HomeMy WebLinkAboutTrans 2014-05-27 Item 2G - Resolution - 2015-2020 Transportation Improvement ProgramTO:
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director_!
BY: Cyndy Knighton, Senior Program Manager
DATE: May 23, 2014
SUBJECT: Resolution for Six -Year Transportation Improvement Program (2015 -2020)
ISSUE
Resolution to adopt the annual update of the Six -Year Transportation Improvement Program for 2015 -2020.
BACKGROUND
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of Washington
(RCW). The TIP is adopted by resolution after a public hearing at the local agency level and incorporated into
regional and state TIPs. The TIP is primarily a financial planning document for projects competing for grants. Any
project submitted for federal grant funding must be included in the local, regional and state adopted TIPs. The TIP is
a rolling plan showing various funding sources: grants, developer and local funds. Projects "roll" as funds or stages
occur (design report, final design and construction).
Tukwila's TIP and Capital Improvement Program (CIP) list many of the same transportation- related projects. The TIP
generally lists only those transportation- related projects planned within the next six years that are deemed regionally
significant or that have grant funding awarded or expected. The City's CIP lists transportation projects planned in the
next six years and beyond, as well as water, sewer, surface water, and capital facilities projects. The TIP is required
to be adopted by June 30 on an annual basis, while the CIP is prepared during Summer /Fall in conjunction with the
City's budget preparation. Differences between the two may be due to priority changes, funding availability changes,
or other factors which normally occur during the time between adoptions of each document.
ANALYSIS
The attached spreadsheet is the "Draft" 2015 - 2020 TIP and was created by modifying the 2014 - 2019 TIP to add or
remove projects and adjust project costs. No prioritization was assigned and the list of projects is presented in
alphabetical order. Prioritization of projects is reflected in the CIP.
Added: 53rd Avenue S (CIP Page 6),
Deleted: Andover Park W Widening (CIP Page 17), Cascade View Safe Routes to School (CIP Page 3),
Interurban Avenue S (CIP Page 14), Minkler Blvd, Nelsen Place, S 168th St, S 178th Street
Realignment, S 180th St /Andover Park W Intersection, Southcenter Blvd, Thorndyke Safe Routes
to School (CIP Page 4), Traffic Signal Interconnect Program, Tukwila International Boulevard
Phase IV, Tukwila International Boulevard /S 116th Way /SR 599 Intersection, Tukwila
Manufacturing Industrial Center "Street Smart" Non - motorized Project (CIP Page 26), Tukwila
Urban Center Transit Center (CIP Page 16)
Modified: Cascade View Safe Routes to School Phase II
RECOMMENDATION
Council is being asked to approve the Resolution for the 2015 -2020 Six -Year Transportation Improvement Program
and consider this item at the June 9, 2014 Committee of the Whole with a Public Hearing and subsequent June 16,
2014 Regular Meeting.
Attachments: Draft Resolution
2015 — 2020 "Draft" Transportation Improvement Program
Current Adopted 2014 — 2019 TIP
W: \PW Eng \PROJECTS\A- RW & RS Projects \TIP \Info Memo TIP 2015.docx
103
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2015-
2020), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26 as
amended, the City Council of the City of Tukwila has previously adopted a
Transportation Improvement Program and thereafter periodically modified said
Transportation Improvement Program by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2015- 2020); and
WHEREAS, on June 9, 2014, a public hearing was held regarding the City's Six -
Year Transportation improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A six -year Transportation Improvement Program
for the calendar years 2015 -2020 is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the
Secretary of Transportation and the Transportation Improvement Board of the State of
Washington.
W: \Word Processing \Resolutions \TIP 2015 -2020 5 -19 -14
CK:bjs
Page 1 of 2
104
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON,
at a Regular Meeting thereof this day of , 2014.
ATTEST /AUTHENTICATED:
Christy O'Flaherty, MMC, City Clerk De'Sean Quinn, Council President
APPROVED AS TO FORM BY:
Shelley M. Kerslake, City Attorney
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
Exhibit: City of Tukwila Six -Year Transportation Improvement Program from 2015 to 2020
W: \Word Processing \Resolutions \TIP 2015 -2020 5 -19 -14
CK:bjs
Page 2of2
105
DRAFT 2015 - 2020 TIP SUMMARY
May 21, 2014
2015 -2020 2014 CIP Project Costs in Thousands of Dollars FUNDING SOURCES
TIP PROJECT TITLE Page No. 2015 2016 2017 2018 2019 2020 TOTAL Federal State/TIB Developer Unsecured City
1 53rd Ave S (S 137th St - S 144th St)
2 ADA Improvements
3 APE /Industry Dr Intersection
4 APE /Minkler Blvd Intersection
5 Annual Bridge Inspections and Repairs
6 Annual Overlay and Repair Program
7 BNSF Intermodal Facility Access
8 Boeing Access Rd Bridge Rehabilitation
9 Cascade View Safe Routes to School Phase 2
10 E Marginal Way (BAR - S 112 St)
11 Macadam Rd & S 144 St Intersection
12 Multipurpose Trails
13 S 133 St /SR599 Intersection
14 S 144th St Bridge - Sidewalks
15 S 144th St Phase 11 (42 Ave S -TIB)
16 Strander Blvd /SW 27th St Extension
17 TUC/TOD Pedestrian Improvements
18 TUC - Pedestrian /Bicycle Bridge
19 Walk & Roll Program
20 West Valley Hwy (1 -405 - Strander Blvd)
21 W Valley Hwy/ S 156 St Intersection
6 251
21 63
23 0
24 0
10 270
15 1,550
13 0
11 8,828
3 0
27 0
29 0
41 50
28 0
0
19 1,480
31 0
0
12 7,485
30 140
0
25 0
600
63
0
0
270
1,560
0
2,243
0
0
0
0
0
0
0
0
0
0
0
0
0
600
63
0
0
270
1,650
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
63
0
0
335
1,670
0
0
839
0
0
0
0
0
0
0
0
0
0
0
0
0 0
63 63
0 575
O 622
335 335
1,725 1,725
O 13,750
O 0
0 0
O 3,300
O 610
O 280
O 630
0 1,219
O 0
O 33,150
0 1,080
O 0
O 0
0 630
O 1,032
1,451 1,000 451
378 378
575 575
622 622
1,815 1,815
9,880 9,880
13,750 11,763 1,988
11,070 8,805 2,265
839 750 89
3,300 1,300 2,000
610 610
330 330
630 460 170
1,219 975 244
1,480 1,000 480 0
33,150 5,000 27,000 1,150
1,080 500 580
7,485 6,000 1,485
140 140
630 630
1,032 440 592
TOTAL
PROJECTS REVISED FROM 2014 -2019 TIP
20,117 4,736 2,583 2,907 2,123 59,001 91,466 13,805 7,000 480 44,188 25,993
New:
53rd Avenue S (S 137th St - S 144th St)
Modified:
Cascade View Safe Routes to School Phase 11
Deleted:
Andover Park W (Tuk Pkwy - Strander)
Cascade View Safe Routes to School
Interurban Avenue S
Minkler Blvd (APW -S /C Pkwy)
Nelsen Place
S 168th St (S /C Pkwy -APE)
S 178th Street Realignment
S 180th St /Andover Park W Intersection
Southcenter Blvd (I -5 -61st Ave Bridge)
Thorndyke Safe Routes to School
Traffic Signal Interconnect Program
Tukwila Int'I Blvd Phase IV
Tukwila Intl Blvd /S 116th Wy /SR599
Tukwila MIC "Street Smart" Non - motorized Project
Tukwila Urban Center Transit Center
0
rn
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -06601
53rd Avenue S
S 137th St to S 144th St
Design and construct urban residential street improvements that include curb, gutter,
sidewalk and illumination. Street portion will coordinate with Water and Surface
Water capital improvement program projects.
06/09/14
06/16/14
251,000
251,000
04
C G O P S
TW
0.420
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2015
0
0
251,000
251,000
P
CN
2016
0
TIB
1,000,000
200,000
1,200,000
Totals
0
CN
1,000,000
451,000
1,451,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
251,000
0
0
0
0
CN
0
600,000
600,000
0
0
Totals
251,000
600,000
600,000
0
0
Report Date: May 21, 2014
Page 1
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
4th
WA -05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/09/14
06/16/14
378,000
378,000
06
0
63,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2015
4th
0
5th & 6th
0
378,000
378,000
Totals
0
63,000
0
378,000
378,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
63,000
63,000
63,000
63,000
126,000
Totals
63,000
63,000
63,000
63,000
126,000
Report Date: May 21, 2014
Page 2
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03766
Andover Park E /Industry Drive Signal
Andover Park E
Industry Drive to
Design and construct a traffic signal and intersection improvements
06/09/14
06/16/14
575,000
575,000
05
C G O P S
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2020
4th
0
5th & 6th
0
575,000
575,000
Totals
0
0
0
575,000
575,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
0
0
0
0
575,000
Totals
0
0
0
0
575,000
Report Date: May 21, 2014
Page 3
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03764
Andover Park E /Minkler Blvd. Intersection
Andover Park E
Minkler Blvd to
Design and construct intersection and traffic signal improvements and widening for
left turn pockets
06/09/14
06/16/14
20,000
20,000
03
CN
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
20,000
20,000
P
CN
2020
0
0
602,000
602,000
Totals
0
0
0
622,000
622,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
20,000
CN
0
0
0
0
602,000
Totals
0
0
0
0
622,000
Report Date: May 21, 2014
8
Page 4
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
4th
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi- annual inspections as well as construct necessary
repairs and maintenance
06/09/14
06/16/14
1,815,000
1,815,000
06
0
270,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2015
4th
0
5th & 6th
0
1,815,000
1,815,000
Totals
0
270,000
0
1,815,000
1,815,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
270,000
270,000
270,000
335,000
670,000
Totals
270,000
270,000
270,000
335,000
670,000
Report Date: May 21, 2014
Page 5
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/09/14
06/16/14
9,880,000
9,880,000
06
C G O P S
TW
1,560,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2015
4th
0
5th & 6th
0
9,880,000
9,880,000
Totals
0
1,560,000
0
9,880,000
9,880,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,550,000
1,560,000
1,650,000
1,670,000
3,450,000
Totals
1,550,000
1,560,000
1,650,000
1,670,000
3,450,000
_ Report Date: May 21, 2014
N
Page 6
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
FMSIB
WA -05409
BNSF Regional Center Access
New Facility
to
Construct a new access to the BNSF Regional Distribution Center, relocating the
900+ daily truck trips from residential streets in Allentown.
06/09/14
06/16/14
300,000
1,250,000
08
CN
2020
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
FMSIB
950,000
5th & 6th
0
300,000
1,250,000
P
CN
2020
FMSIB
10,812,500
0
1,687,500
12,500,000
Totals
11,762,500
0
0
1,987,500
13,750,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
1,250,000
CN
0
0
0
0
12,500,000
Totals
0
0
0
0
13,750,000
Report Date: May 21, 2014
Page 7
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
STP(BR)
/ 1380(003) TUK -52
Boeing Access Road Bridge Rehabilitation
Boeing Access Road
Interstate 5 to Airport Way South
Rehabilitate the existing Boeing Access Road bridge structure over the Burlington
Norther and Union Pacific Railroads. Work will include rehabilitation of the bridge
sub - structure, seismic retrofit, and construction of a new bridge deck including
pedestrian /bicycle amenities.
06/09/14
06/16/14
45,000
224,500
14
CN
0.200
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2015
STP(BR)
179,500
0
45,000
224,500
S
CN
2015
STP(BR)
8,625,600
CN
0
2,220,100
10,845,700
Totals
8,805,100
0
2,265,100
11,070,200
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
224,500
0
0
0
0
CN
8,603,000
2,242,700
0
0
0
Totals
8,827,500
2,242,700
0
0
0
Report Date: May 21, 2014
Page 8
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -03795
Cascade View Safe Routes to School Phase 2
S 140th St/33rd Ave S
to
Construct an off - street paved shard use path, sidewalks, and a traffic circle at the
intersection of 33rd Ave S and S 140th Street.
06/09/14
06/16/14
89,000
839,000
28
0
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2018
0
WSDOT
750,000
89,000
839,000
Totals
0
0
750,000
89,000
839,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
839,000
0
0
Totals
0
0
839,000
0
0
Report Date: May 21, 2014
Page 9
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03770
East Marginal Way
E Marginal Way
Boeing Access Road to S 112th St
Design and construct widening to 3 lanes including curb & gutter, sidewalks,
drainage, landscaping, and utility undergrounding.
06/09/14
06/16/14
170,000
170,000
03
P S T W
0.280
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
170,000
170,000
P
RW
2020
0
0
700,000
700,000
P
CN
2020
STP
1,300,000
0
1,130,000
2,430,000
Totals
1,300,000
0
2,000,000
3,300,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
170,000
RW
0
0
0
0
700,000
CN
0
0
0
0
2,430,000
Totals
0
0
0
0
3,300,000
Report Date: May 21, 2014
w
Page 10
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
4th
WA -03763
Macadam Road /S 144th St Intersection
Macadam Road
S 144th Street to
Widen Macadam Road to add a northbound left turn lane
06/09/14
06/16/14
90,000
90,000
03
RW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
90,000
90,000
P
RW
2020
0
0
90,000
90,000
P
CN
2020
0
0
430,000
430,000
Totals
0
0
610,000
610,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
90,000
RW
0
0
0
0
90,000
CN
0
0
0
0
430,000
Totals
0
0
0
0
610,000
Report Date: May 21, 2014
Page 11
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
4th
WA -03783
Multipurpose Trails
to
Design and construct safe connections to public trails to promoste pedestrian and
bicycle modes of transportation in lieu of motorized vehicles
06/09/14
06/16/14
50,000
50,000
28
CN
2020
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2015
4th
0
5th & 6th
0
50,000
50,000
P
CN
2020
0
0
280,000
280,000
Totals
0
0
0
330,000
330,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
50,000
0
0
0
0
ALL
0
0
0
0
280,000
Totals
50,000
0
0
0
280,000
Report Date: May 21, 2014
Page 12
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03769
S 133rd St /SR 599 SB Ramps Intersection
S 133rd Street
SR 599 SB Ramps to
Design and construct intersection improvements including a new traffic signal.
06/09/14
06/16/14
60,000
60,000
06
C G O P S
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
60,000
60,000
P
CN
2020
STP
460,000
0
110,000
570,000
Totals
460,000
0
0
170,000
630,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
60,000
CN
0
0
0
0
570,000
Totals
0
0
0
0
630,000
Report Date: May 21, 2014
Page 13
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
STP(BR)
WA -03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1 -5 between 51st Ave S and 53rd Ave S
06/09/14
06/16/14
243,800
1,219,000
28
975,200
0.250
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2020
STP(BR)
975,200
5th & 6th
0
243,800
1,219,000
Totals
975,200
0
0
243,800
1,219,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
1,219,000
Totals
0
0
0
0
1,219,000
Report Date: May 21, 2014
Page 14
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03762
S 144th St Phase 2
S 144th Street
42nd Ave S to Tukwila International Blvd
Design and construct paving, curb & gutter, sidewalks, drainage, illumination, and
utility undergrounding. Coordinate with Tukwila Village development. May include
on- street parking and bike lanes
06/09/14
06/16/15
480,000
1,480,000
03
C G O P S
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2015
0
TIB
1,000,000
480,000
1,480,000
Totals
0
1,000,000
480,000
1,480,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,480,000
0
0
0
0
Totals
1,480,000
0
0
0
0
Report Date: May 21, 2014
Page 15
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
FMSIB
WA -05410
Strander Blvd /SW 27th St Phase III
Strander Boulevard
E City Limits to West Valley Hwy /SR 181
Design and construct 5 -7 lane facility over /under BNSF and UPRR, extending the
current terminus of SW 27th St at the east City limits to West Valley Highway,
including access into the permanent Sound Transit train station
06/09/14
06/16/14
0
5,000,000
01
ALL
2020
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2020
FMSIB
5,000,000
5th & 6th
0
0
5,000,000
P
ALL
2020
TIGER IV
27,000,000
0
1,150,000
28,150,000
Totals
32,000,000
0
0
1,150,000
33,150,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
33,150,000
Totals
0
0
0
0
33,150,000
Report Date: May 21, 2014
Page 16
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
4th
WA -03772
TUC /TOD Pedestrian Improvements
Baker Blvd (if extended)
Andover Park W to E City Limits
Design and construct bike and pedestrian connection between the Tukwila Urban
Center and the Commuter Rail Station /TOD area. Connection may include an
underpass under the UPRR line.
06/09/14
06/19/14
280,000
280,000
28
RW
0.750
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
280,000
280,000
P
RW
2020
0
0
100,000
100,000
P
CN
2020
STP(E)
500,000
0
200,000
700,000
Totals
500,000
0
580,000
1,080,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
280,000
RW
0
0
0
0
100,000
CN
0
0
0
0
700,000
Totals
0
0
0
0
1,080,000
Report Date: May 21, 2014
w
Page 17
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
/ 1320(002) TUK -50
Tukwila Urban Center Pedestrian /Bicycle Bridge over Green River
New bridge over the Green River, approximately between Baker Blvd (if extended)
and Longacres Way (if extended)
Near Riverside office complex to Best Western hotel 15901 WVHwy
Development of a new pedestrian /bicycle bridge across the Green River, connecting
the Tukwila Urban Center 'core' to the Sounder Commuter Rail /Amtrak Station and
surrounding neighborhood of transit-oriented development. The project, a
pedestrian /bicycle bridge across the Green River, will form the backbone of a
pedestrian corridor connecting the compact land uses and high ridership bus stop in
the core of the urban center, with the Sounder Commuter Rail /Amtrak Station and its
surrounding transit - oriented development. This will improve public access to the
station from all parts of the center, and provide a direct, safe and enjoyable walking
experience. The high level of urban level amenity will attract the types and densities
of uses envisioned in a regional center.
06/09/14
06/16/14
1,485,000
7,485,000
28
0
0.640
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2015
0
OTHER
6,000,000
1,485,000
7,485,000
Totals
0
6,000,000
1,485,000
7,485,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
7,485,000
0
0
0
0
Totals
7,485,000
0
0
0
0
Report Date: May 21, 2014
Page 18
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03761
Walk & Roll Plan (Nonmotorized Transportation Plan
Various City Streets
to
Select, design, and construct non - motorized projects including bike lanes, sidewalks
and trails. First priorities are: sidewalks on S 152nd Street, TIB to 42nd Ave S;
sidewalk on S 130th St, TIB to S 130th St; sidewalk/bike lanes on Macadam, S 144th
St to S 150th St.
06/09/14
06/16/15
140,000
140,000
28
0
140,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2015
0
0
140,000
140,000
Totals
0
140,000
0
140,000
140,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
140,000
0
0
0
0
Totals
140,000
0
0
0
0
Report Date: May 21, 2014
01
Page 19
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m al
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
4th
WA -03779
West Valley Highway
SR 181 /West Valley Highway
1 -405 to Strander Blvd
Design and costruct widening to 7 lanes including curb & gutter, sidewalks,
illumination, drainage, and traffic control
06/09/14
06/19/10
60,000
60,000
03
CN
0.500
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
60,000
60,000
P
CN
2020
0
0
570,000
570,000
Totals
0
0
0
630,000
630,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
60,000
CN
0
0
0
0
570,000
Totals
0
0
0
0
630,000
Report Date: May 21, 2014
Page 20
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2015 to 2020
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m ai
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
4th
WA -03765
West Valley Highway /S 156th St
SR181/West Valley Highway
Southcenter Blvd to S 158th St
Construct additional northbound left turn lanes at S 156th Street for northbound HOV
to northbound 1 -405
06/09/14
06/16/15
50,000
50,000
03
O P S T W
2020
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
4th
0
5th & 6th
0
50,000
50,000
P
CN
2020
CMAQ
440,000
0
542,000
982,000
Totals
440,000
0
0
592,000
1,032,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
50,000
CN
0
0
0
0
982,000
Totals
0
0
0
0
1,032,000
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
56,242,800
8,750,000
26,473,400
91,466,200
Report Date: May 21, 2014
Page 21
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/10/13
06/17/13
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2014
0
0
541,000
541,000
Totals
0
0
541,000
541,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
63,000
63,000
63,000
63,000
126,000
Totals
63,000
63,000
63,000
63,000
126,000
Report Date: May 31, 2013
Page 1
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03766
Andover Park E /Industry Drive Signal
Andover Park E
Industry Drive to
Design and construct a traffic signal and intersection improvements
06/10/13
06/17/13
05
C G O P S
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
100,000
100,000
P
CN
2018
0
0
575.000
575,000
Totals
0
0
675,000
675,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
0
0
0
575,000
0
Totals
100,000
0
0
575,000
0
Report Date: May 31, 2013
Page 2
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03764
Andover Park E /Minkler Blvd. Intersection
Andover Park E
Minkler Blvd to
Design and construct intersection and traffic signal improvements and widening for
left turn pockets
06/10/13
06/17/13
03
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
120,000
120,000
P
PE
2019
0
0
20,000
20,000
P
CN
2018
0
0
602,000
602,000
Totals
0
0
742,000
742,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
75,000
45,000
0
0
20,000
CN
0
0
0
0
602,000
Totals
75,000
45,000
0
0
622,000
Report Date: May 31, 2013
Page 3
tate
it Teit tsportati
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
to
Adopted,
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03760
Andover Park West Widening
Andover Park West
Strander Blvd to Tukwila Pkwy
Complete widening for center turn pockets and landscape median for access control,
widen sidewalks, upgrade ADA facilities, modify signal operation, upgrade street
lighting, install pedestrian lighting.
06/10/13
06/17/13
04
C G O P S
TW
0.400
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2014
0
TIB
1,420,000
339,000
1,759,000
Totals
0
1,420,000
339,000
1,759,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,050,000
0
0
0
0
Totals
1,050,000
0
0
0
0
Report Date: May 31, 2013
Page 4
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi- annual inspections as well as construct necessary
repairs and maintenance
06/10/13
06/17/13
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2014
0
0
1,555,000
1,555,000
Totals
0
0
1,555,000
1,555,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
270,000
270,000
270,000
270,000
670,000
Totals
270,000
270,000
270,000
270,000
670,000
Report Date: May 31, 2013
Page 5
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
c'o
Adopted
Amendment
m
c�
o
P
Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/10/13
06/17/13
06
COOPS
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2014
0
0
9,655,000
9,655,000
Totals
0
0
9,655,000
9,655,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,500,000
1,550,000
1,560,000
1,650,000
3,395,000
Totals
1,500,000
1,550,000
1,560,000
1,650,000
3,395,000
Report Date: May 31, 2013
Page 6
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -05409
BNSF Regional Center Access
New Facility
to
Construct a new access to the BNSF Regional Distribution Center, relocating the
900+ daily truck trips from residential streets in Allendtown.
06/10/13
06/17/13
08
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
FMSIB
950,000
0
300,000
1,250,000
P
CN
2019
FMSIB
10,812,500
0
1,687,500
12,500,000
Totals
11,762,500
0
1,987,500
13,750,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
1,250,000
CN
0
0
0
m 0
12,500,000
Totals
0
0
0
0
13,750,000
Report Date: May 31, 2013
Page 7
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required:
14
TUK -52
Boeing Access Road Bridge Rehabilitation
Boeing Access Road
Interstate 5 to Airport Way South
Rehabilitate the existing Boeing Access Road bridge structure over the Burlington
Norther and Union Pacific Railroads. Work will include rehabilitation of the bridge
sub - structure, seismic retrofit, and construction of a new bridge deck including
pedestrian /bicycle amenities.
06/10/13
06/17/13
14
0.200
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
BR
800.000
0
200,000
1,000,000
S
CN
2014
BR
8,880,000
0
2,220,000
11,100,000
Totals
9,680,000
0
2,420,000
12,100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
1,000,000
0
0
0
0
CN
2,100,000
9,000,000
0
0
0
Totals
3,100,000
9,000,000
0
0
0
Report Date: May 31, 2013
Page 8
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
3
m
a
m
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -03795
Cascade View Safe Routes to School
S 140th St/33rd Ave S
to
Construct an off- street paved shard use path, sidewalks, and a traffic circle at the
intersection of 33rd Ave S and S 140th Street.
06/10/13
06/17/13
28
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2018
0
WSDOT
750.000
89,000
839,000
Totals
0
750,000
89,000
839,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
839,000
0
Totals
0
0
0
839,000
0
Report Date: May 31, 2013
Page 9
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
3
o
n g. .
&
m m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
A
m
c
o
z
9
Improvement Type
Utility Codes
Total Length',
Environmental Type
RW Required
16
WA -03770
East Marginal Way
E Marginal Way
Boeing Access Road to S 112th St
Design and construct widening to 3 lanes including curb & gutter, sidewalks,
drainage, landscaping, and utility undergrounding.
06/10/13
06/17/13
03
P S T W
0.280
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
50,000
50,000
P
PE
2019
0
0
170,000
170,000
P
RW
2019
0
0
700,000
700,000
P
CN
2019
STP
1,300,000
0
1,130,000
2,430,000
Totals
1,300,000
0
2,050,000
3,350,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
50,000
0
0
0
170,000
RW
0
0
0
0
700,000
CN
0
0
0
0
2,430,000
Totals
50,000
0
0
0
3,300,000
Report Date: May 31, 2013
Page 10
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
c
n.
m c
m m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
m.
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
TUK -40
Interurban Avenue South (S 143 St to Fort Dent Way)
Interurban Avenue South
S 143 St to Fort Dent Way
Reconstruct and overlay the existing roadway and construct curb and gutter,
drainage, sidewalk, landscaping, illumination, utility burying, channelization, signing,
and signal interconnect.
06/10/13
06/17/13
06
0.900
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2014
STP(U)
2,145,954
TIB
5,000,000
3,554,046
10,700,000
Totals
2,145,954
5,000,000
3,554,046
10,700,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
10,700,000
0
0
0
0
Totals
10,700,000
0
0
0
0
Report Date: May 31, 2013
Page 11
tate
r. Trvnspor'tat *tt
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
a
n
m g
e m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type'
Utility Codes II!
Total Length
Environmental Type
RW Required
17
WA -03763
Macadam Road /S 144th St Intersection
Macadam Road
S 144th Street to
Widen Macadam Road to add a northbound left turn lane
06/10,113
06/17/13
03
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
17,000
17,000
P
PE
2018
0
0
90,000
90,000
P
RW
2018
0
0
90,000
90,000
P
CN
2018
0
0
430,000
430,000
Totals
0
0
627,000
627,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
17,000
0
0
0
90,000
RW
0
0
0
0
90,000
CN
0
0
0
0
430,000
Totals
17,000
0
0
0
610,000
Report Date: May 31, 2013
Page 12
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
c
c
o
E= O .11:
N E
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
D
m
a
3
mm,
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03773
Minkler Blvd
Minkler Blvd
Southcenter Pkwy to Andover Park W
Construct widening for 3 lanes including curb & gutter, sidewalk, drainage and
landscaping
06/10/13
06/17/13
03
P S T W
0.400
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2018
0
0
75,000
75,000
P
CN
2018
0
0
865,000
865,000
Totals
0
0
940,000
940,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
75,000
CN
0
0
0
0
865,000
Totals
0
0
0
0
940,000
Report Date: May 31, 2013
Page 13
S3urrgtOr, ,
p r*n'erlt q�f
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
efl
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -03783
Multipurpose Trails
to
Design and construct safe connections to public trails to promoste pedestrian and
bicycle modes of transportation in lieu of motorized vehicles
06/10/13
06/17/13
28
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2015
0
0
50,000
50,000
P
CN
2019
0
0
280,000
280,000
Totals
0
0
330,000
330,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
50,000
0
0
0
CN
0
0
0
280,000
0
Totals
0
50,000
0
280,000
0
Report Date: May 31, 2013
Page 14
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
c
n
n o
DT g
m m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
ix
al
5
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes li
Total Length
Type
RW Required
19
WA -03780
Nelsen Place
Nelsen Place
S 156th St to S 158th St
Design and construct paving, curb & gutter, sidewalks, drainage, and illumination
06/10/13
06/17/13
05
0.110
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
20,000
20,000
P
CN
2019
0
0
180,000
180,000
Totals
0
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
20,000
CN
0
0
0
0
180.000
Totals
0
- 0
0
0
200,000
Report Date: May 31, 2013
Page 15
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
c
0
f) C
m �
N 91.
iagwnN A ;uoud
A. PIN /Project No.
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description
B. STIP ID
G. Structure ID
1
m
;uawpuawy
ON uogniosaa
adi(j ;uawanoJdwi
0
0
0
edit' iu ;uawuonnu3
pannbab M2!
16
S 133rd St/SR 599 SB Ramps Intersection
S 133rd Street
SR 599 SB Ramps to
Design and construct intersection improvements including a new traffic signal.
WA -03769
06/10/13
06/17/13
06
CGOPS
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
20,000
20,000
P
PE
2018
0
0
60,000
60,000
P
CN
2018
STP
460,000
0
110,000
570,000
Totals
460,000
0
190,000
650,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
20,000
0
0
0
60,000
CN
0
0
0
0
570,000
Totals
20,000
0
0
0
630,000
Report Date: May 31, 2013
Page 16
tats
t Transportation
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
7
m
Adopted
Amendment,
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1 -5 between 51st Ave S and 53rd Ave 5
06/10/13
06/17/13
28
0.250
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
100,000
100,000
Totals
0
0
100,000
100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
100,000
Totals
0
0
0
0
100,000
Report Date: May 31, 2013
Page 17
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
m
,n.
n _.
m o
m m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
XI
m
0
o
o
Improvement Type'
I
Utility Codes'
i
Total Length
Environmental Type
RW Required
17
WA -03762
S 144th St Phase 2
S 144th Street
42nd Ave S to Tukwila International Blvd
Design and construct paving, curb & gutter, sidewalks, drainage, illumination, and
utility undergrounding. Coordinate with Tukwila Village development. May include
on- street parking and bike lanes
06/10/13
06/17/13
03
C G O P S
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
68,000
68,000
P
PE
2018
0
0
230.000
230,000
P
RW
2018
0
0
40,000
40,000
P
CN
2018
0
TIB
1.000,000
480,000
1,480,000
Totals
0
1,000,000
818,000
1,818,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
68,000
0
0
0
230,000
RW
0
0
0
0
40,000
CN
0
0
0
0
1,480,000
Totals
68,000
0
0
0
1,750,000
Report Date: May 31, 2013
Page 18
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
c
n
n E
DT ''
m m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -03778
S 168th St
S 168th St
Southcenter Pkwy to Andover Park E
Design and construct new roadway including curb & gutter, sidewalk, drainiage,
illumination, on- street parking, landscaping, and underground utilities.
06/10/13
06/17/13
01
GO P W
0.800
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
1,372,000
1,372,000
P
RW
2019
0
0
7,500,000
7,500,000
P
CN
2019
0
0
14,372,000
14,372,000
Totals
0
0
23,244,000
23,244,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
1,372,000
RW
0
0
0
0
7,500,000
CN
0
0
0
0
14,372,000
Totals
0
0
0
0
23,244,000
Report Date: May 31, 2013
Page 19
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
m
n
E ..7.
m 'm_
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
Begin & End Termini
F. Project Description G. Structure ID
m
-
m
D
a
-o
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03784
S 178th St Realignment
S 178th St
Southcenter Pkwy to W City Limits
Realign S 178th St from current intersection of Southcenter Pkwy /S 180th St to
intersect with Segale Park Dr C and add a new traffic signal at the new intersection.
06/10/13
06/17/13
01
0.400
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2014
0
0
9,472,000
9,472,000
Totals
0
0
9,472,000
9,472,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
9,382,000
0
0
0
0
Totals
9,382,000
0
0
0
0
Report Date: May 31, 2013
Page 20
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
ai
Adopted
Amendment.
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03781
S 180th St /Andover Park W Intersection
S 180th Street
Andover Park W to
Widen for north /south left turn pockets
06110/13
06/17/13
03
0.200
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
35,000
35,000
P
RW
2019
0
0
15,000
15,000
P
CN
2019
0
0
160,000
160,000
Totals
0
0
210,000
210,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
35,000
RW
0
0
0
0
15,000
CN
0
0
0
0
160,000
Totals
0
0
0
0
210,000
Report Date: May 31, 2013
Page 21
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
-n
c
;
n _.
m g
w m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03776
Southcenter Blvd Widening
Southcenter Blvd
1 -5 to 61st Ave S
Widen Southcenter Blvd and the 61st Avenue Bridge to add a lane for future traffic
growth.
06/10/13
06/17/13
03
C G O P S
TW
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
1,700,000
1,700,000
P
RW
2019
0
0
1,400,000
1,400,000
P
CN
2019
0
0
16,900,000
16,900,000
Totals
0
0
20,000,000
20,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
1,700,000
RW
0
0
0
0
1,400,000
CN
0
0
0
0
16,900,000
Totals
0
0
0
0
20,000,000
Report Date: May 31, 2013
Page 22
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
m
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codesil
Total Length
Type
RW Required
16
WA -05410
Strander Blvd /SW 27th St Phase III
Strander Boulevard
E City Limits to West Valley Hwy /SR 181
Design and construct 5 -7 lane facility over /under BNSF and UPRR, extending the
current terminus of SW 27th St at the east City limits to West Valley Highway,
including access into the permanent Sound Transit train station
06/10/13
06/17/13
01
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2019
FMSIB
5,000,000
0
0
5,000,000
P
ALL
2019
TIGER IV
27,000,000
0
1,148,800
28,148,800
Totals
32,000,000
0
1,148,800
33,148,800
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
33,148,800
Totals
0
0
0
0
33,148,800
Report Date: May 31, 2013
Page 23
I tnutork State
�i'tNlAetof Cff Tra41sporttron:
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
m
c
n
_
n .
m
m
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -03796
Thorndyke Safe Routes to School
S 150th St
Tukwila International Blvd to 42nd Ave S
Construction of roadway improvements including a new sidewalk on the north side of
S 150th St and a new crosswalk in front of Thorndyke Elementary School.
Education, enforcement and encouragement elements are included after the
construction as part of the Safe Routes to Schools program.
06/10/13
06/17/13
28
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2014
0
WSDOT
90,000
0
90,000
P
CN
2014
0
WSDOT
367,000
255,000
622,000
Totals
0
457,000
255,000
712,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
28,000
14,000
0
0
0
CN
622,000
0
0
Totals
650,000
14,000
0
0
0
Report Date: May 31, 2013
Page 24
w
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m m
m a
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03775
Traffic Signal Interconnect Program
Various City Streets
to
Design and install hard wire interconnect system between traffic signals and the
Traffic Operations Center
06/10/13
06/17/13
24
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
300,000
300,000
P
CN
2019
STP
1,200,000
0
1,500,000
2,700,000
Totals
1,200,000
0
1,800,000
3,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
300,000
CN
0
0
0
0
2,700,000
Totals
0
0
0
0
3,000,000
Report Date: May 31, 2013
Page 25
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
m
0
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03772
TUC/TOD Pedestrian Improvements
Baker Blvd (if extended)
Andover Park W to E City Limits
Design and construct bike and pedestrian connection between the Tukwila Urban
Center and the Commuter Rail Station /TOD area. Connection may include an
underpass under the UPRR line.
06/10/13
06/17/13
28
0.750
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
20,000
20,000
P
PE
2019
0
0
280,000
280,000
P
RW
2019
0
0
100,000
100,000
P
CN
2019
STP(E)
500,000
0
200,000
700,000
Totals
500,000
0
600,000
1,100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
20,000
0
0
0
280,000
RW
0
0
0
0
100,000
CN
0
0
0
0
700,000
Totals
20,000
0
0
0
1,080,000
Report Date: May 31, 2013
Page 26
� y+� Washington State
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
=
m
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03774
Tukwila International Blvd (Phase 4)
Tukwila International Blvd
Boeing Access Road to S 116th St
Design and construct widening including paving, curb & gutter, sidewalk, drainage,
illumination, landscaping, and utility undergrounding.
06/10/13
06/17/13
03
O P S W
0.700
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
271,000
271,000
P
CN
2019
0
TIB
3,500,000
820,000
4,320,000
Totals
0
3,500,000
1,091,000
4,591,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
271,000
CN
0
0
0
0
4,320.000
Totals
0
0
0
0
4,591,000
Report Date: May 31, 2013
Page 27
io nzportetttfn
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Jagwnry Ayuoud
A. PIN /Project No.
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description
B. STIP ID
G. Structure ID
2
°m
co
a.
a.
CD
0.
yuewpuewy
•oN uogniosab
Odic j yuewanoidwI
c
0
0.
N
ad (j ieyuawuoJinu3
pannbay MJ
14
Tukwila International Blvd /S 116th St/SR 599 On -ramp
Tukwila International Blvd
S 116th St /SR 599 On -ramp to
Design and construct southbound left turn lane, pedestrian signalization and lighting
WA -03777
06/10/13
06/17/13
03
P
0.400
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
450,000
450,000
P
CN
2019
STP
1,900,000
0
2,325,000
4,225,000
Totals
1,900,000
0
2,775,000
4,675,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
450,000
CN
0
0
0
0
4,225,000
Totals
0
0
0
0
4,675,000
Report Date: May 31, 2013
Page 28
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03798
Tukwila Manufacturing Industrial Center "Street Smart" Non - motorized Project
Various City Streets
to
1. Planning study of non - motorized improvement options along Boeing Access Road,
to provide safe bicycle and pedestrian travel alternatives. 2. PE & CN of bike
facilities on E Marginal Way S between Boeing Access Road and SR 599. 3. PE &
CN of bike lanes and shared use path on Airport Way from Boeing Access Road /E
Marginal Way S to the northern City limit.
06/10/13
06/17/13
28
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
CMAQ
96,960
0
24,240
121,200
S
CN
2015
CMAQ
445,824
0
111,456
557,280
Totals
542,784
0
135,696
678,480
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
121,200
0
0
0
0
CN
0
557,280
0
0
0
Totals
121,200
557,280
0
0
0
Report Date: May 31, 2013
Page 29
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03734
Tukwila Urban Center - Transit Center
Andover Park W
Strander Blvd to Tukwila Pkwy
Design and construct a transit center
06/10/13
06/17/13
23
C G O P S
TW
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2014
5309(Bus)
1,400,000
WSDOT
4,735,000
79,000
6,214,000
Totals
1,400,000
4,735,000
79,000
6,214,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
2,500,000
0
0
0
0
Totals
2,500,000
0
0
0
0
Report Date: May 31, 2013
Page 30
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
/ 1320(002) TUK -50
Tukwila Urban Center Pedestrian /Bicycle Bridge over Green River
New bridge over the Green River, approximately between Baker Blvd (if extended)
and Longacres Way (if extended)
Near Riverside office complex to Best Western hotel 15901 WVHwy
Design and preliminary engineering of a new pedestrian /bicycle bridge across the
Green River, connecting the Tukwila Urban Center 'core' to the Sounder Commuter
Rail /Amtrak Station and surrounding neighborhood of transit - oriented development.
06/10/13
06/17/13
28
0.640
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
CMAQ
1,496,000
0
137,000
1,633,000
P
RW
2014
0
WSDOT
870,000
230,000
1,100,000
P
CN
2014
0
WSDOT
6,000,000
1,485,000
7,485,000
Totals
1,496,000
6,870,000
1,852,000
10,218,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
250,000
0
0
0
0
RW
1,100,000
0
0
0
0
CN
3,743,000
3,742,000
0
0
0
Totals
5,093,000
3,742,000
0
0
0
Report Date: May 31, 2013
Page 31
fate
Tran;sl ortstacxe
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03761
Walk & Roll Plan (Nonmotorized Transportation Plan
Various City Streets
to
Select, design, and construct non - motorized projects including bike lanes, sidewalks
and trails. First priorities are: sidewalks on S 152nd Street, TIB to 42nd Ave S;
sidewalk on S 130th St, TIB to S 130th St; sidewalklbike lanes on Macadam, S 144th
St to S 150th St.
06/10/13
06/17/13
28
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2015
0
0
140,000
140,000
Totals
0
0
140,000
140,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
140,000
0
0
0
Totals
0
140,000
0
0
0
Report Date: May 31, 2013
Page 32
shingri
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
m
eo
Adopted
3
o
a
2 co
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03779
West Valley Highway
SR 181/West Valley Highway
1 -405 to Strander Blvd
Design and costruct widening to 7 lanes including curb & gutter, sidewalks,
illumination, drainage, and traffic control
06/10/13
06/17/13
03
0.500
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2019
0
0
60,000
60,000
P
CN
2019
0
0
570,000
570,000
Totals
0
0
630,000
630,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
60,000
CN
0
0
0
0
570,000
Totals
0
0
0
0
630,000
Report Date: May 31, 2013
Page 33
r shieri}ts t: a
Departrrmii fT�
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2014 to 2019
N Outside
m
9.
m
LI d
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
A
m
0
3
m
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03765
West Valley Highway /S 156th St
SR181/West Valley Highway
Southcenter Blvd to S 158th St
Construct additional northbound left turn lanes at S 156th Street for northbound HOV
to northbound 1 -405
06/10/13
06/17/13
03
0 P S T W
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2014
0
0
75,000
75,000
P
PE
2018
0
0
50,000
50,000
P
CN
2018
CMAQ
440,000
0
542,000
982,000
Totals
440,000
0
667,000
1,107,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
75,000
0
0
0
50,000
CN
0
0
0
0
982,000
Totals
75,000
0
0
0
1,032,000
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
64,827,238
23,732,000
90,912,042
179,471,280
Report Date: May 31, 2013
Page 34