Loading...
HomeMy WebLinkAboutUtilities 2007-08-08 Item 3A - Final Acceptance - Allentown Phase II / Foster Point Water and Sewer Improvements by RL Alia CompanyINFORMATION MEMO To: Mayor Mullet From: Public Works Director Date: July 25, 2007 Subject: Allentown Phase II/Foster Point Water and Sewer Improvements Project No. O1 -SW02 Project Completion and Acceptance ISSUE Accept construction contract as complete and authorize release of retainage in the amount of $369,718.37. BACKGROUND The Notice to Proceed for Contract No. 06 -043 with R.L Alia Company Renton, Washington, was issued on May 15, 2006. This project constructed new water and sewer mains in the Allentown Phase II and Foster Point neighborhoods. This contract was completed on July 6, 2007. There were seventy-six change orders in the amount of $330,746.95 and $524,620.72 in net unit price overruns,See attached change order log. Although this project was primarily lump sum, there were several unit bid prices that were substantially overrun. The primary unit price item overruns were eighty-eight additional water services at $3,000 each and forty-five additional sanitary sewer stubs at $5,000 each. Closeout paperwork has been completed and verified, and the project is now ready for final acceptance. The contract cost is summarized as follows: Contract Award Amount $6,539,000.00 Additions (Change Orders and overruns) 855,367.67 Subtotal 7,394,367.67 Sales Tax* 537.842.87 Total Amount Paid (incl. retainage) 7,932,210.54 Sales tax at 8.8% and 8.9% after April 1, 2007 (except no tax on roadway items). ANALYSIS The bid award was $6,539,000 plus tax ($443,432) plus 10% contingency ($653,900), for a total of $7,636,332. The budgeted amount for construction is $7,834,000 and $1,085,000 for construction management. Construction management expenditures will be approximately $400,000 under budget and overall the project has finished under budget. RECOMMENDATION It is recommended that this contract be forwarded to the Tukwila City Council on the consent agenda for formal acceptance and authorize release of the retainage, subject to the standard claim and lien release procedures. attachments: Notice of Completion of Public Works Contract Change Order and Overrun Summaty \huk2 \von\PUBWORKSIPROIECTS A- SW Projects\OIswO2 Mown R Foster Pt\ CONSIRUCTIONWfo Memo AFP Closeoutdoc 1 From: ess o City of Tukwila 6200 Southcenter Boulevard Tukwila, WA 98188 Description of Contract Allentown/Foster Point Water Sewer Improvements Contractor's Name R.L. Alia Company Contractor's Address 107 Williams Avenue S, Renton, WA 98055 Date Work Commenced Date Work Completed 5/15/06 7/6/07 Surety or Bonding Company Hartford Fire Insurance Company Agent's Address Parker Smith Feek Inc. 2233 112th Ave NE Bellevue WA 98004 Sub -Total 7,394,367.67 Amount of Sales Tax Paid at 537,842.87 (If various rates apply, please send a breakdown) TOTAL 7,932,210.54 Comments: *see attached sales tax breakdown Finance Approval State of Washington Department of Revenue PO Box 47474 RE VENUE Otympia WA 98504-7474 Contractor's Registration No. (UBI No.) 600 149 378 Date 6/25/07 NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT fJOC Contract Amount Additions Reductions l�lic Agpacy n =�I Assigned To Date Assigned Notice is hereby given relative to the completion of contract or project described below 6,539,000.00 855,367.67 0.00 Liquidated Damages Amount Disbursed Amount Retained Signature Type or Print Name Diane Jaber Phone Number (206) 433 -1871 ur. n Office Depaitment Use Only Contract Number 06 -043 Telephone Number 425- 226 -8100 Date Work Accepted TOTAL 0.00 7,562,492.17 369,718.37 7,932,210.54 The Disbursing Officer must complete and mail THREE copies of this notice to the Department of Revenue, PO Box 47474, Olympia, WA 98504 -7474, immediately after acceptance of the work done under this contract. NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of Department's certificate, and then only in accordance with said certificate. To inquire about the availability of this document in an alternate format for the visually impaired, please call (360) 753 -3217. Teletype (TTY) users please call (800) 451 -7985. You may also access tax information on our Internet home page at http: /dor.wa.gov. REV 31 0020e (6- 27 -01) Allentown 1 Foster Point Water and Sewer Improvements Notice to Proceed City of Tukwila Change Order Log Contract (calendar) Days Change Order No, (fr) Location /Type Description 001 I Foster Point Storm (Foster Point 1301h 156th Avenue Storm Drain. Revise catch basin locations to minimize the impact to the 20' gas line, the water line. the existing force main on 1301tq South, and to eliminate encroachment onto private property. I 002 I Allentown Storm 'Allentown Ditch Extension of 12' storm drain pipe at station 21 +07. Pipe was not shown property in the base map, and general poor condition made replacement necessary. 003 I Allentown Roadway /Allentown Gingko Tree Caliper Reduction to 1.75' from 2'. Specified trees are unavailable. I 004 Allentown Water Allentown Watermain Modlflcatton on S 125th Street. The riverbank was found to be unstable and the pipes required restraints using field lock gaskets. The re (design included valvos on both sides of the bank instab0iy area. 005 Allentown Sewer Allentown Raised SS Profile on 44th Place, S 122nd Street and 51st Place S. Change resulted in a significant reduction in the amount of dewatering needed for th e��( pipe installation along 44th Place, 122nd Street and 50th Avenue South. Test holes dug in the vicinity showed a higher than anticipated groundwater table than stated in th geotechnical report 006 I Foster Point- Storm 'Foster Point Extension of 12" Storm Drain at Sta. 24 +10. City maintenance determined a direct connection to the existing catch basin would provide for a better ton term installation and reduce maintenance costs. The work resulted in the pipe crew working nearly an entire day on this connection. 007 1 Foster Point Sewer (Foster Point Realign Sewer on 56th Avenue. Reduced impact on surrounding utilities and private property The credit is primarily due to restocking of manholes. I 008 Foster Point Water Foster Point Pamela Drive Fire Hydrant Extension. Existing fire hydrant is located in the street. Extension will move it beyond the sidewalk into the City of Tukwila' 1 right of way. 009 I Foster Point Storm Foster Point Hancor Pipe to Ductile Iron Pipe: The section of storm pipe between Catch Basin 22 and Catch Basin 23 on 57th was changed from Hancor Pipe to Due Iron Pipe due to insufficient cover. 010 I Allentown Storm (Allentown Ditch Additional 8' lnserta -Tee on S 122nd Street at Sta. 21 +00: Connection of unknown and unmarked storm pipe. 011 Foster Point Sewer (Foster Point Removal of Trees. Contractor was required to remove additional trees which were not shown on the contract drawings. Trees had to be removed lo( facthtate construction, az they conflicted with proposed trench lines and paving Bmits. rl 012 Allentown Sewer Allentown Cut and plug existing 18' Clay Pipe; During installation of the 8' PVC sewer main, an existing 18' clay pipe was encountered al the intersection of 122nd an 42nd (see plan sheet 25 of 70). The 1B' clay pipe was broken. A 12' HOPE had been sleeved through the clay pipe by others. The profile grade of the new 8' PVC via partially into the clay pipe. The Contractor was directed to seal up any opening made as a result of this pipe crossing. 013 Foster Point Sewer Foster Point Relocate Side Sewer Tee 13048 571h Ave S. The side sewer stub for 13048 57th Avenue was installed at the planned location. Following Installation of the stub. the property owner requested a change in the location. The Contractor relocated the stub location on a time and materials (force account) basis. The original Iocatior was plugged and a new tee was cut into the main. 014 Allentown Storm Additional Quarry Spalls at Dutlall Locations: The storm drain outfalls at Foster Point and Allentown specified 4 cubic yards of Quarry Spells per bcalion. Due to the i steep bank conditions and varying topography of the river bank, additional quarry spalls were needed. The installation at Foster Point required a significant quantity of quarry spalls to achieve an installation acceptable to the Department of Fisheries. A total of 137.4 tons of quarry spoils were placed at the outfalls. .1 AFP Change Order Log FINAL Change Order Days Scheduled Completion Date Original Contract Amount without tax: 36,539,000.00 Additional Change Order Change Amount Calendar Modified Contract Amount Total To Date Days Tax) 35,631.05 I 2 5848.68 I 0 (5975.00 0 55.494.491 1 $101.847.0( 0 $1,104.2 1 (55,906.401 0 52,404.4 1 3255.01 5332.211 0 56,504.391 0 $224.7V 0 51,133.04' 0 $7,855.92 1 015 Allentown Storm 'Allentown Gas Line Conflicts at 122nd and 46th: Payment to re -align storm drain and gas conflict at S 122nd St and 46th Ave S vicinity. 5393.861 0 1 016 Foster Point- Water Foster Point Electrical Hookup to Waterline: While performing work in Foster Point. the Contractor encountered an existing Ductile Iron Pipe for water service at then $965.991 0 residence of 13315 56th Avenue. The pipe encountered was carrying thirty volts of electricity, which was touching the steel shoring. There was no lost time and no fuse aid was necessary. Cast impact for this issue included one and a half hours of shutdown time to analyze the situation. Justification for Change: Correct a safety hazard the existed in the field 017 I Foster Point Sewer 'Addition of Flow Meters at Lift Stations: City requested two flow meters at both the Allentown and Foster Point Lift Stations, These devices will provide operation andl 561,121.0 10 maintenance control by providing flow iniennation. 018 Foster Point Sewer Foster Point Dewatering: The two monitoring wells installed in Foster Point, near the lib station, were converted to production wells. The total cost for two addeddl1 334,572.00 0 dewatering wells in Foster Point was! $45,215.00, minus the cost of the eight monitoring wells (included in the contract) at a cost of 310,643.00. The net increase to th contract is 334,572.00. 019 Foster Point Sewer Foster Point Lift Station Elevation: The Foster Point L91 Station site was raised one loot to provide drainage towards the street. The cost to supply and install a one foot 31,699.23 0 section for the 72' wet well totals 31,015.32, and the cost to supply and install a one foot section for the 48' manhole to match the raised wet well totals $683.91. Cost fa grade ad and related features will be dealt with separately. I 'Sales Tax 6.8% 36, 544,631.05 I $5,631.0` 36,545,479.73 1 $6,479.73 $6,544,504.731 35,504.73 $6,549,999.22 I 310,999.22 $6,657,846.22 3118,846.22 $6,658,950.501 $119,950.50 56,653,044.101 $114,044.10 56, 655,448.50 I 5116,44 8.50 56,655,703.52 I 5116.703.52 $6,656,035.73 i 5117,035 73 56,662,540.12 I 5123,540.12 36,662.764.85 5123,764.85 36,663,897.89 5124,897.89 $6,671,753.81 3132,753.81 56.672,147.67 1 56,673,113.66 56,734,234.66 1 5195,234.66 56,768,806.66 5229,80666 56.770,505.89 3231,505.89 56,770,505.89 5231,505 89 Page 1 of 5 Printed: 07/11/2007 5133,147 $134,113.66 Change Order No. Location I Type Description 021 Pump Changes: During the submittal review process, a discrepancy was discovered between the pumps at Allentown and Foster Point. The City decided to use all pumps from Paco. Due to the length of time to decide on the approved pump, the contractor's quote for the bid pumps expired, resulting in additional costs, During the review process, a number of pump manufacturers were discussed. Quotes were received for providing Cornell pumps for both projects. Based on cost of the Cornell pumps m approximately $10,000 In added costs, the use of Paco pumps was approved, The pumps in Allentown were increased in size from 2 to 3 horsepower, based on further review of the pump performance curves and intended use. The added costs include impacts due to expired quotes, upsizing of pumps from 2 to 3 horsepower, anq extending the power supply cords from 25 to 40 feet, I 022 Allentown Sewer Allentown Conflict with Existing 12" Force Mains on 441h Place South: While installing sanitary sewer in Allentown, the existing twin face mains which are depicted on the plans to parallel the 8" sewer line on 44th Place South, were in conflict with the centerline of the 8" PS for 40% of the length of the run. As a result, portions of the twc force mains had to be removed with the excavation of the 8' PS, causing slow down, extra work and eventual disposal of the removed pipe. The sewer main between MH 5C PL -03 and 50 PL -01 was lowered from 1.0% to 0.4 As a result, the 8" stub out of MH 50 PL -01 was in direct conflict with the two 12" abandoned force mains, which had to be cut out and plugged with concrete. 023 Allentown- Water (Allentown Locating Water on 44th Place and 122nd Street: Pothole to locate existing 8" water main in vicinity of proposed sanitary sewer at 44th Place and 122n1 Street. Based on findings, City directed contractor to install two temporary water services to 12207 51st Place and 4918 122nd Avenue. 024 1 Allentown Water 'Allentown Extension of Water Main on 42nd Avenue: Ten feet of additional 4" line was installed at STA 27 +34 on 42nd Avenue South (Plan Sheet 28 of 70). Thd shackle rod restraint and removal of thrust block is incidental to contract work indicaled on the plan note for the water line. 026 Allentown Water Allentown Fire Hydrant Relocation: Contractor relocated two existing fire hydrants. The Ore hydrant at STA 30+97 LT (Plan Sheet 13 of 70) is In direct conflict with th proposed 8' sanitary sewer, and was extended beyond the limits of the sewer trench. The fire hydrant at STA 28+06 RT (Plan Sheet 28 of 70) is to be moved out of th proposed sidewalk lints. Both locations were reviewed and approved by the City of Tukwila Fire Marshall. 027 I Allentown Storm Allentown Curb and Gutter on 42nd Avenue: Based on field review of existing conditions, additional driveways were added to the contract as well as widths o 'driveways being adjusted to accommodate existing driveway locations. 028 Allentown Water Additional Fire Hydrants: At the request of the City of Tukwila, four additional fire hydrants are to be added to the project at the following locations: Allentown 44th Place South 10 +75 23' RT, Allentown 10 50th Place South 21 +25 20' RT; Foster Point C1.06 Pamela Drive 61 +39 17' RT; Foster Point C1.02 56th Ave S, 20+80 17' RT 029 Allentown Sewer Allentown Relocation of Sewer on 49th Avenue S and 124th: Per field directive dated September 29, 2006, the location of SSMH 4-124-04 (plan sheet 12 o170) at the' intersection of South 124th Street and 49th Avenue South was moved north approximately 7 feet. SSMH 4-124-03 (west of SSMH 4-124-04) was moved 2 feet to the north This moved the sewer line out of the roadway to limit the amount of impact to the truck traffic along 124th and reduced the overall amount of roadway rehabilitation necessary, of approximately 175 LF on 124th Street. 030 Foster Paint Sewer Foster Point Field Adjustments for Fiber Optic: Conflicts were encountered with the buried fiber optic cable running near the centerline of 56th Avenue South. On 5113106, while setting Manhole 4 in Foster Point, the fiber optic line was found to cross directly in the planned location of SSMH 4. This manhole was moved 2.5' south lc avoid the conflict. On 5131106, while constructing 8" SS pipe towards SSMH 5, the fiber optic line conflicted with the proposed sanitary sewer alignment, requiring slowed production to protect the existing fiber optic facilities. The fiber optic line was not as shown on the bid documents. 031 Allentown Water Allentown Electric Line Entangled in Magnolia Tree: A magnolia tree was in line with the location for a side sewer service at the residence of 12050 441h Place (plan sheet 2 of 70). Due to the proximity, the sewer location remained and the magnolia tree was removed with the property owner's permission. Upon removal of the tree an its rootball, adjacent underground utilities to the house were damaged, as the roots had grown around the underground lines for power, 032 Allentown Storm Allentown Replace 18" Storm Drain Pipe With 18" Ductile Iron Pipe: Per the request of John Howat, City of Tukwila, the following changes are being made to th storm drain system: 1. Plan sheet C3 of C5 and 4 of 70 Replace existing 18" concrete pipe with 45 LF of 18' ductile Iron pipe from CB 5 (Sta. 21 +71.93 -14.14 RT) to th roadside ditch at sta. 21 +72 LT Install a new CB Type II 48' diameter. and install 100 LF of 24' diameter Hancor Hi -Q pipe (HOPE), and construct a rock spillway in th existing roadside ditch. 2. Plan sheet 3 of 70 Delete the proposed 60 LF of 18' ductile iron culvert at Sta. 16+00 LT this location was found to be at a high spot In the ditch profile, rendering the proposed culvert useless. 033 Foster Point Sewer Foster Point Addition of 7 LF of 12" storm drain pipe: Added storm drain pipe on 56th at added catch basin near the pump station. Due to a conflict with an existing( 5220.5C 0 MCI fiber vault, the catch basin was relocated from Sta. 14+95. 12' LT to Sta. 15 +10, 12' LT. The added crossing, catch basin, and connection to the stormcepler manhole! at Sta. 14+95, 12' RT, was addressed by issue 48 and a separate change order. This specific change is for the shilting of the catch basin, and subsequent need for 7 LF of 12" PSD. ISales Tax 8.8% 034 Allentown Water Allentown Water Main Extensions at 124th and 51st: The proposed sanitary profile conflicted with the design grades of the waterline at the intertie on plan sheet 13 of 54,018.91 1 70 Sta. 18+05 (51st Place South), at the intersection of 51st Place South and 124th Avenue. The resolve the conflict, the following additional work was performed: 1 Construct a vertical waterline adjustment, per plan sheet 47 and 48. 2. Replace the thrust block on the waterline, east of the sanitary sewer, as the existing block was disturbed. 3. Encase the new 8' sanitary sewer in 12' ductile iron pipe for a length of 20 feet, centered on the waterline crossing. The sanitary sewer will be above tha waterline. 4. Backfill the affected area with CDF. Highline water district intertie Water district 75 intertie Water district #75 intertie 035 1 Allentown Sewer 'Allentown Tree Slump Removal at Sta. 14+64 RT: Tree stump encountered at Sta. 14.64 RT, at house 12253 51st Place was not shown on plans. The stump had 10 1 5192.851 0 1 removed to install a 6' side sewer. 036 Allentown Water Allentown Replace 314" Corp with Stainless Steel Repair Band: Abandoned water service at Sta. 13+40 on 501h Place South was struck by Contractor. The service $500.00 0 was unmarked and unknown. The City of Tukwila Water Department directed the Contractor to remove the existing 54' Corp service from the top of the existing water main and install a City provided stainless steel band to patch the hole. AFP Change Order Log FINAL Additional Change Order Change Amount Calendar Modified Contract Amount Total 1'o Dale Days Tax) $1,293.50 69 58,354.85 2 52,095.861 0 0316.001 0 52,079.3:" 1 51,251.601 0 $21,123.00 0 ($14,483.75; 0 52,221.92 0 5767.01 0 510,640.40+ 0 56,771,799.39 $232,799.39 j $6,780,154.24 $241,154.24 56,782,250,101 5243,250.10 $6,782,566.10 1 $243,566.10 $6,784,645.49 5245,645.49 56,785,897.091 $246,897.09 $6,807,020.09 $268,020.09 56,792,536.34 $253,536.34 $6,794,756.26 $255,758.26 $6,795,525.27 5256,525.27 56,806,165.73 $267,165.73 56,806,386.23 5267,386.23 56,806,386.23 1 5267,386 23 56,810,405 14 5271,405.14 56,810,597.99 1 5271,597.99 56,811,097.99 5272,097.99 Page 2 of 5 Printed: 07/11/2007 Change Location 1 Type Description Order No. 037 Foster Point Water Foster Point Water District 8125 Inter -Tie: As directed by City of Tukwila Water Department, the Contractor coordinated a water shutdown with Water District #125 an removed an existing 2' inter -tie tap off the existing 8' main. Repair hole from 2' service connection on 8" main with a stainless steel repair band. Approximate location a Sta. 45+40 RT on 57th Avenue S in Foster Point. 038 I Allentown Sewer (Allentown Addition of Manhole on 44th: As requested by the City of Tukwila, An addit sanitary manhole was added at SLa.18+50 on 44th Place South. Relerer plan sheet 3 of 70. In addition, Install a 8' PVC stub to the property line, approximately 25 LF. This new stub will provide service for future development. 039 Foster Point Roadway Foster Point Toddland Addendum 3: At the intersection of S. 133rd Street and 57th Avenue South (Sta. 42+64). the design show a portion of the roadway extendin beyond the 90 degree lum In the road. This section of road is to act as a fire lane. As directed by the fire marshal, the limits of paving for this area are to be extended 1 feet in width, for a total width of 30 feel, to provide suitable tumaround for the fire department This change will provide for the added pavement and related grading in thi area. 046 Foster Point- Roadway Foster Point Steel Plate Root Barrier: Existing tree roots were cut during installation of sanitary sewer along the north side of street on 57th at Sta. 44+80. A steel plater root barrier was installed to prevent roots from extending into the roadway prism. Reference plan sheet C1.05. Additional Change Order Change Amount Calendar Modified Contract Amount Total To Data Days Tax) 0815.95 0 $1,943.591 0 $845.09 0 040 I Allentown Water 'Allentown Water Corp Repair: Per request by the City of Tukwila Water Department, the Contractor replaced a failed water corp at Sta. 9+97 RT, at the intersection of S. 0238.54 0 I $6,614,941.14 1 $275,941.14 125th Street 46th Avenue South, drawing 14 of 70. I 041 Allentown Roadway Allentown Pre -level Transition from 50th Placa to 130th Street: The existing asphalt pavement conditions at the intersection of 50th Place S. and S. 130th Street' 51,127.18 0 56,816,068.24 $277,068.24 Allentown required the placement of 13 tons of pre -level to provide a consistent cross slope and profile of S. 130th Street, as It Ws into 5011 Place South. The existin paved surface was severely distressed and very uneven. An overlay would not provide a suitable roadway section. 042 Foster Pont- Roadway Foster Point Extension of Overlay on 130th: Change Order 1 extended and re- aligned the storm drain on S. 130th Street to the east side of the roadway, and also( 59,061.W 0 06.82 5286,130,12 extended the stone drain north to Sta. 84 +37, in Foster PoinL Following installation of the stone drain, it was determined that the subgrade conditions were saturated, and not suitable for a 2' asphalt overlay from Sta. 82+70 to Sta. 81+60. Additional shoulder preparation was performed, and the adddion of a 2' g1t of asphalt was constructed k provide a weather proof base, and improve the roadway section strength. Secondly, the limits of the overlay were extended from Sta. 84 +30 to Sta. 82+90 on S. 1308 Street, to Improve the roadway following the instanation of the storm drain an the west side of the roadway. This resulted In an additional 44 Tons of asphalt and relate preparation, striping, and other work. 043 Foster Point Roadway Foster Point Revised Grades at 57th and 133rd: The planned elevations for the asphalt overlay at STA. 41 +92 (corner o15701 Ave S. and S. 130th SL) were too low for $7,110.52' 1 56,832,240.64 $293,240.64 residential driveway transitions. Contractor added 7 tots of recycled concrete to bring sub grade up 12 inches. Sales Tax 8.8°% (NIA Per Rule 171) I 56,832,240.64 1 6293,240.64 044 Foster Point- Water Foster Point Wheaton Property Water Service: A five fool minimum separation between water lines and sanitary sewer is required per the Department of Hea 01,673.821 0 66,833,914.46 5294,914.46 standards. At Sta. 14+40 RT on 56th Avenue South (reference plan sheet C1.01), house number 13361, known as the Wheaton property, the property owner's water servic was within Inches of the sanitary sewer. Per Criteria for Sewage Work Design Standard dated December 1998, the water service was encased In PVC pipe. and backfille with Controlled Density Fill (lean cement sand ma). 045 Allentown Sewer Allentown Re- Alignment of Sanitary Sewer on 47th and 124th: During installation of the Sanitary Sewer line on S. 124th Street, from Sta. 17+50 to 21 +30, the existing( $1,012.4E 2 56,834,926.91 5295,926.91 8' waterline was found to be 5 feet closer to the proposed sewer alignment than' indicated on the plans. The line was only 5 feet from the proposed sewer alignment. The thrust block for the lee at Sta. 19.90 was exposed during trenching operations. This required the replacement of the thrust block. The waterline was immediately shut down, and coordinated with the City of Tukwila Water Department This change provides for the replacement of the thrust bock, temporary bracing, and coordination with the City. $582.55 0 $453.94 0 $2,925.5P' 0 06,811,913.94 $272,913.94 $6,813,857.531 $274.857.53 56,814,702.62 5275,702.62 06,835,509.50 $296,509.50 56,835,963.44 5296.963.44 56,838.889.02 5299,889.02 047 Allentown Water Allentown Y." Water Service Upgrade to 1 h": The existing water service at Sta. 12 +10 (12218 51st Place S) was Increased in size from W to 1 W, as directed by the City of Tukwila Water Department. Reference plan sheet 6 of 70. This property is a commercial machine shop, requiring higher volumes of water. This change is for changes in material cost only. 048 Allentown Water Allentown Fire Hydrant Relocate at Sta. 31 +00: During construction, the existing hydrant at Sta. 31+00 on S. 12411 Street (reference plan sheet 13 of 70) was to abandoned, as the 4' water line was being disconnected. The City Water Department determined that this hydrant should be relocated and connected to the new 1 waterline. This change provides payment for the removal and reconnection of the existing to the new 12" main. This included necessary piping, a new 6' gale valve, an other fittings. 049 Allentown Stone Allentown Added Curb Inlet on 51st: Upon meeting with the City of Tukwila Operations Division after a heavy amount of rainfall, it was noticed that the properly at 122 $2,462.00 0 $6,841,351.10 0302.351.10 51st Place South is exceptionally low and would requires a curb inlet to collect stool runoff. The Contractor was directed to provide a curb inlet at Sta. 13+65 to captur runoff from. Reference plan sheet 6 of 70. Justification for Change: To collect storm runoff to property at 12234 51st Place South. 050 Allentown Water Allentown Stainless Steel Band Repair: At Sta. 13+90 on 124th Street (Plan sheet 13 o170), the Contractor discovered an existing 2' core stop that had been plugged, $1,153.07" 0 56,842,504.17 5303,504.17 in close proximity to a planned 10'x12' tee. This change provides for the removal of the 2' core slop, plugging the main, and providing and installing a 12' stainless stee repair band. Justification for Change: Repair to existing water main. AFP Change Order Log FINAL Page 3 of 5 Printed: 07/11/2007 Change Order No. Location Type Description 051 Allentown Water Allentown Realignment of Water Line on 51st Street S and Sewer Encasement for Water Line: In response to RFI 53, the waterline on 44th Place South, from Sla, $8,005.19 1 56,850,509.36 5311,509.36 r 20+55 to Sta. 21+80, was shifted north, to provide more separation between the proposed waterline and the existing 20" high pressure gas. Field investigation had shown only minimal horizontal separation between the gas and the proposed waterline. Costs for the horizontal shift in the waterline at Sta. 20+55 amounted to 51,478.24, for Ih added fittings, pipe, and related work. At Sta. 21+80, where the line was to bend back to the south and lie into the existing 8' line, the crossing of the sewer One presente clearance Issues. To provide adequate protection between the waterline and the existing sewer, both the water and sewer were encased in 5 CY of cement concrete. Th was sleeved in separate casing 10 feet each side of the crossing. The affected area had to be hand dug, dewatered, and form work placed due to the high groundwater table and the close proximity to the high pressure gas One. This sewer crossing work amounted to 56,526.95. Reference plan sheet 2 of 70. Justification loi 052 Allentown Water Allentown Waterline Connection at 50th Street and 124th: Existing water main has three feet of cover on 124th at Sta. 27+05. The connection to the existing 8' water 51,682.65 0 56.852,192.01 $313,192.01 main on 50th Avenue South did not match in profile. Additional fittings and work was necessary to vertically adjust the waterline and make the tie -in, The assembly was shackled, and a 6" x 8' reducer added. This change provides payment for the added fittings and labor Reference plan sheet 11 of 70 and RFI 044. 053 I Allentown Storm 'Allentown Stub Out for Storm Pipe on 51st Place: Contractor directed to install 4 LF of 8" DI storm drain to existing road side ditch from CB Type 1 al Sta. 18+84. This 5355.101 0 change provides payment for connection to CB. pipe installation, and grading. Reference plan sheet 8 of 70 and field directive dated 12119/06. 054 Allentown Water Allentown Added Fittings for Fire Hydrant on 441h Place: The added hydrant at Sta. 10+75 (reference Issue 47) was moved from the west side of the street to the easy $806.55 0 side. This move was made to provide a more protected location for the hydrant. This change required additional fittings to vertically deflect the hydrant service line tc provide adequate clearance under the existing road side ditch. This change provides payment for the additional fittings and labor to provide to affect this change. The hydrant was paid for under a separate issue. Reference plan sheet 4 of 70. 055 Allentown Roadway Allentown Increase Road Width at S 122nd: Direction was provided to the Contractor to increase the width of the road along S 122nd, from Sta. 27 +75 to 30 +3C 4693.6C 0 (reference plan sheet 5 of 70) from 18' to 20'. This will permit improved turning movements on the roadway. The typical section specified a width of 18' on plan sheet 52 of 70. This change provides payment for the added 8 tons of ACP necessary to accomplish this widening to a 20' width. 056 I Foster Point Sewer (Foster Point Lift Station No. 8 Gate Modifications •The fence gate at Litt Station No. 8 in Foster Point was designed to open into the street. Due to the proximity of the 5429.601 0 gate to the street, the fence was redesigned to slide. This required additional hardware and fence modifications. I I 057 Allentown Roadway VMS Signs for 50th Place Paving: Upon review of the traffic control plan for 50th Place South paving, it was decided that Variable Message Signs (VMS) signs should be $1,201.5C 0 utilized. Justification for Change: 50th Place South is a main thoroughfare for traffic from Interurban to SR900 through Allentown. The paving activities would require! shutting 50th Place South down, thus VMS signs were used in advanced to warn traffic to use alternate routes, therefore lessening the impact to the community. 058 Allentown Roadway Pavement Section Change on 50th Place: The pavement section on plan sheet 52 of 70 varied from the conditions found in the field. The existing pavement depth varied! 530,041.7f 1 from over 12' of ACP to 2' of ACP. To provide a consistent pavement section from Sta. 11+47 to Sta. 23+86, and to provide a stronger cross section for the truck traffic or this roadway, the following pavement section was agreed to, as outlined in DMJM Harris' letter of October 16, 2006. The design section had shown a 2" layer of ACP Class B over 2' of CSTC. The paving was revised to the following: Sta. 11+47 to 18 +75: 4" ACP Class B over 12' of ground existing roadway Sta. 18 +75 to 23+86: 2' ACP Class B overlay. The change resulted in an increase of 310.E tons of ACP Class 8, a reduction of 278 feet of pavement grinding, and a reduction of 370.18 tons of crushed surfacing top course (CSTC). Justification tar Change: Creates better quality product for the amount of traffic using the road. 059 Allentown Sewer Potholing: During construction there were various locations the Contractor was directed to pothole for possible revisions to the contract documents. Exploration was $1,937.28! 0 56,887,663.48 5348,663.48 needed in order to make a decision on a more feasible and less costly change. Justification for Change: Potholing was needed outside of the contract in order to locate the 20' gas main and existing water mains to make a decision on a new location for the sewer main. Ultimately, the potholing led to a value engineering decision. 061 Foster Point Roadway Fostor Point Pavement Section Change on 56th Ave. 5 and S 133rd St.: The pavement section will be changed on 56th Avenue South and South 133rd Street as" 59,727.56i 2 $6,897,391.04 5358,391.04 described in DMJM Harris fetter of October 4, 2006. This change will reduce the width of the travel lane froml2 feet to 11 feet, and provide a 5 foot walking path. The thickened edge will be reduced from 18' wide to 6'. The net result is an increase in roadway width by 1 foot. Striping 8' in width will be added to the roadway to delineate the road striping. The total estimate quantity is 1,700 LF The material shall be thermoplastic. A new type 22 catch basin and 24 LF of 8' DIP (class 52) will be added tc provide drainage from the proposed Ilft station to the stormceptor catch basin at Sta. 14+95.18 12' RT The location for the new catch basin is Sta. 14+95 12' LT. Reference plan sheet C1.01. Justification for Change: Road section changed to provide paved walking lane. Drainage added to account for super elevation transition from bridge 10 roadway 062 Foster Point Sewer Foster Point Generator Size Increase: Increase Foster Point Pump Station generator set and associated custom sound attenuated enclosure from 25 kw 10 35 kw. Thi modification is to replace the original 25 kw generator originally planned for this site to accommodate the increase in pump size planned for this pump station. Cost increase! includes cost from Cummins Northwest for the upsize in the generator set and related enclosure, as well as additional costs for Ashford Electric to remove previously installed conduits in the generator slab and relocate due to the change in position of the conduit stub up location related to the new generator set. Justification for Change: The Foster Point pump velocity was increased due to increased need for capacity. In turn, the generator size was increased for operation. Additional Change Order Change Amount Calendar Modified Contract Amount Total To Date Days Tax) $6,745.20 0 56,852,547.11 1 5313,547.11 $6,853,353.66 $314,353.66 $6,854,047.26 $315,047.26 56,854,476.921 5315,47652 56,855,684.42 5316,664.42 56,885,726.20 5346,726.20 56,904,136.24 5365,136.24 063 Allentown Roadway Allentown 42nd Avenue PSE Gas Main Relocation: PSE was ensile under emergency conditions to replace the aging 2' gas main from 116th Avenue to 122nd Avenue, $9,828.68 30 56,913,964.92 5374,964.92 Contractor was directed to cease work operations to allow PSE to replace the line. Impact to the contractor included extending critical work into adverse weather conditions as well as re- sequencing their work, Justification for Change: The contractor was directed to install import material for sidewalk bedding due to adverse weather conditions In order to place concrete for sidewalk. AFP Change Order Log FINAL Page 4 015 Printed: 07/11/2007 Change Location 1 Type Description Order No. 064 Foster Point Sewer Allentown 1 Foster Point Conduit Size Increase: Seattle City Light requested the 2' conduit be increased to 3' at both the Allentown and Foster Point Pump Stations. 512,415.021 4 Drawings and specifications required 2' conduit from generator to service pole. Seattle City Light came out for inspection and directed DMJM Harris to have the Contractor use 3' conduit instead of 2" which also increased the size of the junction box. Per Seattle City tight, this Is a standard that was not addressed in the design process. Due tc the scheduling of the pavement for both lift stations, DMJM directed the Contractor to utilize all work force and work overtime to complete the replacement 01 conduit In order to start paving the following week. Justification for Change: Required per Seattle City Light standards. 065 Allentown Roadway Allentown Guardrail on 42nd Avenue: After placement of asphalt on 42nd Avenue, the edge of road had been constructed closer to the edge of river due to the widening( $13,373.13 0 of 42nd Avenue. Near 116th Street it was particularly close and DMJM Harris directed Contractor to place approximately 250 feel of guardrail from Sta 33+00 to Sta. 36+00 Justification for Change: Safety concerns for traffic on 42nd Avenue. 066 Allentown Water Allentown Installation of 8" Water Line to Connect to 4" Line: Alter installing the 8' water line to connect to the existing 4' line at 42nd Avenue and 124th, the" Contractor was directed to make the connection further back to eliminate all of the old 4'. In doing so, the new line was approximately 2 W higher than the new connection point. In order to make the connection, the City of Tukwila required al pipe to be restrained to an "H" beam assembly encased in concrete. Sta. 27 +34, 2' LT. Justification for Change: The location on the drawings for the connection was not true to the actual location in the field. Therefore, the Contractor incurred additional excavation anq material costs I I 067 Foster Point Sewer Foster Point Woody Debris Bacilli: The soil backlit over the woody debris buried in the bank at Foster Point was entirely washed away by tidal action of the river. This void required 111 of the fife loose mixture (one -man to 4' size rock) to provide fdl for the void, armoring of the bank and security of the bank embedded portion of the woody debris. Justification for Change: Within the hydraufo permit, the Contractor was able to secure woody debris habitat from washing away into the river. 068 Allentown Roadway Allentown Additional Concrete for Property Owners on 42nd Avenue: Additional concrete was required to meet existing conditions of driveways and existing( sidewalks along 42nd Avenue. In some cases, steps were formed and placed as well as extending aprons to meet existing concrete driveways. Justification for Change: Severity of transitions on 42nd Avenue on various sidewalks and driveways were such that the Contractor incurred additional costs for concrete and labor. 069 Allentown Roadway Allentown 1 Foster Point- Additional Asphalt and Re- Grading: Alter the streets were paved throughout Foster Paint and Allentown, the City Engineer and DMJM Ham reviewed the site and identified driveways that should have had asphalt aprons to accommodate driveway transitions. Also Included in this change is the asphah around th flow -meter at Foster Point. The asphalt was needed around the lbw -meter because of the location at bridge. Recently, it was observed by the City of Tukwila that th landscape strip behind the Foster Point Litt Station was not desired for maintenance purposes. DMJM Harris directed the Contractor to place asphalt in the strip. 075 076 Foster Point Sewer (Allentown 1 Foster Point Intrinsic Safe Barrier Relays: The City of Tukwila directed the Contractor to furnish and install intrinsic safe barrier relays for float switches all "both the Allentown and Foster Point Pump Stations. Foster Point Sewer 'Allentown 1 Foster Point Pressure Switches: The City of Tukwila directed the Contractor to furnish and install pressure switches at both the Allentown and Foster P010 Pump Stations. AFP Change Order Log FINAL Additional Change Order Change Amount Calendar Modified Contract Amount Total To Date Days Tax) $1,513.92 0 $634.9( 0 $2,000.0( 0 $12,701.67 0 070 Allentown Roadway Allentown Channelization on 42nd Avenue and 56th Avenue: Contract plans did not indicate channelization for 42nd Avenue. DMJM Harris met with the City o $16,426.00 0 Tukwila to discuss channelization requirements. It was determined that channelization was needed and DMJM Harris worked with the City of Tukwila to develop a plan an executed a directive to the Contractor. Justification for Change: Due to the traffic on 42nd Avenue, channelization was needed. 071 Foster Point Sewer Foster Point Additional Block at Foster Point Litt Station: Elevation of the wens and vaults at the Foster Point Lilt Station mandated the block wall around the station( $4,385.0x 0 exceed the elevation which required two additional courses of block on the wall. This was determined after the frst four courses had been laid and finish elevations were' determined. Justification for Change: Additional block material and labor were required in order to bring the wall past the grade of asphalt at the Foster Point Lift Station 072 Foster Point Sewer Foster Point Forcemeln Conflicts on Interurban: 1) Drawing C4.O1 shows the FM alignment next to the existing concrete sidewalk in asphalt path. However, at Sta,' $8,980.65 0 201+50 there is an existing box, 2' x 4', forcing the trench to the north. This put the trench in direct conflict with the duct bank. Also, the duct bank was full of water, flooding' out the crew. 2) Sheet C4.01 shows electrical line. 2 each at Station 201+40. A total of 9 each were in the duct bank causing delays with extra depth and crossing Sta. 201+80. 3) Alia crews ran Into concrete duct bank. fiber optic duct bank and direct bury cable, none of which were shown on the contract drawings. 073 Foster Point Sewer Foster Point Lift Station Fence: The Foster Point Lift Station generator included an enclosure. Upon seeing the generator in place. it was observed that the north face o $2,800.0C 0 enclosure door would not open wide enough for operations to maintain service. DMJM Harris directed the Contractor to take a panel of fencing and cantilever it over the lac of the block wall to allow more space for the door opening. 074 Allentown Water Allentown: Additional Water Services: The City and DMJM Harris have reviewed the quantity of water service connections added to the contract in Schedule B item B -3 (5125,000.001 0 Based on a takeoff of the bid documents, a total of 34 planned water services were counted, and should have been included in the base bid for the project. Section 1-04.6 0 the Standard Specifications states that quantities over 25% of the planned quantity can be subject to renegotiation. 25% of the planned 34 water services provides a Iota quantity of 43 services, or an additional 9 services that would be performed at the unit price of 53,000 as bid. The total additional wafer services provided by R.L. Alia Iota 88 each, or a total of 122 services added. This does not include those service called for being adjusted in the plan documents, which were excluded from the total of 43 planned services. Per Section 1-04.6, a total of 9 services would be paid at the bid price of 53,000. The remaining 79 services would be paid for at a unit price of 31,417.00 each. The unit price of $1,417.00 Is based on a measured mite analysis prepared by DMJM Harris. The daily production Is based on a production of 3 services per day. Fro $843.11 0 53,908.311 0 56,926,379.94 $387,379.94 56,939,753.07 5400,753.07 56,941.266.99 $402,266.99 56,941,901.97 5402,901.97 56,944,701.97 5405,701.97 $6,957,403.64 5418,403.64 $6,973,829.64 5434,829.64 56,978,214.64 5439.214.64 $6,987,195.49 5448,195.49 56,989,995.49 6450,995,49 56,864,995.49 5325,995.49 56,865,838.64 I 5326.838.64 16,869,746.951 1330,746.95 Page 5 of 5 Printed: 07/11/2007