HomeMy WebLinkAboutReg 2015-02-02 Item 4C - Contract Supplement #1 - Tukwila Urban Center Transit Center Construction Management with AECOM Technical Services for $160,090.29COUNCIL AGENDA SYNOPSIS Initials MeetingDate Prepared 02/02/15 BG Ma r 's review Council review ITEM INFORMATION ITEM No. 4.C. STAFF SPONSOR: BOB GIBERSON ORIGINAL AGENDA DATE: 02/02/15 AGENDA ITEM TITLE Tukwila Urban Center - Transit Center and Andover Park West Projects Construction Management Supplemental Agreement with AECOM CATEGORY Discussion Mtg Date 0 Motion Date 02/02/15 Resolution Mtg Date Ordinance Mtg Date El Bid Award Al tg Date Public Hearing Mtg Date 1] Other Mtg Date Mfg SPONSOR E Council II Mayor 0 HR [ DCD Finance Fire IT n P&R fl Police NV SPONSOR'S Contract No. 13-199 with AECOM Technical Services provided construction management SUMMARY for the TUC Transit Center and Andover Park W Street and Water Improvements. Due to various issues, the project has been delayed and AECOM will need to continue to provide CM services through February 2015. Contingency of $905,626.00 will cover AECOM's Supplemental Agreement No. 1. Council is being asked to approve AECOM's Supplement No. 1 to Contract No. 13-199 in the amount of $160,090.29. REVIEWED BY n COW Mtg. r CA&P Cmte F&S Cmte Utilities Cmte Arts Comm. E Parks Comm. DATE: 01/20/15 COMMITTEE CHAIR: I Transportation Cmte 0 Planning Comm. JOE DUFFIE RECOMMENDATIONS: SPONSOR/ADMIN. Comma-FEE Public Works Department Unanimous Approval; Forward to Consent Agenda COST IMPACT / FUND SOURCE EXP1NDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $160,090.29 $905,626.00 $0.00 Fund Source: 104 ARTERIAL STREETS (PAGE 16 & 17, 2015 CIP) Comments: MTG. DATE RECORD OF COUNCIL ACTION 02/02/15 MTG. DATE ATTACHMENTS 02/02/15 Informational Memorandum dated 01/16/15 AECOM Supplement Agreement No. 1 to Contract No. 13-199 Minutes from the Transportation Committee meeting of 01/20/15 2 TO: City of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM Mayor Haggerton Transportation Committee FROM: Bob Giberson, Public Works Director BY: Peter Lau, Senior Program Manager DATE: January 16, 2015 SUBJECT: TUC Transit Center Project; Andover Park West Street and Water Projects Project Numbers 90610402, 98810404 and 99840105, Contract No. 13 -199 Supplemental Agreement No. 1 with AECOM Technical Services ISSUE Approve Supplemental Agreement No. 1 for construction management (CM) contract with AECOM Technical Services (AECOM), in the amount of $160,090.29 for the Tukwila Urban Center (TUC) Transit Center; Andover Park West Street and Water Improvement Projects (Transit Center Project). BACKGROUND A CM contract with AECOM for managing the Transit Center Project was executed on December 5, 2013. While in -house City staff has been leading the CM effort on the construction project, AECOM has provided a significant amount of CM assistance for full -time field engineering, inspections, documentation compliance support, as well as on -call specialty support. DISCUSSION Due to a substantial number of unexpected underground utility conflicts, design deficiencies, and delays from material suppliers and sub - contractors, the Transit Center Project is scheduled to be physically complete by the end of January or early February 2015. Contract Supplement No. 1 will allow AECOM to continue providing CM services through the end of February 2015, including inspections, punch list items, and project close -out documentation compliance. FINANCIAL IMPACT The Transit Center Project construction contingency of $905,626.00 will be used to pay for this Supplement. Transit Center Project Construction Contingency AECOM Supplemental Agreement No. 1 Transit Center Construction Change Orders 1 - 9 PSE Facility Relocation Change Order No. 3 Total Contract and Budget Contingency Expenses $160,090.29 84,887.92 119,435.31 $364,413.52 Budget $905,626.00 $905,626.00 RECOMMENDATION Council is being asked to approve Supplemental Agreement No. 1 to Contract No. 13 -199 with AECOM Technical Services in the amount of $160,090.29 and consider this item on the Consent Agenda at the February 2, 2015 Regular Council Meeting. Attachment: AECOM Supplemental Agreement No. 1 to Contract No. 13 -199 W:1PW Eng1PROJECTS\A- RW & RS Projects\Transit Center (90610402)1Construc6on - City use only\CM Consultant Selec6on11nfo Memo for AECOM CM Supplement #1, 1 -16 -15 sb.doc 3 4 ,•"7"•42114.,m, Vikethington State r// Department of Transportation Supplemental Agreement Number No. 1 Organization and Address AECOM Technical Services 710 Fifth Avenue, Suite 1000 Seattle, WA 98004 Phone: 206.624.9349 Original Agreement Number 13 -199 Project Number 90610402 Execution Date 12/5/2013 Completion Date 6/30/2015 Project Title Tukwila Urban Transit Center New Maximum Amount Payable $ 899,440.35 Description of Work Construction Management Services The Local Agency of City of Tukwila desires to supplement the agreement entered into with AECOM Technical Services and executed on 12/5/2013 and identified as Agreement No. 13 -199 All provisions in the basic agreement remain in effect except as expressly modified by this supplement. The changes to the agreement are described as follows: Section 1, SCOPE OF WORK, is hereby changed to read: continuation of resident engineering and document control services through February 77 2015; anch Continuation of - • I I- •Sl - - - I I I .I .r I 2015 I I Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for completion of the work to read: 6/30/7015 III Section V, PAYMENT, shall be amended as follows: Total Value is 5160 090 79 which includes an increase to fixed fee value of X16 666 04 as set forth in the attached Exhibit A, and by this reference made a part of this supplement. If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces below and return to this office for final action. By: DOT Form 140 -063 EF Revised 9/2005 By: Consultant Signature Approving Authority Signature Date 5 6 Exhibit A City of Tukwila - Tukwila Transit Center Budget Summary - Supplement No. 1 Additional Budget for 12 -1 -2014 through 2 -28 -2015 .XOM AECOM Labor - Home Office Employee Classification Hours Rate* Cost Mike Horton PM / QC 49.50 $ 73.88 $3,657.00 49.50 $3,657.00 $3,657.00 Overhead (OH Cost -- Including Salary Additives): OH Rate x DSC of 156.22% x $3,657.00 $5,712.97 Fee Fee Rate x DSC of 29.85% x $3,657.00 $1,091.61 Labor Subtotal - Home Office $10,461.58 AECOM Labor - Field Office Employee Classification Hours Rate* Cost Jim Fillis RE 210.00 $ 83.66 $17,568.30 Janet Lee ARE 396.00 $ 44.98 $17,812.87 Robert Moody Field Lead 310.50 $ 41.06 $12,749.13 Jamie Shinsato Documentation 88.00 $ 26.45 $2,327.60 Jesse Rogers Arch. Finishes 54.00 $ 31.81 $1,717.74 1,058.50 $52,175.64 Overhead (OH Cost -- Including Salary Additives): OH Rate x DSC of 122.43% Fee Rate x DSC of 29.85% Labor Subtotal - Field Office Fee: Total DSC $52,175.64 x $52,175.64 $63,878.64 x $52,175.64 $15,574.43 $131,628.71 Labor Subtotal * 2015 escalated base labor rates (2 %) Reimbursable Vehicles - Mileage Expenses Subconsultant Materials Testing Allowance Surveying $142,090.29 Cost $ 4,000.00 $ 2,000.00 $6,000.00 Cost $12,000.00 $0.00 $12,000.00 (Total $160,090.29 Original Budget Hours vs. Corresponding Actual Hours Supplemental Hours 2014 2015 March April January Feburary March April May June July August September October November December January February budget actual delta 4 -26 thru 5-30 12- 20thru 1 -31 2 -1 thru 2 -28 3 -1 thru 3 -28 3 -29 thru 4 -25 4 -26 thru 5 -30 5 -31 thru 6 -27 6 -28 thru 7 -25 7 -25 thru 8 -29 8 -30 thru 9.26 9.27 thru 10 -31 11 -1 thru 11 -28 11 -29 thru 12 -26 12 -27 thru 1 -30 2 -1 thru 2 -28 12 -20 thru 1 -31 2 -1 thru 2 -28 3 -1 thru 3 -28 3 -29 thru 4 -25 4 -26 thru 5 -30 5 -31 thru 6 -27 6 -28 thru 7 -25 7 -25 thru 8 -29 8 -30 thru 9 -26 9 -27 thru 10 -31 11 -1 1hru 11 -28 11-29 thru 12 -26 12 -27 thru 1 -30 2 -1 thru 2 -28 201 ?._ 80 5 16 64 _ --._ 0, 13.5 0 66 Mike Marto n - PM /QA B4 16 188 208,5 -20.5 Mike Horton - PM /QA 16 14 16 15 16 21 16 20 20 24 16 20 16 19 20 ?8.5 16 15 Jim Fillis - RE 96 48 64 99 64 102 64 73 80 59 64 -'S 64 3:1 80 96.5 80 62 64 160 _-4 154 800 7-7 23 Janet Lee - ARE 160 19.5 160 364.5 160, 970.5 160 150 200 166 160 16 160 e5 2001 195 160 164.5 200' 196 0 7S 0 144 0 0 32 0 1720 1839 -119 Inspection 200 125 160 '94 160 153 160 165 360 200 150 397 160 182 360 312.5 150 181.5 40I 179.5 0 121 0 118.5 118.5 1105 192 . 1920 2069 149 Jaime Shinsato - Documentation 0 0 32 0 32 0 32 0 40 0 32 0 32 112 40 205 32 140 281 401 <7 0 0 0 0 0 8 22 0 88 0 300 200 501 x08 -201 92 Jesse Rogers - Arch. Insp. 0 0 0 5 0 0 0 0 0 5 0 -0 0 4 0 _ 160 19 Other 0 0 0 2 0 1 0 1 0 9 0 30.2 0 0 D 12 0 0 0 5532.2 0 _„ 0 O. 20.7 -29.7 5128 5532.2 -404,2 Supplemental Hours Total Hours January Feburary March April May June July August September October November December January Feb uary budget actual delta 12 -20 thru 1 -31 2 -1 thru 2 -28 3 -1 thru 3 -28 3 -29 thru 4 -25 4 -26 thru 5-30 5 -31 thru 6 -27 6 -28 thru 7 -25 7 -25 thru 8 -29 8 -30 thru 9 -26 9 -27 thru 10 -31 11-1 thru 11 -28 11 -29 ti ru 12 -26 12 -27 thru 1 -30 2 -1 th u 2 -28 12 -20 thru 1 -31 2 -1 thru 2 -28 3 -1 thru 3 -28 3 -29 thru 4 -25 4 -26 thru 5 -30 5 -31 thru 6 -27 6 -28 thru 7 -25 7 -25 thru 8 -29 8 -30 thru 9 -26 9 -27 thru 10 -31 11 -1 1hru 11 -28 11-29 thru 12 -26 12 -27 thru 1 -30 2 -1 thru 2 -28 Mike Harlon - PM /QA Mike Marto n - PM /QA B4 16 15 16 ?1 16 29 20 <. 16 ,_7 16 19 20 28.5 16 FS 201 : 80 2001 196 401 „ • 9 281 13.5 13.6 20 13.4 ev 144 929.5 16 49.5 13.5 36 Jim Fillis • RE 25 249 245 129.5 -113 Jim Fillis -RE 96 a° 60.5 64 160 a €6.15 64 160 ?02 1'0.5 64 160 7_ 960 80 200 59 ..a_ 64 160 r5 160 64 160 _-4 154 80 200 66 46 80 160 64. 200 210 56 144 Janet Lee -ARE 153 160 165 360 -2 1601 19'+ 160 10' 360 312.5 160 181,5 1 0 0 32 0 44 144 192 0 160 _ 396 134 252 Inspection 201 32 140 Jesse Rogers- Arch. Insp. 0 0 0 3 0 0 0 0 1 u 0 ?6 0 118.5 1105 192 . 0 0 310.5 118.5 192 Jaime Shinsato - Documentation 16 254 108 146 Other 0 0 0 s 0 _ 0 _ 0 0 8 3 40 0 40 0 88 0 80 Jesse Rogers - Arch. Insp. 0 0 0 0 29.7 -29.7 _22i o _5 16 ib 54 22 32 0 0 0 0 0 0 Other 6184 5532.2 651.8 1108 372 736 Total Hours January Feburary March April May June July August September October November December January Feb uary budget actual delta 12 -20 thru 1 -31 2 -1 thru 2 -28 3 -1 thru 3 -28 3 -29 thru 4 -25 4 -26 thru 5 -30 5 -31 thru 6 -27 6 -28 thru 7 -25 7 -25 thru 8 -29 8 -30 thru 9 -26 9 -27 thru 10 -31 11 -1 1hru 11 -28 11-29 thru 12 -26 12 -27 thru 1 -30 2 -1 thru 2 -28 Mike Harlon - PM /QA 16 B4 16 15 16 ?1 16 29 20 <. 16 ,_7 16 19 20 28.5 16 FS 201 : 80 2001 196 401 „ • 9 281 16 64 0 0 0 _00 ,_ .�0 _26 13.5 66 44 118.5 81 13.4 ev 144 929.5 16 80 160 160. 40 16 80 160 0 40 233.5 1026 2084 2198.5 388 208.5 777 1839 2069 501 25 249 245 129.5 -113 Jim Fillis -RE 96 a° 60.5 64 160 a €6.15 64 160 ?02 1'0.5 64 160 7_ 960 80 200 59 ..a_ 64 160 r5 160 64 160 _-4 154 80 200 S 195 80 160 52 169,5 Janet Lee ARE 160 Inspection 200 125 160 134 160 153 160 165 360 -2 1601 19'+ 160 10' 360 312.5 160 181,5 Silvia Manescu - Documentation 0 0 32 0 32 0 32 0 40 _ 32 x 32 __e 40 201 32 140 Jesse Rogers- Arch. Insp. 0 0 0 3 0 0 0 0 0 u 0 ?6 0 0 -? 160 . 401 <_ 0 + 22 .,2 16 16 254 108 146 Other 0 0 0 s 0 _ 0 _ 0 0 0 10.2 0 0 12 0 - 0' 2 0 1.5 0 0 0 0 29.7 -29.7 6184 5532.2 651.8 8 Transportation Committee Minutes January 20, 2015 - Page 2 Supplemental Agreement: Tukwila Urban Center Transit Center Project Staff is seeking Council approval of Supplemental Agreement No. 1 with AECOM Technical Services in the amount of $160,090.29 for the Tukwila Urban Center (TUC) Transit Center, Andover Park West Street and Water Improvement Projects (Transit Center Project). This supplement will allow AECOM to continue providing construction management services through the end of February 2015 when construction is expected to be complete. Funds for this supplement are available from the project's contingency fund. UNANIMOUS APPROVAL. FORWARD TO FEBRUARY 2, 2015 REGULAR CONSENT AGENDA. D. Project Completion: Tukwila Manufacturing /Industrial Center Smart Street Non - Motorized Staff is requesting Council approval of project completion and release of retainage to Macnak Construction, LLC in the amount of $179,694.88 for the MIC Smart Street Non - Motorized Project. The project constructed bicycle /street improvements such as pavement and striping removal, shoulder reconstruction, paving, signage, re- channelization and striping, and was physically complete on October 15, 2014. One change order was executed for additional pavement marking removals. The total budget was $249,326.90 UNANIMOUS APPROVAL. FORWARD TO FEBRUARY 2, 2015 REGULAR CONSENT AGENDA. III. SCATBd Councilmember Hougardy noted that she plans to continue as the Council representative on SCATBd for 2015 and will represent the City's position on key topics such as a future Boeing Access Road light rail station. IV. MISCELLANEOUS Committee member Duffie requested that staff assist a resident seeking information regarding an accident that occurred in SeaTac at the intersection of South 154th and Tukwila International Boulevard. Staff distributed a draft copy of the 2015 Transportation Committee Work Plan and indicated that further discussion would be held at the February 9 Committee of the Whole meeting. Meeting adjourned at 6:03 p.m. Next meeting: Tuesday, February 17, 2015 ) Committee Chair Approval Menu," s by LH, Reviewed by GL 9