Loading...
HomeMy WebLinkAboutUtilities 2009-06-23 Item 3A - Contract Supplement #1 - 2009 Small Drainage Program Construction Management with KPG IncCity of Tukwila TO: Mayor Haggerton Utilities Committee FROM: Public Works Director DATE: June 16, 2009 SUBJECT: 2009 Small Drainage Proaram Project No. 09 -DR01, Contract 09 -044 Supplement No. 1 for Construction Management ISSUE INFORMATIONAL MEMORANDUM Approve Supplemental Agreement No. 1 to Consultant Contract No. 09 -044. BACKGROUND Base contract No. 09 -044 with KPG, Inc. of Seattle, WA was to provide design engineering services for the 2009 Small Drainage Program. Council awarded the construction contract to Green River Construction on June 15, 2009. This supplemental agreement with KPG will provide construction management support during the construction phase. ANALYSIS To properly manage this construction project, the City will need construction management support during the construction phase. Through this supplement, KPG staff will provide limited site inspections, reviews for material submittals, change order requests and as -built drawing preparation. Tukwila construction management staff will provide the majority of the construction management and field inspections. BUDGET SUMMARY Supplemental Agreement No. 1 was carefully reviewed and is reasonable. Contract Budaet $29,956.68 $40,000 Construction Management Attachment: Supplemental Agreement No. 1 W \PW Fno PROJECTS \A- DR Projects \09 -DRO (2009 SDP) Construction \Before Construction \Info Memo for KPG's CM Supp 91 6 -16 -09 Final doc Jim Haggerton, Mayor RECOMMENDATION The Council is being asked to approve Supplemental Agreement No. 1 with KPG, Inc. in the amount of $29,956.68 for the 2009 Small Drainage Program and consider this item at the July 13, 2009 Committee of the Whole meeting and subsequent July 20, 2009 Regular Meeting. City of Tukwila Public Works Department 6300 Southcenter Boulevard #100 Tukwila, \VA 98188 PROJECT: 2009 Small Drainage Program Construction Engineering Services This SUPPLEMENTAL AGREEMENT NO. 1 is to supplement the agreement entered into with KPG, Inc. and the City of Tukwila, which was executed on the 17` day of February, 2009. All provisions in the basic agreement remain in effect, except as expressly modified as follows: Article 2, Scope of Services, shall be modified as follows: The Consultant agrees to provide construction engineering services as requested by the City in accordance with the scope of work included as Exhibit A. Article 4, Payment, shall be modified as follows: Payment for work provided by Consultant shall be Horde as proviclecl on Exhibit B, attached hereto, provided that the total amount of payment to the Consultant for this work not exceed 829, 956.68 without express written modification of the Agreement signed by the City. The new total contract shall not exceed 888,5 without express written modification of the Agreement signed by the City. IN WITNESS WI- EREOF, the parties hereto have set their hands and seals this day of 2009. APPROVED: APPROVED: C1CY OF TUKWILA KPG, INC. Jim Haggerton Nelson Davis, Mayor Principal Attested: Christy O'Flaherty, City Clerk SUPI'LEMIENTAL AGREEMENT No. 1 AGREEMENT NO. 09 -044 PROJECT NO. 09-DRO1 KPG, Inc. 753 9th Avenue N. Seattle, WA 98109 Deliverables: Exhibit A City of Tukwila 2009 Small Drainage Program Supplement No. 1 Construction Support Scope of work June 5, 2009 The Consultant shall provide Construction Engineering support services for the 2009 Small Drainage Program as outlined below: A. Prepare for and attend pre construction conference with the City, Contractor, and affected utilities. B. The Consultant shall provide the field support to the inspector for the duration of construction. The level of effort for field support time is estimated at 12 hours per week for the contract duration. C. The Consultant shall review material submittals and RFI's provided by the Contractor as requested by the City. D. The Consultant shall review change conditions as they arise and make recommendation to the City for field changes /change orders. E. Prepare Record Drawings for the 2009 Small Drainage Program based on redline drawings provided by the City. Items to be provided by the Consultant: Documentation from site meetings, change conditions, and field directives. Change orders, if required. Full size Record Drawing mylars, 2009 Small Drainage Program HOUR AND FEE ESTIMATE EXHIB[T B Project: City of Tukwila 2009 Small Drainage Program Supplement No. '1 Construction Support I Labor Hour Estimate Total Fee Project Project Design Task Description Manager Engineer Engineer Technician Clerical 178.51 125.35 106.11 93.28 65.78 Fee Task 1 Construction Support A. Prepare for and attend are con meeting B. On call field support C. Submittal Review D. Field reviews /change orders E. Prepare Record Drawings Reimbursable expenses see breakdown for details Task Totals 2 8 4 8 2 4 0 0 0 0 0 1 0 0 858.42 144 I 0 1 8 17,234.16 16 I 0 1 4 2,674.92 16 1 16 1 4 4,881.44 8 24 1 4 3,707.74 1 600.00 29,956.68 24 I 4 184 40 I 20 June 5, 2009 PG Architecture Landscape Architecture Civil Engineering Total Estimated Fee: 29,956.68 Cost Reimbursable Breakdown Task 1 Construction Support Mileage 400.00 Reproduction 200.00 Task 1 Total 600.00