City of Tukwila
INFORMATIONAL MEMORANDUM
Mayor Haggerton
UTILITIES COMMITTEE
FROM: Public Works Directo
DATE: May 14, 2009
SUBJECT: Interurban Ave S Waterline Project
Project No. 04 -WT02, Construction Contract No. 08-093
Change Order Nos. 2 3
ISSUE
Approve Change Order Nos. 2 3 for the Interurban Ave S Waterline Project.
Jim Haggerton, Mayor
BACKGROUND
Gary Merlino Construction Company, Inc. was awarded the construction contract for the Interurban Ave S
Waterline Project for $311,000.00 plus sales tax with a 10% contingency of $33,899.00. Due to the
discovery of an unforeseen 8" waterline connection near the north end of the project, Change Order No. 1
was issued for $13,800.00.
DISCUSSION
After issuance of Change Order No. 1, additional items were required for the unforeseen 8" waterline.
Another existing water main to be connected was previously thought to be 8 inches but was actually 12
inches. Both of these circumstances required substantially more effort and materials to complete the
connections to the new water main.
Project staff and construction management consultants, Anchor QAE, reviewed the stated change order
requests and negotiated the proposed fees stated in Change Order Nos. 2 and 3 for $30,714.00
($16,390.21 $14,323.79). These costs were determined to be reasonable payment for the additional
work. The cost increase from these change orders is over the authorized 10% construction contingency of
$33,899.00 and require Council approval.
RECOMMENDATION
The Council is being asked to approve and forward Change Order Nos. 2 and 3 with Gary Merlino
Construction Company Inc., for the Interurban Ave S Waterline Project in the amount of $30,714.00 for
consideration at the June 8, 2009 Committee of the Whole meeting and subsequent June 15, 2009
Regular Meeting.
W \PW Eng PROJECTS \A- WT Protects \04WT02 IU WaterI,ne \Construction Phase \Gary Merino Construction \Change Orders 2 5 4-23-09\ Info memo CO 2 3 5 14 -09
Final doc
PROJECT NO.: 04 -WTO2
We the undersigned Contractor, have
this proposal is approved, that we will
noted above, and perform all services
therefore the prices shown above and
compensation.
ACCEPTED: Date
6A/
By
Original Contract (without tax)
Previous Change Order (1)
This Change Order (without tax)
REV. CONTRACT AMOUNT
Additional Calendar Days due to this change: 14 to 125 days
ORIGINAL: City Clerk (1 of 2)
Contractor (2 of 2)
file: p: \forms\
CITY OF TUKWILA
CONTRACT CHANGE ORDER NO. 2
DATE: 4 -27 -09 BUDGET NO.: 401.02.594.343.63.36
CONTRACT NO.: 08 -093
PROJECT NAME Interurban Ave. S. Waterline Construction
TO: Gary Merlino Construction Company, Inc.
You are hereby directed to make the herein described changes to the plans and specifications or do the
following described work not included in the plans and specifications on this contract:
NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued.
Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and
covenants; and
B. The rights of the "Owner" are not prejudiced; and
C. All claims against the "Owner" which are incidental to or as a consequence of this change are
waived; and
D. The Contractor must submit all Field Overhead and Horne Office Overhead Rates for approval
in advance of all change orders.
CHANGE: Additional Connections. Due to an the discovery of the unforeseen 8" waterline connection near the
north end of the project as addressed in Change Order No.1, additional work items beyond the CO No. 1 costs
($13,800) occurred. The related work included the addition of a 12" gate valve along with restraints needed to
isolate the two systems for future maintenance purposes between the 8 inch point of connection and the 12 inch
point of connection to the south. Also included was work needed to provide additional site restoration in parking
and landscaped areas.
When the work was performed, City staff and Anchor (CM consultant) documented and confirmed the required
additional work. The Contractor submitted a cost proposal and the actual amount was negotiated to $16,390.21.
This cost was determined to be reasonable payment for the additional work.
given careful consideration to the change proposed and hereby agree, if
provide all equipment, furnish all materials, except as may otherwise be
necessary for the work above specified, and will accept as full payment
below. This change represents a fair, equitable and complete
$311,000.00
13,800.00
16.390.21
$341,190.21
Contractor )/NRJ
Title
APPROVED BY THE CITY OF TUKWILA
By
Date
Mayor
cc: Finance Department (w /encumbrance)
Construction Inspector
Construction Engineer
o m 11° \y
1 GI
PROJECT NO.: 04 -WT02
CITY OF TUKWILA
CONTRACT CHANGE ORDER NO. 3
DATE: 4 -27 -09 BUDGET NO.: 401.02.594.343.63.36
CONTRACT NO.: 08 -093
PROJECT NAME: Interurban Ave. S. Waterline Construction
TO: Gary Merlino Construction Company, Inc.
You are hereby directed to make the herein described changes to the plans and specifications or do the
following described work not included in the plans and specifications on this contract:
NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued.
Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and
covenants; and
B. The rights of the "Owner" are not prejudiced; and
C. All claims against the "Owner" which are incidental to or as a consequence of this change are
waived; and
D. The Contractor must submit all Field Overhead and Home Office Overhead Rates for approval
in advance of all change orders.
CHANGE: During the course of construction it was anticipated that an existing water line from the east was 8 inches in diameter as shown on
City As -Built Plans and determine through the field review of existing water valves approximately 200 feet east of the point of connection. The
contractor installed the new 12" line with an 8" tee fitting to make the re- connection. After the new lines with the 8" tee were installed, the
contractor dug down approximately 12 feet to intercept the existing 8" line. When they reached it, it was actually a 12" line. This discovery
required the need to remove the previously attached 12' x 8" tee and 8" valve, and replace these with a 12" x 12" tee and a 12" valve. Staff also
added a 12" gate valve on the north leg of the new line to provide isolation of this portion of the system when needed in the future. This added
valve would isolate a smaller part of the local system thus resulting in lesser degree of service disruption and fire protection concerns to local
customers should the need for a temporary shutdown occur.
When the work was performed, City staff and Anchor (CM consultant) documented and confirmed the required additional work. The Contractor
submitted a cost proposal and the actual amount was negotiated to $14,323.79. This cost was determined to be reasonable payment for the
additional work.
We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefore the prices shown above and below. This change represents a fair, equitable and complete
compensation.
ACCEPTED: Date 7/ U "i Contractor
By
Additional Calendar Days due to this change: 14 to 139 days
Original Contract (without tax)
Previous Change Orders
This Change Order (without tax)
REV. CONTRACT AMOUNT $355,514.00
ORIGINAL: City Clerk (1 of 2)
Contractor (2 of 2)
We: p: \forms\
Title
$311,000.00
30,190.21
14.323.79 By
Mayor
APPROVED BY THE CITY OF TUKWILA
Date
cc: Finance Department (w /encumbrance)
Construction Inspector
Construction Engineer
TO: Ebenal General, Inc.
REV. CONTRACT AMOUNT
ORIGINAL: City Clerk (1 of 2)
Contractor (2 of 2)
CITY OF TUKWILA
CONTRACT CHANGE ORDER NO. 5
DATE: 5 -14 -09 BUDGET NO: 303.00.594.190.62.35 City Hall
PROJECT NO: 06 -BG01 CONTRACT NO: 08 -086
PROJECT NAME: Standby Power Upgrades Year One Construction
You are hereby directed to make the herein described changes to the plans and specifications or do the following described work
not included in the plans and specifications on this contract:
NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued,
Conditions: A. The following change, and work affected thereby, are subject to all contract
stipulations and covenants;
B. The rights of the "Owner" are not prejudiced;
C. All claims against the "Owner" which are incidental to or as a consequence of
this change are waived; and
D. The Contractor must submit all Field Overhead and Home Office Overhead Rates
for approval in advance of all change orders.
CHANGE:
The proposed work in Change Order No. 5 initially resulted from the discovery of the proposed generator site location at the west
side of was within a stream buffer. This location would create a sizeable amount of mitigation if built in this location. A new site
was needed to be determined. New sites were evaluated and design plans were revised with a location in the sloped lawn area in
front of City Hall. The costs associated with this location were becoming prohibitive. Finally a site was chosen in the furthest
westerly stall of the lower parking lot. This is the nearest feasible location in regard to the location of the existing electrical facilities
being connected.
We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all
services necessary for the work above specified, and will accept as full payment therefore the prices shown above and below.
This change represents a fair, equitable and complete compensation.
ACCEPTED: 9 Contractor: Ebenal General, Inc.
1s�
By Title I etovc Ae
Original Contract (without tax) 480,000.00 APPROVED BY THE CITY OF TUKWILA
Previous Change Order 14742.00 Date
This Change Order (without tax) 50,565.03
By
$545,307.03 Mayor
Additional Calendar Days due to this change: 76 for a revised total of 243 days