acceptance Test Plan 3
Task 10.4 System Graphics and database development 3
Task 10.5 System Set -up and In -house System Integration and Testing 4
Task 10.6 On -Site Central System Installation and Off -Line Testing 5
Task 11: Traffic Management System Field Elements Integration and Validation 5
Task 11.1: System integration 5
Task 11.2: End -to-End System Testing 6
Task 11.3: Documentation 6
Task 11.4: Training 6
Maintenance Support and Warranty 7
Siemens ITS Page 1
3
SIEMENS
Introduction
Task 9: Project Coordination with City of Tukwila
Budget
The budget for Task 9 is $14,717.
Task 10.1 System Architecture Report
Deliverables
System Architecture Report
This scope of work describes the supplemental agreement No. 2 to be completed by the Siemens ITS Team.
The scope of work describes the following tasks
Project Coordination with City of Tukwila
Architecture Development and Implementation of an integrated Traffic Management system at the
TOC
Siemens will coordinate the execution of the subsequent Tasks 10 and 11 with the City of Tukwila. This task
includes two meetings with the City, maintenance of Overall project schedule, and submittal of invoices. In
addition, this task includes two meetings with the IT group to discuss future connections to Emergency
Operations Center and Police Department (note that the actual connection to those agencies is not part of this
task but may be performed at a later point in time as a separate task). The actual technical management of the
ACTRA implementation and integration is included in the budgets for the subsequent tasks.
Task 10: Architecture Development and Implementation of an
integrated Traffic Management system at the TOC
Using the Concept plan and PS &E documents which will identify the locations of field improvements to be
deployed as part of this phase of the project, Siemens will prepare a system architecture report. The report will
document the existing infrastructure at the City and will include a hardware architecture diagram showing all
hardware connections and interfaces at the central as well as in the field. All hardware components including
necessary computer equipment for ACTRA as well as TOC equipment, and communications equipment will be
shown in this diagram. Existing and new equipment to be procured will be identified.
Task 10.2 Procurement List of all TOC Hardware and Software
Based on the system architecture developed in the previous task, Siemens will provide a list of all required
hardware (communication servers; UPS; workstations; Ethernet switches), and 3rd party software (e.g.
MSSQL, etc.) in order to deploy a fully, functional system to the City for review. The list may be revised based
on City's comments.
Siemens ITS Page 2
SIEMENS
Deliverables
Hardware and software procurement specifications
Meet with Tukwila IT Department to coordinate needs
Task 10.3 Procurement of System Hardware and 3' Party Softwrae
Based on the system architecture and procurement list developed in the previous tasks, Siemens will procure
all system hardware (servers, UPS, workstations) and 3rd Party Software required to deploy a fully functional
system. The system hardware will be loaded with ACTRA and tested in a later task, see 10.6.
Deliverables
One Dell PowerEdge 2950 in Dell 4210 Enclosure
One HP Color Laserjet 4700n
One Dell Optiplex GX620 Workstation
One APC Smart UPS RM 2200VA
Three CF -30 Toughbooks
Task 10.4 System Acceptance Test Plan
Siemens will provide the ACTRA standard acceptance test procedures. Said procedures shall identify various
functions (e.g. Download /Upload, SYNCHRO Interface, CCTV, etc.) for testing. A SAT document shall be
submitted for review and approval by the City prior to commencement of system testing.
Deliverables
System Acceptance Test Document
Task 10.5 System Graphics and database development
The City shall supply the following information to Siemens for input into the system and preparation of the
graphical displays:
Map of the City in electronic format (.bmp or .wmf format) or an aerial photograph of the
City
Intersection layouts for the 28 intersections to be under the control of the system
Siemens shall be responsible for the input of the data supplied by the City into the system, and for the
preparation of the map graphic and individual graphical displays for all signals.
The following is a list of the 28 intersections that will be under the control of the system:
S 180fri St Southcenter Pkwy
S 180th St Andover Park W
S 180th St Andover Park E
S 180th St Sperry Dr
S 180th St /West Valley Hwy
Siemens ITS Page 3
5
6
SIEMENS
SW 43dd St 72nd Ave S
Southcenter Pkwy Blk 17500
Southcenter Pkwy Minkler Blvd
Southcenter Pkwy 168th St
Southcenter Pkwy Strander Bivd
Southcenter Pkwy Klickitat
Southcenter Pkwy /1-5 NB Off Ramp
53rd Ave S Klickitat Dr
Andover Park E Costco Dr
Andover Park E Minkler Blvd
Andover Park E Stander Blvd
Andover Park E Baker Blvd
Andover Park E Tukwila Pkwy
Andover Park W Minkler Bivd
Andover Park W Strander Blvd
Andover Park W Baker Blvd
Andover Park W Tukwila Pkwy
61St Ave S Tukwila Pkwy
Strander Blvd/Mall Entrance /61st PI S
Tukwila Pkwy Mall Entrance
Southcenter Blvd 66th Ave S
Southcenter Blvd 61St Ave S
Southcenter Blvd Macadam Rd S
Deliverables:
One citywide map showing:
Major arterials
28 Intersections
CCTV locations
28 intersection graphics
Upload and store intersection data
rs
Task 10.6: System Set -up and 1n -house System Integration and Testing
In this task, Siemens Integration Team will configure the system in its systems laboratory. The COTS software
and ACTRA software will be installed on the Servers and Workstations. The Workstations will be configured
with the City map and intersection graphics and database. The system will be configured for bench testing
with two Type M50 controllers with the appropriate firmware, and required communications equipment. The
City will provide the communications equipment for testng.
The system will be tested according to standard in -house test procedures for ACTRA and SEPAC.
Following successful testing, the system will be packed and shipped to City of Tukwila for installation.
Siemens ITS Page 4
SIEMENS
Deliverables
Document summarizing the details of the testing results in accordance with the SAT procedures.
Configured system ready for On -Site installation
Task 10.7 On -Site Central System Installation and Off -Line Testing
Siemens staff will install the system equipment at the City's TOC per the system architecture plan approved by
the City in Task 10.1.
By using the test system of controllers, Siemens staff will run through the acceptance test procedures with this
configuration in the presence of City staff. This off-line test will be conducted and completed within one day.
Any problems that occur during the test, and are attributable to either Siemens's work or equipment delivered
by Siemens, will be rectified and the relevant part of the test will be repeated.
The Installed System will include one licensed copy of SYNCHRO. Siemens' terms and conditions for the
licensing of SYNCHRO will apply.
Deliverables
Configured system ready for connection to field equipment.
Completed Test Procedures and Results consistent with the approved SAT document.
Meet with IT to discuss results
One license of SYNCHRO
Budget
The budget for Task 10 is $86,798.
Task 11: Traffic Management System Field Elements
Integration and Validation
Task 11.1: System integration
City personnel will be on hand throughout this task.
.At the end of this task, the system will be ready for the Final Acceptance Test.
Following successful testing of ACTRA in task 10.6 and construction of field elements (including installation of
cabinets, controllers and cameras) by others, Siemens wil bring on -line the controllers and CCTV cameras to
ACTRA.
It is assumed that timing plans will be developed and installed on controllers under a separate contract by the
City's consultant.
Siemens ITS Page 5
7
8
SIEMENS
Deliverables
System fully connected to intersections and cameras
Task 11.3: Documentation
Deliverables
ATMS User's Manual CD
ATMS Administrator's Manual CD
Firmware User Manual
Final System Architecture Report
Task 11.2: End -to -End System Testing
End -to-End System Acceptance Testing for all intended functions will be performed once all hardware and
communications equipment is installed at central and in the field.
Siemens staff will be on site to administer and conduct the test in accordance with the standard test
procedures. The test will be conducted within one day. The test results will be documented and City
personnel will observe the testing.
If any part of the test involving Siemens supplied software fails, relevant sections of the test will be repeated
following correction of the software as agreed by both parties.
Deliverables
Completed Test Procedures and Results consistent with the approved SAT document
Siemens will provide a CD with User Manual, and System Administration Manual for ACTRA. A User Manual
will also be provided for SEPAC. As part of this task Siemens will also update the System Architecture report
to reflect the as -built conditions. The user's manual is geared towards the system operator and complements
the On -line Help facility. The document contains complete written instructions explaining the use of the user
interface and operation of the system. The controller data base screens are also described in full.
Task 11.4: Training
After the On -Site System Central Installation and Off -Line Testing task are completed, a three -day classroom
training session (24 hours) for up to ten (10) individuals will be held. Another 24 hours of training distributed
over three days will be provided after the completion of Communications Cut -Over task. These sessions will
cover all aspects of ACTRA and SEPAC operations. Training will be tailored to individuals with knowledge of
PC and Windows operations.
The training sessions will be conducted at the City TOC where ACTRA is located so that the installed system
can be used to demonstrate features.
Siemens ITS Page 6
SIEMENS
Deliverables:
Training Course
Training Materials
Budget
The budget for Task 11 is $40,606.
Maintenance Support and Warranty
Siemens provides a one -year warranty (free of charge) of the delivered software measured from the date of
acceptance of the software.
During this period, Siemens will also answer City's questions regarding system capability and operations.
Maintenance shall be conducted through telephone trouble- shooting and as- required, on -site examination of
the reported problem. Siemens will also offer to the City one free upgrade of the software during the one -year
warranty period. The work associated with the upgrade will be performed by the Siemens staff.