HomeMy WebLinkAboutTrans 2014-11-24 Item 2D - Change Order #3 - Tukwila Urban Center - Transit Center and Andover Park West Widening with Puget Sound Energy (Utility Relocation Agreement)T{]: City of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM Mayor Haggerton Transportation Committee FROM: Bob Giberson, Public Works Director BY: Peter Lau, Senior Program Manager DATE: November 21, 2014 SUBJECT: Tukwila Urban Center — Transit Center and Andover Park West Widening Puget Sound Energy — Facility Relocation Agreement, Contract No. 13-121 Change Order No. 3 ISSUE Approve Change Order No. 3 for the Utility Relocation Agreement between the City and Puget Sound Energy (PSE). BACKGROUND On July 2, 2013^ a Facility Relocation Agreement was executed between PSE and the City. This agreement defined the roles and financial responsibilities for the relocation of two underground vaults and two above-ground switches related to the Transit Center and Andover Park West Widening construction p ject. The two underground vaults straddled the right-of-way (ROW) line along the Southcenter Mall frontage; therefore, relocation costs to move the vaults out of the ROW are shared by PSE and Tukwila. The two switches are on Westfield Southcenter Mall property and are 100% the financial responsibility of the City. A cost estimate of $738,400.00 was included as part of this Facility Relocation Agreement. One underground vault (V10) and the two switches were then relocated by PSE in 2013. Change Order Nos. 1 and 2 were generated as a result of the extra work to relocate V10 and the two switches respectively. The two Change Orders were approved by City Council on February 18, 2014 for $75.914.80, bringing the total City responsibility to $814,314.80. DISCUSSION PSE has completed relocating the final remaining underground vault (V12) at the west Transit Center bus pull-out lane. The relocation cost has exceeded the original cost estimate due to the following: • The dewatering cost for vault relocation was significantly higher than the cost included in the original cost estimate. • PSE's wire crew had to reroute unknown service cables in vault V12. These unknown service cables were not documented in PSE's own record drawing; and the cable rerouting cost was not anticipated in the original cost estimate. • PSE's work crew had to extend their vault relocation work from two weeks (as estimated) to four weeks due to limited access space as the City's contractor was simultaneously constructing the walls at the west Transit Center. • Extended traffic control and unanticipated pedestrian safety measure costs for the additional two weeks. • PSE was required to replace an existing utility vault lid with a new anti-skid lid and some PSE manhole lids were also readjusted from existing locations to meet ADA requirements. psPro**s1Trans4 Center ' Contract Documents \020' Special Project Agreements & Permits1(005) - Franchise Utility Agreements\lnto Memo tar INFORMATIONAL MEMO Page 2 • The PSE vault relocation work was adjacent to the southbound travel lanes, resulting in the need for additional shoring and steel plates to prevent subgrade sloughing to the adjacent travel lanes. • The original cost estimate in the Facility Relocation Agreement was based on the vault being located within a landscaped area. It was discovered during construction that the vault was partially under the roadway, necessitating the installation of a traf iC bearing lid at additional cost. The bus pull-out was extended to avoid having the vault located directly under the curb and gutter. This re-design altered the grades for the vault, causing it to be installed deeper than originally proposed. The installation costs were increased due to additional subgrade excavation and other physical conflicts. • The original cost estimate in the Facility Relocation Agreement was based on 2012 PSE labor rates. The labor costs were increased since the actual work took place in 2014. FISCAL IMPACT The total amount of the cost increase to relocate Vault V12 was $147,451.00, in which PSE is responsible for 19%O[$28'O15.O9 and the City iS responsible for 81%O[$11S,435.31.The Transit Center P ject construction contingency of $905,626.00 will be used to pay for PSE Change Order No. 3. As of today, nine change orders for $84,887.92 were executed for the Transit Center P ject and there is a remaining $820,738.08 in construction contingency that is adequate to pay for PSE Change Order No. 3. RECOMMENDATION Council is being asked to approve PSE Change Order No. 3 in the amount of $119,435.31 to Contract No. 13-121 for the Tukwila Urban Center Transit Center Utility Rg|ooation, and consider this item on the Consent Agenda at the December 1, 2014 Regular Meeting. Attachment: Change Order No. 3 W:\ PW RS Projects \ Transh Center (90610402)\Construction14.100 - Contract Documents \ 020 'Special Project Agreements aPermits \ (005) - Franchise Utilrly Agreements \Info Memo or PUGET SOUND ENERGY To: City of Tukwila Attn: Cyndy Knighton Project: TUKWILA - Andover Park W P.I Description of work: CHANGE ORDER V12 Date: 9/2/2014 Project Number: 101080841 Project Manager: GRENNER This change order is for the costs In excess of the original estimate provided in "Exhibit C" of the relocation agreement between the City of Tukwila and Puget Sound Energy, These excess costs associated with this portion of the work are detailed on the attached explainatlon of costs. Item Amount Comments Materais 63 346 Construction $ 131 578 Engineering & Management 14 620 Right of Way Overhead 37,718 Estimate Total $ 247,261 Actual Materials 93,527 Construction $ 233,027 Engineering & Management s 22,748 Right of Way Overhead 45,409 Actual Total $ 394,712 Change Order Total $ 147,451 Allocation of Change Order Total Company 19% Government Entity 81% Chan .e Order Total 28,016 $ 119,435 47,451 Note: This change order will be effective only when signed by both parties: Puget Sound 1ergy Signed: Title: Date: (Please sign and return one copy) City of Tukwila Signed: Title: Date: 3591 7-04 Puget Sound Energy PO Box 90868 Bellevue, WA 98009-0868 PUGET SOUND ENERGY a subsidiary of PUGET ENERGY 15 CHANGE ORDER V12 EXPLANATION OF COSTS *ALL COSTS INCLUDE ENGINEERING /MANAGEMENT, EQUIPMENT, SALES TAX, AND OVERHEADS* 1) Dewatering of vaults. Additional costs: $7,000 Original estimate did not include dewatering of vaults due to... 1. Unknown amount of water 2. Unknown schedule for work months (weather) 2) Traffic control and pedestrian safety. Additional costs: $8,532 (11 crew days) A) Original estimate addressed 2 weeks of work. Work was over a 4 week period. B) City and PSE granted extra flaggers for pedestrian safety and increased foot traffic during heavy periods. 3) Wire crew performing rerouting of unknown service cables out of existing vault V12 that were undocumented and unreferenced on the original estimate. Additional costs: $9,203 (one crew day) Original estimate did not include the wire work to remove and relocate street light wire and secondary service cables. 4) Additional time for civil crew caused by lack of access to our vault due to the City's contractor performing their work in the immediate area (limiting our access to one side and doubling time on site). Additional costs: $33,186 (11 crew days) A) Original estimate was an estimated 2 weeks of work. Actual work took 4 weeks. B) Original estimate was based on the City and contractor removing the Firestone canopy to allow for work to be done on the vault with complete access. C) City's contractor removed canopy and immediately began work on the transit center site. Limiting our access to the vault. 5) Additional work per the request of the City to aid in the construction of the transit center. Additional costs: $15,613 (2 crew days) A) Replace lid at J01 with new anti -skid lid B) Adjust location of manhole covers to address the alignment with the City's curb and gutter 6) Shoring and steel plates Additional costs: $12,160 A) Original estimate was an estimated 2 weeks of work. Actual work took 4. 16 B) Due to the location of the vault additional shoring was required to avoid undermining the road during wet weather. 7) Materials Additional costs: $30,181 Original estimate was based off of the best information at the time. Actual materials used differed. 8) Planned to actual differential Additional costs: $31,576 Original estimate was based off of the best information at the time (Footages). Actuals differed. 9) Labor rate increase Original estimate was based off of 2012 labor rates. Actual work was based off of 2014 rates. 17