ITEM INFORMATION
ITEM No.
4.E.
CAS NUMBER:
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATE: 02/02/15
AGENDA ITEM TITLE Tukwila
Project
Manufacturing/Industrial Center Smart Street Non-Motorized Project
Completion and Acceptance
CATEGORY TI Discussion
Mtg Date
Motion
Date 02/02/15
[1 Resolution
Mtg Date
[ Ordinance
Mtg Date
Bid Award
Mtg Date
1-1 Public Hearing
Mtg Date
[ Other
.AftgDate
'
Mtg
SPONSOR fl Council EI Mayor El HR DCD E Finance r---1 Fire IT r---1 P&R LI Police IA PIV
SPONSOR'S The contract with Macnak Construction, LLC of Lakewood, WA is complete for the Tukwila
SUMMARY Manufacturing/Industrial Center (MIC) Smart Street Non-Motorized Project. This project
installed 5,280 linear feet of bicycle facilities along East Marginal Wy S, Boeing Access Rd
S, and Airport Wy S from SR 599 to the City limits. One change order was issued and under
runs totaled ($39,404.68). Council is being asked to accept and finalize the contract with
Macnak Construction in the amount of $179,694.88.
REVIEWED BY COW Mtg. E CA&P Cmte F&S Cmte
Utilities Cmte r Arts Comm. Parks Comm.
DATE: 01/20/15 COMMITTEE CHAIR: JOE
i4 Transportation
Cmte
E Planning Comm.
DUFFIE
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMVIME
Public Works
Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$179,694.88 $0.00 $0.00
Fund Source: 104 ARTERIAL STREET FUND
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
02/02/15
MTG. DATE
ATTACHMENTS
02/02/15
Informational Memorandum dated 01/16/15
State of WA Depart of Revenue Notice of Completion 14-125
Minutes from the Transportation Committee meeting of 01/20/15
27
28
TO:
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
BY: Peter Lau, Senior Program Manager
DATE: January 16, 2015
SUBJECT: Tukwila Manufacturing/Industrial Center Smart Street Non-Motorized Project
Project No. 91310406, Contract No. 14-125
Project Completion and Acceptance
ISSUE
Accept construction contract as complete, and authorize release of retainage.
BACKGROUND
The Notice to Proceed for Contract No. 14-125 with Macnak Construction, LLC of Lakewood, Washington was
issued on September 15, 2014 for the Tukwila Manufacturing/Industrial Center (MIC) Smart Street Non-
Motorized Project. The MIC Smart Street project constructed roughly 5,280 linear feet of bicycle facilities along
East Marginal Way South, South Boeing Access Road, and Airport Way South from SR 599 to the City limits.
The street improvements included pavement and striping removal, shoulder reconstruction, hot mix asphalt
paving, new signage, re-channelization, and striping.
DISCUSSION
The MIC Smart Street Non-Motorized Project was physically completed on October 15, 2014. One change order
was executed for additional quantities of pavement markings that were required to be removed.
FINANCIAL IMPACT
The construction budget for this project was $249,326.90. Unit price under-runs were due to some bid items not
completely utilized during construction. The under-utilized bid items include; unanticipated construction conflict,
flaggers and spotters and property restoration (project was in City right-of-way). No retainage was withheld from the
contractor as the MIC Smart Street Project had $379,292.00 in federal grant funding for design and construction.
Construction Contract Amount
Change Order No, 1
Unit Price Under-runs
Budget with 15% Contingency
Total Contract and Budget
CM Expenses
$216,806.00
$2,293.56
($39,404.68)
0.00
$179,694.88
Budget
$249,326.90
$249,326.90
RECOMMENDATION
The Council is being asked to formally accept this construction contract as complete and authorize the release
of retainage, subject to standard claim and lien release procedures, for the MIC Smart Street Non-Motorized
Project with Macnak Construction, LLC in the final amount of $179,694.88, and to consider this item on the
Consent Agenda at the February 2, 2015 Regular Council Meeting.
Attachment: Notice of Completion
W:IPW Eng1PROJECTSIA- RW & RS Projects\Tukwila MIC Smart Street Non-Motorized Project (91310406)IConstructiondt700 - Post Construction & CloseoutInfo Memo Closeout MIC Smart Street 1-16-15 sb.doc
29
30
Date:
[l Original
[�
�� Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Contractor's UBI Number: 602 739 651
City of Tukwila
6200 Southcenter Blvd
Tukwila WA 98188
UBI Number: 179 000 208
Assigned o:
Date Assigned:
Notice is hereby iven relative to the completion of contract or project described below
Project Name
Tukwila Mfg/lndustrial Center Smart St Non-Motorized Proj.
Contract Number
#14-125 Project #91310406
Job Order Contracting
El] Yes V No
Description of Work Done/Include Jobsite Address(es)
Construction of roughly 5.280 linear feet of bicycle facilities along East Marginal Way G. Boeing Access Road S. and
Airport Way S from SR 599 to Tukwila city limits. Work included pavement and striping romova|, shoulder
reoons1ruction. HMA, signing, and channelization.
Federally funded transportation project? Sii Yes [l No (if yes, provide Contract Bond Statement below)
Contractor's Name
Macnak Construction, LLC
E-mail Address
www.macnak.com
Affidavit ID*
543318
Contractor Address
2G24112thStG. Suite A-1. Lakewood, VVAQ84Q8
Te
253-212-2378
ephone #
If Retainage is not withheld, please select one of the follo ing and List Surety's Name & Bond Number.
r] Retainage Bond Contract/Payment bond (valid for federally funded transportation projects)
Name: North American Speci a/ty|nauranoeCompony
|
|BondNumber:2185683
Date Work Completed
October 15, 2014
Date Work Accepted
Date Contract Awarded
August 18, 2014
Date Work Commenced
September 15, 2014
Were A ��� ��l
Affidavit ID* - No L&I release will be granted until all affidavits are listed.
Contract Amount
Additions (+)
Reductions ( - )
Sub-Total
Amount of Sales Tax
0.0
(If variou rates apply, please send a breakdown
roc.0 ��
n cloyru*�� u'
$ 218.806.00
$ 2,293.56
$ 39'404.68
$ 179,694.88
�
TOTAL $
179,694.88
Liquidated Damages $ 0.00
Amount Disbursed $ 179.694.88
Amount Retained $ 0.00
NOTE: These two totals must be equa
TOTAL $ 170.094.88
Comments:
Note: The Disbursing Officer must submit this completed notic immediately atte acceptance of the work done unde this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all releas certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber
Email Address: umno.jauer@tvxwilawuenv
Department of Revenue
Public Works Section
(360) 704-5650
REV 31 0020e (4/28/14) F2l5-038-000 04-2014
Washington State Deparrment of
Labor & Industries
Contract Release
Title: Fiscal Specialist
Phone Number: 206-433-1871
Employment Security
Department
Registration, Inquiry,
Standards & Coordination
Unit
(360) 902-9450
publicworks@esd.wagov
Addendum A: Please List all Subcontractors and Sub -tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L &I release will be granted until all affidavits are listed.
Subcontractor's Name:
UBI Number: (Required)
Affidavid ID*
Advanced Government Services, Inc.
602 304 323
539452
Apply A Line, Inc
600 553 941
543930
Evergreen Concrete Cutting, Inc.
601 605 667
537359
Puget Paving & Construction, Inc.
600 403 309
538973
For tax assistance or to request this document in an alternate format, please call 1- 800 - 647 -7706. Teletype (TTY) users may use the
Washington Relay Service by calling 711.
REV 31 0020e Addendum (04/28/14) F215- 038 -000 04 -2014
32
Transportation Committee Minutes January 20, 2015 - Page 2
C. Supplemental Agreement: Tukwila Urban Center Transit Center Project
Staff is seeking Council approval of Supplemental Agreement No. 1 with AECOM Technical
Services in the amount of $160,090.29 for the Tukwila Urban Center (TUC) Transit Center,
Andover Park West Street and Water Improvement Projects (Transit Center Project). This
supplement will allow AECOM to continue providing construction management services through
the end of February 2015 when construction is expected to be complete. Funds for this
supplement are available from the project's contingency fund. UNANIMOUS APPROVAL.
FORWARD TO FEBRUARY 2, 2015 REGULAR CONSENT AGENDA.
D. Project Completion: Tukwila Manufacturing /Industrial Center Smart Street Non - Motorized
Staff is requesting Council approval of project completion and release of retainage to Macnak
Construction, LLC in the amount of $179,694.88 for the MIC Smart Street Non - Motorized Project.
The project constructed bicycle /street improvements such as pavement and striping removal,
shoulder reconstruction, paving, signage, re- channelization and striping, and was physically
complete on October 15, 2014. One change order was executed for additional pavement
marking removals. The total budget was $249,326.90 UNANIMOUS APPROVAL. FORWARD
TO FEBRUARY 2, 2015 REGULAR CONSENT AGENDA.
III. SCATBd
Councilmember Hougardy noted that she plans to continue as the Council representative on SCATBd
for 2015 and will represent the City's position on key topics such as a future Boeing Access Road light
rail station.
IV. MISCELLANEOUS
Committee member Duffie requested that staff assist a resident seeking information regarding an
accident that occurred in SeaTac at the intersection of South 154th and Tukwila International
Boulevard.
Staff distributed a draft copy of the 2015 Transportation Committee Work Plan and indicated that
further discussion would be held at the February 9 Committee of the Whole meeting.
Meeting adjourned at 6:03 p.m.
Next meeting: Tuesday, February 17, 2015
). Committee Chair Approval
Minuf s by LH, Reviewed by GL