HomeMy WebLinkAboutUtilities 2009-08-25 Item 3B - Bid Award - Reed Trucking and Excavating for Gilliam Creek Basin Stormwater OverflowCity of Tukwila TO: Mayor Haggerton UTILITIES COMMITTEE FROM: Public Works Directoriri) DATE: August 19, 2009 INFORMATIONAL MEMORANDUM SUBJECT: Gilliam Creek Basin Stormwater Overflow Project No. 03 -DRO9 BID AWARD ISSUE Award the bid for construction of the Gilliam Creek Basin Stormwater Overflow. Jim Haggerton, Mayor BACKGROUND This project is not currently budgeted for construction until 2013 but is proposed for construction in 2009 in response to the problems at Howard Hanson Dam. Additional flows from the dam may lead to flooding in Gilliam Creek and affect the Tukwila Urban Center. This project will construct an 18" overflow pipe along Strander Blvd between the intersections of Andover Park West and Andover Park East. This overflow pipe will allow the Gilliam Creek Basin to drain to the Strander Blvd Pump Station to reduce potential flooding associated with high river events. The project was advertised for bids on August 5 and 12, 2009 and nine bids were received and opened on August 19, 2009. Reed Trucking Excavating, Inc. is the low bidder with a bid of $360,530.00. The engineer's estimate was $376,825.00. ANALYSIS The bids were reviewed and tabulated. No errors were found. Reed Trucking Excavating Inc's references were checked and found to be satisfactory. BUDGET AND BID SUMMARY (All amounts include sales tax.) Bid Results Estimate *Budget Construction 360,530.00 376,825.00 0 Contingency (20 72,106.00 75,365.00 0 Total 432.636.00 452.190.00 0 *Funding for this project is not programmed until 2013 and will come from the Surface Water Fund's ending fund balance. RECOMMENDATION Due to the urgency of this project, the Council is being asked to award the construction of the Gilliam Creek Basin Stormwater Overflow project to Reed Trucking Excavating, Inc. in the amount of $360,530.00 at the September 8, 2009 Regular Meeting. Attachments Bid Tabulation CIP Sheet W \PVd Eng \PROJECTS\A- DR Protects \03 -DR09 (Gilliam Creek Basin Stormwate: Overflow); Into Memc Bid Award doc Owner: City of Tukwila Project: Gilliam Creek Basin Sformwater Overflaw Engineers: PACE Engineers. Inc. ITEM ITEM OR NO. TASK DESCRIPTION ,I I, 2 3 4 1 5 6 7 I8 19 i 10 11 12 13 14 15 16 17 18 19 1 20 21 22 23 ROADWAY 11 -inch HMA 1/2" Patch TRAFFIC CONTROL DEVICES Traffic Control Devices Loop Detector. 6 -foot Diameter Plastic Arrow Plastic Stripe Raised Pavement Markers Type 1, Type 2 ROADSIDE DEVELOPMENT Property Restoration STORM DRAINAGE Contractor- Supplied Surveying and Staking Temporary Water Polution/Erosion Control Mobilization Resolution of Utility Conflicts Pothotnq Traffic Control Labor (Min, $35 /hr) Uniformed Police Officer Abandon Storm Drain Structure Trench Excavation Protection Storm Drain Pipe, 24 -inch Diameter Catch Basin. Type 2, 54 -inch Catch Basin, Type 2, 60 -inch with canal gate Catch Basin. Type 2. 72 -inch Connection to Drainage Structure Plug Existing Storm Drain Monument, Casing and Cover Sales Tax included in Unit and Lump Sum prices per Rule 171 Gilliam Creek Bid Tab 8-19-09.xls ENGINEER'S ESTIMATE QUANTITY NO. UNIT UNIT UNIT UNITS PRICE COST PRICE COST 1,160 SY $6400 574,240.00 $60.00 $69,600.00 1 LS 57.000,00 37,000 00 $5,000 00 95.000 00 $10,000.00 I 510.000 00 2 EA 5400.00 5800,00 51,000.00 52,000.00 5740,00 51,480.00 13 EA $95,00 $1,23500 3170.00 02,210.00 $165.00 92.145 100 LF $3.00 5300.00 $6 50 $650 00 $7.00 $700.00 20 100 5185.00 $3.70000 $1.00 520.00 $510.00 $10,200.00 1 FA 55.000.00 $5,000.00 55,000.00 $5,000.00 35,000.00 1 LS 53,000.00 83,000,00 53,800.00 1 FA 02,000.00 32,000,00 $2,000.00 1 LS $35.000.00 535.000 00 530,000.00 1 FA 55.000.00 $5,000.00 $5,000.00 1 FA 52,300 00 $2,300.00 $2,300 00 350 Hour 1 535.00 512,250.00 $35 00 175 Hour 1 $80 00 514,000,00 550,00 1 EA 1 $500 00 5500.00 $2,500,00 1 LS 515,000.00 $15,000.00 55,000,00 1030 LF 0150,00 5154,500.00 1 5165,00 2 EA 54,500.00 89,000,00 11 $5,000.00 2 EA i t $10,200 00 520,400.00 1 $6,000 00 1 EA 1 59 000.00 59,000,00 $10,000.00 1 EA 51.000,00 $1,000.00 11 5500,00 2 EA 0300.00 5600.00 1 2 EA 5500,00 $1,000 00 5750 00 Subtotal $376,825.00 $360,530.00 TOTAL BID $376,825.00 5360,530.00 REED TRUCKING 8 r ARCHER CONSTRUCTION I SCI INFRASTRUCTURE LLC 11 RODARTE CONSTRUCTION I ROAD CONSTRUCTION NW MOSBRUCKER EXCAVATING UNIT UNIT UNIT UNIT UNIT PRICE COST PRICE COST II PRICE COST PRICE COST PRICE 582,00 $95.120.00 871,50 082.940,00 575.00 $87,000.00 858,25 867,570.00 1 $62.00 53,800.00 $2,200.00 32,000.00 $2.000.00 $30,000 00 538,000.00 35,000.00 $5.000.00 52,300.00 $2,300.00 512,250.00 $45.00 58,750 00 $125.00 52,500.00 I $2,000.00 55,000.00 1 53,500.00 5169,950 00 11 5120,00 510,000.00 11 $5,700.00 $12.000 00 1 $9,420.00 510,000.00 1 $10,750.00 5500,00 11 52,150.00 5500.00 11 $670.00 $1,500.00 11 $930 00 11 $5,000 00 52,200 00 32.000,00 538,000.00 55,000.00 52,300.00 $15,750,00 $21,875.00 52,000.00 $3,500 00 5387,210.00 $387,210.00 BID TABULATION $2.000,00 5725.00 $115.00 $16,00 5215 00 $5,000.00 52,000.00 52,000.00 515.000,00 $5,000,00 $2,300.00 $42.50 $55,00 $1,500 00 54,200.00 5123,60000 $200.00 $11.400 00 82,800,00 $18,840.00 1 $7,000.00 510,750.00 11 011,500,00 52.150,00 1F$2.000.00 51,340.00 1 $750 00 $1,860.00 1 5800 00 1 52,000.00 51,450,00 31,495,00 $1,600,00 $4,300.00 $9.000 00 $800 00 5200 00 317.00 510,00 35,000.00 II 55,000.00 $2,000.00 52,000.00 $15,000.00 $5,000 00 $2,300.00 $14,875.00 $9,625.00 $1,500.00 $4,200.00 $206,000,00 55,600,00 $14,000 00 $11,500,00 $2,000.00 $1,500.00 $1,600.00 $5.000.00 $2,000 00 548,000.00 $5,000 00 $2,300.00 542 00 575.00 $2,000 00 $100.00 5250.00 $5,000,00 59,000.00 $12,000,00 $6,000,00 5200 00 $500,00 $9,000.00 51.600.00 $2,600.00 $1,700.00 $200,00 $5,000.00 $5,000.00 $5,000.00 $2,000.00 $48,000.00 $5,000.00 52,300.00 514,700.00 $13,125.00 52,000 00 $100.00 $257.500.00 $10.000,00 518,000.00 $12,000.00 $6,000.00 $400.00 $1,000.00 5397,485,00 5504,225 00 $397,485 00 $504,225.00 56,000.00 $765 00 $165 00 $13.00 $355.00 $5,300,00 52.000.00 342,400,00 $5,000.00 $2,300.00 548.00 380.00 $1,400,00 $16,800.00 $270.00 $6,100.00 $10,000.00 $12,600.00 51.200,00 $500 00 $900.00 I. 56,000,00 1 1 52,400.00 $1,530,00 I $770.00 $2.145,00 $170 00 $1,300,00 $6.60 $7.100.00 1 $530 00 05,00000 '1 55,000.00 $5,300,00 $2,000,00 $42,400 00 $5,000 00 52,300.00 $16,800 00 $14,000.00 51,400,00 516,800.00 $278,100.00 $12,200.00 $20,000.00 $12,600 00 31,200.00 $1,000.00 51.800 00 $523,545,00 $523,545 00 53,700.00 52,000,00 $34,940.00 55,000.00 $2.300.00 $51.00 $55.00 53,065.00 53.000.00 $348 40 54,790.00 $10,039.00 816.054 00 33,134,00 $1,069.00 5160.00 CONSTRUCTION COST 871.920.00 52,400.00 $1,540.00 $2,210.00 3660.00 $10.600,00 55,000.00 $3,700,00 52,000.00 $34,940.00 $5.000.00 $2,300.00 517,850.00 $9,625.00 $3,065.00 $3,000,00 $358,852.00 59.580,00 $20.078 00 $16,054.00 33,134,00 $2,178,00 5320 00 3586,006.00 5586,006,00 DONOVAN EXCAVATING 1fR. L. ALIA COMPANY UNIT PRICE COST $85.00 $7,700 00 $760.00 $170.00 $7.00 $525.00 $5,000.00 $2,200.00 $2,000.00 $34,000.00 $5,000,00 52,300.00 $44.00 $87.00 $4,900,00 $16,200.00 $278 00 511,100.00 $15,200 00 524,100.00 $7,400.00 $900.00 $770 00 $98,600 00 1l $70.00 $7,700,00 $1,520,00 52,210.00 $700.00 $10,500 00 55.000,00 $2.200.00 $2,000 00 $34,000.00 $5,000,00 52,300,00 $15,400 00 $15,225.00 $4,900.00 $16,200,00 5286,340,00 $22,200.00 1 $30,400.00 $24,10000 $7,400.00 $1,800.00 51,540.00 $597,235.00 5597,235.00 UNIT PRICE $7,000,00 $735,00 $160.00 $6.00 5500.00 55,000.00 $3,500.00 $2,000.00 $58,000,00 55,000 00 52,300.00 543,00 $80.00 52,900.00 510,000,00 $234 00 $12.500,00 $18,000,00 575,000.00 $3,000 00 $500.00 $700,00 08/20/2009 COST $81,200.00 $7,000,00 $1,470,00 $2,080,00 $600.00 1 510,000.00 I $5,000.00 53.500,00 $2.000 00 $58,000.00 $5,000.00 $2,300.00 515,050 50 510,500.00 $2.900 00 $10,000.00 $241,020.00 325.000,00 536,000 00 $75,000.00 $3,000 00 51.000,00 51 400.00 $599,020.00 $599,020.00 PROJECT: Gilliam Creek Basin Stormwater Overflow LINE ITEM: 412.02.594.38 PROJECT NO. 03 -DRO9 Provide storm drainage system to route Gilliam Creek basin outflow to the new Strander Boulevard storm drainage pump, when the flap gates are closed at the Gilliam Creek outlet. Reduces flooding at downstream properties by providing a method to drain the Gilliam Creek basin during high river events. DESCRIPTION: JUSTIFICATION: STATUS: MAINT. IMPACT: Decreases need for emergency pumping. COMMENT: Will reduce likelihood of roadway flooding at intersection of Andover Park East and Tukwila Parkway. FINANCIAL Through Estimated (in $000's) 2007 2008 2009 2010 2011 2012 2013 2014 BEYOND TOTAL EXPENSES Design 50 50 Land (RAN) 0 Const. Mgmt. 50 50 Construction 350 350 TOTAL EXPENSES 0 0 0 0 0 50 400 0 0 450 FUND SOURCES Awarded Grant 0 Proposed Grant 0 Mitigation Actual 0 Mitigation Expected 0 Utility Revenue 0 0 0 0 0 50 400 0 0 450 TOTAL SOURCES 0 0 0 0 0 50 400 0 0 450 Project Location CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2009 to 2014 J Monti Crook a N m 0 Q 2a 2009 2014 Capital Improvement Program 153 Existing Storm Drainage System ,0 Provide New I Overflow Pipe I StranderlBlvd W' Y tit a 0 Existing Storm Drainage System ro+I! Cnnsirsen Rd Puep'Slauon i