Loading...
HomeMy WebLinkAboutUtilities 2014-05-19 Item 2B - Bid Award - James W Fowler Company for East Marginal Way South Storm Pipe ReplacementCity of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Utilities Committee FROM: Bob Giberson, Public Works Director- By: Ryan Larson, Senior Program Engineer DATE: May 16, 2014 SUBJECT: East Marginal Way S Storm Pipe Replacement Project No. 91241206 BID AWARD ISSUE Award the bid for construction of the East Marginal Way S Storm Pipe Replacement Project. BACKGROUND On November 19, 2012, a large sinkhole was created by a break in a 30 -inch storm water pipe on East Marginal Way South just south of S 124th St. The pipe conveys flows from the east fork of Riverton Creek, as well as local drainage in the area near Group Health. The pipe system within the area was investigated and found to be undersized and failing in several locations requiring a complete replacement. ANALYSIS The City's Sensitive Area Ordinance requires that existing piped streams be day lighted where feasible. Day lighting Riverton Creek within this segment was determined to not be feasible because of the build out nature of the alignment. The Muckleshoot Tribe has requested that, as part of mitigation for this project, the City commits to completing the Riverton Creek Flap Gate Removal project within a five -year timeframe (which is an existing CIP project currently programed for construction in 2017). The East Marginal Way S Storm Pipe Replacement project was advertised for bids on April 29 and May 6, 2014. Five bids were received and opened on May 13, 2014. The bids were checked and tabulated. James W. Fowler Co. is the apparent low bidder with a bid of $2,058,782.30. The engineer's estimate was $2,485,995.00. James W. Fowler has successfully constructed other municipal projects, but has not specifically done work with the City of Tukwila. The total project amount includes required relocation work on Valley View Sewer and Water District 125 facilities. To reduce the impacts to the utilities and construction schedule, it is proposed that the City relocate these utilities with reimbursement expenses paid by the specific utilities through a separate agreement (which will be forthcoming to Council). The bid with contingency is over budget and the Surface Water's Ending Fund Balance will be utilized to supplement as this important project has a very limited time schedule due to the fish window associated with Riverton Creek. BUDGET AND BID SUMMARY (All amounts include sales tax.) Bid Results Estimate 2014 Budget Bid Amount $2,058,782.30 $2,485,995.00 $2,000,000.00 Valley View Sewer District 32,214.90 Water District 125 49,187.40 Excess Design Funds 10,000.00 Surface Water Ending Fund Balance 175,000.00 Contingency (10 %) 205,878.23 248,599.50 0.00 Total $2264,660.53 $2,734 594.50 $2,266,402.30 RECOMMENDATION Council is being asked to award the construction contract for the East Marginal Way S Storm Pipe Replacement project to James W. Fowler Co. in the amount of $2,058,782.30 and consider this item at the May 27, 2014 Committee of the Whole Meeting and subsequent June 2, 2014 Regular Meeting. Attachments: Bid Tabulations Contract Recommendation Letter W IPW EngIPROJECTS64- DR Projects\EMWS Emergency Storm Pipe Repair 11 -19 -12 (91241206)1Designpnfo Memo Bid Award.doc 15 16 CITY OF TUKWILA DEPARTMENT OF PUBLIC WORKS East Marginal Way S Storm Pipe Replacement - Project No. 91241206 Bid Tabulation - DRAFT IC G May 13, 2014 J Engineer's Estimate James W. Fowler Co. .oad Construction Northwest, In R.L. Alia Company Ceccanti Frank Coluccio Construction Co. No. Section No Item Qty Unit Unit Cost Total Cost Unit Cos ' Total Cost Unit Cost Total Cost Unit Cost Total. Cos 4 Unit Cost - Total Cost Unit Cost Total Cost SCHEDULE A- DOWNSTREAM AND INLET IMPROVEMENTS 4 ROADWAY Al 1 04 Minor Change 1 1 FA LS $ 30,000 00 $ 20,000.00 S 30 000.00. $ 20,000.00 $ 39.000 00. $ 2,200.00 $ 30,000 00 $ 2,200.00 $ 30. 000.00 $ 3,000.00 $ ._. 39,00090- $ 3,000.00 $ 39009 0 $ 7000.00 $ 30,000 00 $ 7,000.00 $._30 000.00. $ 5,000.00 .$ 30,000.90 $ 5,000.00 $ 39,000 90 $ 20,000.00 $ -: 30,000.00 $ 20,000.00 A2 1 -05 Roadway Surveying A3 1 -07 Resolution of Utility Conflicts 1 FA $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 A4 1 -07 SPCC Plan 1 LS $ 1,000.00 $ 1,000.00 $ 2,500.00 $ 2,500.00 $ 1,400.00 $ 1,400.00 $ 1,000.00 $ 1,000.00 $ 2,000.00 $ 2,000.00 $ 1,500.00 $ 1,500.00 AS 1 -09 Mobilization 1 LS $ 100,000.00 $ 100,000.00 $ 100,000.00 $ 100,000.00 $ 84,000.00 $ 84,000.00 $ 150,000.00 $ 150,000.00 $ 100,000.00 $ 100,000.00 $ 100,000.00 $ 100,000.00 A6 1 -10 Project Temporary Traffic Control 1 LS $ 100,000.00 $ 100,000.00 $ 21,000.00 $ 21,000.00 $75,000.00 $ 75,000.00 $ 50.000.00 $ 50,000.00 $ 30,000.00 $ 30,000.00 $ 65,000.00 $ 65,000.00 A7 2 -01 Clearing and Grubbing 1 LS $ 6,000.00 $ 6,000.00 $ 5,300.00 $ 5,300.00 $ 1,700.00 $ 1,700.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 10,000.00 $ 10,000.00 A8 2 -02 Pavement Removal Incl. Haul 1,550 SY $ 25.00 $ 38,750.00 $ 6.50 $ 10,075.00 $ 30.00 $ 46,500.00 $ 7.00 $ 10,850.00 $ 10.00 $ 15,500.00 $ 10.00 $ 15,500.00 AS 2 -02 Cement Conc. Sidewalk Removal Incl. Haul 120 SY $ 25.00 $ 3,000.00 $ 10.00 $ 1,200.00 $ 10.50 $ 1,260.00 $ 7.00 $ 840.00 $ 10.00 $ 1,200.00 $ 10.00 $ 1,200.00 A10 2 -02 Cement Conc. Curb Removal Incl. Haul 250 LF $ 10.00 $ 2,500.00 $ 5.00 $ 1,250.00 $ 5.50 $ 1,375.00 $ 3.00 $ 750.00 $ 2.00 $ 500.00 $ 7.50 $ 1,875.00 All 2 -02 Removal of Structure and Obstruction 1 LS $ 50,000.00 $ 50,000.00 $ 5,500.00 $ 5,500.00 $ 17,700.00 $ 17,700.00 $ 5,00090 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 45,000.00 $ 45,000.00 Al2 4 -04 Crushed Surfacing Top Course 350 TN $ 25.00 $ 8,750.00 $ 48.00 $ 16,800.00 $ 45.00 $ 15,750.00 $ 20.00 $ 7,000.00 $ 30.00 $ 10,500.00 $ 30.00 $ 10,500.00 A13 5 -04 HMA Cl. 1/2" PG 64 -22 700 TN $ 125.00 $ 87,500.00 $ 110.00 $ 77,000.00 $ 112.00 $ 78,400.00 S 125.00 $ 87,500.00 $ 110.00 $ 77,000.00 $ 115.00 $ 80,500.00 A14 8 -01 Erosion /Water Pollution Control 1 FA $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 A15 8 -01 Temporary Erosion and Sediment Control Facilities 1 LS $ 20,000.00 $ 20,000.00 $ 5,700.00 $ 5,700.00 $ 18,500.00 $ 18,500.00 $ 5,000.00 $ 5,000.00 $ 2,500.00 $ 2,500.00 $ 50,00090 $ 50,000.00 A 6 8 -04 Cement Conc. Traffic Curb and Gutter 200 LF $ 25.00 $ 5,000.00 $ 24.00 $ 4,800.00 $ 22.00 $ 4,400.00 $ 20.00 $ 4,000.00 $ 24.00 $ 4,800.00 $ 22.00 $ 4;400.00 SIDEWALK A17 8 -04 Extruded Curb, Type 6 30 LF $ 10.00 $ 300.00 $ 5.00 $ 150.00 $ 26.00 $ 780.00 $ 20.00 $ 600.00 $ 20.00 $ 600.00 $ 25.00 $ 750.00 A 8 8 -06 Cement Conc. Driveway Entrance Type 1 100 SY $ 50.00 $ 5,00090 $ 53.00 $ 5,300.00 $ 42.00 $ 4,200.00 $ 50.00 $ 5,000.00 $ 4090 $ 4,000.00 $ 55.00 $ 5,500.00 Al 8 -14 Cement Conc. Sidewalk 40 SY $ 35.00 $ 1,400.00 $ 43.00 $ 1,720.00 $ 42.00 $ 1,680.00 $ 40.00 $ 1,600.00 $ 24.00 $ 960.00 $ 45.00 $ 1,800.00 STORM DRAINAGE 70.00 $ 84,000.00 $ 55.00 $ 66,000.00 $ 55.00 $ 66,000.00 $ 5.50 $ 6,600.00 $ 50.00 $ 60,000.00 $ 38.00 $ 45,600.00 A20 2 -05 Excavation, Handling, and Disposal of Petroleum Impacted Soil - LOW 1,200 TN $ A21 2 -05 Excavation, Handling, and Disposal of Petroleum Impacted Soil - HIGH 500 TN $ 110.00 $ 55,000.00 $ 55.00 $ 27,500.00 $ 55.00 $ 27 500.00 $ 5.50 $ 2,750.00 $ 50.00 $ 25,000.00 $ 70.00 $ 35,000.00 A22 2 -05 Excavation, Handling, and Disposal of Cement Kiln Dust - Subtitle "D" 300 TN $ 130.00 $ 39,000.00 $ 55.00 $ 16,500.00 $ 55.00 $ 16,500.00 $ 5.50 $ 1,650.00 $ 80.00 $ 24,000.00 $ 55.00 $ 16,500.00 A23 2 -08 Dewatering 1 LS $ 150,000.00 $ 150,000.00 $ 86,000.00 $ 86,000.00 $ 87,000.00 $ 87,000.00 $ 70,000.00 $ 70,000.00 $ 65,000.00 $ 65,000.00 $ 170,000.00 $ 170,000.00 A24 2 -08 Contaminated Groundwater Treatment 1 FA $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 A25 2 -08 Abandon Monitoring Well 2 EA $ 1,500.00 $ 3,000.00 $ 1,300.00 $ 2,600.00 $ 1,600.00 $ 3,200.00 $ 500.00 $ 1,000.00 $ 1,250.00 $ 2,500.00 $ 3,500.00 $ 7,000.00 A26 2 -12 Construction Geotextile for Separation 1,900 SY $ 10.00 $ 19,000.00 $ 1.00 $ 1,900.00 $ 225 $ 4,275.00 $ 6.00 $ 11,400.00 $ 2.00 $ 3,800.00 $ 3.00 $ 5,700.00 A27 7 -02 Beveled End Sect. with Debris Barrier 42 In. Diam. 1 LS $ 10,000.00 $ 10,000.00 $ 6,000.00 $ 6,000.00 $ 3,000.00 $ 3,000.00 $ 3,000.00 $ 3,000.00 $ 2,000.00 $ 2,000.00 $ 15,000.00 $ 15,000.00 A28 7 -04 CPEP Storm Sewer Pipe 12 In. Diam. 160 LF $ 60.00 $ 9,600.00 $ 115.00 $ 18,400.00 $ 74.25 $ 11,880.00 $ 140.00 $ 22,400.00 $ 150.00 $ 24,000.00 $ 65.00 $ 10,400.00 A29 7 -04 CPEP Storm Sewer Pipe 30 In. Diem. 15 LF $ 140.00 $ 2,100.00 $ 215.00 $ 3,225.00 $ 219.00 $ 3,285.00 $ 300.00 $ 4,500.00 $ 300.00 $ 4,500.00 $ 130.00 $ 1,950.00 A30 7 -04 CPEP Storm Sewer Pipe 42 In. Diam. 980 LF $ 180.00 $ 176,400.00 $ 235.00 $ 230,300.00 $ 245.00 $ 240,100.00 $ 521.00 $ 510,580.00 $ 475.00 $ 465,500.00 $ 195.00 $ 191,100.00 A31 7 -04 Class III Reinf. Conc. Storm Sewer Pipe 42 In. Diam. 30 LF $ 300.00 $ 9,000.00 $ 280.00 $ 8,400.00 S 300.00 $ 9,000.00 $ 500.00 $ 15,000.00 $ 500.00 $ 15,000.00 $ 275.00 $ 8,250.00 A32 7 -04 Ductile Iron Storm Sewer Pipe 42 In. Diam. 20 LF $ 400.00 $ 8,000.00 $ 420.00 $ 8,400.00 $ 470.00 $ 9,400.00 $ 500.00 $ 10,000.00 $ 500.00 $ 10,000.00 $ 425.00 $ 8,500.00 A33 7 -04 Remove /Abandon Existing Storm Sewer Pipe 450 LF $ 20.00 $ 9,000.00 $ 50.00 $ 22,500.00 $ 45.00 $ 20,250.00 $ 10.00 $ 4,500.00 $ 16.00 $ 7,200.00 $ 20.00 $ 9,000.00 A34 7 -05 Connection to Drainage Pipe 12 EA $ 1,000.00 $ 12,000.00 $ 600.00 $ 7,200.00 $ 3,500.00 $ 42,000.00 $ 500.00 $ 6,000.00 $ 2,500.00 $ 30,000.00 $ 5,500.00 $ 66,000.00 A35 7 -05 Concrete Inlet 1 EA $ 1,079.00 $ 1,079.00 $ 1,300.00 $ 1,300.00 $ 1,000.00 $ 1,000.00 $ 700.00 $ 700.00 $ 1,000.00 $ 1,000.00 $ 1,250.00 $ 1,250.00 A36 7 -05 Catch Basin Type 2 84 In. Diam. 2 EA $ 8,000.00 $ 16,000.00 $ 8,300.00 $ 16,600.00 $ 14,000.00 $ 28,000.00 $ 9,000.00 $ 18,000.00 $ 14,000.00 $ 28;000.00 $ 7,500.00 $ 15,000.00 A37 7 -05 Manhole 48 In. Diam. Type 3 3 EA $ 4,000.00 $ 12,000.00 $ 3,800.00 $ 11,400.00 $ 4,800.00 $ 14,400.00 $ 3,000.00 $ 9,000.00 $ 5,000.00 $ 15,000.00 $ 3,200.00 $ 9,600.00 A38 7 -05 Manhole 60 In. Diam. Type 3 1 EA $ 5,500.00 $ 5,500.00 $ 5,100.00 $ 5,100.00 $ 6,500.00 $ 6,500.00 $ 4,000.00 $ 4,000.00 $ 7,000.00 5 7,000.00 $ 5,500.00 $ 5,500.00 A39 7 -05 Manhole 72 In. Diam. Type 3 4 EA $ 7,000.00 $ 28,000.00 $ 10,000.00 $ 40,000.00 $ 10,300.00 $ 41,200.00 $ 5,000.00 $ 20,000.00 $ 10,000.00 $ 40,000.00 $ 7,500.00 $ 30,000.00 A40 7 -05 Manhole 84 In. Diam. Type 3 4 EA $ 8,000.00 $ 32,000.00 $ 11,000.00 $ 44,000.00 $ 13,300.00 $ 53,200.00 $ 10,000.00 $ 40,000.00 $ 14,000.00 $ 56,000.00 $ 12,500.00 $ 50,000.00 A41 7 -05 Abandon Existing Manhole 1 EA $ 1,500.00 $ 1,500.00 $ 1,950.00 $ 1,950.00 $ 1,400.00 $ 1,400.00 $ 100.00 $ 100.00 $ 500.00 $ 500.00 $ 5,000.00 $ 5,000.00 A42 7 -05 Storm Drain Marker 8 EA $ 50.00 $ 400.00 $ 80.00 $ 640.00 $ 45.00 $ 360.00 $ 20.00 $ 160.00 $ 50.00 $ 400.00 $ 65.00 $ 520.00 A43 7 -06 Pothole Existing Utilities 10 EA $ 700.00 $ 7,000.00 $ 710.00 $ 7,100.00 $ 800.00 $ 8,000.00 $ 500.00 $ 5,000.00 $ 500.00 $ 5,000.00 $ 1,000.00 $ 10,000.00 A44 7 -08 Bedrock Excavation Incl. Haul 50 CY $ 200.00 $ 10,000.00 $ 80.00 $ 4,000.00 $ 115.00 $ 5,750.00 $ 50.00 $ 2,500.00 $ 80.00 $ 4,000.00 $ 100.00 $ 5,000.00 A45 7 -08 Shoring or Extra Excavation Class B 31,000 SF $ 1.00 $ 31,000.00 $ 0.35 $ 10,850.00 $ 0.50 $ 15,500.00 $ 1.00 $ 31,000.00 $ 0.10 $ 3,100.00 $ 0.50 $ 15,500.00 A46 7 -08 Gravel Backfill for Foundations 400 CY $ 25.00 $ 10,000.00 $ 85.00 $ 34,000.00 $ 42.00 $ 16,800.00 $ 30.00 $ 12,000.00 $ 24.00 $ 9,600.00 $ 35.00 $ 14,000.00 A47 7 -08 Select Trench Backfill 3,200 TN $ 25.00 $ 80,000.00 $ 20.00 $ 64,000.00 $ 14.75 $ 47,200.00 $ 25.00 $ 80,00090 $ 24.00 $ 76,800.00 $ 20.00 $ 64,000.00 A48 7 -20 Temporary Stormwater Bypass System 1 LS $ 15,000.00 $ 15,000.00 $ 6,500.00 $ 6,500.00 $ 19,200.00 $ 19,200.00 $ 5,000.00 $ 5,000.00 $ 20,000.00 $ 20,000.00 $ 12,000.00 $ 12,000.00 A49 8 -15 Hand Placed Rip Rap 25 TN $ 125.00 $ 3,125.00 $ 120.00 $ 3,000.00 $ 65.00 $ 1,625.00 $ 50.00 $ 1,250.00 $ 40.00 $ 1,000.00 $ 105.00 $ 2,625.00 CITY OF TUKWILA DEPARTMENT OF PUBLIC WORKS East Marginal Way S Storm Pipe Replacement - Project No. 91241206 Bid Tabulation - DRAFT May 3, 2014 Engineers Estimate James W Fowler Co. ,oad Construction Northwest, In R.L. Alia Company Ceccanti Frank Coluccio Construction Co. No. Section No. Item Qty Unit Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost c Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost A50 8 -15 Quarry Spats 25 TN $ 10000 $ 250000 $ 45.00 $ 1,125.00 $ 65.00 $... 1,625.00 $ 50.00 $ 1,250.00 $ 40.00 $ 1,000.00 $ 65.00 $ 1,625.00 TRAFFIC SIGNALS A51 8 -20 Traffic Signal Modifications at E Marginal Way S & S 124th Street 1 I LS $ 9,200.00 $ 9,200.00 $ 7,700 00 I $ 7 700.00 11 $ 40,000 00 $ 40,000 00 $ 10 000.00 $ 10,000.00 $ 10,000.00 I $ 10,00a00 $ 25,000 00 I $ 25 000.00 TRAFFIC CONTROL DEVICES A52 8 -09 Raised Pavement Marker Type 1 11 HUND $ 250.00 $ 2,750.00 $ 320.00 $ 3,520.00 $ 300.00 $ 3,300.00 $ 275.00 $ 3,025.00 $ 300 00 $ 3,300.00 $ 295.00 $ 3,245.00 A53 8 -09 Raised Pavement Marker Type 2 1 HUND $ 350.00 $ 350.00 $ 425.00 $ 425.00 $ 625.00 $ 625.00 $ 400.00 $ 400.00 $ 400.00 $ 400.00 $ 425.00 $ 425.00 A54 8 -21 Permanent Signing 1 LS $ 1,500.00 $ 1,500.00 $ 5,300.00 $ 5,300.00 $ 1,500.00 $ 1,500.00 $ 5,000.00 $ 5,000.00 $ 4,000.00 $ 4,000.00 $ 5,000.00 $ 5,000.00 A55 8 -22 Plastic Traffic Arrow 6 EA $ 150.00 $ 900.00 $ 200.00 $ 1,200.00 $ 150.00 $ 900.00 $ 100.00 $ 600.00 $ 100.00 $ 600.00 $ 105.00 $ 630.00 A56 8 -22 Plastic Bicycle Lane Symbol 2 EA $ 150.00 $ 300.00 $ 160.00 $ 320.00 $ 150.00 $ 300.00 $ 150.00 $ 300.00 $ 150.00 $ 300.00 $ 175.00 $ 350.00 A57 8 -22 Plastic Wide Lane Line 150 LF $ 2.00 $ 300.00 $ 4.00 $ 600.00 $ 2.00 $ 300.00 $ 2.50 $ 375.00 $ 2.00 $ 300.00 $ 2.50 $ 375.00 ROADSIDE DEVELOPMENT A58 8 -01 Topsoil /Fine Compost 15 CY $ 45.00 $ 675.00 $ 65.00 $ 975.00 $ 55.00 $ 825.00 $ 30.00 $ 450 00 $ 40.00 $ 600.00 $ 50.00 $ 750.00 A59 8 -01 Bark or Wood Chip Mulch 15 CY $ 45.00 $ 675.00 $ 44.00 $ 660.00 $ 55.00 $ 825.00 $ 30.00 $ 450.00 $ 40.00 $ 600.00 $ 50.00 $ 750.00 A60 8 -01 Hydroseed 60 SY $ 4.00 $ 240.00 $ 11.00 $ 660.00 $ 7.00 $ 420.00 $ 10.00 $ 600.00 $ 2.00 $ 120.00 $ 20.00 $ 1,200.00 A61 8 -01 High Visibility Fence 700 LF $ 4.00 $ 2,800.00 $ 4.00 $ 2,800.00 $ 3.00 $ 2,100.00 $ 5.00 $ 3,500.00 $ 2.00 $ 1,400.00 $ 3.00 $ 2,100.00 A62 8 -02 Property Restoration 1 FA $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 A63 8 -12 Chain Link Fence Type 3 210 LF $ 80.00 $ 16,800.00 $ 45.00 $ 9,450.00 $ 40.00 $ 8,400.00 $ 40.00 $ 8,400.00 $ 35.00 $ 7,350.00 $ 45.00 $ 9,450.00 A64 8 -12 Double 14 Ft. Chain Link Gate 1 EA $ 800.00 $ 800.00 $ 1,100.00 $ 1,100.00 $ 1,200.00 $ 1,200.00 $ 1,500.00 $ 1,500.00 $ 1,200.00 $ 1,200.00 $ 1,250.00 $ 1,250.00 A65 8 -12 Sing!, 6 Ft. Chain Liu'. -7 ^`.. 1 EA $ 500.00 $ 500.00 $ 450.00 $ 450.00 $ 1,375.00 $ 1,375.00 $ 1,500.00 $ 1,500.00 $ 500.00 $ 500.00 $ 550.00 $ 550.00 FRANCHISE UTILITY ITEMS A66 8-19 ITempo ary Utility Pole Support 2 EA $ 3,000 00 $ 6,000.00 $ 5,300.00 $ 10,600.00 $ 4,000.00 $ 8,000.00 $ 1,000.00 $ 2,000.00 $ 800.00 $ 1,600.00 $ 2,200.00 $ 4,400.00 ESTIMATED CONSTRUCTION COST SUBTOTAL (SCHEDULE A) $ 1,429,194.00 $ 1,157,745.00 $ 1,325,865,00 $ 1,373,580.00 $ 1,398,730:00 $ 1 395,62000 SCHEDULE B - UPSTREAM IMPROVEMENTS ROADWAY $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 B1 1 -04 Minor Change 1 FA $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 B2 1 -05 Roadway Surveying 1 LS $ 5,000.00 $ 5,000.00 $ 2,000.00 $ 2,000.00 $ 2,100.00 $ 2,100.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 20,000.00 $ 20,000.00 B3 1 -07 Resolution of Utility Conflicts 1 FA $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 B4 1 -09 Mobilization 1 LS $ 40,000.00 $ 40,000.00 $ 64,000.00 $ 64,000.00 $ 36,800.00 $ 36,800.00 $ 20,000.00 $ 20,000.00 $ 60,000.00 $ 60,000.00 $ 40,000.00 $ 40,000.00 B5 1 -10 Project Temporary Traffic Control 1 LS $ 65,000.00 $ 65,000.00 $ 10,000.00 $ 10,000.00 $ 18,700.00 $ 18,700.00 $ 20,000.00 $ 20,000.00 $ 30,000.00 $ 30,000.00 $ 35,000.00 $ 35,000.00 66 2 -01 Clearing and Grubbing 1 LS $ 8,000.00 $ 8,000.00 $ 5,500.00 $ 5,500.00 $ 1,250.00 $ 1,250.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 7,500.00 $ 7,500.00 B7 2 -02 Pavement Removal Incl. Haul 450 SY $ 25.00 $ 11,250.00 $ 6.50 $ 2,925.00 $ 35.00 $ 15,750.00 $ 7.00 $ 3,150.00 $ 10.00 $ 4,500.00 $ 10.00 $ 4,500.00 B8 2 -02 Cement Conc. Sidewalk Removal Incl. Haul 360 SY $ 25.00 $ 9,000.00 $ 10.00 $ 3,600.00 $ 10.50 $ 3,780.00 $ 7.00 $ 2,520.00 $ 10.00 $ 3,600.00 $ 10.00 $ 3,600.00 B9 2 -02 Cement Conc. Curb Removal Incl. Haul 620 LF $ 10.00 $ 6,200.00 $ 5.00 $ 3,100.00 $ 5.50 $ 3,410.00 $ 3.00 $ 1,860.00 $ 2.00 $ 1,240.00 $ 7.50 $ 4,650.00 B10 2 -02 Removal of Structure and Obstruction 1 LS $ 25,000.00 $ 25,000.00 $ 5,500.00 $ 5,500.00 $ 12,000.00 $ 12,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 35,000.00 $ 35,000.00 B11 4 -04 Crushed Surfacing Top Course 200 TN $ 25.00 $ 5,000.00 $ 50.00 $ 10,000.00 $ 45.00 $ 9,000.00 $ 20.00 $ 4,000.00 $ 30.00 $ 6,000.00 $ 30.00 $ 6,000.00 B12 5 -04 HMA Cl. 1/2" PG 64 -22 270 TN $ 125.00 $ 33,750.00 $ 110.00 $ 29,700.00 $ 112.00 $ 30,240.00 $ 125.00 $ 33,750.00 $ 110.00 $ 29,700.00 $ 115.00 $ 31,050.00 B13 8 -01 Erosion /Water Pollution Control 1 FA $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 B14 8 -01 Temporary Erosion and Sediment Control Facilities 1 LS $ 10,000.00 $ 10,000.00 $ 6,000.00 $ 6,000.00 $ 9,500.00 $ 9,500.00 $ 4,000.00 $ 4,000.00 $ 2,500.00 $ 2,500.00 $ 38,500.00 $ 38,500.00 B15 8 -04 Cement Conc. Traffic Curb and Gutter 620 LF $ 25.00 $ 15,500.00 $ 24.00 $ 14,880.00 $ 22.00 $ 13,640.00 $ 20.00 $ 12,400.00 $ 24.00 $ 14,880.00 $ 22.00 $ 13,640.00 SIDEWALK 016 8 -04 Cement Conc. Pedestrian Curb 40 LF $ 20.00 $ 800.00 $ 20 00 $ 800.00 $ 35.00 $ 1,400.00 $ 20.00 $ 800.00 $ 24.00 $ 960.00 $ 22.00 $ 880.00 B17 8 -04 Extruded Curb, Type 6 30 LF $ 10.00 $ 300.00 $ 5.00 $ 150.00 $ 25.00 $ 750.00 $ 20.00 $ 600.00 $ 20.00 $ 600.00 $ 25.00 $ 750.00 B18 8 -06 Cement Conc. Driveway Entrance Type 1 500 SY $ 50.00 $ 25,000.00 $ 43.00 $ 21,500.00 $ 42.00 $ 21,000.00 $ 40.00 $ 20,000.00 $ 40.00 $ 20,000.00 $ 55.00 $ 27,500.00 B19 8 -14 Cement Conc. Sidewalk 2,500 SY $ 35.00 $ 87,500.00 $ 30.00 $ 75,000.00 $ 28.00 $ 70,000.00 $ 30.00 $ 75,000.00 $ 24.00 $ 60,000.00 $ 30.00 $ 75,000 00 620 8 -14 Cement Conc. Curb Ramp Type Parallel A 2 EA $ 2,000,00 $ 4,000.00 $ 1,600.00 $ 3,200.00 $ 1,150.00 $ 2,300.00 $ 1,500.00 $ 3,000.00 $ 2,200.00 $ 4400.00 $ 1,500.00 $ 3,000.00 EC, CITY OF TUKWILA DEPARTMENT OF PUBLIC WORKS East Marginal Way S Storm Pipe Replacement - Project No. 91241206 Bid Tabulation - DRAFT KPG May 13, 2014 I Engineer's Estimate James W. Fowler Co. ,oad Construction Northwest, In R.L. Alia Company Ceccanti Frank Coluccio Construction Co. No. Section No. Item Qty Unit Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost STORM DRAINAGE B21 2 -05 Excavation, Handling, and Disposal of Petroleum Impacted Soil - LOW 100 TN $ 70.00 $ 7,000.00 5 55.00 $ 5,500.00 $ 55.00 $ 5 500 00 $ 5.50 $ 550.00 $ 50.00 $ 5,000.00 $ 38.00 $ 3,800.00 B22 2 -05 Excavation Handling, and Disposal of Petroleum Impacted Soil - HIGH 100 TN $ 110.00 $ 11,000.00 $ 55.00 $ 5,500.00 $ 55.00 $ 5,500.00 $ 5.50 $ 550.00 $ 50.00 $ 5,000.00 $ 70.00 $ 7,000.00 B23 2 -05 Excavation, Handling, and Disposal of Cement Kiln Dust - Subtitle "D" 850 TN $ 130.00 $ 110,500.00 $ 55.00 $ 46,750.00 $ 55.00 $ 46,750.00 $ 5.50 $ 4,675.00 $ 80.00 $ 68,000.00 $ 55.00 $ 46,750.00 B24 2 -08 Dewatering 1 LS $ 65,000.00 $ 65,000.00 $ 65,000.00 $ 65,000.00 $ 30,400.00 $ 30,400.00 $ 30,000.00 $ 30,000.00 $ 50,000.00 $ 50,000.00 $ 65,000.00 $ 65,000.00 625 2 -08 Contaminated Groundwater Treatment 1 FA $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 B26 2 -12 Construction Geotextile for Separation 1,000 SY $ 10.00 $ 10,000.00 $ 1.00 $ 1,000.00 $ 225 $ 2,250.00 $ 6.00 $ 6,000.00 $ 2.00 $ 2,000.00 $ 3.00 $ 3,000.00 B27 7 -04 CPEP Storm Sewer Pipe 12 In. Diam. 20 LF $ 60.00 $ 1,200.00 $ 115.00 $ 2,300.00 $ 75.00 $ 1,500.00 $ 140.00 $ 2,800.00 $ 150.00 $ 3,000.00 $ 65.00 $ 1,300.00 B28 7 -04 CPEP Storm Sewer Pipe 30 In. Diam. 20 LF $ 140.00 $ 2,800.00 $ 215.00 $ 4,300.00 $ 219.00 $ 4,380.00 $ 240.00 $ 4,800.00 $ 300.00 $ 6,000.00 $ 130.00 $ 2,600.00 B29 7 -04 CPEP Storm Sewer Pipe 42 In. Diam. 580 LF $ 180.00 $ 104,400.00 $ 235.00 $ 136,300.00 $ 248.00 $ 143,840.00 $ 521.00 $ 302,180.00 $ 475.00 $ 275,500.00 $ 195.00 $ 113,100.00 B30 7 -04 Remove /Abandon Existing Storm Sewer Pipe 750 LF $ 20.00 $ 15,000.00 $ 50.00 $ 37,500.00 $ 23.00 $ 17,250.00 $ 10.00 $ 7,500.00 $ 16.00 $ 12,000.00 $ 20.00 $ 15,000.00 B31 7 -05 Connection to Drainage Structure 1 EA $ 1,200.00 $ 1,200.00 $ 600.00 $ 600.00 $ 1,100.00 $ 1,100.00 $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,500.00 $ 1,500.00 B32 7 -05 Connection to Drainage Pipe 4 EA $ 1,000.00 $ 4,000.00 $ 600.00 $ 2,400.00 $ 900.00 $ 3,600.00 $ 500.00 $ 2,000.00 $ 2,500.00 $ 10,000.00 $ 7,500.00 $ 30,000.00 B33 7 -05 Catch Basin Type 1 1 EA $ 1,200.00 $ 1,200.00 $ 1,300.00 $ 1,300.00 $ 1,900.00 $ 1,900.00 $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,400.00 $ 1,400.00 B34 7 -05 Manhole 54 In. Diam. Type 3 1 EA $ 5,500.00 $ 5,500.00 $ 5,800.00 $ 5,800.00 $ 6,200.00 $ 6,200.00 $ 3,500.00 $ 3,500.00 $ 6,000.00 $ 6,000.00 $ 5,500.00 $ 5,500.00 B35 7 -05 Manhole 72 In. Diam. Type 3 1 EA $ 7,000.00 $ 7,000.00 $ 9,100.00 $ 9,100.00 $ 10,300.00 $ 10,300.00 $ 5,000.00 $ 5,000.00 $ 10,000.00 $ 10,000.00 $ 7,500.00 $ 7,500.00 B36 7 -05 Manhole 84 In. Diam. Type 3 4 EA $ 8,000.00 $ 32,000.00 $ 11,000.00 $ 44,000.00 $ 13,000.00 $ 52,000.00 $ 10,000.00 $ 40,000.00 $ 14,000.00 $ 56,000.00 $ 12,500.00 $ 50,000.00 B37 7 -05 Abandon Existing Manhole 1 EA $ 1,500.00 $ 1,500.00 $ 2,000.00 $ 2,000.00 $ 500.00 $ 500.00 $ 100.00 $ 100.00 $ 500.00 $ 500.00 $ 4,500.00 $ 4,500.00 B38 7 -05 Storm Drain Marker 6 EA $ 50.00 $ 300.00 $ 80.00 $ 480.00 $ 45.00 $ 270.00 $ 20.00 $ 120.00 $ 50.00 $ 300.00 $ 65.00 $ 390.00 B39 7 -06 Pothole Existing Utilities 5 EA $ 700.00 $ 3,500.00 $ 710.00 $ 3,550.00 $ 800.00 $ 4,000.00 $ 500.00 $ 2,500.00 $ 500.00 $ 2,500.00 $ 1,250.00 $ 6,250.00 B40 7 -08 Shoring or Extra Excavation Class B 17,500 SF $ 1.00 $ 17,500.00 $ 0.75 $ 13,125.00 $ 0.50 $ 8,750.00 $ 1.00 $ 17,500.00 $ 0.10 $ 1,750.00 $ 0.50 $ 8,750.00 641 7 -08 Gravel Backfill for Foundations 250 CY $ 25.00 $ 6,250.00 $ 85.00 $ 21,250,00 $ 43.00 $ 10,750.00 $ 30.00 $ 7,500.00 $ 24.00 $ 6,000.00 $ 20.00 $ 5,000.00 B42 7 -08 Select Trench Backfill 1,950 TN $ 25.00 $ 48,750.00 $ 19.00 $ 37,050.00 $ 14.75 $ 28,762.50 $ 25.00 $ 48,750.00 $ 24.00 $ 46,800.00 $ 20.00 $ 39,000.00 B43 7 -20 Temporary Stormwater Bypass System 1 LS $ 10,000 00 $ 10000 00 $ 7,000.00 $ 7,000.00 $ 13,000.00 $ 13 000.00 $ 5,000.00 $ 5,000.00 $ 20,000.00 $ 20,000.00 $ 12,500.00 $ 12 500.00 TRAFFIC CONTROL DEVICES B44 8 -09 Raised Pavement Marker Type 1 2 HUND $ 250.00 $ 500.00 $ 325.00 $ 650.00 $ 300 00 $ 600.00 $ 275.00 $ 550.00 $ 300.00 $ 600.00 $ 295.00 $ 590.00 B45 8 -09 Raised Pavement Marker Type 2 1 HUND $ 350.00 $ 350.00 $ 425.00 $ 425.00 $ 625.00 $ 625.00 $ 400.00 $ 400.00 $ 400.00 $ 400.00 $ 425.00 $ 425.00 B46 8 -21 Permanent Signing 1 LS $ 1,200.00 $ 1,200.00 $ 5,300.00 $ 5,300.00 $ 1,500.00 $ 1,500.00 $ 2,000.00 $ 2,000.00 $ 4,000.00 $ 4,000.00 $ 5,000.00 $ 5,000.00 B47 8 -22 Plastic Traffic Arrow 6 EA $ 150.00 $ 900.00 $ 200.00 $ 1,200.00 $ 150.00 $ 900.00 $ 100.00 $ 600.00 $ 100.00 $ 600.00 $ 105.00 $ 630.00 B48 8 -22 Plastic Stop And Crosswalk Line 130 LF $ 10.00 $ 1,300 00 $ 7.50 $ 975.00 $ 6.00 $ 780.00 $ 4.00 $ 520.00 $ 4.00 $ 520.00 $ 5.00 $ 650.00 849 8 -22 Plastic Bicycle Lane Symbol 2 EA $ 150.00 $ 300.00 $ 160.00 $ 320.00 $ 150.00 $ 300.00 $ 150.00 $ 300.00 $ 150.00 $ 300.00 $ 185.00 $ 370.00 B50 8 -22 Plastic Wide Lane Line 600 LF $ 2.00 $ 1,200.00 $ 4.00 $ 2,400.00 $ 2.00 $ 1,200.00 $ 2.50 $ 1,500.00 $ 2.00 $ 1,200.00 $ 2.50 $ 1,500.00 ROADSIDE DEVELOPMENT B51 8 -01 Topsoil /Fine Compost 30 CY $ 45.00 $ 1,350.00 $ 65.00 $ 1,950.00 $ 55.00 $ 1,650.00 $ 30.00 $ 900.00 $ 40 00 $ 1,200.00 $ 50.00 $ 1,500.00 B52 8 -01 Bark or Wood Chip Mulch 40 CY $ 45.00 $ 1,800.00 $ 44.00 $ 1,760.00 $ 55.00 $ 2,200.00 $ 30.00 $ 1,200.00 $ 40.00 $ 1,600.00 $ 50.00 $ 2,000.00 B53 8 -01 Hydroseed 170 SY $ 4.00 $ 680.00 $ 11.00 $ 1,870.00 $ 5.00 $ 850.00 $ 10.00 $ 1,700.00 $ 2.00 $ 340.00 $ 18.00 $ 3,060.00 B54 8 -01 High Visibility Fence 500 LF $ 4.00 $ 2,000.00 $ 3.25 $ 1,625.00 $ 3.00 $ 1,500.00 $ 5.00 $ 2,500.00 $ 2.00 $ 1,000.00 $ 3.00 $ 1,500.00 B55 8 -02 Property Restoration 1 FA $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 FRANCHISE UTILITY ITEMS B56 8 19 Temporary Utility Pole Support 3 EA $ 3 000.00 $ 9,000 00 $ 5,500 00 $ 16 500.00 $ 4,000 00 $ 12,000 00 $ 1 000.00 $ 3,000 00 $ 800 00 $ 2,400.00 IHI $ 2 500.00 $ 7,500 00 ESTIMATED CONSTRUCTION COST SUBTOTAL (SCHEDULE Bj $ 912,480.00 $ 818,635.00 $ 749,227.50 ` $ 799,275.00 $ 930,890.00 H $ 876,135.00 CITY OF TUKWILA DEPARTMENT OF PUBLIC WORKS East Marginal Way S Storm Pipe Replacement - Project No. 91241206 Bid Tabulation - DRAFT May 13, 2014 J Engineer's Estimate James W. Fowler Co. ,oad Construction Northwest, In R Alia Company Ceccanti Frank Coluccio Construction Co. G. Section No It em Qty Unit '.., Uni4 Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost SCHEDULE C - SANITARY SEWER RELOCATION Cl 1 -04 Minor Change or Sanitary Sewer Relocation 1 FA $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ loaoo.go $ 10,000.00 $ 10,000.00 $ 10.000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 C2 1 -09 Mobilization 1 LS $ 5,000.00 $ 5,000.00 $ 2,500.00 $ 2,500.00 $ 2,000.00 $ 2,000.00 $ 1,000.00 $ 1,000.00 $ 500.00 $ 500.00 $ 5,500.00 $ 5,500.00 C3 7 -06 Pothole Existing Utilities 2 EA $ 700.00 $ 1,400.00 $ 710.00 $ 1,420.00 $ 800.00 $ 1,600.00 $ 500.00 $ 1,000.00 $ 500.00 $ 1,000.00 $ 1,250.00 2,500.00 C4 7 -08 Shoring or Extra Excavation Class B 1,000 SF $ 1.00 $ 1,000.00 $ 0.50 $ 500.00 $ 0.50 $ 500.00 $ 1.00 $ 1,000.00 $ 0.10 $ 100.00 $ 1.00 _$ $ 1,000.00 C5 7 -17 Sanitary Sewer Force Main Modifications, Complete 1 LS $ 45,000.00 $ 45,000.00 $ 15,000.00 $ 15,000.00 $ 26,700.00 $ 26,700.00 $ 30,000.00 $ 30,000.00 $ 12,000.00 $ 12,000.00 $ 44,000.00 $ 44,000.00 ESTIMATED CONSTRUCTION COST SUBTOTAL (SCHEDULE C) WSST (9.5 %) TOTAL (SCHEDULE C) $ 62,400.00 S 5,928.00 $ 29,420.00 $ 2,794.90 $ 40,800.00 $ 3,876:00 $ 43,000 00 $ 4,085.00 '. $ 23,600.00 $ 2,242.00 $ 63,000.00 $ 5,985.00 $ 68,328.00 $ 32,214.90 $ 44,676,00 $ .47,085,00 $ 25,842.00 $ 68,985.00. SCHEDULE D - WATER MAIN RELOCATION $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 Dt 1 -04 Minor Change for Water Main Relocation 1 FA $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 D2 1 -09 Mobilization 1 LS $ 6,000.00 $ 6,000.00 $ 2,500.00 $ 2,500.00 $ 2,000.00 $ 2,000.00 $ 1,000.00 $ 1,000.00 $ 500.00 $ 500.00 $ 5,500.00 $ 5,500.00 D3 7 -06 Pothole Existing Utilities 2 EA $ 700.00 $ 1,400.00 $ 710.00 $ 1,420.00 $ 800.00 $ 1.600.00 $ 500.00 $ 1,000.00 $ 500.00 $ 1,000.00 $ 1,250.00 $ 2,500.00 D4 7 -08 Shoring or Extra Excavation Class B 2,000 SF $ 1.00 $ 2,000.00 $ 0.50 $ 1,000.00 $ 0.50 $ 1,000.00 $ 1.00 $ 2,000.00 $ 0.10 $ 200.00 $ 1.00 $ 2,000.00 D5 7 -17 Water Main Modifications, Complete 1 LS $ 50,000.00 $ 50,000.00 $ 30,000.00 $ 30,000.00 $ 33,500.00 $ 33,500.00 $ 20,000.00 $ 20,000.00 $ 17,000.00 $ 17,000.00 $ 48,000.00 $ 48,000.00 ESTIMATED CONSTRUCTION COST SUBTOTAL (SCHEDULED) WSST (15 %) TOTAL (SCHEDULE D) $ 69,400.00 $ 6,593.00 ` $ 44,920.00 $ 4,267.40 $ r 48,100.00 $ 4,569.50 $ 34,000.00 $ 3,230.00 $ 28,700.00 $ 2,726.50 $ 68,000.00 $ 6,460.00 $ 75,99100 $ 49,187.40 $ 52,669.50. $ 37,230.00 $ 31,426.50 $ 74,460.00 ESTIMATED CONSTRUCTION COST SUMMARY ESTIMATED CONSTRUCTION COST TOTAL (SCHEDULE A) $ 1,421194.00 $ 1,157,745.00 $.1,325,865.00 $ 1,373,580,00 $ 1,398,730.00 $ 1,395,620.00 ESTIMATED CONSTRUCTION COST SUBTOTAL (SCHEDULE B) $ 912,480.00 $ 819,635.00 $ 749,227,50' $ 799,275.00 $ 930,890.00 $ 876,135,00. ESTIMATED CONSTRUCTION COST TOTAL (SCHEDULE C) $ 68,328.00 -, $ 32,214.90 $ ' 44,676.00 $ 47,085.00 $ 25,842.00 $ 68,985.00 ESTIMATED CONSTRUCTION COST TOTAL (SCHEDULE D) $ 75,993 00 $ 49,187.40 $ 52,669.50: $ 37,230.00 $ 31,426,50 $ 74,460.00 ESTI A OT4STRtl r NI "TED � ,.. UCT#OISF COST TOAL`(SCT€EDULE.A +Sd1: D) $ 2;4x995 Oii :,, :' -.: $ 2 QSE',71;2 SO ,$,2 172,48.0[i $ 2,257'{70 00 , $ 2 38$'88.:5b '415 2fi0 Ofi6 "- O ENGINEERS ARCHITECTS LANDSCAPE ARCHITECTS SURVEYORS SEATTLE • TACOMA May 14, 2014 Ryan Larson, PE Public Works City of Tukwila 6300 Southcenter Blvd Tukwila, WA 98188 RE: East Marginal Way S Storm Pipe Replacement Dear Mike, As requested, KPG has tabulated the bids and reviewed the bid packages submitted for the City of Tukwila East Marginal Way S Storm Pipe Replacement Project. The lowest bidder in the amount of $2,058,782.30 is James W Fowler, Co. As part of our review, we called Harbor Sanitary District where James W Fowler, Co. completed Pump Station No.14 Pipeline. The sanitary district had no issues. The project came in on schedule and within budget. We have also checked the status of James W Fowler, Co. on the Washington State Labor and Industries web page to confirm they are currently insured, bonded, and licensed. It is KPG's recommendation that the East Marginal Way S Storm Pipe Replacement Project he awarded to James W Fowler, Co. We have enclosed the original bid package along with the contractor verification for your review. Sincerely, KPH, Inc. Nelson Davis, P.E. cc: Mike Ronda Enclosures: James W Fowler. bid package including Contractor Verification 753 9TH Avenue North • Seattle, WA 98109 • Phone (206) 286 -164o • Fax (206) 286 -1639 2502 Jefferson Avenue • Tacoma, WA 98402 • Phone (253) 627 -0720 • Fax (253) 627 -4144 www.kpg.com 21