HomeMy WebLinkAboutTrans 2007-05-29 Item 3B - Final Acceptance - 2006 Overlay and Repair Program with Lakeside IndustriesTo: Mayor Mullet r. From: ¥`'Public Works Director Date: May 18, 2007 Subject: 2006 Overlay and Repair Program Project Completion and Acceptance ISSUE Accept contract as complete and authorize release of retainage bond. BACKGROUND The Notice to Proceed for Contract No. 06 -080 with Lakeside Industries of Covington, Washington, was issued September 11, 2006, for construction of the 2006 Overlay and Repair Program. This Project No. 06 -RWO1 provided repairs and overlays on the following roadway segments: S 144 St (51 Ave S to 1000 ft west, storm drain only. Deleted overlay to be done by Sound Transit) Macadam Rd (S 128 St to S 131 Pl) Southcenter Blvd (53 Ave S to Macadam Rd) S 130 St (E Marginal Wy to Macadam Rd) This contract was completed on March 30, 2007. Four change orders were issued during construction and are summarized on the attachment. Unit price overruns were primarily caused by the use of more traffic control labor than originally estimated. RECOMMENDATION INFORMATION MEMO Contract Award Amount Change Orders Unit Price Overruns Unit Price Underruns Sales Tax (N /A Rule 171) Total Amount Paid (incl. retainage bond) It is recommended that this contract be forwarded to the Tukwila City Council on the consent agenda for formal acceptance and authorize the release of the retainage, subject to the standard claim and lien release procedures. BG:ad attachments: Change Order Summary Notice of Completion of Public Works Contract (P:P ojacs\A. RW RS Projecesi06AW01 2006 Oveslay%CosuvttimWlFO MEMO Aaepnnce 2006 Overlay) 723,105.00 (65,863.00) 124,402.05 (20,409.00) 0.00 761,235.05 Attachment III.B. 9 Change Order No. I ITEM Change Order 1 CO1 Item 1 CO1 Item 2 /0 2006 OVERLAY PROGRAM Change Order Summary ADD DELETE Delete S 144 St overlay. Delete 4 junction boxes and add 4 communication vaults on Southcenter Blvd. CO1 Item 3 Replace discovered failing storm drain pipe. Change Order 2 CO2 Delete trenched conduits and add directionally drilled conduits on Southcenter Blvd. Change Order 3 CO3 On Macadam Rd, delete aluminum handrail and add black vinyl coated chain link fence. Change Order 4 C04 On Southcenter Blvd, reduce plan quantity of pavement grinding and reinforcing fabric. I JUS flFICATION To be overlayed by Sound Transit. Junction boxes not large enough for future fiber optic interconnect. Surface water was saturating subgrade. Less surface restoration and traffic control costs. Bid for aluminum was more than double the price of vinyl- coated chain link fence. Deleted bid item credit value: $78,765.00 Further field review found this quantity not necessary. Total COST (16,160.00) 6,514.00 20,000.00 10,055.00 (78, 765.00) (7,507.00) 65,863.00 From: State of Washington Department of Revenue 11A PO Box 47474 RE VENUE Olympia WA 98504 -7474 Contractor's Registration No. I No. g (UBI No.) 600 090 607 Description of Contract Lakeside Industries Contractor's Address Finance Approval Date 4/30/07 NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT City of Tukwila 6200 Southcenter Boulevard Tukwila, WA 98188 d ress of 1'ublic agency Notice is hereby given relative to the completion of contract or project described below 2006 Overlay and Repair Program (Project No. 06 -RWO1) 06 -080 Contractor's Name Telephone Number 18808 SE 257th Street, Covington, WA 98042 Date Work Commenced Date Work Completed 9/11/06 3/30/07 Surety or Bonding Company Travelers Casualty and Surety Company of America Agent's Address Parker, Smith Feek, Inc., 2233 112th Ave. NE, Bellevue, WA 98004 Contract Amount 723,105.00 Additions 124,402.05 Reductions 86,272.00 Sub -Total 761,235.05 Amount of Sales Tax Paid at 0.0 0.00 (If various rates apply, please send a breakdown) TOTAL 761,235.05 Comments: Retainage Bond was provided by Lakeside Industries. Rule 171 applies to sales tax. Signature Type or Print Name Diane Jaber Phone Number 206 433 -1871 'Department Use Only Assigned To Date Assigned Amount Disbursed Amount Retained Contract Number 206 343 7375 Date Work Accepted Liquidated Damages 0.00 761,235.05 0.00 TOTAL 761,235.05 isbursiiig =4 ce r The Disbursing Officer must complete and mail THREE copies of this notice to the Department of Revenue, PO Box 47474, Olympia, WA 98504 -7474, immediately after acceptance of the work done under this contract. NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of Department's certificate, and then only in accordance with said certificate. To inquire about the availability of this document in an alternate format for the visually impaired, please call (360) 753 -3217. Teletype (TTY) users please call (800) 451 -7985. You may also access tax information on our Internet home page at http: /dor.wa.gov. REV 31 0020e (6- 27 -01)