HomeMy WebLinkAboutTrans 2015-02-17 Item 2B - Final Acceptance - 2014 Overlay and Repair Program with Miles Construction-City of Tukwila Jim Haggerton, Mayo; TO: Mayor Haggerton Transportation Committee A FROM: Bob Giberson, Public Works Director BY: Dave Sorensen, Project Manager DATE: February 13, 2015 SUBJECT: 2014 Overlay and Repair Program Project No. 91410401, Contract No. 14-089 Project Completion and Acceptance ISSUE Accept contract as complete and authorize release of retainage bond. BACKGROUND The Notice to Proceed for Contract No. 14-089 with Miles Construction Inc., of Tacoma, Washington was issued on July 11, 2014 for the 2014 Overlay and Repair Project. This overlay project provided hot mix asphalt (HMA) paving at eight locations throughout the City and overlay of a portion of the parking lot at Fort Dent Park. The street improvements included; paving; removing and replacing concrete curbs, gutters, sidewalks and ADA ramps; installing traffic loops and junction boxes; adjusting surface utilities to grade; and installing roadway channelization. ANALYSIS Construction was physically completed on November 7, 2014. Two change orders were executed to include additional work for electrical junction boxes and a time extension. Asphalt quantities and pavement repairs were less than expected and the major factors in a cost savings of $104,773.25. No retainage was withheld by the City for this project as there was a contractor retainage bond. The total budget for the 2014 Overlay & Repair Project was $1,123,283.70 and included a 5% contingency, which was not expended on this project. Construction Contract Amount $1,069,794.00 Change Order Nos. 1 — 2 13,000.00 Underruns (104,773.25) Total Amount Paid $ 978,020.75 The Council is being asked to formally accept and authorize the release of the retainage bond, subject to standard claim and lien release procedures, for the 2014 Overlay and Repair Project with Miles Construction in the final amount of $978,020.75 and to consider this item on the Consent Agenda of the March 2, 2015 Regular Meeting. Attachment: Notice of Completion WAPW Eng\PROJECTSVA- RW & RS Projects\Annual Overlay & Repair Programs\2014 Overlay & Repair Program (91410401)\Construction\Contractor\Pre CloseoutUoseouti)ocsto TC\Project Closure Docs to Mlnfo Memo - 2014 Overlay Closeout 02-13-15 - sb.docx y 5ta f^ r ❑ Original 'ryx ❑ Revised # YfS. ff iti Fa v NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT Date: 12/19/14 Contractor's UBI Number: 171 - 004 -760 Name & Mailing Address of Public Agency Department Use Only City of u wl a Assigned to: 6200 Southcenter Boulevard Tukwila, WA 98188 Date Assigned: UBl Number: 91- 6001519 Notice is herebv eiven relative to the comnletion of contract or nroieet described below Project Name Contract Number Job Order Contracting 2014 Overlay Program Project No. 91410401 114-089 El Yes Y No Description of Work Done /Include Jobsite Address(es) Hot mix asphalt (HMA) overlay of up to eight sites, all within the City of Tukwila Federally funded transportation project? ❑ Yes Lys No (if yes, provide Contract Bond Statement below) Contractor's Name E -mail Address Affidavit ID* Miles Resources, LLC 1534782 Contractor Address ITelephone # 400 Valley Ave NE, Puyallup WA 98372 253 - 383 -3585 If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number. VRetainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects) Name: Liberty Mutual Insurance Company 113ond Number: 023028481 Date Contract Awarded Date Work Commenced Date Work Completed Date Work Accepted 5/28/2014 7/11/2014 11/7/2014 Were Subcontracters used on this project? If so, please complete Addendum A. Yes ❑ No Affidavit ID* - No L, &I release will be granted until all affidavits are listed. Contract Amount Additions ( + ) Reductions (- ) Sub -Total Amount of Sales Tax 0.0 (If various rates apply, please send a breakdown) a Comments: $ 1,069,794.00 $ 13,000.00 $ 104,773.25 $ 978,020.75 TAL $ 978,020.75 NOTE: These two totals must be Liquidated Damages $ 0.00 Amount Disbursed $ 978,020.75 Amount Retained $ 0.00 TOTAL $ 978,020.75 Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract. NO PAYMENT SIIAIJ, BE MADE FROM RETAINED FUNDS until receipt of all release certificates. Submitting Form: Please submit the completed form by email to all three agencies below. Contact Name: Title: Email Address: Department of Revenue Washington State Department of Public Works Section Labor & Industries (360) 704 -5650 Contract Release PWC @dor.wa.gov (855) 545 -8163, option # 4 ContractRelease @LNI. WA.GOV REV 31 0020e (4/28/14) F215- 038 -000 04 -2014 Phone Number: 5hEmployment Security Department Registration, Inquiry, Standards & Coordination Unit (360) 902 -9450 publicworks@esd.wa.gov 6 Addendum A: Please List all Subcontractors and Sub -tiers Below This addendum can be submitted in other formats. Provide known affidavits at this time. No L &I release will be eranted until all affidavits are listed. Subcontractor's Name: UBI Number: (Required) Affidavid ID1 Cascade Channel & Grouting 601- 426 -821 548043 Ground Up Road Construction 602 - 790 -246 550410 Highmark Concrete Contractors 603- 004 -408 550178 Northwest Traffic, Inc. 602 - 140 -049 543275 Petersen Brothers, Inc. 600- 072 -474 531860 Transportation Systems, Inc. 602 - 726 -209 546042 Evergreen Concrete Cutting, Inc. (Sub to Miles) 601- 605 -667 546887 Combined Cutting Contractors 601 - 439 -180 523197 Evergreen Concrete Cutting, Inc. (Sub to Transpsortation Systems) 602- 726 -209 530007 Briar Group, Inc. 602 -110 -282 546586 Heinrich's Trucking 275 - 005 -110 533635 For tax assistance or to request this document in an alternate format, please call 1- 800 -647 -7706. Teletype (TTY) users may use the Washington Relay Service by calling 711. REV 31 0020e Addendum (04128/14) F215- 038 -000 04 -2014