RE:.Gateway Corporate Center - Building No. 10
Dear Bob:
I have reviewed your revised plans and descriptions for Building No. 10 and
compared them with the previously approved plans. Following are my findings:
SEPA: The existing SEPA can be used for completion of the project. As you
suggest with regard to traffic impacts, modifications to the SEPA may be made to
address project changes.
Shoreline Permit: A new shoreline permit is required as L93 -0012 has expired.
Design Review: The BAR approval expired June 17, 1996 per Condition #1 of
that approval. Even without that expiration, administrative authority to approve
modifications to BAR approved designs is limited to "minor, insignificant
modifications which have no impact on the design" (TMC 18.60.030(3)). The
proposed project results in several changes which impact design such as.
expanded parking and service areas, added screen wall, and modified building
footprint and architectural details. These changes do not qualify as minor and
insignificant.
The applications for Shoreline and BAR approval can be submitted concurrently,
in which case they will be treated as Type 4 permits and be heard
simultaneously before the Planning Commission /Board of Architectural Review.
Upon determination that your applications are complete, we will schedule the
project for the next available public hearing, no sooner than 60 days from the
determination of completeness.
6300 Southcenter Boulevard, Suite #100 • Tukwila, Washington 98188 • (206) 431-3670 • Fax (206) 431-3665
Enclosed are the current shoreline and BAR applications for your use. Note that
the requirements for mailing labels have expanded to include all properties within
500 feet of the site and all labels for all tenants as well as owners located within
that radius need to be provided.
If you. have any questions, don't hesitate to call me at 431 -3663.
Sincerely,
Joh Jimerson
As • ciate Planner
cc: Project Files: L93 -0010
L93 -0011
L93 -0012
PROPOSED BUILDING #10
GATEWAY CORPORATE CENTER
GATEWAY DRIVE & CAMERON DRIVE
TUKWILA, WASHINGTON
0
(1)
nl0
11
0
CO
m
73
r
0(1)
m
Tfl
CD
73
P -1 Kril finish 6050, M- 28970
P -2 Kril finish 6092, M -28980
P -3 kril finish 6094, M- 28990
P -4 Benjamine Moore A -16
RECEIVED
JUN 1 1 1993
COMMUNITY
DEVELOPMENT