HomeMy WebLinkAboutReg 2014-06-02 Item 4H.2 - Contract Supplement #2 - Interurban Avenue South (South 143rd Street to Fort Dent Way) Design Support with KPG Inc for $357,973WA/ DePartnisest of TransPertedari
Supplemental Agreement
Number No. 2
OKPG' I con and Address
753 9th Avenue N
Seattle, WA 98109
Phone: 206 - 286 -1640
Original Agreement Number
13 -028
Project Number
90310402
Execution Date
1/29/2013
Completion Date
12/31/2015
Project Title
Interurban Avenue S, Fort Dent Way to S 143rd St.
New Maximum Amount Payable
$ 744,752.65
Description of Work
Provide construction engineering services during the pre - construction, construction, and closeout of the Interurban
Avenue S - S 143rd Street to Fort Dent Way project.
The Local Agency of City of Tukwila
desires to supplement the agreement entered into with KPG
and executed on 01/29/2013 and identified as Agreement No.
13 -028
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
The enntrart shall include the additional grope for cnnstnictinn engjneering cPrvicpc identified in the attached
Exhibit A -7
11
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for
completion of the work to read: No change in the completion date of 17/31 /2015
III
Section V, PAYMENT, shall be amended as follows:
Payment for the added scope items shall not exceed 5157,973 00 as shown in Exhibit E -9 without prior approval by
the Ciro
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces
below and return to this office for final action.
By:
Nelson Davis, KPG By:
DOT Form 140 -063 EF
Revised 9/2005
Consultant Signature Approving Authority Signature
Date
169
170
Exhibit M -4
Certificate of Current Cost or Pricing Data
This is to certify that, to the best of my knowledge and belief, the cost or pricing data (as defined in
section 15.401 of the Federal Acquisition Regulation (FAR) and required under FAR subsection 15.403 -4)
submitted, either actually or by specific identification in writing, to the contracting officer or to the
contracting officer's representative in support of City Project No 03 -RWO2 *
are accurate, complete, and current as of May 8, 2014 * *. This certification includes
the cost or pricing data supporting any advance agreements and forward pricing rate agreements between
the offeror and the Government that are part of the proposal.
Firm Anchor QEA, LLC
Name Ed Berschinski
Title Partner
Date of Execution*** May 9, 2014
* Identify the proposal, quotation, request for price adjustment, or other submission involved,
giving the appropriate identifying number (e.g., RFP No.).
** Insert the day, month, and year when price negotiations were concluded and price agreement
was reached.
* ** Insert the day, month, and year of signing, which should be as close as practicable to the date
when the price negotiations were concluded and the contract price was agreed to.
DOT Form 140 -089 EF Exhibit M-4
Revised 6/05
171
EXHIBIT A -2
City of Tukwila
Interurban Avenue S
S 143rd Street to Fort Dent Way
Supplement No. 2
Construction Engineering Support
KPG
Scope of Work
May 12, 2014
A. BACKGROUND
The following represents the general Scope of Services (Scope) to be performed by KPG Inc.
(Consultant) during the pre- construction, construction, and closeout of the Interurban Avenue S — S 143rd
Street to Fort Dent Way project (Project), for the City of Tukwila (City). The lead Construction
Management (CM) consultant will be Anchor QEA (Anchor) who will perform the day to day field
management under separate contract with the City during the construction phase of the Project. KPG will
provide on -call design support and Construction Engineering services (CE) under supplement of the
original design contract. KPG will work at the direction of the City's Project Manager in coordination with
the overall CM effort. All effort on this project will be as requested by the City or City assigned
Construction Manager. It is anticipated that budgets between Tasks will be adjusted as required to
provide the requested services.
B. SCOPE OF WORK
TASK 1 - MANAGEMENT / COORDINATION / ADMINISTRATION
1.1 The Consultant shall provide continuous project management for the project duration from June
1, 2014 to December 31, 2015.
1.2 The Consultant shall prepare monthly progress reports identifying work completed in the previous
month, work in progress, upcoming work elements, and reporting of any delays, problems, or
additional information needs. These reports shall be submitted with the Consultant invoices.
1.3 The Consultant shall provide continuous management and administration of all subcontractors
included in this scope of work.
Task 1 Deliverables: Monthly progress reports (20 months)
TASK 2 — PRECONSTRUCTION SERVICES
2.1 The Consultant shall provide on -call support, which may include, review of records management,
preconstruction utility coordination, and preparation and attendance at preconstruction meeting,
on an as- needed basis. Specific tasks are anticipated to include:
• Coordination meetings with City, Contractor and CM Consultant.
• Preparation of map graphics to facilitate utility coordination.
• Preparation of conformed plans and specifications.
• Prepare for and attend preconstruction meeting.
Task 2 Deliverables: Conformed Plans and Specifications
City of Tukwila Page 1 of 3 KPG
Interurban Ave S Construction Engineering Support 5/12/2014
172
TASK 3 — CONSTRUCTION PHASE SERVICES
3.1 The Consultant shall provide on -call support, which may include, weekly progress meetings,
review shop drawings, interpretation of plans and specifications, and construction change order
assistance on an as- needed basis. Specific tasks are anticipated to include:
• Construction Meetings: Attend weekly construction meetings or other project meetings at
the construction site to review, in conjunction with the City, the Contractor's progress and
construction schedule. Weekly attendance is not anticipated for the project duration;
however, the project engineer and other engineers will attend as requested. Provide
feedback and follow up as appropriate. Budget allowances for meeting attendance is
shown on the attached hour estimate based on the following assumptions on meeting
attendance:
• Weekly attendance for initial 6 months of construction (26 meetings)
• Attendance in preparation of traffic shifts between stages (4 meetings)
• Other meetings as requested by the City or City's field staff (estimate 10
meetings)
• Submittals: Review and comment on the Contractor's submittals as requested, including
shop drawings. Many of the submittals will be reviewed by the City or Construction
Management Services Consultant. It is anticipated that the Consultant will receive the
following submittals for review:
• Structural walls
• Irrigation system
• RRFB systems
• Illumination systems
• Drainage detention and water quality treatment components
• Other submittals as requested (see exhibit E for budget assumptions)
• Interpretation of Plans and Specifications: Provide technical assistance to clarify and
interpret the contract documents at the request of the City. Assist the City in answering
Contractor questions. Respond to requests for information (RFIs), prepare requests for
quotation (RFQs), and prepare construction field directives (CFDs).
• Change Order Assistance: In the event that the provisions of the Contract Documents
need to be revised, prepare the necessary revisions to the drawings and specifications.
On request, provide engineering or independent peer review of contractor, City, or utility
proposed plan changes.
• Subconsultant Construction Support: Project Subconsultants for structural (CivilTech)
and environmental (Widener & Associates) will be retained for construction support on an
as requested basis. Budget allowances for each Subconsultant are shown on the
attached reimbursable breakdown.
• On -call survey support: Provide surveyor support to verify contractors survey or layout,
assist with quantity verification, or other support needs as requested by the City.
• Materials Testing: Provide feedback as requested on any failing materials tests or
material substitution requests for compliance with contract requirements for gradation,
compaction, strength, etc.
• Assist with preparation and attendance at special events, such as preconstruction open
house, ribbon cuttings, and other events as requested.
Task.3 Deliverables: Documentation as requested in support of on -call construction support
City of Tukwila Page 2 of 3 KPG
Interurban Ave S Construction Engineering Support 5/12/2014
173
TASK 4 — UTILITY AND AGENCY COORDINATION ALLOWANCES
4.1 The Consultant will provide assistance to facilitate franchise utility relocations and adjustments as
requested by the City. These services may include design modifications that may be required to
facilitate franchise utility work. The purpose of this task is to provide a budget allowance and
tracking mechanism for possible reimbursement to the City by the franchise utilities. Work for
each utility will be tracked separately on monthly invoices. The City will be responsible for
obtaining reimbursement on these charges when applicable.
4.2 Assist the City with obtaining necessary project specific franchise utility agreements for utility
relocation work as requested.
4.3 Assist the City /CM with obtaining a general or specific utility permit from WSDOT for facilities in
State right of way limits.
4.4 Provide independent review of CM documentation records and assist with up to three (3)
progress audits with WSDOT.
4.5 Assist the City with obtaining a necessary administrative noise variance for night time work
anticipated and required through the contract specifications. The budget assumes that this is an
administrative approval and that public hearings are not required.
Task.4 Deliverables: Documentation as requested in support of on -call utility and agency support
TASK 5 — CLOSEOUT ASSISTANCE
5.1 The Consultant will provide record drawings within 60 days of receipt of information provided by
the construction contractor and the City of Tukwila.
5.2 The Consultant shall provide independent review of final construction documentation files and
assist with Project Management Review with WSDOT local programs.
Task.5 Deliverables:
• Record Drawing Mylars (full size)
• Half -size copy of draft
• Full -size and half -size copies of final record drawings
• Electronic files
C. OTHER SERVICES
The City of Tukwila may require other services of the Consultant. These services could include other
work tasks not included in the scope of work. These services may include, but are not necessarily limited
to, additional construction support; assistance with property issues; utility, agency, or audit support in
excess of the budget allowances contained in Exhibit E; or other services deemed necessary by the City.
At the time these services are required, the Consultant shall provide the City with a detailed scope of
work and an estimate of costs. The Consultant shall not proceed with the work until the City has
authorized the work and issued a Notice to Proceed.
City of Tukwila Page 3 of 3 KPG
Interurban Ave S Construction Engineering Support 5/12/2014
174
HOUR AND FEE ESTIMATE
Project; City of Tukwila
Interurban Avenue S
S 143rd Street to Fort Dent Way
Supplement No. 2 - Construction Engineering Services
Task
Description
EXHIBIT E -2,
Labor Hour Estimate
Project Senior-:; Project Const
Manager ; . Engineer. Engineer, Engineer
$ "179.26: $ 143.58 5.36':. $ 125.96n
t Architecture •
Landscape Architecture
• Civil Engineering •
To Bud • et:
Design Survey Document; 0
echnician ,Crew Specialist, ,Admin`.�:
86.18. $ 139 96' 1$ ; 112,70ii, $ - `74,25
Budge
Task 1 - Mana• ement / Coordination / Administration
Management and admin (20 months)
Monthly progress reports and invoices
Subcontractor Coordination
Mileage
Reproduction
Task Totals
17,310.50
5,070.11
2,535.05
200.00
Task 2 - Preconstruction Services
Coordination meetings with City and CM consultan
Prepare map graphics for utility relocation
Prepare conformed plans and specifications
Prepare for and attend precon meeting
Mileage
Re +roduction
Task Totals
Task 3 - Construction Phase Services
Construction Meetings / support
Submittal Reviews (Anticipated)
Submittal Reviews (As requested
Interpretation of Plans and Specs
Change order review and assistance
Subconsultant support coordination
On call survey support
Materials testing review
Mileage
Reproduction
CivilTech Budget Allowance
Widener Bud t Allowance
Task Totals
$ 9,020.26
$ 15,001.88
5,925.16
$ 7,055.79
100.00
2,500.00
9, 603.10
$ 40,488.66
$ 27,306.58
$ 7,245.65
$ 26,257.54
$ 37,149.07
4 $ 3,087.78
05/19/2014
$ 9,618.49
$ 5,455.77
$ 1,000.00
$ 500.00
$ 15,000.00
$ 5,000.00
$ 178,109.53
HOUR AND FEE ESTIMATE
Project: City of Tukwila
Interurban Avenue S
S 143rd Street to Fort Dent Way
Supplement No. 2 - Construction Engineering Services
Task!
EXHIBIT E -2
abor =Hour- Estimate
Project Senior Projects ; Cosst: .,Design;
Manager engineer ngineer Engineer« • $2 4179.26` ;$� 143.58 .`,$ 125.96_
Architecture •
Landscape Architecture
t Civil Engineering •
Total Bu d
Document . ,Office
ecialist Admin
112.70 $,,= :74.25 ='
•e
udget
Task 4 - Utili and A•enc Coordination Allowances
Su port franchise relocation tracking
Franchise requested change allowance
Assist with franchise agreements
Assist with WSDOT permit
Progress audit assistance
Assist City with administrative noise variance
Mileage
Reproduction
Task Totals
Task 5 - Record Drawings
Prepare Draft Record Drawings
Final Record Drawings
PMR audit support
Mileage
Reproduction
Task Totals
190 40 80
$ 17,702.23
$ 16,753.97
$ 19,740.88
$ 4,850.19
$ 12,322.59
$ 1,556.57
$ 200.00
$ 200.00
$ 73,326.44
4
16
40
0
40
60
0
0
4
4
4
8
0
10
20
0
0
4
$ 17,074.14
5,229.24
17,814.43
200.00
1,500.00
41,817.82
0
12
40
0
0
0
80
32
8
20 50 40 50 80 0 80 40
-------
Total Pro`ect Bud !et
Hourly rates are based on the following:
Direct Salary Costs
65.00
$ 52.06
41.83
45.67 $ 36.06
Overhead Rate
Fixed Fee
46%
31.25 $ 50.75
40.87
26.92
30%
05/19/2014
7,972
Totals
$ 120,230.81
$ 175, 272.48
$ 36, 069.24
$ 331,572.54