Permit 86-53-SMP - SEGALE - BUILDING 861 SHORELINE SUBSTANTIAL DEVELOPMENT
ANDREA BEATTY RINIKER
Director
January 14, 1987
Mario A. Segale
P. O. Box 88050
Tukwila, WA 98188
cc: City of Tukwila
STATE OF WASHINGTON
DEPARTMENT OF ECOLOGY
Mail Stop PV -11 • Olympia, Washingtotl 9f3504 -8711 • (205) 459-6000
Dear Mr. Segale:
Re:. City of Tukwila Permit #86- 53 -SMP
Mario A. Segale - Applicant
Shoreline Substantial Development Permit #590-14-6604
The subject Shoreline Management Substantial Development
Permit was received by this office on January 12, 1987. The
review period by the Department of Ecology and the Attorney
General's Office will terminate 30 days from the receipt
date.
If no notice of appeal is received, construction pursuant to
the permit may commence following expiration of the review
period, provided that all other federal, state and local
laws regulating such construction have been complied with.
Other than a notice of appeal, this letter constitutes final
notification of action on this permit.
Sincerely,
. f 4A,..._o /h • /3e
Karen M. Beatty
Shorelands Management Section
(206) 459 -6771
,IAN 5 I:Jci/
D
CITY
T&• 1 J util
PLANNI`J Z DEPT.
(FM.SHR.M) (CP.SHR)
SHORELINE MANAGEMENT ACT OF 1971
PERMIT FOR SHORELINE MANAGEMENT SUBSTANTIAL DEVELOPMENT
NOTE - THIS PAGE FOR LOCAL
GOVERNMENT USE ONLY
Type of Action
[a Substantial Development Permit
Q Conditional Use
( J Variance
Pursuant to RCW 90.58, a permit is hereby granted to:
Mario A. Segale dba Segale Business Park
name of applicant)
Application No. 86 53 - SMP
Administering Agency Tukwila Planning Dept.
Approved XX Denied
Date
to undertake the following development: Three - Story 64,5nn siquvP fnnt rnnrrPte
(be specific)
office facility.
upon the following property: Northeast 1/4 35 -23 -4 in S.E. cnrnPr of South 180th
(legal description, i.e.. section,
and Andover Park West intersection.
township, range)
within ' Green River
(name of water area)
and /or its associated wetlands.
The project will be within shorelines of statewide significance
(be /not be)
(RCW 90.58.030). The project will be located within a urban
(environment)
designation. The following master program provisions are applicable to this
development Master Pro ram 4.2 .. 4.7• TMC 18.44.110 .130 .140 .150
(state the master program sections or page numbers
Development pursuant to this permit shall be undertaken pursuant to the follow-
ing terms and conditions staff approval of luminaire design
This permit is granted pursuant to the Shoreline Management Act of 1971 and
nothing in this permit shall excuse the application from compliance with any
other federal, state or local statutes, ordinances or regulations applicable to
this project, but not inconsistent with the Shoreline Management Act (Chapter
90.58 RCW).
This permit may be rescinded pursuant to RCW 90.58.140(8) in the event the per -
mittee fails to comply with the terms or conditions hereof.
CONSTUCTION PURSUANT TO THIS PERMIT WILL NOT BEGIN OR IS NOT AUTHORIZED UNTIL
THIRTY (30) DAYS FROM THE DATE OF FILING AS DEFINED IN RCW 90.58.140(6) AND
WAC 173 -14 -090, OR UNTIL ALL REVIEW PROCEEDINGS INITIATED WITHIN THIRTY DAYS
FROM THE DATE OF SUCH FILING HAVE TERMINATED; EXCEPT AS PROVIDED IN
RCW 90.58.140(5)(a)(b)(c).
12._-act-c56
(date)
Dir
AP
Tanning Department
THIS SECTION FOR DEPARTMENT OF ECOLOGY USE ONLY IN REGARD TO A SUBSTANTIAL
DEVELOPMENT PERMIT WITH A CONDITIONAL USE OR VARIANCE PERMIT.
Date received by the department
Approved Denied
This conditional use /variance permit is approved /denied by the department pur-
suant to chapter 90.58 RCW.
Development shall be undertaken pursuant to the following additional terms and
conditions:
(date) (Signature of Authorized Department Official)
4smETIO
►
December 23, 1986
Municipality of Metropolitan Seattle
Exchange Building • 821 Second Ave. • Seattle, WA 98104 -1598
Lfl I_ 1J °J
[DEC 241986]
CITY Crr T ilK.4 %1',LA
PLANNING DEPT.
Rick Beeler
Planning Director
City of Tukwila
6200 Southcenter Blvd.
Tukwila, Washington 98188
Determination of Non - Significance
File No.: EPIC - 347 -86 Mario A. Segale, Inc.
Metro staff has reviewed this proposal and anticipates no
significant adverse impacts to its wastewater facilities.
Public Transportation
South 180th Street, through Tukwila and Renton, is one of the
most congested arterials in the Green River Valley. Any new
development that will add traffic to this arterial needs to take
aggressive action to reduce trips generated from the site.
Metro recommends the following Transportation System Management
(TSM) activities, for an office development of this size and
nature.
1. Post transit /rideshare information and distribute to
existing and new employees.
2. Distribute ridematch applications annually.
3. If several developments of this size are located within a
two mile radius and are in a designated critical area, the
local jurisdiction may require the developer to join or to
form (with the assistance of Metro and the local
jurisdiction) an employee transportation association. The
purpose of this association will be to mitigate collective
traffic impacts.
4. Provide secure bicycle parking.
5. Establish a Employee Transportation Coordinator.
6. Provide preferential car /vanpool parking.
7. Provide HOV transportation subsidies (transit pass or
car /vanpool subsidies).
Rick Beeler
December 23, 1986
Page Two
8. Conduct periodic promotions.
9. Sell. Metro monthly bus passes.
10. Encourage flexible work hours where feasible.
The Transportation Management Plan and. Employee Transportation
Coordinator are essential pieces of a successful. Transportation
Management. Program. For more information or questions contact
Carol Thompson, Market Development, at 684 -1610.
Thank you for the opportunity to review and comment.
Sincerely,
Gregory M. Bush, Manager
Environmental Planning Division
GMB :vbg
WAC 197 -11 -970
Proponent
Mario A_ Sogale, Inc_
Responsible Official Rick Beeler
Position /Title
Address
Date,
FM.DNS
12/9/86
Planning Director
DETERMINATION OF NONSIGNIFICANCE
Description of Proposal A (4,6Do Square foot, 3 -story concrete office building in the
shoreline area.
Location of Proposal, including street address, if any Andover Park West and S. 180th Street,
Lead Agency: City of Tukwila File No. EPIC -347 -86
The lead agency for this proposal has determined that it does not have a probable
significant adverse impact on the environment. An environmental impact statement
(EIS) is not required under RCW 43.21C.030(2)(c). This decision was made after
review of a completed environmental checklist and other information on file with the
lead agency. This information is available to the public on request.
0 There is no comment period for this DNS
gi This DNS is issued under 197 -11- 340(2). Comments must be submitted by
12/23/86 . The lead agency will not act on this
proposal for 15 days from the date below.
6200 Southcenter Boulevard Tukwi
n. r+ a.. rz!. r�: trz�.*. rm: �w�yf! �f: w�; �C�! 4:. k"n± ^ ^�; :' -: .
Phone 433 -1845
Signature
You may appeal this determination to the C ty Clerk at City Hall, 6200 Southcenter
Boulevard, Tukwila, WA 98188 no later than 10 days from the above date by written
appeal stating the basis of the appeal for specific factual objections. You may be
required to bear some of the expenses for an appeal.
Copies of the procedures for SEPA appeals are available with the City Clerk and
Planning Department.
9. Do you know whether
proposals directly
explain.
No, do not know
of any.
ENVIRONMENTAL CHECKLIST
. BACKGROUND
1. Name of proposed project, if applicable: Building 861
2. Name of applicant: Mario A. Segale, d/b /a Segale Business Park
'1 `o. (136 ✓3170
• Epic File No. EPIC ,
Fee S100.00 Receipt No. 4459
3. Address and phone number of applicant and contact person: P. 0. Bax 88050,
Tukwila, WA 98188 - Attn: Ann Nichols
4. Date checklist prepared: . 9/86
5. Agency requesting Checklist: City of Tukwila
6. Proposed timing or schedule (including phasing, if applicable): Commence
Surcharge
7. Do you have any plans for future additions, expansion, or further activity
related to or connected with this proposal? If yes, explain. No
8. List any environmental information you know about that has been prepared, or will
be prepared, directly related to this proposal.
Environmental Impact Statement for Segale Business Park
Shoreline Management Substantial Development Permit - 1974
Shoreline Permit Buildinz 862
applications are pending for governmental approvals of other
affecting the property covered by your proposal? If yes,
�� tiwt.AtliC'itCe 'sic"c�uit'u:�'rF >k;.i, i ?�n;.Sut >i<s,(t,'Ci,..tia'tL4i
R :: *e:n:'•.ZY.t$ :,c.GfFi�.�,L"d� . �:•: 1T�., rieusr� ;cs.aa•s•.�ui7az.rr ruwr.». 1lWatw :yee 4.v. 1ganorcm azxvr."„:m" .vctrrrs vra^ xs^ r. �. 2 2v exel ikat,` f93Vi`,edSIY�'. i;u�wr
10. List any government approvals or, permits that will be needed for your proposal.
Shoreline Permit _
Building Permit
BAR Review •& Approval
12. Location of the proposal. Give sufficient information for a person to understand
the precise location of your proposed project, including a street address, if
any, and section, township, and range, if known. If a proposal would occur over
a range of area, provide the range or boundaries of the site(s). Provide a legal
description, site plan, vicinity map, and topographic map, if reasonably
available. While you should submit any plans required by the agency, you are not
required to duplicate maps or detailed plans submitted with any permit applica-
tions related to this checklist.
Directly so uth of SEC Int ersection of Andover Park West and S. 180th Street
NEk. Sec. 35. Township 23N. Ranee 4E. W.M.
11. Give brief, complete description of your proposal, including the proposed uses
and the size of the project and site. There are several questions later in this
checklist that ask you to describe certain aspects of your proposal. You do not
need to repeat those answers on this page. Section E requires a complete
description of the objectives and alternatives of your proposal and should not be
summarized here.
Three stogy concrete office building
13. Does the proposal lie within an area designated on the City's Comprehensive Land
Use Policy Plan Map as environmentally sensitive?
Yes, portion lies within the. Shoreline Mani emeit Urban Environment.
(Within 200 feet of Green River)
i J _. ✓ ` ; L : i • . 1 i Sari..
b. ENVIRONMENTAL ELEME.rTS
1. Earth
-
a. General description of the site (circle oneW
rolling, hilly, steep slopes, mountainous, other
b. What is the steepest slope on the site (approximate
percent slope)? 0
c. What general types of soils are found on the site
(for example, clay, sand, gravel, peat, muck)? If
you know the classification of agricultural soils,
specify them and note any prime farmland.
Silty sand
d. Are there surface indications or history of unstable
soils in the immediate vicinity? If so, describe.
No
e. Describe the purpose, type, and approximate quanti-
ties of any filling or grading proposed. Indicate
source of fill. Minor site grading for drainage
and landscaping source (import gravel borrow).
f.. Could erosion occur as a result of clearing,
construction, or use? If so, generally describe.
No
g. About what percent of the site will be covered with
impervious surfaces after project construction (for
example, asphalt or buildings)? 902 .
Agency Use Only
2. Air
LvaluatIon for
r Agency Use Only
h. Proposed measures to reduce or control erosion, or
other impacts to the earth, ifrany: N/A
a. What types of emissions to the air would result from
the proposal (i.e., dust, automobile odors,
industrial wood smoke) during construction and when
the project is completed? If any, generally
describe and give approximate quantities if known.
Dust, construction machine odors during
construction. Automobile odors
b. Are there any off -site sources of emissions or odor
that may affect your proposal? If so, generally
describe. No.
c. Proposed measures to reduce or control emissions or
other impacts to air, if any: Nona,.
3. Water
a. Surface:
after completion.
1) Is there any surface water body on or in the
immediate vicinity of the site (including year -
round and seasonal streams, saltwater, lakes,
ponds, .wetlands)? If yes, describe type and
provide names. If appropriate, state what
stream or river it flows into. Yes, Green
River.
2) Will the project require any work over, in, or
adjacent to (within 200' feet) the described
waters? If yes, please describe and attach
available plans. Landscape along toe of
dike, driveways, parking areas, portion
of building.
3) Estimate the amount of fill and dredge material
that would be placed in or removed from surface
water or wetlands and indicate the area of the
site that would be affected. Indicate the
source of fill material. None
4) Will the proposal require surface water
withdrawals or diversions? Give general
description, purpose, and approximate quan-
tities, if known. No.
5) Does the proposal lie within a 100 -year
floodplain? If so, note location on the site
plan. No.
6) Does the proposal
waste materials to
describe the type
volume of discharge.
involve- any discharges of
surface waters? If so,
of waste and anticipated
No.
• Lval aLi)n for
Agency Use Only
b. Ground:
c
1) Will ground water be withdrawn, or will water be
discharged to ground water? Give general
description, purpose, and approximate quan-
tities, if known. No.
OMNI
2) Describe waste materials that will be discharged
into the ground from septic tanks or other sour-
ces, if any (for. example: Domestic sewage;
industrial, containing the following
chemicals...; agricultural; etc.) Describe the
general sire of the system, the number of such
systems, the number of houses to be served (if
applicable), or the number of animals or humans
the system(s) are expected to serve.
None project will be served by
Tukwila sewer system.
c. Water Runoff (including storm water):
1) Describe the source of runoff (including storm
water) and method of collection and disposal, if
any (include quantities, if known). Where will
this water flow? Will this water flow into
other waters? If so, describe.
Storm water runoff will be collected
in catch basins and discharged into an
existing storm water Elston which is
pumped into the Green River by the
City of Tukwila.
_'.,i.63:1 :n for
Agency use Only
kttu�';- .::xsltav; qua: Y.: xsv: aranm.: s. ssw«.. ror ,.w„n. ».,.....r.e............ - - - - --
4. Plants
2) Could waste materials enter ground or surface
waters? If so, generally describe. No. _
d. Proposed measures to reduce or control surface,
ground, and runoff water impacts, if any:
No adverse impacts are expected.
a. Check or circle types of vegetation found
site:
deciduous tree: alder, maple, aspen, other
evergreen tree: fir, cedar, pine, other
shrubs
j 6_ grass
pasture
crop or grain
wet soil plants: cattail,
skunk cabbage, other
water plants: water 111.1
X other types of— vegetation
buttercup, bullrush,
eelgrassi milfoil, other
b. What kind and amount of vegetation will be removed
or altered? Ada.
c. List threatened or endangered species known to be on
or near the site. None .
evaluation for
Agency Use Only
on the
_............. w w w. v. nn u_.... avw. Y.�..w.y..r+.re..m�.w.aaWe�r.s. xur. mauwsFUanm+ uvw�maoaw..+ �w: m-. wa..,. wo.,r.. +nnrw.....w�x�,.rnm..a�...i,oro . ...,.+.*,..omrmi.n aISPRP WEVASIVINOW tAl*Mr
d. Proposed landscaping, use of native plants, or other
measures to preserve or enhance vegetation on the
site, if any: Existing vegp a i on wiLljNa___
removed and replaced with plaul=natural
to the Pacif i, . Northw�a such gs .juniper,
Photinea. etc.
5. Animals
a. Circle any birds and animals which have been
observed on or near the site or are known to be on
or near the site:
birds: hawk, heron, eagle, songbirds, other:
None observed.
mammals: deer, bear, elk, beaver, other:
None observed.
fish: • bass, salmon, trout, herring, shellfish,
other: None observed.
b. List any threatened or endangered species known to
be on or near the site. Not aware of any,
c. Is the site part of a migration route? If so,
explain. Not aware of any.
d. Proposed measures to preserve or enhance wildlife,
if any: None.
Evaluation for
Agency Use Only
7. Environmental Health
6. Energy and Natural Resources
a. What kinds of energy (electric, natural gas, oil,
wood stove, solor) will be used to meet the
completed project's energy needs? Describe whether
it will be used for . heating, manufacturing etc.
Electric energy for heating, cooking,' lighting.
b. Would your project affect the potential use of solar
energy by adjacent properties? If so, generally
describe. No .
c. What kinds of energy conservation features are
included in the plans of this proposal? List. other.
proposed measures to reduce or control energy
impacts, if any: Double glazing of windows,
others to code.
a. Are there any environmental health hazards,
including exposure to toxic chemicals, risk of fire
and explosion, spill, or hazardous waste, that could
occur as a result of this proposal? If so,
describe. No .
1) Describe special emergency services that might
be required. None.
2) Proposed measures to reduce or control environ-
mental health hazards, if any: None.
Evaluation for
Agency Use Only
b. Noise
c. Describe any structures on the site. None.
1) What types of noise exist in the area which may
affect your project (for example: traffic,
equipment, operation, other) ?
2) What types and levels of noise would be created
by or associated with the project on a short -
term or a long -term basis (for example: traf-
fic, construction, operation, other)? Indicate
what hours noise would come from the site.
Construction noise during construct-1W:
Automobile noise after completion.
3) Proposed measures to reduce or control noise
impacts, if any: None.
8. Land and Shoreline Use
a. What is the current use of the site and adjacent
properties? Vacant.
b. Has -the site been used for agriculture? If so,
describe. Not for at least ten years:
Evaluation for
Agency Use Only
u'.w ra: ws. w:.! c u.�r���.urlur:,wer:mrerx�nx.`ry tg...R rra: rsw......•xnv n.. r..:. rrv..+ w.w r..wuwnhutwrsiyw.nn:.t.ste)4xvanr i+ .x nnn c^sxwva.ncrtw:NtitiMl«A5r'cd +S XW.110..C',�+V4bT.i::2 IEW
d. Will any structures be demolished? If so, what?
No.
MIMED
e. What is the current zoning classification of the
site? M -2
f. What is the current comprehensive plan designation
of the site? Heavy Industrial.
g. If applicable, what is the current shoreline master
program designation of the site? Urban.
h. Has any part of the site been classified as an
"environmentally sensitive" area? If so, specify.
Yes. within 200 feet of Green River,
i. Approximately how many people would reside .or work
in the completed project? 1 50
j. Approximately how many people would the completed
project displace? None.
k. Proposed measures to avoid or reduce displacement
impacts, if any: N/A
1. Proposed measures to ensure the proposal is com-
patible with existing and projected land uses and
plans, if any: Is compatible wi,th existing - And
surrounding office and industrial uses
Evaluation for
Agency Use Only
9. Housing
a. Approximately how many units would be provided, if
any? Indicate whether high, middle, or low- income
housing? None _
b. Approximately how many units, if any, would be eli-
minated? Indicate whether high, middle, or low-
income housing. None.
c. Proposed measures to reduce or control housing
impacts, if any: None .
10. Aesthetics
a. What is the tallest height of any proposed
structure(s), not including antennas; what is the
principal exterior building material(s) proposed?
Concrete glass.
b. What views in the immediate vicinity would be
altered or obstructed? None.
c. Proposed measures to reduce or control aesthetic
impacts, if any: None .
Evaluation for
Agency Use Only
12. Recreation
11. light and Glare
a. What type of ,light or glare will the proposal
produce? What time of day would it mainly occur?
None. Glazing reflectivity less than 15%
(non reflective glass) . --
b. Could light or glare from the finished project be a
safety hazard or interfere with views?
No. primarily concrete.
Glazed window fenestration with reflectivity
of less than 15% (non - reflective glass) .
c. What existing off -site sources of light or glare may
affect your proposal? None.
d. Proposed measures to reduce or control light and
glare impacts, if any: Types of lighting
(building and pa will be
restricted to interior of site
a. What designed and informal recreational oppor-
tunities are in the immediate vicinity?
Green River Trail entry.
b. Would the proposed project displace any existing
recreational uses? If so, describe. No.
c. Proposed measures to reduce or control impacts on
recreation, including recreation opportunities to be
provided by the project or applicant, if any:
None. Project is close to Green
River Trai entrance.
AIMIMMIr
-14-
».rwv�...,..o.r�.e.n..s. •n.....- .w.smwlr .10 .271 '9YAsettx7Ft}PA.7f.11S.rxr Y'
Evaliation for
Agency Use Only
13. Historic and Cultural Preservation
r
a. Are there any places or objects listed on, or pro-
posed for, national, state, or local preservation
registers known to be on or next to the site? If
so, generally describe; No.
b. Generally describe any landmarks or evidence of
historic, archaeological, scientific, or cultural
importance known to be on or next to the site.
None.
c. Proposed measures to reduce or control impacts, if
any: None.
14. Transportation
a. Identify public streets and highways serving the
site, and describe proposed accss to the existing
street system. Show on site plans, if any.
Andover Park West, Andover Park East
S. 180th Street
West Valley Highway
1 -405 and I -5
b.- Is the site currently served by public transit? If
not, what is the approximate distance to the nearest
transit stop? Yes, two blocks.
c. How many parking spaces would the completed project
have? How many would the project eliminate?
Will have 302 parking spaces, will eliminate
none.
Evaluation for
Agency Use Only
C
d. Will the proposal require any new roads or streets,
or improvements to existing. roads or streets, not
including driveways? If so, generally describe
(indicate whether public or private). No.
e. Will the project use (or occur in the immediate
vicinity of) water, rail, or air transportation? If
so, generally describe. No.
f. How many vehicular trips per day would be generated
by the completed project? If known, indicate when
peak volumes would occur. Does not apply.
g. Proposed measures to reduce or control transpor-
tation impacts, if any: Name.
15. Public Services
a. Would the project result in an increased need for
public services (for example: fire protection,
police protection, health care, schools, other)? If
so, generally describe. Fi and police
to cover project; health care only insofar
as rpnants might require emergency care.
b. Proposed measures to reduce or control direct
impacts on public services, if any. Tenant
security system.
�m.+ nw.. rra. r.. w. ranw�wo•. �w. wmvuwwv+ w.+ �r+ r,. r. nr.. uwy �nWnranww.+tt.mM.nMS�4efIX'MS.Yf JkYSAA !Ai1Sl`ri'i�lln!�4N).1YuPQ�h.i�
Lv,:waLion for
Agency Use Only
16. Utilities
a. Circle utilities currently available at the site:
(electricit natural as w t r r f
to ephone, sanitary sewer.) septic system, other.
b. Describe the utilities that are proposed for the
project, the utility providing the service, and the
general construction activities on the site or in
the immediate vicinity which might be needed.
Pi,gpt Power; Washington Natural Gas; Water
nictrit'r #75: Tukwila Sewer; Seattle Transfer;
Pacific+ Northwest Be11: City of Tukwila Water.
Signature
The above answers are true and complete to the best of
my knowledge. I understand that the lead agency is
relying on them to make its decision.
Signature: ice—.._
Date Submitted: September 26, 1986
Evauation, for
Agency Use Only
TO BE CO:AETED 7 Evaivatic,n for
; Agency Use Only
E. SUPPLEMENTAL SHEET FOR ALL PROJECT AND NON PROJECT
PROPOSALS
The objectives and the alternative means of reaching the
objectives for a proposal will be helpful in reviewing the
aforegoing items of the Environmental Checklist. This
information provides a general overall perspective of the
proposed action in the context of the environmental infor-
mation provided and the submitted plans, documents, suppor-
tive information, studies, etc.
1. What are the objective(s) of the proposal?
Develop three story concrete office building.
2. What are the alternative means of accomplishing these
objectives? Build an alternate design or
use alternate materials.
3. Please compare the alternative means and indicate the
preferred course of action: Other designs and
materials have been considered evaluated
and eliminated. The proposed project
represents the preferred course of action_
. Does the proposal conflict with policies of the Tukwila
Comprehensive: Land Use Policy Plan? If so, what poli-
cies of the. Plan? No.
Proposed measures to avoid or reduce the conflict(s)
are: N/A
-23-
Evaluation for
Agency Use Only
LEGAL DESCRIPTION (LOT 3)
That portion of the southwest quarter of the northeast quarter
and Government Lot 2 in Section 35, Twonship 23 North, Range 4
East, W.M. in King County, Washington described as follows:
COMMENCING at the northeast corner of the southwest quarter
of the northeast quarter of said section thence South 07 ° 44'
56" West, 409.70 feet; thence South 82 °15'04" East, 30.00
feet to the TRUE POINT OF BEGINNING; thence South 88 ° 15'04"
East, 85.36 feet; thence along a curve to the left having a
radius of 241.24 feet through a central angle of 31 °29'15"
an arc distance of 132.58 feet; thence North 60 °15'41" East,
89.08 feet to a point on a curve whose center bears South
73 ° 35'20" East; thence southerly along said curve to the left
having - a radius of 800.00 feet through a central angle of
13 °05'26 ", an arc distance of 182.79 feet, thence South 03
19'15" West, 141.75 feet; thence along a curve to the right
having a radius of 3,500.00 feet through a central angle of
03 °41'20" an arc distance of 225.34 feet; thence South 07 °00'
35" West, 20.08 feet; thence South 09 ° 03'25" West, 210.13
feet; thence North 82 °15'11" West, 289.85 feet; thence northerly
along a curve to the left the center of which bears North 79
31'39" West, having a radius of 2,530.00 feet through a central
angle of 02 ° 43'25 ", an arc distance of 120.27 feet; thence
North 07 °44'56" East, 546.97 feet to the TRUE POINT.OF BEGINNING.
Containing: 198,426.32 sq. ft., 4.56 ac.
LEGAL DESCRIPTION (LOT 3)
That portion of the southwest quarter of the northeast quarter
and Government Lot 2 in Section 35, Twonship 23 North, Range 4
East, W.M. in. King County, Washington described as follows:
COMMENCING at the northeast corner of the southwest quarter
of the northeast quarter of said section thence South 07 °44'
56" West, 409.70 feet; thence South 82 °15'04" East, 30.00
feet to the TRUE POINT OF BEGINNING; thence South 88 °15'04"
East, 85.36 feet; thence along a curve to the left having a
radius of 241.24 feet through a central angle of 31 °29'15"
an arc distance of 132.58 feet; thence North 60 °15'41" East,
89.08 feet to a point on a curve whose center bears South
73 °35'20" East; thence southerly along said curve to the left
having a radius of 800.00 feet through a central angle of
13 °05'26 ", an arc distance of 182.79 feet, thence South
19'15" West, 141.75 feet; thence along a curve to the right
having a radius of 3,500.00 feet through a central angle of
03 °41'20" an arc distance of 225.34 feet; thence South 07 °00'
35" West, 20.08 feet; thence South 09 °03'25" West, 210.13
feet; thence North 82 °15'11" West, 289.85 feet; thence northerly
along a curve to the left the center . of which bears North 79°
31'39" West, having a radius of 2,53 feet through a central
angle of 02 °43'25 ", an arc distance of 120.27 feet; thence
North 07 °44'56" East, 546.97 feet to the TRUE POINT.OF BEGINNING
Containing: 198,426.32 sq. ft.,•4.56 ac.
i'iR; ?C+;,v.. :.M:\I%
1,0 mss;
LEGAL DESCRIPTION (LOT'3)
LEGAL DESCRIPTION (LOT 4)
.u,a.a.:eeyn:
sr 211. M3
That portion of the southwest quarter of the northeast quarter
and Government Lot 2 in Section 35, Twonship 23 North, Range 4
East, W.M. in King County, Washington described as follows:
COMMENCING at the northeast corner of the southwest quarter
of the northeast quarter of said section thence South 07 °44'
56" West, 409.70 feet; thence South 82 °15'04" East, 30.00
feet to the TRUE POINT OF BEGINNING; thence South 88 °15'04"
East, 85.36 feet; thence along a curve to the left having a
radius of 241.24 feet through a central angle of 31 °29'15"
an arc distance of 132.58 feet; thence North 60 °15'41" East,
89.08 feet to a point on a curve whose center bears South
73 °35'20" East; thence southerly along said curve to the left
having a radius of 800.00 feet through a central angle of
13 °05'26 ", an arc distance of 182.79 feet, thence South 03
19'15" West, 141.75 feet; thence along a curve to the right
having a radius of 3,500.00 feet through a central angle of
03 °41'20" an arc distance of 225.34 feet; thence South 07 °00'
35" West, 20.08 feet; thence South 09 °03'25" West, 210.13
feet; thence North 82 ° 15'11" West, 289.85 feet; thence northerly
along a curve to the left the center of which bears North 79°
31'39" West, having a radius of 2,530.00 feet through a central
angle of 02 °43'25 ", an arc distance of 120.27 feet; thence
North 07 °44'56" East, 546.97 feet to the TRUE POINT.OF BEGINNING.
Containing: 198,426.32 sq. ft., 4.56 ac.
That portion of the southwest quarter of the northeast quarter
and Government Lots 2 and 5 all in Section 35, Township 23
North, Range 4 East, W.M. in King County, Washington described
as follows:
COMMENCING at the northeast corner of the southwest quarter
of the northeast quarter of said section; thence South 07°
44'56" West, 956.67 feet; thence along a curve to the right
having a radius of 2500 feet through a central angle of 02°
43'25 ", an arc distance of 118.84 feet; thence South 79 ° 31'39"
East, 30.00 feet to the TRUE POINT OF BEGINNING, thence South
82 ° 15'11" East, 289.85 feet; thence South 09 ° 03'25" West,
369.11 feet; thence South 06 West, 82.23 feet; thence
North 66 ° 54'09" West, 338.39 feet to a point of a curve whose
center bears North 71 ° 16'17" West; thence along said curve to
the left having a radius of 2,530.00 feet through a central
angle of 08 °15'22 ", an arc distance of 364.25 feet to the TRUE
POINT OF BEGINNING.
Containing: 124,141.73 sq.ft., 2.85 acres.
=
I' •
1
• ••• .
r A...*
'krt.
3
Al•
• ••
• -----•-_ - -
••••
5.•
' 2; „ • ,,•
Z. •
\L.
$-5.2••••1" acr
3
; "• •
r. •
i! • • -
//
m.■•■
■ . ;
t! •
r ■••• , !. 411..•
4 1 ••••t•r
1 I
s
ve
fr
2rt 1,
'
t•4•'f2 F..i.
------S•••Ag•••c muter ir
r
—
— - e.
11;
z
— —
---I
•
••• , —■■ a • •
•
• e
•••1:
fv• , ROW.'
/1 ••••
yrr Ago /10.4••••(.4l.0
P1
‘4,74.c••••■
• •.•t:
/••• 111
t•-• ICI•am.
4.•••••4•••
•••.e.••
• A... • I
1 I /
; , I. • \ ;
„ • • /
•
•••:71 534
1— e"-r
KC raw m •
t a.
■•■••SI.!••••1-.
• it •r:
• t „ . i I • t
i : • ,-.41 X•\.-f\-- \
, • •••■■1 0 . . _
1 • ,./ •-:. '
Ili„, ' • ' I . •
— V • ri • .::
i , / I • ()OM, :
. \
SI. WI,. ....
, A 1 '
2 • !---- ,
: • I
• : ----:". i ll i .5:-.
• I • ' ^ L.: / .,"
4
• • i -....,
.. I r "---- ‘• ,• , / \
WALE &WPM AVII,
WC/wry AAP l t_ .Vi ---4 i l i T
I. ';.. 5r / 0* •
\ \ \\\ \
r1 .. 7.-"'...
"...\.... . . , •••• • cow .:•,:tr Er • -A--... • i" - N - - -7- • • -'". . \ '''• - , - ..... ''v - - 4- - " . --
___1_,• :z 11 '' - - 1 a — — \ • ‘ 0 \ \ s a , -
r •- .- - 1, • •• 3r....,..• - . - 7." . 1 • 4 1.- -
....,_t /...- •
I
77
/11/41••
J.** AY
/•••••••••••••2 loom 6
4121,••••....••••••••••••••••
-64
— ... • —
••••
• • •
• --
r/1•110•••••• • Wt•
•.1
4.
•
s.•••••••r mown
•
••
a
Alin••• ..1
.■ n.f.
.062
I. I
', \ C•
• V•f
1b* t•
if* Ca.;•
.1
•
. \ .
'--,
....
:a. z .....-.... .... .....,-=. -...... -.■. -......m. ■.. - . 4.7 . ;•::
at r. • 3 ...•
.. • " ../• J•
4
/ /*/ /771/ //Xi
Pa
•
•-•- \
, • ••••• •■•• r. 71. ■•■• •I• Alm
, .. . .,. • f•••••• _ — n?r• •_•• _
-- 4. 07'
••■■■•,'
• r - • t ,
4)
A
1 I I
11
\ \ \,■\ %),
„,\, \a's . ;
'\\.■ \ \ WAV
/ h1/1///7/1 )
▪ ••-• I:Ater
••••••
i)cil =V/
„.• •
r. • •••••■•.! .•••••
Az-
4.
4.
4.
4.
SITE PLAIT
SEGUE BUSINESS PUB
C1C
PROJECT BM I /0 •
CITY OF TUKWILA
PLANNING DIVISION
PLANNING COMMISSION
STAFF REPORT
AGENDA ITEM • 86- 53 -SMP: Mario Segale
...,., w.a oughtW WMAWM1nav ' a 4WAV a.:vna:F'.V
INTRODUCTION
Mario Segale is proposing to develop an office building within the shoreline
environment of the City and is requesting a shoreline permit for the develop-
ment, which is within the Segale Business Park south of the intersection of
Andover Park West and 180th Street.
FINDINGS
1. Per TMC 18.60.030(2)(A), the Board of Architectural Review (BAR) is to
review plans for any development within two hundred feet of the Green River
and which requires a shoreline substantial developments permit. The BAR
shall use the guidelines of TMC 18.60.050 to either approve, approve with
conditions, or deny the project (Exhibit A).
2. The project is a three -story 19,500 square foot office building (Exhibits B
and C), to be located south of the southeast corner of the intersection of
Andover Park West and 180th Street. The 4.5 -acre property is zoned M -2
Heavy Industrial.
3. Two -way ingress and egress is shown at two locations on Andover Park West, a
private street within the Segale property. Two -way ingress and egress is
shown on the adjoining Building #862 property to the north (Exhibit D).
4. An easement is required to provide access from the adjacent northerly
property.
5. The building elevations show board -form textured concrete as horizontal
banding separating windows with solar tinted glazing. The vertical supports
will be smooth, light textured concrete spaced along the facades. The
height and scale of the building is similar to other adjoining buildings in
the office park.
CONCLUSIONS
Tukwila Municipal Code (TMC) Review Guidelines
1. TMC 18.60.050(1) - Relationship of Structure to Site
BOARD OF ARCHITECTURAL REVIEW
Staff Report
86- 53 -SMP: Mario Segale
Page 2
The proposed building is surrounded by its asphalt parking area. There are
several small landscaped islands at various points of the lot.
2. TMC 18.60.050(2) - Relationship of Structure and Site to Adjoining Area
The proposed structure is consistent with existing structures in the busi-
ness park and is in character with the commercial /industrial development in
the area. Pedestrian circulation is provided around the perimeter of the
building and is proposed along the street frontages. Two -way north /south
circulation is along the eastern edge of the parking lot. One -way northerly
traffic may be more safe and more efficient with two -way access points on
Andover Park West. Pedestrian circulation is provided along the perimeter
of the building and along Andover Park West. The current project does not
preclude development of a waterfront pedestrian trail at a later date, if so
desired.
3. TMC 18.60.050(3) - Landscaping and Site Treatment
The required 15 -foot front yard landscaped area complies with the Zoning
Code (Exhibit D). 8' to 10' Douglas Fir trees approximately 60' on center
are proposed along the eastern property line next to the dike. TMC
18.44.140(2)(c)(iii) requires "large hardy shade or fruit trees....or other
species approved by the Planning Director at the maximum of thirty feet on
center..." The Planning Director has determined Douglas Fir to be appro-
priate provided the 30' spacing requirement is met. The applicant agreed to
this revision.
4. TMC 18.60.050(4) - Building Design
The proposed building is a concrete structure of the same basic design as
other buildings in this multiple - building office park. Building illumina-
tion is not indicated.
5. TMC 18.60.050(5) - Miscellaneous Structures and Street Furniture
The dumpster enclosure is not detailed. No information was provided on
luminaire design.
RECOMMENDATIONS
The staff recommends approval of the proposal subject to:
1. Douglas Fir spaced not more than thirty feet on center must be planted along
the east property line.
2. An easement must be provided for access between the northerly property and
the subject site.
3. Staff review and approval of luminaire design.
BOARD OF ARCHITECTURAL REVIEW
Staff Report
4. Staff review and approval of dumpster screening.
EXHIBITS
A. Shoreline Profile
B. Elevations
C. Floor Plan
D. Landscape Plan
86- 53 -SMP: Mario Segale
Page3
.......•■••••••■••••■-■■•■•■■■■■■•••••■•
•••■••■••■• •■••••■••• .1••••
t911 1331171171
S3111.101141 3H113110145
7wa
'mu ssamsne 31V93S
7 4. , 1• •- t - .7
6.1 , Z
or.742,7
fln -v:w./7,e • .17.7
..PO en I wen*, tee% 4,C ft —
7.7 - r-1 . 77,721 :renvor7..
.tr1/7, s. 1•Z
• t.telf .7.0V• Arretri.ot 7
TOR
•••••17
cjir •
sir*
.7 .•*J r r 1
7I lwr7.7 .170
7 . 7.‘ ,7- 7 7
71.1r.V
•
I. ....„,
....
''''....
I ri 1, ,•••• • .••7d I
I
I
eleo I
.e .7
1
•
Ai 67../ sns:s
I
cr 7.. ,, ,1 %. O .7 cel .... ir .7 a a a .4 a •I cos J..: r! 71
PV.V. ,e7
„v../ •••■••••J **,g L77,.7./
Rs, 77
777
nr ...0 OW "II.?
de I' • ■710 t”.4,11
..17.4417 07.7"
In1J5
c."
se
a 4? • vo. 71 •• 7.2 .7 7? O .1 oof
et 477. .7 77 ••• •7 •4 err ofr .7 ea oor
—1—
• i
rootoPthkriGH-
erarateats ale
w Use.'.. • ..r..s....a. Mien • N/ ON OW
SE4ALC 661 BUiL. I NG∎
ier
ears.«
does
■••■■■
1
a
Ci3O012-
72 ' I rigis=tileres
orchltaats ale
ta0 astoolle • wattle welt .,s& • PO DOI ••••
- 13
r
r
r
cn
tA
6eolAt.e 661 bUIL.DINGI
Y.t.111311
00 Jut
•••••
0.0000
tot 00
f.,..,,,t0toottAtrattaa.=
•
NEW /Rift. Gll:11
Au.'f.VaC PARK 'ANT
; I
:.sx. —vs.sM
ff sw. o
#-:D
i ? 1 •J Al• RA
--r ,�... L L • .
e- amour
- N A
..r tza.u. n••}
.
4
_wsa+. Rivers
a
'v_ r. .0.,...7-..... - rfa rY
1•r
frg abr. �.•nasrn. -
<w•ar+vror v y.,, 0 . 1
o • p 1 ' C —
f� �N
•
•
.a r" F'--' —>
a
. p•r. *c r.tc;r.racet
• 1
AYr.7 L'� 1
C �..RL:•
0'14 ies G. ie...w :.: aiF
••G eC.:.: .;- •G1,,•
1 a'c•L• 4'ae.
a
0,144 - - r.r.+• •;wG•�w:w •
/ I
0 4
A- � �/i Invest - -b'
y�•tc2 ADVIC.Arl n'Ir r
/ /
0 r .'..fi rrrf • :.'.�.r...s
r w-
4 C ' D.O.
YD N_"V 1
c
�� ,..-� •-- r ^Ism•✓'•' -w - R.G\wR/
-AP :4k GY•li •4?v4
• � -. V 7 �r.G•
Witt rv. "-etx,q /er tar
1 ?•-• ii C.4
r✓•
- SEGALE BUSINESS PARK
LANDSCAPE PLAN
PROJECT 561
Vi-Vi5t
y ✓ H
•
tS:i
n'
City of Tukwila
6200 Southcenter Boulevard
Tukwila Washington 98188
(206) 433 -1800
Gary L. VanDusen, Mayor
CITY OF TUKWILA
Notice of Public Meeting of the
Board of Architectural Review
NOTICE IS HEREBY GIVEN that the Board of Architectural Review has fixed the
18th day of December, 1986, at 8:00 p.m., in the Council Chambers of
Tukwila City Hall, 6200 Southcenter Blvd., Tukwila, Washington, as the time
and place for the public meeting to review the following:
86- 64 -DR: Six Star Building - M. N. Sandler and Associates is requesting
approval of a two -story building containing approximately 12,000 square .
feet of office space. The building site is located south of 144th Street
and on the west side of Interurban Avenue South.
86- 56 -DR: DT&C Building - M. N. Sandler and Associates requesting approval
for one office building containing approximately 10,000 square feet of
space. The building site is located south of 144th Street and on the west
side of Interurban Avenue South.
86- 53 -SMP: Segale Office Park Building #861 - Mario Segale is requesting
approval to construct a three -story office building containing
approximately 64,500 square feet of space. The building site is located
south of 180th, on the west side of Andover Park West.
Any and all interested persons are invited to attend.
Published: Record Chronicle - December 7, 1986
Distribution: Mayor, City Clerk, Property Owners /Applicants ,
Adjacent Property Owners, File
. .....,.......,•..+rrdtu:u.±.�.. r..,wa..+..,,...�sTi.;.�4 a..>,,o..G.:,x.
Published in:
Distribution:
(23 /SHORE11 -6)
Ar: < ». u...r.i', .r { : zt :', ; , : ...r . , e ,•rty ^4+l 4. .tVr1.,h• r zpIrmg! vp fvy : �•f !
"r` a .YIY.. . w1' ,( ✓� 3Z. ,. r:
....,.. Tni.zn.',fG l" o_Y`t� � rr.a.S,�, i.Y 1. �...t. ... , f �� �r'.t..`-rH Gh+ 4" � `S� r^7 '�
t �;::�;i* S .ts.....i�.. .. k.. ., 1.,... :.:ur,i,7,.'�� E �`��St<��.:hur .T.:..u!.•r.Y.:,.....:i��.v� . _ aad7. .t Si:F3'...n.,.,).¢. Y?. ,:3.�U a..�`..Y+n....•�i,.:�.�.� tt.,s4v:; , .�u�:'ry ...
t
City of Tukwila
6200 Southcenter Boulevard
Tukwila Washington 98188
(206) 433 -1800
Gary L. VanDusen, Mayor
NOTICE OF APPLICATION
FOR
SHORELINE MANAGEMENT SUBSTANTIAL DEVELOPMENT PERMIT
Notice is hereby given that Mario A. Segale dba Segale Business Park, who is the
owner of the below - described property has filed an application for a substan-
tial development permit for the development of a three -story concrete building
located south of Andover Park West and South 180th Street, also including the
western portion of Tax Lot #352304 -9055 within the NE } of Section 35 of Town-
ship 23N., Range 4E W.M., in Tukwila, King County, Washington. Said develop-
ment is proposed to be within the Green River and /or its associated wetlands.
Any person desiring to express his views or to be notified of the action taken
on this application should notify Rebecca Fox, Planning Department, City of
Tukwila, 6200 Southcenter Boulevard, Tukwila, WA 98188, in writing of his
interest within thirty days of the final date of publication of this notice
which is November 16, 1986.
Written comments must be received by December 16, 1986.
Record Chronicle - November 9 and 16, 1986
City Clerk, Mayor, Adjacent Property Owners,
Department of Ecology, Property Owner, File
, tgyi`li:i, tj K y �'„!! i`+ ! % _ f.9c ,•.:`.iF M ^i08 ,1 ;:;q
Published in:
Distribution:
(23 /SHORE10 -16)
4c `,^,i::.L�``,ikf.:.6 F: ir'u:h5'.itin", ».F;t���a�i�,i!� mft. §m;:r,"e
City of Tukwila
6200 Southcenter Boulevard
Tukwila Washington 98188
(206) 433 -1800
Gary L. VanDusen, Mayor
a.<
4 Y•:.
'�si7 . , rte :.hru.;�.a»r+�� .rr � � °,�tr� . '.St�e�tron�a ? r �iti :�r�#i+.`�.n..,C, �.trtr.,
:;'�:4..+� 5.��.5,..«..Rr .. u. r. �. ��•`." iG... a.' �. �,. C` reS.';. ��t..:. rb": ��. a:., as-f< n�+ i' 1. t�u��: s.,: .s ».ri��
Written comments must be received by November 25, 1986.
Notice is hereby given that Mario A. Segale dba Segale Business Park, who is the
owner of the below - described property has filled an application for a substan-
tial development permit for the development of a three -story concrete building
located at Andover Park West and South 180th Street, within the NE * of Section
35 of Township 23N., Range 4E W.M., in Tukwila, King County, Washington. Said
development is proposed to be within the Green River and /or its associated wet-
lands. Any person desiring to express his views or to be notified of the action
taken on this application should notify Rebecca Fox, Planning Department, City
of Tukwila, 6200 Southcenter Boulevard, Tukwila, WA 98188, in writing of his
interest within thirty days of the final date of publication of this notice
which is October 26, 1986.
NOTICE OF APPLICATION
FOR
SHORELINE MANAGEMENT SUBSTANTIAL DEVELOPMENT PERMIT
Record Chronicle - October 19 & 26, 1986
City Clerk, Mayor, Adjacent Property Owners,
Department of Ecology, Property Owner, File
.� :r %..• 1 c
MASTER LAND DEVELOPMENT APPL I CAT 1 ON FORM
Central Permit System
SECT I CN I : GENERAL DATA
< ; v i . ‘ ' Vi ' LL/:
TYPE OF APPL I CAT 1 ON :❑ e s I P
S
PLAT
S) ANTICIPATED PERIOD OF CONSTRUCT I ON: FROM 1 / 87 TO 1/88
a) • I LL PROJECT BE DEVELOPED I N PHASES? D YES DB NO I F YES . DESCRIBE :
a)
suBsQIIBED A.Np SWC BEFORE MC
TN 1 S f' (n DAY OF •P rk L ' . 111(2.
ll
'r
et Or
DsusolvlsloN
DATE q 1? /8'4 X �h� . � G
I:
®sNORELI N!
PERMIT
_- 4o
38
PLEASE WRITE LEG 1 ■LY OR TYPE ALL RE uESTEO I NFORMATION - • I tl IPLETE APPLICATIONS WILL NOT BE
ACCEPTED FOR PROCESS IPG
PRD DPMYD C3 INTEIAIVRRA
0 CONDII IOMAL rUNC `$ ❑ VAR I ANC! ❑ I NO PLAN
•
Mario A. Segale
APPLI CANT: NAME d/b /a Segale Business Park Tt uzraioN>: ( 206 )575 -3200
ADDIS P. 0. Box 88050 Tukwila, WA zip 98188
PROP. a11NER: NAME Same as above TELEI°NONE t )
ADDRESS ZIP
PROJECT mamma: ¶ STREET ADDRESS . GEOGRAPHIC, LOT/ sl. m) Approximately 18 Andover
Park West. west side of Andover Park West
S ECTION II: PROJECT INFOR AT1ON
4) DESCRIBE BRI EFLY THE PROJECT WU PROPOSE Three story concrete office building
7) PROJECT STATISTICS:
A) AcarAGE or PROJECT SITE: NET 4.5 AC G7toss 198,345 SF EAsniorgs . 11,250 SF
a) FLOORS or Cor6TRUCTI ON: 'TOTAL I FLOORS 3 INCLUDES: ❑ BASEMENT 0 MEZZAN I NE
TOTAL GROSS 64,500 INCLUDES: D BASEMENT DMEZZAN I NE
• FLOOR AREA
C) SITE UTILIZATION: EXISTING PROPOSED NOTES
ZONING DESIGNATION M -2 M -2
COMP. PLAN DESIGNATION
BUILDING FOOTPRINT AREA O "` 19;500
LANDSCAPE AREA 0 0 30.000 0
PAVING AREA 0 0 148.845 0
TOTAL PARKING STALLS:
- STANDARD SIZE . 0 207
- COMPACT S I ZE 0 90
- HANDICAPPED SIZE 0 5
TOTAL LOAD 1 PG SPACES 0 2
AVER • SLOPE OF PARK I NIG AREA 0
AVER. SLOPE OF SITE —�—
Is This SITE DESIGNATED FOR SPECIAL CONSIDERATION ON THE CITY•S ENVIMONKENTAL SASE
NAP? ❑ YES Dm
SECTION III: APPLI AFFIDAVIT
I . ario A SPgale . BEING DULY SWORN DECLARE THAT $ AM TIME
Cam TRACT pureCHAS EB OR OWNER OF THE PROPERTY INVOLVED IN THlB APPLICATION AND THAT THE FORE•
GO I NG STATEMENTS AND ANSWERS HERE I N COrfTA I NED AND ME I NM/04AT I ON HERE, ITN WAIN 1 TIED ARC I N
ALL RESPECTS RUE AND CORRECT 10 THE REST OF MY KNOWLEDGE AND BEL I EF
( S I GNATLRE OF CGNTAAGT ItJRO4YISDI CR OWNER
•
I IS 914
"I d92 S
ii QL dui
t� - 911 - 41 � a , 'DJ
LcQ9 s f Malci
4vw-°a • 4kAil
• 300 90 BO • Po Lo So
RIDG
• /0 Zoo • • go No' 20 Go $o q0 jo 20 /0 /00 90 go 20 eo fo qo J0 . • • 20 /o
5o tyo 30 2 2/0 goo 90 g . 2° 10 fo
F/NIsh item ZZ -- 8.4/,
3 9 8 90 Lo 30 Ho 3o 20 / zoo 90 go
8 .
t T .DRI LA :‘
SBcT /oN No . 3
5C/4 t' / /o
42 .
—z_ 6x7EA /OR /9ATER /AL ;
.30A4a FOR!? coNc.,16cre ANa GLASS
'/0 3 Lo /o /00 90 80 70
Scale / "s /o' = / 4r`V
Silo/dime /or"c /r/pacr ENV%/10NMENT AR EA..
•
/00'
I Imo rot Of "9 //4' EL. 3/
Low • /,/PACT • •/A'✓moNeEA/r AREA
/cm,'
•LOW /MPAC.T /NV //tQNMENT AREA
/DO
PROJECT 861
NOTE:
/7/4//),7A4 'ENGvYA7.k'4/ (EsTiiziTEQ I ;'zda
•,!, / /.yf R 6' io►!EL?'Wg0;l 2ba -li?o
:4 ~ 2 boT �RsiEL,"/�G9E' iVid ERl%
T eih4Av9. io4rq'es1Jeu>1(v':0t riao
Sow10E' of 7 4,f r'/AtFA /AG is /�y6d Pr7j` L%
144 StA/F A-:444;
3.A,L S' jio2agy r?ecreloAD .►✓. //
an/ TNE' 8o,COi/✓G P,iO Fo✓1 3EYltEi7E iiT
▪ pURPOJES. (EST,/w76O4T .So'oays):'7 , ;'.
• $0044E oF Ti' /S SA/vO ti 64414Z. /S Aeso (fAyY!o
,aiT Ao.Qbr1N, ks4.. 7 /241"E/Z/4, W /LL 4E'.',
fiEHO✓EO fAay vie .SiTE76 hA. 9G6 4.; /.vv,
_ 0 — SANO C G//A✓EL 0Pe.147I0>v',
4.4,60"/..c/6 ,7oN /rYG - /7 -2
S: Ow/vER : /"/,A. SEGACE
— / GREEN Riven
v f:/G// l'Are4 : ,QASEO o / • vs' & s 0,9Tur/
SEGALE BUSINESS;PARK
x:u;AS NOTED: " .:.r: DRAWN = 6,56
o "Tr q l!avwo •' J.; '' ...
,.*4 ... ..wnu a, wa. ,u.a, Ctw ST. .
•
° ,w ..� r, t f...r;y R >,.: , .Sy .. et ": e. •�.: Yti ': " S�. 2... t !•Ni`..�..� 5 '�
I�f�I�I�I�I�I�I�IIIIIIIIIIJII111IIlIIl11Il11Il11I111I111IIIIIIIIIIIIIIIIIIIIIIIIIIIl�J11 }1J LIIIII111. I11lllll �lilllilll�I���il�i�ilijilllililililililil��il�I�li�ililili��lil�li��lilililililili�
0 •" ' ..w 1 2 3 4 . • 5 6 7 8 9 • 10 11 .o.W,^ 12
1 1FLETAIIIIH7f4C7271crig DOCUMENT IS LES S, ICEIT IS DUE TO' oe 6Z ee Lz 9S 9z nz C ; • THE UALITY OF THE ORIGINAL DOCUMENTI ° : 9 L 9 s h E a 1 " ^ 0
.,.) 1111 1
1,11. i Ill 1111lllll 1111 uulnu 1 111111 ii iiili i Ilia iii 11111,111 im11m511iinluuhm6m i 11nin�nnlini11 il�ii 1.1 iip yii 111111114111. 1i i,1. lit duu1nnlmi1uuluu1uuh111114ni1llll m�..
,.I }. ^-m, ^'S1." �•eT ± �!z� I ...�.� n� �• fi^, � . !° � k?'!"^" n- �'•"F - ,
X
sX
C Q •. 5
4.f: 20.0
67?E(/V
J ?/VE/z
l; ,,
- NEW BUILDING ire
/ PROTECT 86/
TOTAL float AREA 6H,•OasF
`y • 1 f /RSTF.Coa AitEA . /9500 SF
/31P/t /N6 .4E47• 2.5 // oo /C2
PNRI(ING S / /oWil/ -'Z?/ /000 502
54 - 2H • 5/ re AREA /9663HSF 6
ZoNE • /y.,2
Co '5TIWcT /oM 2SL
f'Ii/r0I%AT/c..Fat S lIN (ZE✓IS
MAX. / /E /GNT ,;o f2Er
1 STREET L/ONT/NG { 1:'Xur/A/G
\ , P&t /P2ETEf !(3(Nio NG 216N77N6.
--1—
n \ \ \\ r
F/N /SN F2001
ACCP Se '
5✓g
Acce5S
FN-
/4 /.
SAMNA
VA r
:._.. — 31 '1 •
JoAO
_ Ji .s
/KCP
S: / : .
S MAx
\ \
\ \\
SIGN wlTh /NNIANAToM2L1 \
SYfl&/ or ACCESS I \
' 5/0CW,nu<
r RI! Bo"
ASP/62LT /44t/e0
• ,SLOpt MAX /•'.fo I.'
/NTfRNAT /ONAL $y0183 d/
ACCESS PAI.vTtD oV/'A v4W6'T
/o 2 0 0 v a - 14 . _WA
£xls7 /NG 27 %4CCP e— = - = = c •
6' SUEw:/ALI<
O.S
_N.9 °49'5'1 "6 _ SHt.
SCALE: /•,: 20.
'DATE: $" /z•BL
SITE PLAN
APPROVE'D'DYt
REVISE°
'DRAWN BY
'SE'0AL6' /3U5 /NE5S PAM<
V eINI T • MAP -
- ScALE
NE CoR,
s. NE. y
0
. MINO ORRO. 14041 CIEAAMI.t
5 7 ° HH . 54"N./
1 h , ( 17
10
411 0
.vo 9. 20
1:1/5
.1/
.
SE" I p..SS I,' ":se:/ , ,
01/7/L� 6 < 9�Z /Py 7,
EX /ST//VG 22'L2
/S'UT/ / /Ty �f_/1SC/"IENT
R
j, %
23.3E - V = � = V = _
MN
2
4
21•/2
ANOOV / P'Ai'< W6S7" ( 520. , 1_E 6' /WC ,/1)
1
23,35 22.40 25.35`
; 0
0
SCALE
'/0 • CO
EXn7 /4/& STORn M//
16= J 50 /�Ytcc /'
ouT.<ET Et. 29" r /3.0C
12.
2/.52
.1.12./5"
2.66END
EX/STima C0N7'OU/l5
CX/57/ '6 ELEVAT/o/✓s
F /N/s // CLE ✓/17 /DNS
A .,rus �
,- vl S� aiN 4 .m
�..,I:r +. u,., .
, ),„ : ,dn c.r
. .,.�.:, 4 ., . „: ,"..tt.
...� „1 ';i,n i,,i4.ki urr tt a •c"`+�V..s .
..c1v., s'
1111111 �
1 1 1 1 1 1 1 _w1.11111111111111111111IU111[1 1I'IJ111 111111 {1111111111111111111111111 1111111111111111111111111111111
0 I.t..I.°. 1 7 3 4 5 6 7 \ 8 9 10 11 Nom°°° 12
IF THIS M ICROFILMED DOCUMENT IS LESS }I •
{CLEAR THAN THIS NOTICE, IT IS DUE TO
of ez Re /z 9z sz oa Cz; zz 'z OTHE UAUAL THE ORIGINAL e e 1 g s , c z 1 °.0
1lpdnp1u1111o1 {1 11111111{ 1111691 1111111111111111 1111{n 4111111141inliTli uu 1 i111milniiluulim6iiduulmllunlnnliiu11T1dnnluuliiul 111161un1iu1I1u1uuluuluul nulgilIilidmllmdilliIunluuIm
1�
4 25
2.v
—1 81va
STREET
4 /G.vr
F. 86.. 53_P
CNA/7 /TAI 15 41Cu 74 GUTS
PER: eove.
9--
z2.Yo
PROJECT 861
. 0-
29./4-
4_,a4
/t:2530ot
/20.1k
AWING NUMBER
A
I•.
is
N i. M•'MRI ONBARD.t of COMM •
. X 5.. 07 °4 '/09
8.4
2548
y .
/0
30
Zo
as
51 x -s£cT f'T. 0 d3
7S •
GREEN
3 L H
\ VE /0
V •g
5 3 ° /9 �!
SHoREG/^!E
ste
22P
2S
Z t_
20 f - p C1 /n/ oNr�T
5/10 EL /NC X•ECT. /
A , 3 °4 so
d
21
V
a 3
, 3S
30
/.=22S3y
211
701 of 5uRC/ /Race -
22.
M.
22,87 22.1e 22.87 22./2
22.$3 7
ANO0 P/IRK 1,/CST sEGAlf D/VVV A
_L-
23 3S I 2 0 23.85
2/•
20.2
ZEE
1 22./0
9
2s"
2i z7
22./s
'
IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII1IIIIIIIII IIIIIIIIIIIIIIIIRII1iliji1111_1 j!11�iU.11 1 1 1R I EJ 1 1111111 1 1j11111 1 1111111 1 1111111 1 1111111 1 1111111 1 1111111 1 1111111 1
3 4 5 _ 6 _ 7 � _._. 8 9 10 11 ... 12
HS R IMED DOCUMENT ISD SS.\
CLEAR IF T I
THAN TH O FIL
S NOTICE, IT IS DUE LE •
TO�
z CE: az Ie • THE UALITY OF THE ORIGINAL DOCUMENT; D a c 9 9 .9 C z R 0
1un ml a Diu �niim Ill) un m mliliulmlhmhlalud mlTlillitai ililiiidunlw m1111 14b uulpu1uuluu1mdml1un11!111u 11A1n1111p1un1110
1 I , 1 r r
9.
X 2.0
�1yS
•
22 3
22�
22.3
2/.92
1 22yo
Z �
30
.2
IM F $6- 53 -5rnP
_.9101£2/n/f X -SECT 'J
- - 0 572°OOs 0
22.43"
/0
2S
32.12 22•52
SCALE
DAYS: -/.
P
2t.
PROJECT 861
5 4.177------ 9 ° 03 ' 25' . v/ 2/043
2'.
APPROVED BY:
SURCHARGE PLAN
22.e
7
9- 22.90 /s
SEGALE BUSINESS PARK
NI
col
DRAWN BY
REVISED
G50
I DRAWIND NUMBER
z
_
-,
- - _ - - - - - - - - - i
/ r - -- - - NEW BUILDING SITE
I
( PROJECT 861
/3U /LO /N6 -AREA 6/6560 sr 3- SToRy .
F' /RST F[oor2 AREA .2/, Goo sr
P /w /51/ FLOOR EL. 2 %o
Top 0f Sur2CHARGE 3
SURG//ARGff t 1000 Cys .,
I
5 -E-= 23• AE W�� / //1 T /'VVrltoVr
o
I mo ° ° -
1 .
I (
/
0p 5NL/. of 5
7 � f GE SURCH 3 et. 30° 5
►-
T r �'. , I /S:/ Si S106360,01=
/e:
4":
slop,
I•.
is
N i. M•'MRI ONBARD.t of COMM •
. X 5.. 07 °4 '/09
8.4
2548
y .
/0
30
Zo
as
51 x -s£cT f'T. 0 d3
7S •
GREEN
3 L H
\ VE /0
V •g
5 3 ° /9 �!
SHoREG/^!E
ste
22P
2S
Z t_
20 f - p C1 /n/ oNr�T
5/10 EL /NC X•ECT. /
A , 3 °4 so
d
21
V
a 3
, 3S
30
/.=22S3y
211
701 of 5uRC/ /Race -
22.
M.
22,87 22.1e 22.87 22./2
22.$3 7
ANO0 P/IRK 1,/CST sEGAlf D/VVV A
_L-
23 3S I 2 0 23.85
2/•
20.2
ZEE
1 22./0
9
2s"
2i z7
22./s
'
IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII1IIIIIIIII IIIIIIIIIIIIIIIIRII1iliji1111_1 j!11�iU.11 1 1 1R I EJ 1 1111111 1 1j11111 1 1111111 1 1111111 1 1111111 1 1111111 1 1111111 1 1111111 1
3 4 5 _ 6 _ 7 � _._. 8 9 10 11 ... 12
HS R IMED DOCUMENT ISD SS.\
CLEAR IF T I
THAN TH O FIL
S NOTICE, IT IS DUE LE •
TO�
z CE: az Ie • THE UALITY OF THE ORIGINAL DOCUMENT; D a c 9 9 .9 C z R 0
1un ml a Diu �niim Ill) un m mliliulmlhmhlalud mlTlillitai ililiiidunlw m1111 14b uulpu1uuluu1mdml1un11!111u 11A1n1111p1un1110
1 I , 1 r r
9.
X 2.0
�1yS
•
22 3
22�
22.3
2/.92
1 22yo
Z �
30
.2
IM F $6- 53 -5rnP
_.9101£2/n/f X -SECT 'J
- - 0 572°OOs 0
22.43"
/0
2S
32.12 22•52
SCALE
DAYS: -/.
P
2t.
PROJECT 861
5 4.177------ 9 ° 03 ' 25' . v/ 2/043
2'.
APPROVED BY:
SURCHARGE PLAN
22.e
7
9- 22.90 /s
SEGALE BUSINESS PARK
NI
col
DRAWN BY
REVISED
G50
I DRAWIND NUMBER
z
• . ,
41
•111•11 11111111111
_111•111111 muffin pow
1 1 1 1 1
1 1 1 1 1
1 1 1
11
Imilortimmummommemosso
unnow iumuniolunman mommi unnim IIMUI mom
111111111iiiii I 1101 111111111111111
1 1 1 1 1
1 1 1 1 1
E-L4c\-not
n T 1 1
Mit I 111
1 1 11
t, 6w ok_i
0,0Ago roa
Wilt, 6 6P , c 1-11)(261, v
fr MEAL
CqJa-b
It kipH
OLA bODiJM,
&L- 11.-1 bRo■-
4.011111U hk/\5k
1111111111111111 I
Holossull 1111,.. li soms lll
mum isminn monts
imsionsommem III
1 .
, 1111
11
lj
.1
1
W11
1 1
1 1 1 1
jI
1r) k j PIPM
OoRzr
111
moan
liuIilw
1
- 111111111116
L .,111t
111
NUM
t.c.vt\ 1 - oPP 1-1A110
n1F 119-65-smP
..4,,...,.. ^V
1‘ 7 Al.''. '
':' '
k .4') . ':1t!.,10 , ,,'.‘, , ,,,, , ., F ililkiT..... .:1Q,',,... ,. . ...„,„ ^ ..Z,, r;,',, ,Y,11.:4+. 0, , , .:.. ...0,' f.'4' .1 4, ' , •
IiIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIILIIIIIIIIIII
0 4 ' , .....c. 1 7 3 4 5 6 7 8 9 10 11 ....... 12
OE DD se a sz sz .,S szl \lCLEAR T lil T tO I s ill N i O E T o -- 1 10 E CUM r rirS s l D u rE E 1 i 4 \ •
E z 8 THE ..guALA OF THE ORIGINAL DOCUMENT1 6 9 4 9 9 V C 3 1 .". 0
„111,0j1111111 Ilikl$011j11,IIIIIIIIiiiiIIIIIIIIIIkdillilliallilk0411114614
°''''..:,..:.''' - - .” :',. !, , : ,...,. ''''',','',`,' ,. ;.,.''',-,..:::', r.';', , ". ' -,;', , , ,, :rit', ,. . CA. , '•;1'■` . ....'',,,..'' . '''.;' , f.: - ",•: , , , ,w.: „ ;: , .. , ,: , .,:,7 , ., , , , ,., ,,- i,.. , .p7:1qi.t:? - 4; , .'... -, :,...q.q..*:.7., .<.!'. •.. :
0
0
0
c
‘1_
17
0
0
0
0
0
•0
c
0
0
0
0
sheet
5
F PLAN - 2 Am° 3
Arm, az.5.09
poi Q pii.
•
A$6 oat) 44
LOotS PLAN • LEVEL L 1
law+ a sip'
z_.MUVrt •
2 5€7'
4MAT Goglet rut
,••• Lit* OP .1001 ASOVIt
-
1 F 16-55-3mP
•
t „ •
11111111111IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIPIIIIIIIIIIIII111111111111111/1111111-1[1111IIIIIIIIIIIIIMIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII • 0 ........ 1 2 3 4 5 6 7 . 8 9 10 11 ............ 12
\ I IF THIS MICROFILMEITDOCUMENTIS LES
CL THAN THIS NOTICE, IT IS DUE TO •
oc 6z Be iz 9z gZ V i CE I ZE tZ 10THE UALITY OF THE ORIGINAL DOCUMENTI 6 9 1. 9 S , C Z 1".0
„. Iiiillidli*16111 . 161 , 1 , 1140)1 iiiiiiiiiiiii ii [lliiiiii
. M ...., , '. r.t, , ....7., , ,,, , ,;.:',77 ,,7 7r , . f` ,,, , ,, Iy,, ,-, , .-' , , "777 7 r5 , 17 , 77 , , , , .., MIT , ..”!......:77777: .7 -
A
0
L
c
o
0
1.
0
c
5
1 2 1
co
0
0
I. a
ED
m in
sheet
P3
111
10
01
0
tv
01
Al
0l
•
•
•
•
0
•
•
•
0
j
... alliarillffinlIMINIM I
frrwaVirp..1111, —
117‘71.:11:1111111111111111111111111111111111111IPAtitilP154111111111 111111111111111111141 iiiiiIMMIIIMMINIMPOV I IIMIMU01101111 11000101111M 1111111V1-1
. i.4,VZ 1.1 I :':
qiiii11111111",
ry ;Ill tcyllioom ponineigirmailmoinvol 119V
>46,
1101111.11 rig111111 IIMP11111101111111 I I pegililli1111010011/1 , -„..,,,... 1111E0PP/1W
• ""tv • • 4,,,IP• ° "'" 4 -41`41N-4-1' Wa4:41: _\;:v.Crawar.410,41 1.P. . • if.. 016. V4010 14. ran: :11;
71"
ri
. el
r*V . 1\ A I/
cr,""--=-114514 . "W. ■'.10.A.Mei Nit* '#...- .i.....: ..if :NnalaktrAtairtAtii,:a Mr AT'A'''''' S., *kV ',40.4V9F~F.t.ziti47,4 rA a , , ,..,-;-:149/..h -witir.wia gi , ii7 ,-, ,,T..1r , ws meg.
4 _.i,...._ __ IIIMEArr gti41,-"WW: 3"79r.:3
. ighlii , o , ',/,rilill :avalumiiP7.iv i iti7Zii NITE2IEVAlikvintimitkagir ijaifirffigafti , ii 7.7 ;;Ittiviiig „7. winglatnr:Irra -- '1,,,r+c - tvag s"52- ramizT . :::::viti,:,;zaigi , ..,ko lv g_uv "
Val x,';osgii own"
t. "
iwout%rrhofta, vie.mzies-m
. : •
0- to
•
4■114TV.A141'..rly .
lll ; wt'4 ‘01 Ni .•
• :tXX)(eLdr tr.
' lea I
• Izt;WitlistivRt •
44,41 /2•VVE-Er6:'t..)1/1
pilTrVo'A
• - .1-1114,1 6,10)r.INd•
2
e4,_vonLaritsliAL.:-. •
.. rHuflUt • c.t)
ID
• ,
—11.4.111='E-1).0 6,71
• o142ip ••';
•
MslIcX ,"
• • 4e"e: L!
/
:=4."' 0 pi Nti/4 .6
•
„ • . .
„,*..
, •,..m.41 , A 46,44.1 11,r .r., . P4 " 604. . 14
• Illi.11i'. . . ‘i : :A7r :gs ' v: 61.-----L— Y. : ::F .1 ,/ ". 40 ' L ■e4L_srP '.
•I'eoN,0 - ne,, --. - -
-1 i r - Kr..01..r_14s4y1z. 1
. f
124. M ...:,:.:"...'
.\IV't. Ww/N
Avt. ivy
gininD
‘ , 0 :7t.P1 , o vr i, 17 , 1Ne4 . , i . '
•
0'41'1141Y, hYL.Ne. I wpkj);
/r/WAI 46.61-44.4 rosla
•, . .
iiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiil
0 — ..... 1 2 3 4 5 6 7 " 8_ 9 10 11 ,,,,,,,,,,, 12
IF THIS MICROFILMED DOCUMENT IS LESS; ' 4D
.HCLEAR THAN THIS NOTICE, IT IS DUE TO
oE 62 BL LE 9E S 9E 2E; EZ tZ OTHE QUALITY OF THE ORIGINAL DOCUMENIII. isi? v il^.()
li -T-
llifilliFilikiiiiillibiliiiiNilgirilliiiiiimiiIiiiiiiiIII!plinillidlillimIIIIIIhimilliihilliotIfilillidiiiihoduldfillilliii
'
•
x
NOV 2O986
;ITV OF TOKINILA
PLANNING DEPT.
PROJECT 861
r
•
14
Thr 819-53- Sm P
SEGALE BUSINESS PARK: • •
`
" eipp5/0
LANDSCAPE PLAN.
"" ,
•
--`411191