HomeMy WebLinkAboutUtilities 2008-04-07 Item 3C - Final Acceptance - Southcenter Boulevard Water Main by RL Alia Company
INFORi\1ATION MElVIO
To:
From:
Date:
Subject:
Mayor Haggerton
Public W orks Directo~
April 2, 2008
Southcenter Boulevard Water Main
Project No. 98-WT05, Contract 07-054
Project Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of retainage.
BACKGROUND
The Notice to Proceed for Contract No. 07-054 with R.L. Alia Company of Renton was issued
April 10, 2007. This project became critical after the 2001 Nisqually Earthquake broke the
existing 12-inch cast iron water main in the Green River Trail. The water main was repaired
but it was determined that the existing line needed to be upgraded to ductile iron pipe.
This contract was totally completed on November 13, 2007. Change Order No.1 was issued
in the amount of $24,000 for installing one 4" conduit for Time Warner Communications
along with two 2" spare conduits for Tukwila. Time Warner reimbursed Tukwila for the cost
of the 4" conduit. Change Order No.2 was issued as a fmal contract settlement in the amount
of $73,000.00, which caused the project to be over budget. Change Order No.2 was approved
by City Council on February 19, 2008. The change orders, fmal payment, and all fmal
documentation have been processed and the project is ready for closeout. The contract costs
are as follows:
Contract Award Amount
Change Orders
Subtotal
Sales Tax (8.9%)
Total Contract Amount
$ 703 ,000.00
97.000.00
$ 800,000.00
71.200.00
$ 871.200.00
RECOMMENDATION
It is recommended that this contract be forwarded to the Tukwila City Council on the
consent agenda for formal acceptance and authorize release of the retainage, subject to the
standard claim and lien release procedures.
Attachments: Vicinity Map
Information Memo Change Order No.2
Notice of Completion of Public Works Contract
P:\PROJECTS\A- wr Projects\98wt05 Southcenter Blvd\JNFO MEMO Acceptance - ALIA - Scu Blvd Water Main.doc
Southcenter Boulevard Water Main
Aerial Photo Map
Project No. 98-WT05, Contract 07-054
Project Completion and Acceptance
INFORMATION MEMO
TO: Mayor Haggerton
FROM: Public Works Director
DATE: February 6, 2008
SUBJECT: Southcenter Boulevard Water Main Replacement Project
Project No. 98-WT05, Contract No. 07-054
Change Order No.2 - Final Settlement - Budget Shortfall
ISSUE
Approval of Change Order No.2 brings total final project cost over budget.
BACKGROUND
R.L. Alia Company overran the contract time by approximately 100 days and was initially
assessed liquidated damages of over $100,000. Subsequently, R.L. Alia fIled a protest and
provided additional documentation and details demonstrating that, in a lawsuit, they may be
able to show that the plans were not clear enough to allow the bidder to plan for all the
intricacies required to install the new water main across the Southcenter Boulevard Bridge
through existing knockouts and penetrations without significant extra labor, materials,
equipment and contract time.
Subsequently, the final settlement Change Order was negotiated in the amount of $73,000 to
compensate R.L. Alia Company for all additional direct labor, equipment and material costs.
The fmal total for the construction contract is estimated to be $871,200.
Due to the overruns in time, the base contract of $89,615 for construction management (CM)
was increased with Amendment 1 by $12,414 and Amendment 2 is pending at $6,771, for a
CM total of $108,800.
The attached closeout budget analysis shows that the expenditures exceed the budget amounts
by $49,035.
ANALYSIS
This fmal settlement Change Order is a fair and equitable complete compensation.
Furthermore, this settlement minimizes the risk of a protracted battle with a.contractor and
eliminates potential litigation costs.
An upcoming agenda item for an interlocal agreement with King County Metro includes
savings of up to $110,000 for the City of Tukwila. King County will pay for the design and
construction if Tukwila agrees to pay for bidding and construction management. See page 81 of
the 2008 CIP for proposed savings.
RECOMMENDATION
Authorize the Mayor to sign Change Order No.2 for $73,000 and approve using ending water
fund balance due to savings in the Interurban Water Reuse project to pay for project budget
shortfall.
Attachments: Closeout Budget Analysis
2008 CIP page 81
C:\TempIXPGrpWlSe\Info Memo C0#2 2-06-08 - UC budget paper gLdoc
From:
State of Washington
Department of Revenue
PO Box 47474
REVENUE Olympia WA 98504 -7474 Contractor's Registration No. (UBI No.) 600 149 378
Date 3/20/08
City of Tukwila
6200 Southcenter Boulevard
Tukwila, WA 98188
Southcenter Boulevard Water Main (Proj. 98 -WT05)
Contractor's Name
Sub -Total 800,000.00
Amount of Sales Tax Paid at 8.9 71,200.00
(If various rates apply, please send a breakdown)
TOTAL 871,200.00
Comments: 8.9
Finance Approval
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Name Address of Public_Agency
r\
d
Notice is hereby given relative to the completion of contract or project described below
Description of Contract Contract Number
R.L. Alia Company
Contractor's Address
107 Williams Avenue S, Renton, WA 98057
Date Work Commenced Date Work Completed Date Work Accepted
4/10/07 11/13/07 3/15/07
Surety or Bonding Company
Hartford Fire Insurance Company
Agent's Address
Parker Smith Feek Inc. 2233 112th Ave NE, Bellevue WA 98004
Contract Amount 703,000.00
Additions 97,000.00 Liquidated Damages 0.00
Reductions 0.00
Signature
Type or Print Name Diane Jaber
Phone Number (206) 433 -1871
Department Use Only
Assigned To
Date Assigned
07 -054
Telephone Number
425- 226 -8100
Amount Disbursed 831,200.00
Amount Retained 40,000.00
lsbitrsing. officer:
TOTAL 871,200.00
The Disbursing Officer must complete and mail THREE copies of this notice to the Department of Revenue,
PO Box 47474, Olympia, WA 98504 -7474, immediately after acceptance of the work done under this contract. NO
PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of Department's certificate, and then only in
accordance with said certificate.
To inquire about the availability of this document in an alternate format for the visually impaired, please call (360) 753 -3217. Teletype
(TTY) users please call (800) 451 -7985. You may also access tax information on our Internet home page at http: /dor.wa.gov.
REV 31 0020e (6- 27 -01)