SPONSOR'S Contract No. 13 -036 with KPG provided design and construction management for the East
SUMMARY Marginal Way S Storm Pipe Replacement Project. Due to various issues, the project has
been delayed and KPG will need to continue to provide construction management through
April 2015. Contingency of $205,878.23 will cover KPG's Supplemental Agreement No. 6.
Council is being asked to approve KPG's Supplement No. 6 to Contract No. 13 -036 in the
amount of $137,575.04.
RI VIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ❑ Transportation Cmte
® Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 02 /10/15 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works Department
CoMMrI""E'E' Unanimous Approval; Forward to Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$137,575.04 $205,878.23 $0.00
Fund Source: 412 SURFACE WATER FUND (PAGE 89, 2015 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
02/17/15
ITEM INFORMATION
ITEMNO.
4.E.
17
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATE: 02/17/15
AGENDA ITEM TITLE East Marginal Way S Storm Pipe Replacement
Construction Management Supplemental Agreement with KPG
CATEGORY ❑ Discussion
Mtg Date
® Motion
Mtg Date 02117115
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police ® PV
SPONSOR'S Contract No. 13 -036 with KPG provided design and construction management for the East
SUMMARY Marginal Way S Storm Pipe Replacement Project. Due to various issues, the project has
been delayed and KPG will need to continue to provide construction management through
April 2015. Contingency of $205,878.23 will cover KPG's Supplemental Agreement No. 6.
Council is being asked to approve KPG's Supplement No. 6 to Contract No. 13 -036 in the
amount of $137,575.04.
RI VIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ❑ Transportation Cmte
® Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 02 /10/15 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works Department
CoMMrI""E'E' Unanimous Approval; Forward to Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$137,575.04 $205,878.23 $0.00
Fund Source: 412 SURFACE WATER FUND (PAGE 89, 2015 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
02/17/15
MTG. DATE
ATTACHMENTS
02/17/15
Informational Memorandum dated 02/06/15
KPG Supplement Agreement No. 6 to Contract No. 13 -036 with Exhibits
Minutes from the Utilities Committee meeting of 02/10/15
17
im
-City of Tukwila
Jim Haggerton, Mayor
TO: Mayor Haggerton
Utilities Committee
FROM: Bob Giberson, Public Works Director 431—)
BY: Mike Ronda, Construction Project Manager
DATE: February 6, 2015
SUBJECT: East Marginal Way S Storm Pipe Replacement
Project No. 91241206, Contract No. 13-036
Supplement No. 6 for additional Construction Engineering support
ISSUE
Execute Supplement No. 6 for KPG, Inc. to provide additional construction engineering services for the East
Marginal Way S Storm Pipe Replacement Project.
BACKGROUND
KGP was hired to provide design and construction management services for the East Marginal Way S Storm Pipe
Replacement Project. The contract working days established at the time of bid placed the contract completion
date in early January 2015, The project has encountered several delays associated with unexpected site
conditions and conflicts with existing utilities and the most current anticipated project completion date is now mid-
April 2015.
DISCUSSION
This supplement will provide additional budget to support the extra field oversight required to track, manage, and
record the ongoing construction work. KPG's field team has been performing this scope for the entire project and
currently consists of a full-time inspector, supported by a nearly full-time project engineer, and an administrative
assistant. KPG is currently engaged in the conflict resolution and tracking active, disputed, and extra work by the
contractor. Continued construction management support is needed to resolve outstanding issues and complete
the work in the most time and cost effective way possible.
FISCAL IMPACT
The fiscal impact of extending the KPG contract for roughly 14 weeks on Supplement No. 6 is $137,575.04. The
Project's 10% contingency is $205,878.23, leaving a $68,303.19 balance for all other cost over-runs.
Additional contractor expenditures will also be required due to unexpected site conditions and utility conflicts. The
extent of these additional costs is not known at this time.
Council is being asked to approve Supplement No. 6 to Contract 13-036 for $137,575.04 with KPG, Inc. for the
East Marginal Way S Storm Pipe Replacement Project and consider this item on the Consent Agenda at the
February 17, 2015 Regular Meeting.
Attachment: Supplement No. 6
WAPW Eng\PROJECTS\A- DR Projects\EMWS Emergency Storm Pipe Repair 11-19.12 (91241206)\Consultant Selectiori\(010) - CM Scope and Encumbrances\lnfo Memo KPG Sup #6 02-06-2015 sb.docx 19
20
SUPPLEMENTAL AGREEMENT No. 6
AGREEMENT No. 13 -036
PROJECT No. 91241206
City of Tukwila KPG, Inc.
Public Works Department 753 - 9th Avenue N.
6300 Southcenter Boulevard #100 Seattle, WA 98109
Tukwila, WA 98188
PROJECT: E. Marginal Way Storm Pipe Replacement — Construction Services
This SUPPLEMENTAL AGREEMENT NO. 6 is to supplement the agreement entered into with KPG,
Inc. and the City of Tukwila, which was executed on the 5`'' day of February, 2013.
All provisions in the basic agreement remain in effect, except as expressly modified as follows:
Article 2, Scope of Services, shall be supplemented with the following:
The Consultant agrees to provide constructionn services in accordance with the scope of work included as
Exhibit A.
Article 4, Payment, shall be modified as follows:
Payment for work provided by Consultant shall be made as provided on Exhibit B, attached hereto,
provided that the total amount of payment to the Consultant for this work not exceed $137,575.04 without
express written modification of the Agreement signed by the City. The new total contract shall not exceed
$687,437.11 without express written modification of the Agreement signed by the City.
IN WITNESS WHEREOF, the parties hereto have set their hands and seals this day
of , 2015.
APPROVED:
CITY OF TUKWILA
Jim Haggerton
Mayor
Attested:
Christy O'Flaherty, City Clerk
APPROVED:
KPG, INC.
Nelson Davis, P.E.
Principal
21
1 *A:ll:lk911
City of Tukwila
East Marginal Way S
Storm Pipe Replacement
Supplement No. 6
Construction Services
Scope of Work
January 18, 2015
A. Project Description
The purpose of this scope is to amend the services and the associated fee defined in the East Marginal
Way S Storm Pipe Replacement Project. Due to unforeseen site conditions and the contractor's work
approach, the most current project schedule estimate places the conclusion of the construction portion
of the project at April 15, 2015. This date is approximately 14 weeks past the originally scheduled
project conclusion date of January 5, 2015. This extension has resulted in the need for additional days
for the construction team to manage the project, provide construction documentation support, and field
inspection oversight.
This scope and fee will serve as Supplement #6 for Project No 91241206. The Consultant Fee
Determination is attached to this scope of work and is labeled Exhibit B -1.
B. Deliverables
Consultant deliverables are described in Task 10 of the Scope of Work.
C. Proposed Schedule
This supplement does not change the current contract completion date of June 31, 2015.
D. Scope of Work
Task 10 — Additional Construction Services
This task covers the effort required to manage the contract and assure that the project meets the City's
expectations for schedule, budget and quality of product. Effort included under this task is as follows:
10.1 Management /Coordination — The consultant shall continue Project Management and
Coordinate the project team through April 15, 2015.
10.2 Construction Services (Office) — The consultant shall provide additional construction
documentation support and contractor coordination through April 15, 2015.
Task 10 Deliverables:
• Extended Construction Management, Documentation and Office Support
City of Tukwila — East Marginal Way
Storm Pipe Replacement
Construction Services
Scope of Work
22
Page 1 of 7
KPG
Project Number 13156
512912014
Exhibit B
Consultant Fee Determination
Project Name: City of Tukwila
East Marginal Way Storm Pipe Replacement
Supplement No 6 - Construction Services
Consultant: KPG
COST PLUS FIXED FEE
Classification
Hours
Rate
Cost
Project Manager
14
$
65.00
$
910
Senior Engineer
14
$
52.06
$
729
Project Engineer
280
$
44.90
$
12,572
Design Engineer
0
$
36.06
$
-
CAD Technician
0
$
31.25
$
-
Construction Inspector
560
$
37.00
$
20,720
Surrey Crew
0
$
50.75
$
-
Document Specialist
56
$
40.87
$
2,289
Office Admin
420
$
26.92
$
11,306
Total Direct Salary Cost (DSC)
Overhead (145.78% x DSC)
Fixed Fee (30% x DSC)
REIMBURSABLES
1,344
Subtotal:
$48,5261
$70,741.221
14,557.801
825.04
Construction Vehicles (3 months @ $750) $2,250
Miscellaneous - Mileage, Repro, Field Supplies $1,500
Subtotal: $3,750
SUBCONSULTANT COSTS
Material Testing Allowance $0
Subtotal: $0
TOTAL
$ 137,575.04
23
HOUR AND FEE ESTIMATE
Project: City of Tukwila
East Marginal Way Storm Replacement Project
Supplement No. 6 - Construction Services
EXHIBIT B
Estim
CAD Const
Task Description Manager Engineer Engineer Engineer Technician Inspector Crew Specialist
KPG
It Architecture •
LnndMCarrc A rch,tccture
f Civil Engineering t
179.26 $ 143.58 $ 123.83 $ 99.45 $ 88.18 $ 102.04 $ 139.98 $ 112.71 $ 74.241
1 - Management, Coordination, Administration (Estimated duration 32 weeks)
Weald level of effort b Classification 0 0
i_ Y ;
Budget
0
0
0
Preconstruction Budget Estimate
0 0
0
1 0
0 0
0 0
2 Preconstruction Services (Estimated duration 4 weeks)
Weekly level of effort by Classification 0 0 0 0 0
Q 0 0
Preconstruction Budget Estimate 0
0 0 0 0 0 0 0 0
3 - Construction Services (Estimated duration 14 weeks)
Weekly level of effort by Classification 1
1 20 0 0 40 0 4 30
1 Construction Period Budget Estimate 14 14 280 0 0 560 0 56 420 $ 133,825.04 1
4 - Closeout/Record Dwg Services (Estimated duration 3 weeks)
Weektj level of effort by Classification 0 0 0 0 0
0
0 0
1 Closeout / Record Dwg Budget Estimate 0 0 0 0 0 0 0 0 0 $ - 1
Subtotal - Labor
14 14 280 0 0
0
420
Reimbursables 8 Subconsultants
133,825.04
Material Testing Allowance 5
Construction Vehicles (3 months @ $750) $
Miscellaneous - Mileage, Repro, Field Supplies $
2,250.00
1,500.00
Subtotal - Relmburaables
3,760.00
Total Project Budget
137,675.04
City of Tukwila
* Utilities Committee
UTILITIES COMMITTEE
Meeting Minutes
February 10, 2015 — 5:30 p.m. — Foster Conference Room
PRESENT
Councilmembers: Dennis Robertson, Chair; Verna Seal, De'Sean Quinn
Staff: David Cline, Bob Giberson, Robin Tischmak, Frank Iria
Ronda, Gail Labanara, Mike Cusick and Laurel Humph
CALL TO ORDER: Committee Chair Robertson called the meeting
I. PRESENTATIONS
No presentations.
II. BUSINESS AGENDA
A. Supplement No. 6
Staff is seeking Council approval of Supplement No. 6 to Cc
amount of $137,575.04 for the East Marginal Way South 5toi
construction management supplement will , provide additic
oversight of the ongoing construction work, delayed by unE
trees and utility conflicts. Staff displayed several photos of the
FORWARD TO FEBRUARY 17, 2015 REGULAR CONSENT
FBI
rodin, Peter Lau, Mike
at 5 :30.D.m.
-act 13 -036 with KPG, Inc. in the
Pipe Replacement Project. This
budget to support extra field
)cted site issues such as rocks,
aject. UNANIMOUS APPROVAL.
iENDA.
ilitation /Andover Park W
rk
Staff provided the Committee with a briefing on the CBD Sanitary Sewer Rehabilitation and
Andover Park West to Andover Park East Sewer Repair Projects. These projects are part of an
effort to extend the life of deteriorating sewer lines within the CBD to include repair of a collapsed
sewer line and 2,440 feet of sliplining. Following the repair and cleaning of the collapsed pipe
near the railroad tracks between APE and APW, an additional collapse occurred on February 4.
Staff showed before and after video images of this area. The newly collapsed pipe is currently
being repaired, with costs to follow. INFORMATION ONLY.
III. MISCELLANEOUS
No discussion was held on the Utilities Committee Work Plan.
Committee Chair Robertson requested an update on the Army Corps of Engineers' planned
rehabilitation of the Desimone Levee. Staff is preparing for a meeting with Colonel Buck to review the