HomeMy WebLinkAboutUtilities 2015-04-14 Item 2A - Agreement - 2015 Annual Small Drainage Program - Longacres Way South Construction with Laser Underground and EarthworksCity of Tukwila
Jim Haggetton, Mayo;
TO: Mayor Haggerton
Utilities Committee
FROM: Bob Giberson, Public Works Director 4A
By: Ryan Larson, Senior Program Manager
DATE: April 10, 2015
SUBJECT: 2015 Annual Small Drainage Program — Longacres Way South
Project No. 91541201
Contractor Selection
ISSUE
Award a construction contract to Laser Underground and Earthworks, Inc. for construction of the
2015 Annual Small Drainage Program — Longacres Way South.
BACKGROUND
Washington State Department of Transportation (WSDOT) is preparing to overlay West Valley
Highway between South 180th Street and 1-405. As part of the construction, WSDOT will correct
roadway grading issues and overlay a portion of the City's Longacres Way South. The City's 2015
Annual Small Drainage Program also has a project to install a drainage system within the Longacres
Way overlay project's parameters. The City was coordinating with WSDOT on this work, but was
recently notified that the WSDOT project is approximately two months ahead of schedule and the
overlay is now scheduled to be completed by the end of May.
ANALYSIS
To complete the drainage portion of the Longacres project within the limited construction window,
staff broke out the Longacres Way South drainage work as a separate standalone project and
solicited proposals using the MRSC roster. Eight proposals were received on April 6, 2015 and were
checked and tabulated. Laser Underground and Earthworks, Inc. submitted the lowest cost proposal
in the amount of $55,441.00. The engineer's estimate was $66,845.00. Laser Underground and
Earthworks, Inc. has successfully completed drainage projects and their current references were
satisfactory.
The remaining projects in the 2015 Small Drainage Program will be advertised at a later date.
BUDGET AND BID SUMMARY
Laser Underground Contract
2015 SDP Budget (pg. 82, 2015 CIP)
Contingency (15%)
Total
RECOMMENDATION
Proposal Amount Estimate 2015 Budge
$55,441.00 $66,845.00
$325,000.00
8,316.15 10,026.75 .00
$63,757.15 76 871.75 $325,000.00
Council is being asked to award the construction contract for the 2015 Annual Small Drainage
Program — Longacres Way South to Laser Underground and Earthworks, Inc. in the amount of
$55,441.00 and consider this item on the Consent Agenda at the April 20, 2015 Regular Meeting.
Attachments: Page 82, 2015 CIP
Proposal Tabulations
WAPW EngTROJECT&A- DR ProjeGts\Annual Small Drainage Programs\2015 SDP (91541201)\Construdon\Long Acres Way - Stand Alone ContracAlnfo Memo Contractor Selection Longacres Way gl-sb.doc
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2015 to 2020
PROJECT: Annual Small Drainage Program Project No. Varies
DESCRIPTION: Select, design, and construct small drainage projects throughout the City.
JUSTIFICATION: Provide drainage corrections for existing /ongoing drainage problems throughout the City, including culvert
replacements, drain extensions, and pavement upgrades.
STATUS: Projects for this annual program are taken from Small Drainage Project List.
MAINT. IMPACT: Reduces maintenance.
Ongoing project, only one year shown in first column. Construction expenses may occur over two calendar
COMMENT: years. Budget for 2014 includes $270k for Thorndyke Safe Routes to School (S 150th St). Grants from State
Municipal Stormwater Capacity Grants.
FINANCIAL Through Estimated
(in $000'sl 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL
EXPENSES
Design
60
80
80
80
80
80
80
80
620
Land (R/W)
0
Const. Mgmt.
70
80
80
80
80
80
80
80
630
Construction
279
270
325
525
525
525
525
525
525
4,024
TOTAL EXPENSES
409
270
485
685
685
685
685
685
685
5,274
FUND SOURCES
Awarded Grant
50
50
100
Proposed Grant
0
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
409
220
485
635
685
685
685
685
685
5,174
TOTAL SOURCES
409
270
485
685
685
685
685
685
685
5,274
2
2015 - 2020 Capital Improvement Program 82
CITY OF TUKWILA - DEPARTMENT OF PUBLIC WORKS
2015 Small Drainaoe Prooram
Proposal Tubulation - Lonoacres Wav
Proiect No. 91541201
4/07/2015
Note: Costs shown in bold have been corrected
Engineers Estimate (KPG)
Laser Underground
Pivetta Brothers
RW Scott
RL Alia
Tucci & Sons
Green Field Services
Iron Creek Const
Reed Trucking
No
Section
No.
Item
Qty
Unit
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
Unit
Cost
Total
Cost
ROADWAY
1
1 -07
Minor Change
1
FA
1,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
2
1 -07
Temporary Water Pollution /Erosion
1
LS
1,000.00
1,000.00
500.00
500.00
192.00
192.00
1,400.00
1,400.00
300.00
300.00
2,000.00
2,000.00
375.08
375.08
500.00
500.00
1,500.00
1,500.00
3
1 -09
Mobilization
1
LS
5,500.00
5,500.00
4,400.00
4,400.00
4,155.00
4,155.00
23,816.00
23,816.00
5,000.00
5,000.00
7,300.00
7,300.00
11,994.36
11,994.36
5,000.00
5,000.00
13,700.00
13,700.00
4
1 -10
Project Temporary Traffic Control
1
LS
5,000.00
5,000.00
3,000.00
3,000.00
9,718.00
9,718.00
7,800.00
7,800.00
5,000.00
5,000.00
12,775.00
12,775.00
16,875.40
16,875.40
15,000.00
15,000.00
6,500.00
6,500.00
5
2 -01
Clearing and Grubbing
1
LS
500.00
500.00
1.00
1.00
388.00
388.00
1,200.00
1,200.00
1,000.00
1,000.00
250.00
250.00
157.41
157.41
1,050.00
1,050.00
2,000.00
2,000.00
6
2 -02
Pavement Removal
180
SY
15.00
2,700.00
5.00
900.00
24.00
4,320.00
15.00
2,700.00
5.00
900.00
25.00
4,500.00
45.19
8,134.20
10.00
1,800.00
49.00
8,820.00
7
4 -04
Crushed Surfacing Top Course
120
TN
35.00
4,200.00
22.00
2,640.00
37.05
4,446.00
40.00
4,800.00
30.00
3,600.00
58.60
7,032.00
41.80
5,016.00
40.00
4,800.00
49.00
5,880.00
8
5 -04
HMA CL 1/2" PG 64 -22
70
TN
150.00
10,500.00
100.00
7,000.00
226.00
15,820.00
190.00
13,300.00
260.00
18,200.00
134.00
9,380.00
202.41
14,168.70
275.00
19,250.00
190.00
13,300.00
ROADSIDE DEVELOPMENT
9
8 -01
Topsoil /Fine Compost
3
CY
50.00
150.00
50.00
150.00
112.00
336.00
70.00
210.00
30.00
90.00
100.00
300.00
177.50
532.50
100.00
300.00
130.00
390.00
10
8 -01
Seeding and Fertilizing
3
SY
15.00
45.00
100.00
300.00
51.00
153.00
50.00
150.00
10.00
30.00
25.00
75.00
77.18
231.54
50.00
150.00
20.00
60.00
11
8 -04
Cement Conc. Traffic Curb
10
LF
60.00
600.00
50.00
500.00
50.50
505.00
100.00
1,000.00
20.00
200.00
50.00
500.00
8.59
85.90
80.00
800.00
90.00
900.00
12
8 -14
Monolithic Cement Conc. Sidewalk
10
SY
100.00
1,000.00
100.00
1,000.00
290.80
2,908.00
200.00
2,000.00
200.00
2,000.00
335.00
3,350.00
60.19
601.90
200.00
2,000.00
250.00
2,500.00
STORM DRAINAGE
13
2 -09
Shoring or Extra Excavation Class 8
1
LS
2,500.00
2,500.00
500.00
500.00
575.00
575.00
500.00
500.00
100.00
100.00
250.00
250.00
629.63
629.63
1,000.00
1,000.00
5,000.00
5,000.00
14
7 -04
Ductile Iron Storm Sewer Pipe 8 In. Diam.
20
LF
85.00
1,700.00
60.00
1,200.00
130.05
2,601.00
65.00
1,300.00
100.00
2,000.00
238.00
4,760.00
45.59
911.80
150.00
3,000.00
145.00
2,900.00
15
7 -04
Solid Wall PVC Storm Sewer Pipe 12" Diam
270
LF
65.00
17,550.00
55.00
14,850.00
41.90
11,313.00
69.00
18,630.00
147.00
39,690.00
95.25
25,717.50
72.54
19,585.80
90.00
24,300.00
80.00
21,600.00
16
7 -05
Connection to Drainage Structure
1
EA
1,000.00
1,000.00
4,000.00
4,000.00
1,120.00
1,120.00
300.00
300.00
1,000.00
1,000.00
925.00
925.00
1,617.78
1,617.78
500.00
500.00
650.00
650.00
17
7 -05
Concrete Inlet
5
EA
900.00
4,500.00
1,000.00
5,000.00
1,120.00
5,600.00
900.00
4,500.00
1,000.00
5,000.00
1,225.00
6,125.00
1,130.63
5,653.15
1,500.00
7,500.00
1,700.00
8,500.00
18
7 -05
Catch Basin, Type 1
2
EA
1,100.00
2,200.00
1,500.00
3,000.00
1,482.50
2,965.00
1,200.00
2,400.00
1,000.00
2,000.00
1,225.00
2,450.00
1,111.74
2,223.48
2,000.00
4,000.00
3,000.00
6,000.00
19
7 -06
Pothole Existing Utilities
3
EA
400.00
1,200.00
500.00
1,500.00
296.00
888.00
400.00
1,200.00
900.00
2,700.00
1,000.00
3,000.00
1,007.40
3,022.20
500.00
1,500.00
300.00
900.00
TOTAL ESTIMATED CONSTRUCTION COST 1 $66,845.00
$55,441.00
$73,003.00
$92,206.00
$93,810.00
$95,689.50
$96,816.83
$97,450.00
$106,100.00
Note: Costs shown in bold have been corrected