HomeMy WebLinkAboutPark 2014-06-18 Item 4A - Project Update PARKS COMMISSION PROJECT UPDATE CURRENT PROJECTS Restroom Counters Replacement at the Clubhouse Researching equipment, materials, and options for work to be completed. Target Completion Date: Spring 2014 Project Stage: Investigating materials and options Project Budget: $10,000 Duwamish Hill Preserve (DHP) Consultant to prepare design options for review for Phase II. Target Completion Date: On -going Project Stage: Design work Project Budget: $900K Ft Dent Parking Lot Repair Work This work is in conjunction with the Interurban Avenue overlay project. Construction bid has been awarded to Walsh Construction and work on the entire project is tentatively slated to begin July 5. Target Completion Date: 2014 Summer Project Stage: Pre - Construction Project Budget: $250K 5