HomeMy WebLinkAboutTrans 2015-05-04 Item 2B - Contract Supplement #12 - Tukwila Urban Center Pedestrian-Bicycle Bridge with KPFFTO: City of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM Mayor Haggerton Transportation Committee FROM: ,- Bob Giberson, Public Works Director BY: Cyndy Knighton, Senior Program Manager DATE: May 1, 2015 SUBJECT: Tukwila Urban Center Pedestrian /Bicycle Bridge Project No. 90510403, Contract No. 07 -123 Supplemental Agreement No. 12 ISSUE Approve Supplemental Agreement No. 12 with KPFF in the amount of $164,371.10 to provide additional engineering design and right of way acquisition services for the Tukwila Urban Center (TUC) Pedestrian /Bicycle Bridge project. BACKGROUND Since 2006, KPFF has been under contract to site and then design the TUC Pedestrian /Bicycle Bridge over the Green River. The design work is predominately funded by federal grants and in 2013 Tukwila was awarded funds through the State of Washington's Regional Mobility Grant Program for right of way (ROW) acquisition and construction. In late 2013, Supplemental Agreement No. 10 was approved which included funds for final design, additional studies required by permitting agencies, and ROW acquisition services. At this time the design is nearly 90% complete however continuing complications with ROW acquisition have resulted in delay in the design and permitting. The bridge landing locations were shifted slightly to the north to avoid significant ROW impacts to the Riverview Plaza Office Park. That shift requires additional studies of cultural resources as well as deep boring to study soil conditions on the property commonly called the Nelsen Parcel at 16113 West Valley Highway. DISCUSSION Supplemental Agreement No. 10 included scope and fee for certain tasks which are no longer needed with the new location of the bridge. Some tasks which were originally included have been modified to address the design changes and some new tasks are being added. Supplemental Agreement No. 12 clearly documents which tasks are new, modified or deleted. The scope of work indicates the changes in the task titles. Fee sheets show negative hours for tasks being deleted and new hours for new tasks or additional hours for existing tasks. There are two separate rates, or multipliers, used in the fee sheets which reflect the changes in salaries since Supplemental Agreement No. 10 was approved. Only new hours are using the higher multiplier. All work currently under contract which is not being changed by this supplement will remain at the lower rate. FINANCIAL IMPACT The additional costs associated with the redesign of the bridge, as well as the ROW acquisitions work is $164,371.10. This includes removal of work no longer required from Supplemental Agreement No. 10 in the amount of - $42,795.69. As the additional work is primarily in response to ROW concerns, the ROW budget will be used for this work. Right of Way Budget Nelsen Property Initial Offer Supplement No. 12 Remaining Budget $1,100,000.00 - 248,000.00 - 164,371.10 $ 687,628.90 RECOMMENDATION Approve Supplemental Agreement No. 12 and consider this item on the Consent Agenda at the May 18, 2015 Regular meeting. Attachments: Supplemental Agreement No. 12 with Exhibits CIP Pg. 12 w: \pw eng \projects \a - rw & rs projects \tuc ped bicycle bridge (90510403) \information memo - supplement agreement #12 - additional design & row - 5 -1 -15 - sb.docx 17 V7V7;Washington State Department of Tlransportation Supplemental Agreement Number 12 Organization and Address KPFF Consulting Engineers 1601 Fifth Avenue, Suite 1600 Seattle, WA 98101 Phone: (206) 622 -5822 Original Agreement Number 07 -123 (k) Project Number 05 -RWO3 Execution Date Completion Date Project Title Tukwila Urban Center, Ped/Bicycle Bridge PSE New Maximum Amount Payable $ 1,998,227.42 Description of Work Modified hydraulic, surveying, permitting, geotechnical engineering and right of way acquisition services. See scope of work (Exhibit A -1) for complete description. The Local Agency of the City of Tukwila desires to supplement the agreement entered into with KPFF Consulting Engineers and executed on and identified as Agreement No. 07 -123 All provisions in the basic agreement remain in effect except as expressly modified by this supplement. The changes to the agreement are described as follows: Section 1, SCOPE OF WORK, is hereby changed to read: See attached. 11 Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for completion of the work to read: III Section V, PAYMENT, shall be amended as follows: The total contract value increases by $164,371.10 to a new maximum payable amount of $1,998,227.42. as set forth in the attached Exhibit A, and by this reference made a part of this supplement. If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces below and return to this office for final action. By: David K. McMullen, PE By: City of Tukwila DOT Form 140 -063 EF Revised 9/2005 Consultant Signature Approving Authority Signature Date 18 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian/Bicycle Bridge - Supplement #12 Page 1 Exhibit A -1 Scope of Work Tukwila Urban Center, Pedestrian/Bicycle Bridge Supplement No. 12 - Modified Hydraulic, Surveying, Permitting, Geotechnical Engineering and Right of Way Acquisition Services PROJECT DESCRIPTION KPFF is currently under contract with the City of Tukwila (City) for the Plans, Specifications and Cost Estimate (PS &E) Phase of the Tukwila Urban Center Pedestrian and Bicycle Bridge project. Issues with acquiring the necessary Right -of- Way required that the previous trail /bridge alignment be relocated further north along the Green River Trail. Because of this trail realignment, portions of the scoped services found in Supplement #10 are no longer applicable. Additionally, relocation of the trail requires additional design effort related to the final bridge alignment, including: • Evaluation of alternative alignments north of Riverview Properties and supplementation of the original TS &L report. • Critical flaws evaluation of the preferred alternative alignment selected in the TS &L supplement • Additional effort included in updating the design of the new alignment to 60 %, 100 %, and final design of trail, bridge, and landings for multi -use trail crossing the Green River, connecting West Valley Highway to Baker Blvd at Christensen Rd. • Additional Geotechnical Engineering. • Additional Surveying • Modified Right -of -Way Acquisition The table below gives a summary of the tasks from Supplement 10 that are being deleted and /or modified as well as new tasks that are being added as a part of this supplement (Supplement 12) Summary of Supplement 10 and 12 Task Changes 1.40, 1.50, 2.12, 3.10, 3.11, 3.20, 3.21, Supplement 10 Tasks Deleted 3.22, 3.23, 3.24, 3.30, 3.31, 3.32, 3.34, 3.35, 3.40, 3.50, 5.10, 5.21, 3.33, 8.33, 8.34, 8.61, 8.81, 8.82 Supplement 10 Tasks Modified 5.20, 5.30, 8.21, 8.32, 8.81 2.13, 3.60, 3.61, 3.62, 3.63, 3.70, 3.71, 3.72, 3.73, 3.74, 3.80, 3.81, 3.82, 3.83, 3.90, 4.30, 4.40, 4.50, 4.60, 4.70, 5.40, Supplement 12 New Tasks 5.50, 7.0, 7.10, 7.20, 8.100, 9.0, 9.11, 9.12, 9.13, 9.14, 10.0, 9.10, 10.10, 10.11, 10.12, 10.13, 10.14, 10.20, 10.21, 10.22, 10.30, 10.31, 10.32, 10.33, 10.34, 10.35 19 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 2 PROJECT OBJECTIVES The overall objectives of this supplement include: • Supplement to TS &L Report evaluating alternative alignments north of the Riverview Plaza properties • Obtain technical data necessary for completion of the PS &E Phase based on the new alignment • Update design according to the new alignment PROJECT TEAM This supplement includes effort by the following project design team members: Prime Consultant Structural Engineering Civil Engineering Surveying Landscape Architecture and Planning Geotechnical Engineering Environmental and Permitting Services River Hydraulics Right of Way Acquisition KPFF Consulting Engineers KPFF Consulting Engineers KPFF Consulting Engineers KPG Inc. KPG, Inc. Landau Associates Landau Associates Watershed Science & Engineering Universal Field Services 20 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 3 SCOPE OF WORK The following is a scope of work for modifications /additions to design efforts including geotechnical engineering, surveying, permitting, planning, structural engineering, civil engineering, and right of way acquisition services in support of this project's PSE Phase. In addition to the basic services scoped in this document, the Consultant has included additional services that can be performed at the City's request. TASK NO. 1.0 - PROJECT MANAGEMENT AND ADMINISTRATION Task No. 1.40 - Design Team Meetings and Coordination (Supp. 12 TASK ADDED) The consultant team will need two (2) additional internal meetings to coordinate modified project tasks and incorporate scope changes into the project design. Additionally, KPFF will perform general coordination and be the main point of contact for the multidiscipline team. KPFF will collect and disseminate information for the team. Task No. 1.50 - Project Team Meetings with City (Supp. 12 TASK ADDED) An additional two (2) meetings with the City will be required to coordinate tasks associated with this scope of work. Deliverables: • Monthly progress reports and invoices • As- needed Project Schedule Updates • Team meetings o Participation in internal consultant team meetings o Participation in project meetings with the City 21 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 4 TASK No. 2.0 - TOPOGRAPHIC AND BOUNDARY SURVEY The following is a scope of work for additional survey items needed as design proceeds on this project. KPG has included time and expense for project meetings, management of surveying and drafting efforts, professional review and quality control in our proposal. Task No. 2.10 - Additional Survey and Mapping Subtask No. 2.12 - Extend Survey of Green River Trail (Supp. 10 TASK DELETED) The survey of the Green River Trail shall be extended northerly approximately 100 -feet to the limit of proposed improvements Subtask No. 2.13 - Survey North GRT, Additional Christensen Rd and New Bridge Abutment locations (Supp. 12 TASK ADDED) Additional survey for the north Green River Trail segment, additional Christensen Road from the existing Green River Trail head to Baker Boulevard. 22 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 5 TASK No. 3.0 - ALTERNATIVE ALIGNMENT PRELIMINARY DESIGN, AND TS&L SUPPLEMENT OF NEW ALTERNATIVE ALIGNMENTS Task No. 3.10 - Survey at Riverview Plaza Parking Lot (Supp. 10 TASK DELETED) KPG shall provide the field survey and mapping to augment the Riverview Plaza parking lot, including studies and alignments of alternative routes. Subtask No. 3.11 - Utility Locating (Supp. 10 TASK DELETED) A separate cost for private utility locating services has been included, which assumes 24 hours of underground utility sensing and locating. Task No. 3.20 - Walkway Section/ Parking Lot Trail Alignment Studies (Supp. 10 TASK DELETED) KPG and KPFF Civil shall provide alternative layouts and improvements to the Riverview Plaza property, including parking lot reconfiguration. This work will include additional design studies for proposed improvements, meetings with property owners of Riverview Plaza, and coordination with the property owner's consultants Subtask No. 3.21 - Trail Realignment Alternatives for (Supp. 10 TASK DELETED) Subtask No. 3.22 - Riverview Frontage /Property Studies DELETED) Subtask No. 3.23 - Meetings for Riverview Plaza Coordination (Supp. 10 TASK DELETED) Subtask No. 3.24 - Alternative Alignment Schematic Comparison (Supp. 10 TASK DELETED) Riverview Plaza (Supp. 10 TASK Property Owner Cost Estimate Deliverables: • Trail Alignment Alternatives and Selected Alternative Plan (including conceptual parking lot reconfigurations.) KPFF civil shall provide cost estimates for two (2) alternative alignments, compare the estimated costs to the current alignment, and identify changes to project cost as a result of alignment revisions. Task No. 3.30 - 30% Plans (Supp. 10 TASK DELETED) KPFF civil will meet with Riverview Plaza property owner representatives to discuss project progress selected alternative alignment to 30% design. Anticipated work includes preparation of new plan sheets for horizontal alignment, vertical alignment, site preparation, utility relocation, storm drainage, pavement markings and signing, and paving plans. 23 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 6 Subtask No. 3.31 - Site Preparation Plans (Supp. 10 TASK DELETED) Subtask No. 3.32 - Utilities Plans (Supp. 10 TASK DELETED) Subtask No. 3.33 - Storm Drainage and Grading (Supp. 10 TASK DELETED) Subtask No. 3.34 - Paving Plans (Supp. 10 TASK DELETED) Subtask No. 3.35 - Pavement Marking Plans (Supp. 10 TASK DELETED) Task No. 3.40 Update Storm Drainage Report (Supp 10. TASK DELETED) Storm Drainage report will need to be revised to assess impacts due to revised alignment. This may trigger stormwater detention requirements, and will also change basin delineation. Task No. 3.50 - Update Cost Estimate (Supp 10. TASK DELETED) Cost estimate will be revised to integrate quantities for preferred alignment. Task No. 3.60 - New Trail Alignment (Supp. 12 NEW TASK) KPG will update the Urban Design, Landscape and Illumination plans to a 60% design level based upon the new preferred alignment which will be selected in the TS&L Report Supplement 01. Subtask No. 3.61 - Update New Trail Alignment Urban Design to 60% (Supp. 12 NEW TASK) Subtask No. 3.62 - Update New Trail Alignment Landscape Design to 60% (Supp. 12 NEW TASK) Subtask No. 3.63 - Update New Trail Alignment Illumination Design to 60% (Supp. 12 NEW TASK) Task No. 3.70 - TS &L Alignment Studies (Supp 12. NEW TASK) KPFF shall evaluate up to 6 alternative alignments connecting Baker Blvd at Christensen Rd to West Valley Highway with a multi -use trail and bridge crossing. Work will include alignment layout, evaluation of project costs and other impacts with existing conditions and future improvements and development, right -of -way needs, and supplemental report to existing TS&L Report. 24 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 7 Subtask No. 3.71 - Subtask No. 3.72 NEW TASK) Alternative Alignment Layouts (Supp. 12 NEW TASK) - Evaluation of Alternative Alignment Layouts (Supp. 12 Subtask No. 3.73 - Subtask No. 3.74 TASK) TS &L Report Supplement 01 (Supp. 12 NEW TASK) - Design Team and City Review Meetings (Supp. 12 NEW Task No 3.80 - Fatal Flaw Assessment of Subsequent Preferred Alignment (Supp. 12 NEW TASK) KPFF shall evaluate the preferred alignment identified from the additional alignments evaluated in the TS &L Supplement. This evaluation includes meetings with King County Flood District representatives to evaluate impacts to levee, evaluation of structures within the levee and river, evaluation of river modeling done by King County Flood District for establishment of the 100 year flood elevation, assessment of horizontal alignment, and development of vertical alignment alternatives for clearances of the structure over the Green River. Work also includes meeting with City staff to review proposed alternative and resultant realignment of preferred multi -use trail along the north side of Riverview Plaza and revised landing alignment east of Green River to West Valley Highway. Subtask No. 3.81 - River and Levee Constraints (Supp. 12 NEW TASK) Subtask No. 3.82 - Horizontal and Vertical Alignment Alternatives (Supp. 12 NEW TASK) Subtask No. 3.82 - Design Team and City Review Meetings (Supp. 12 NEW TASK) Task 3.90 - Presentation Graphics (Supp. 12 NEW TASK) KPFF will prepare graphics for City suitable for presentation to the general public and the elected officials. 25 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 8 TASK No. 4.0 - CIVIL ENGINEERING Task No. 4.30 - Trail Alignment and Modeling (Supp 12. NEW TASK) KPFF civil team shall meet and coordinate design elements for revised trail alignment and layout. This work includes coordination meetings, evaluation of City standards for future frontage improvements, coordination of design elements and scope of improvements, evaluation of grades for landings, and other coordination necessary to develop the preliminary concept to a schematic design level. Task No. 4.40 - Storm Drainage Approach (Supp. 12 NEW TASK) KPFF shall design new storm drainage improvements for trail. Work includes new storm drainage report evaluating runoff and detention criteria. KPFF will present findings to City and work with the City to provide required improvements which may include mitigated collection and detention within an adjacent basin, dispersed runoff across adjacent city owned park, raingardens along West Valley Highway, and other measures currently unidentified. KPFF civil shall review all other discipline reports and information, including new survey topographic map and terrain model, supplemental geotechnical report, and proposed layout from Planners and Landscape Architect. Review will include providing comments and requests for additional information or revisions, and review of resubmittal. Task No. 4.50 - Quantities and Cost Estimate (Supp. 12 NEW TASK) KPFF shall quantify construction elements and earthwork, and prepare a preliminary cost estimate for new proposed improvements. Task No. 4.60 - Wall /Railing Assessment (Supp. 12 NEW TASK) KPFF shall work with team to design new trail alignment north of Riverview Plaza's north entrance, and along the north side of their parcel. Work shall include design of new horizontal and vertical alignment, modeling of pavement section, evaluation of trail and shoulder widths, evaluation of wall heights and types of retaining walls and railings Task No. 4.70 - 30% Plan Sheet and Layout (Supp. 12 NEW TASK) KPFF civil shall provide permit support for revised environmental permitting information. This information is typically total earthwork summaries, stormwater impacts, project and construction description, evaluation of tree impacts, and support graphics for same. 26 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 9 TASK No. 5.0 - ENVIRONMENTAL AND PERMITTING SERVICES Landau Associates will provide supplemental environmental and permitting services for this project. The scope of services is based on discussions with and information provided by a City of Tukwila (City) Shoreline Planner regarding impacts to trees adjacent to the Green River, 30 percent plan review documentation referencing an illumination study associated with proposed bridge lighting, and coordination with WSDOT Local Programs. Task No. 5.10 - USCG Navigation Survey and Bridge Permit Application (Supp. 10 TASK DELETED) The purpose of this task is to conduct the required Navigation Survey and prepare the General Bridge permit application materials to USCG standards. To conduct the Navigation Survey, Landau Associates will contact local waterway users /managers to determine the type and characteristic of watercraft common to the stretch of the Green River affected by the proposed project. Contact with local waterway user groups /managers will include: City officials City Chamber of Commerce WDFW USACE Port of Seattle and select number of tenants. Landau Associates will document findings into a memorandum format that will include a summary of methods and results. Landau will also prepare the application cover letter formatted to the USCG Bridge Permit Application Guide. Landau will prepare draft documentation for review and comment by KPFF and the City, and then final documentation. Assumptions: No team meetings or onsite meetings with waterway user groups are included in this scope of services. Contact with no more than three Port tenants will be required as part of the Navigation Survey. Waterway user group survey will be limited to email /phone correspondence. Vessel traffic from the Port does not pass downstream of the Duwamish River Turning Basin (i.e., approximate River Mile 6). Deliverables: An electronic (MS Word) copy of the draft Navigation Survey memorandum and application cover letter. An electronic (Adobe PDF) and one paper copy of the final Navigation Survey and application cover letter. 27 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 10 Task No. 5.20 - Tree Assessment (Supp. 10 and Supp. 12 TASK MODIFIED) Landau Associates will conduct a tree assessment on the 16113 West Valley Highway property within 50 feet of the proposed bridge alignment and bridge landing. For the assessment, Landau Associates will identify the species, approximate height and crown spread, and general age class and health of trees identified on project survey. Landau will also conduct an assessment of the approximate extent of shade provided by identified trees. The shade assessment will be based on analysis of the height and crown spread of trees and altitude of the sun at 8:00 a.m., 10:00 a.m., and noon, on the Winter Solstice (i.e., altitudes with potential to provide the maximum extent of shade over the Green River). Landau will amend the project survey to identify tree species and required tree protection zone. Methods and results of the tree assessment will be summarized in shoreline permitting documentation included in Landau Associates' existing contract. Assumptions: • Determination of age class will be made following shoreline permitting requirements (i.e. young, mature, over mature). • Tree assessment field effort will require a single site visit by two Landau Associates staff members and will take no more than 8 hours to complete. • The City will arrange for any necessary right of entry to complete the tree assessment. • The need for quantitative shade assessment will be determined based on evaluation of trees to be impacted by the project. A qualitative assessment of shade provided by impacted trees will be evaluated based on size /shape of tree and distance to the River. Quantitative assessment will be needed for native species determined to likely provide significant shade to the River. • Shade analysis will be completed using hand calculations, and will be completed for individual trees or groups of trees as applicable. Deliverables: • Draft and final tree assessment documentation to be incorporated into shoreline permitting documentation included under existing contract. 28 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 11 Task No. 5.21 - Biological Assessment (Supp 10. TASK DELETED) KPFF civil engineers shall establish revised bridge alignments to accommodate WDFW request to save two large Douglas -Fir trees located along the east bank of the Green River. Two alignments will be created, one to clear only the tree located furthest to the south, and another to clear both large trees. Task No. 5.30 - Lighting Study Support (Supp. 10 and Supp. 12 TASK MODIFIED) Landau Associates will provide support to KPFF in developing the lighting study associated with proposed bridge illumination. Landau Associates is including a level of effort to include no more than 12 hours of Associate, 8 hours of Senior CAD support, and 5 hours of Staff/ Senior Technician. The purpose of the study will be to determine the impacts of bridge lighting on the Green River below in support of the permitting process. Deliverables: • To be determined Task 5.40. - De Minimis Section 4(f) Evaluation (Supp 12. TASK ADDED) Landau Associates will prepare necessary documentation to support Section 4(f) evaluation associated with potential trail improvements to the Green River Trail in the vicinity of City -owned open space immediately north of Riverview Plaza. The documentation will consist of the WSDOT Section 4(f) De Minimis Impact Determination form. Landau Associates will prepare the WSDOT Section 4(f) De Minimis Impact Determination form for review and comment by KPFF and the City, and then a final document. Assumptions • Programmatic Section 4(f) evaluation does not apply to the proposed project due to presence of critical habitat. • The City will complete necessary public outreach associated with the evaluation process. • The City Parks Department will provide written support for the proposed project and unavoidable impacts to Section (4f) resources. Deliverables • An electronic (Adobe PDF) copy of the draft and final technical memorandum. Task 5.50. - Historic Property Inventory (Supp. 12 TASK ADDED) Landau Associates will retain the services of Equinox Research and Consulting International, Inc. (ERCI) to support inventory of the residence on the Nelsen 29 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 12 property for required compliance with Section 106 NHPA. ERCI will prepare an Historic Property Inventory Form to support Section 106 NHPA compliance. Landau Associates will prepare copies of necessary forms to assist with agency consultation. Assumptions: • WSDOT has indicated requirement to inventory the residence on the Nelsen property. Deliverables: • Historic Property Inventory Form TASK No. 7.0 - GEOTECHNICAL ENGINEERING SERVICES (SUPP. 12 NEW TASK) Task No. 7.10 - Field Explorations and Laboratory Testing (Supp. 12 NEW TASK) Landau Associates will advance a boring on the property at 16113 West Valley Highway (King County Parcel number 000580033) to characterize subsurface conditions near the proposed east bridge abutment. This boring will be advanced to a depth of about 120 ft below the existing ground surface (BGS). One additional boring will be advanced at least 160 ft BGS from the existing trail and will be located near the proposed east bridge abutment. The borings will be completed using a track - mounted drill rig using mud - rotary drilling techniques. The drilling will be accomplished by Holocene Drilling of Puyallup, Washington under subcontract to Landau Associates. A geologist or geotechnical engineer from Landau Associates will supervise the explorations, obtain soil samples from the borings, and prepare field logs of conditions encountered in the explorations. Soil samples will be obtained from the borings on about a 5 -ft depth interval using the Standard Penetration Test (SPT) procedure, and delivered to our laboratory for further classification. Soil samples obtained from the explorations will be held in our laboratory for 30 days after submittal of the final report. After that date, the soil samples will be disposed of, unless arrangements are made to retain them. Drill cuttings will be placed in steel drums and transported to WM Dickson's facility in Tacoma, Washington for disposal. Prior to drilling, a representative of Landau Associates will mark the boring locations in the field and arrange for an underground utility locate (1- 800... call before you dig). Landau Associates will also arrange for a private utility locate at each of the boring locations. Landau Associates will conduct geotechnical and analytical laboratory testing on representative soil samples obtained from the exploratory borings to aid in their classification and determination of engineering properties. Laboratory testing completed in our laboratory is expected to consist of 4 natural moisture 30 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 13 content determinations, 3 fines content determinations, 5 index tests (either mechanical sieve analysis or Atterberg limit determinations), and 3 combined analyses (mechanical sieve and hydrometer). Task No. 7.20 - Geotechnical Evaluation, Reporting, and Meetings (Supp. 12 NEW TASK) Based on the results of our previous explorations for the TSL design phase, the field investigation, and laboratory testing program completed for this project, Landau Associates will complete geotechnical engineering analyses to confirm and or modify our previous recommendations to support 30% design of the bridge, including: • Recommendations for earthwork and site preparation including: clearing, stripping, and grubbing; the suitability of onsite soils for reuse in structural fill; import structural fill requirements, subgrade preparation; and placement and compaction of structural fill. • Pavement subgrade preparation. • Porous asphalt and porous concrete pavement sections (asphalt or Portland cement concrete and base course thickness) required for structural support of the proposed traffic. • Conventional asphalt and Portland cement concrete pavement design. • Seismic design criteria, including an evaluation of liquefaction and lateral spreading potential. • An evaluation of the stability of the riverbanks and recommended stabilization measures. • Recommendations for approach embankment structural earth wall including: embedment depth, foundation subgrade preparation, design parameters, nominal bearing pressure, anticipated foundation settlement, and wall backfill and drainage considerations. • Estimated settlement of the approach embankments. • Recommended foundation type (driven piles /drilled shafts); recommended tip elevations; expected range of nominal axial capacity; uplift capacity; downdrag loads; estimated settlements of bridge foundations; additional lateral loads caused by lateral spreading; soil parameters for input into L -Pile (or equivalent) lateral pile capacity software. • Construction considerations for the recommended foundation type. • Discussion of the impacts of constructing the bridge abutment and approach embankment on the existing dike located at the west side of the bridge and any recommended mitigation measures. The results of the field explorations and geotechnical engineering analyses will be summarized in a geotechnical report. The report will include a site plan 31 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 14 showing the exploration locations, summary logs of conditions observed in the borings, results of the geotechnical and analytical laboratory testing, and a discussion of subsurface soil and groundwater conditions at the exploration locations. Assumptions: • City will obtain the right of entry to perform all geotechnical sampling • No permit fees will be charged for the borings • All field work will be performed during daylight hours between Monday and Friday and any traffic control will consist of traffic cones Deliverables: • Draft geotechnical report (2 hard copies and Adobe PDF) • Final geotechnical report (4 hard copies and Adobe PDF) TASK No. 8.0 - RIGHT OF WAY SERVICES It is assumed federal funds are participating in the project, however there are no federal funds participating in the Right of Way phase. Universal Field Services, Inc. (UFS) will complete all Right of Way services in accordance with the City of Tukwila (City) Washington State Department of Transportation's (WSDOT) approved Right of Way Acquisition Procedures, the federal Uniform Relocation Assistance and Real Property Acquisitions Policies Act (URA), WSDOT Local Agency Guidelines - Section 25 (Right of Way Procedures), and the Washington Administrative Code (WAC 468 -100) state Uniform Relocation Assistance and Real Property Acquisition. The project area consists of primarily business use properties. Up to four (4) separate tax parcels will require various real property rights as shown in Table A below. One (1) residential occupant may be displaced by this project. Additional parcels or real property rights other than those shown in Table A will require an amendment to this scope of work and related fee estimate. Right of Way plans are not available for review and use at this time. This scope of work is based on the following: • Discussions with the City's design team KPFF. • Recent tour of the project limits. • Review of limited public on -line information (mapping / ownership information). • Preliminary Schematic Drawing and Exhibits - Right of Way plans not available. Task No. 8.20 - Title /Ownership Review (Supp 10. TASK MODIFIED) 32 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 15 Subtask No. 8.21 - UFS Title /Ownership Review (Supp. 10 TASK MODIFIED) Obtain title reports from the City or KPFF and perform reviews of existing right of way and ownership information. (If requested, UFS will order title reports or any updates). Review special exceptions described in each title report to determine the City's acceptance of title at closing. Provide the City with a parcel summary memo listing ownerships, title exceptions, etc. Deliverable: • Prepare parcel summary memo listing ownerships, title exceptions, etc. Task No. 8.30 - Data Collection and Limit Identification Subtask No. 8.32 - Right of Way Limits and Easements (Supp. 10 and Supp. 12 TASK MODIFIED) KPFF civil engineers will identify limits of right of way takes, as well as temporary and permanent easements for the project. Limits will be provided to the survey team, and the right of way acquisition team, for legal description and exhibits for use by the right of way acquisition team. Subtask No. 8.33 - Temporary Right of Entry /Access Permit (Supp. 10 TASK DELETED) As part of the feasibility planning and preliminary design phase for the project, the City and the consulting team may require temporary access to gather pertinent information for investigational geotechnical, environmental studies, hydrology, and land survey purposes, etc. It is intended Right of Entry (ROE) Permits will be inclusive of all purposes as stated in this task. It is assumed property owners will not be compensated for the temporary grant of access and all properties will be left in the same condition as was prior to entry. See Table A below for parcels requiring ROE Permits. The City or KPFF will provide exhibits as attachments to each permit depicting the extents of the ROE area. Deliverable: Obtain one (1) Right of Entry Permit due to common ownership. Subtask No. 8.34 - Legal Description and Exhibits for Acquisition (Supp 10. TASK DELETED) Eight (8) Legal descriptions and exhibits shall be prepared for right -of -way acquisition. • Prepare legal descriptions and graphic exhibits for temporary easements as well as for permanent easements for each of the four Riverview Plaza parcels (8 legal descriptions). • Provide staking or painting of easements for viewing purposes. 33 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 16 Deliverables • Updated Survey Project Base Map (two hardcopies, one electronic copy) • Copies of title reports • Acquisition legal descriptions with graphic exhibits Task No. 8.60 - Relocation Plan (Supp. 10 TASK DELETED) A relocation plan will be developed based on WSDOT's Right of Way Manual and LAG Manual Section 25. According to the City, the owner of the residential site has purchased another residence and has vacated the premises, possibly because of the pending project. Relocation eligibility and entitlements are subject to discussions with the City and the owner. This scope of work assumes the property owner is displaced by the project. It is assumed there will be one (1) residential owner- occupant of a single family home displaced as a result of this project (see Table A). UFS will develop a relocation plan resulting from personal assessment interviews with the occupant(s). If additional displacements are subsequently discovered, the Relocation Plan will be amended by UFS. Additional relocations will require an amendment to this scope of work and related fee estimate. Deliverable: • Relocation Plan Subtask No. 8.61 - FHWA Funds Authorization for ROW (Supp. 10 TASK DELETED) Shortly after the Right of Way Plans (prepared by KPFF), the PFE, and Relocation Plan have been submitted to WSDOT and assuming NEPA clearance has been obtained, the City would typically receive a letter from FHWA through WSDOT Highways and Local Programs authorizing the use of federal funds to acquire Right of Way. This letter of authorization is required in order for the City to receive federal funding participation and reimbursement for costs incurred with Appraisal, Appraisal Review, Acquisition Negotiations, and Relocation Assistance services. Deliverable: For informational purposes only Task No. 8.80 - Acquisition Negotiation, Relocation and Closeout Subtask No. 8.81 - Acquisition Negotiation (Supp. 10 and Supp. 12 TASK MODIFIED) Acquire real property rights from up to four (4) separate tax parcels (including City of Tukwila) as shown in Table A below. Appraisals, Appraisal Reviews, and AOS worksheets completed in the Appraisal and Appraisal Review task will be submitted to the City for written approval 34 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 17 establishing the amount of Just Compensation to the property owner. Upon written approval from the City, UFS will prepare the offer package(s) and promptly present offers to purchase all the required real property interests and negotiate in good faith to reach a settlement with each property owner(s). Offers will be presented in person when at all possible. Negotiations will be conducted in accordance with statutory and regulatory requirements and will include: Coordinate administrative settlement approvals with the City; Negotiate as necessary with lien holders, assisting escrow in the closing process; Prepare and maintain parcel files to include fair offer letters, acquisition documents, a standard diary form indicating all contacts with owner(s), and other items necessary for negotiations. Negotiations shall not be deemed to have failed until at least three significant meaningful contacts have been made and documented with each owner and /or their representative through direct personal contacts. Out - of -area owner(s) will be contacted by telephone and by certified mail. If negotiations reach an impasse, UFS will provide the City with written notification. The filing and cost of condemnation proceedings shall be the responsibility of the City. Deliverables: • Acquisition Negotiation services with owners of up to four (4) separate tax parcels. • Completed parcel files including necessary records of all Right of Way Acquisition services. Subtask No. 8.82 - Relocation (Supp. 10 TASK DELETED) According to the City, the owner (Nelson) of the residential site recently purchased another residence and has vacated the premises, possibly because of the pending project. Relocation eligibility and entitlements are subject to discussions with the City and the owner. This scope of work assumes the property owner is displaced by the project. It is assumed there will be one (1) residential owner- occupant of a single family home displaced as a result of this project. Universal will provide Relocation Assistance and Advisory Services under the guidelines of the federal URA, WSDOT LAG Manual - Section 25 and the City's approved Policies and Procedures, as directed. Relocation services are generally outlined as follows: • Inform displaced occupants, in writing, of their potential displacement, eligibility, entitlements, and provide an explanation of their relocation benefits. • Assist in search of replacement site(s). • Assist displaced occupant(s) in filing relocation claims for payment. • Maintain a current relocation diary for each displaced occupant. • Maintain necessary records to support state audit of the relocation services portion of the project. 35 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 18 Deliverables: • Relocation Advisory and Assistance Services for one (1) residential owner - occupant. • Completed relocation assistance files. Task No. 8.100 - Green River Trail Easement Negotiation (Supp. 12 TASK ADDED) The City of Tukwila is the Grantee on two existing easements for public access, trail, road and flood control under recording numbers 8009190876 and 9108301275. These easements are located, in part, along the northerly boundary of tax parcel numbers 2523049077 and 2523049039. Both parcels are owned by BRCP Riverview Plaza, LLC. During survey work for this project it was discovered that a portion of the Green River Trail as currently constructed is located outside of the legally described limits of the easements. At the City's request, UFS will negotiate with the Grantor of the easements in an attempt to modify the legal descriptions. UFS will contact the parcel owner or their representative and conduct up to two (2) on site meetings. If it is determined the owners are not receptive to modifying the easements, the negotiations will be deemed to have failed. It is assumed the City will not use eminent domain for the modification of these easements. Deliverables: • Revised easements under recording numbers 8009190876 and 9108301275 Additional Work If other tasks are required to be performed or there are changes in pertinent information or if negotiations exceed the industry standard for a good faith effort to negotiate (three "in- person" landowner contacts), UFS reserves the right to request additional compensation as an equitable adjustment. UFS shall not be responsible for delays caused beyond its control. 36 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 19 Assumptions: The City / KPFF will provide the following: • Exhibit maps to accompany Right of Entry Agreements • Preliminary Commitments (Title Reports) for all parcels shown in Table A. If requested, UFS will order title reports or any updates. The title company will bill the City directly for each report. • Approve designation of the escrow company used for this project. The escrow company will bill the City directly for all escrow services provided. • Right of Way Plans and Drawings, Maps, Exhibits, Right of Way Staking, etc., as necessary. • The necessary Environmental Site Assessments prior to commencing the PFE as discussed in the Project Funding Estimate task. • Legal descriptions in electronic format for all real property rights to be acquired and easement areas • Form approval, in electronic format, of all legal conveyance documents prior to use (i.e. offer letters, purchase and sale agreements, escrow instructions, easements, deeds, leases and permits). • Review and approval of all determinations of value, established by the project appraisers. Provide written authorization prior to offers being made to property owners. • Review and approval of all relocation entitlements prior to presentation to the displaced person. • Payment of any and all compensation payments to property owners, recording fees, relocation payments, legal services and any incidental costs which may arise necessary to complete each transaction. • Send "Introduction Letters" to property owners as necessary. • Property staking for easement modification, if necessary. 37 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian/Bicycle Bridge - Supplement #12 Page 20 TABLE A - PARCEL ACQUISITION & EASMENT MODIFICATION No. Tax Parcel No Taxpayer / Owner Current Use Easement Modification Total Fee Simple Partial Fee Simple Perm Trail Easement Temp. Const. Easement AR / AOS (See Note 3) 1 000580 -0033 Nelsen Single Family Residence X (See Note 1) AR 2 252304 -9081 City of Tukwila River Trail To Be Determined AOS 3 022310 -0040 Park East Real Estate LLC Office Bldg / Bank X X AOS AOS 4 022310 -0099 Andover Plaza LLC Retail X X 5 252304 -9077 BCRP Riverview Plaza LLC Office Bldg X 6 252304 -9039 Notes: 1. AR (Appraisal and Appraisal Review) / AOS (Administrative Offer Summery - in lieu of Appraisal) Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian/Bicycle Bridge - Supplement #12 Page 21 TASK No. 9.0 - ADDITIONAL STRUCTURAL DESIGN (SUPP. 12 NEW TASK) Task No. - 9.10 Additional Structural Design (Supp. 12 NEW TASKS) KPFF will revise the current 30% design plans to the new alignment (Alternative Alignment A) as well as provide additional structural design and drawings associated with the new layout. Subtask No. 9.11 - Update 30% Bridge Drawings to New Alignment (Supp. 12 NEW TASK) KPFF will update the current bridge drawings to reflect the new bridge alignment and additional approach span and associated foundation. Subtask No. 9.12 - Approach Span Design and Drafting (Supp. 12 NEW TASK) KPFF will design and produce drawings associated with the approximately 45 -foot long approach span at the western landing Subtask No. 9.13 - Abutment Design and Drafting (Supp. 12 NEW TASK) KPFF will design and produce drawings associated with the abutment that supports the approach span at the west landing. Subtask No. 9.14 - Revise Drilled Shaft Design (Supp. 12 NEW TASK) KPFF will revise and update the drilled shaft foundation design and drawings based on the new locations, additional loads imposed by the approach span and the new geotechnical information based on the additional geotechnical borings. TASK No. 10.0 - BRIDGE AESTHETICS COLLABORATION (SUPP. 12 NEW TASK) LMN will revise the overall bridge structural aesthetic to the current bridge alignment, to be documented in graphics used for design workshops and presentation renderings. This will require remodeling the proposed bridge to adjust bridge features to the revised alignment. Task No. 10.10 - Bridge Structure (Supp. 12 NEW TASK) Subtask No. 10.11 - Arch Geometry (Supp. 12 NEW TASK) Subtask No. 10.12 - Suspension Cable Connections (Supp. 12 NEW TASK) Subtask No. 10.13 - Bridge Deck Connections (Supp. 12 NEW TASK) Subtask No. 10.14 - Tied Arch Connections (Supp. 12 NEW TASK) 39 Exhibit A -1 - Scope of Work Tukwila Urban Center, Pedestrian /Bicycle Bridge - Supplement #12 Page 22 Task No. 10.20 - East Approach (Supp. 12 NEW TASK) Subtask No. 10.21 - Deck Treatments (Supp. 12 NEW TASK) Subtask No. 10.22 - Handrail System (Supp. 12 NEW TASK) Task No. 10.30- Design Development and Coordination (Supp. 12 NEW TASK) Subtask No. 10.31 - Tied Arch Sketches (Supp. 12 NEW TASK) Subtask No. 10.32 - West Approach Sketches (Supp. 12 NEW TASK) Subtask No. 10.33 - East Approach Sketches (Supp. 12 NEW TASK) Subtask No. 10.34 - Study Model Development (Supp. 12 NEW TASK) Subtask No. 10.35 - Renderings (Supp. 12 NEW TASK) 40 - $42,795.69 Fee Removed Supplement 10 EXHIBIT E -1 KPFF Consulting Engineers CONSULTANT FEE DETERMINATION SUMMARY OF COST Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Classification Principal in Charge Technical Specialist Project Manager Senior Engineer Design Engineer CADD Technician Project Coordinator Administration Overhead (OH) Cost OH Rate x DSC of Fixed Fee (FF) Reimbursables Adjustments FF Rate Subtotal Total Hours X Rate = Cost 42.00 X $64.43 = $2,706.06 0.00 X $64.04 = $0.00 216.00 X $54.60 = $11,793.60 14.00 X $45.00 = $630.00 703.00 X $35.40 = $24,886.20 356.00 X $39.23 = $13,965.88 8.00 X $28.85 = $230.80 4.00 X $20.00 = $80.00 132.62% 30.00% DSC Subtotal $54,292.54 $54,292.54 $72,002.77 $54,292.54 $16,287.76 Subconsultant Costs (See Exhibit G) - $42,795.69 $64,583.73 GRAND TOTAL: $164,371.10 Date: 4/23/2015 41 Hour Summary ENGINEERING COST ESTIMATE: KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 KPFF Consulting Engineers KPFF Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Principal in Charge Technical Specialist Project Manager Senior Engineer Design Engineer CARD Technician Project Coordinator Administratio n Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER I Supp 10 Rates $62.50 $60.10 $50.77 $43.27 $32.89 $35.19 $24.81 $20.00 2.7516 Item SCOPE OF WORK Supp 12 Rates $64.43 $64.04 $54.60 $45.00 $35.40 $39.23 828.85 820.00 2.6262 1.0 PROJECT MANAGEMENT 8 12 _- - 80.00 $3,074.33 1.40 Design Team Meetings (Assume 2) and Coordination - Supp 12 NEW TASK (KPG & KPFF) 1.50 Project Team Meetings with City (2) - Supp 12 NEW TASK (KPG & KPFF) 8 12 $0.00 $3,074.33 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $6,148.67 Supp 12 Labor Added Subtotal: 16 0 24 0 0 0 0 0 Reimbursables $0.00 $0.00 2.0 TOPOGRAPHIC AND BOUNDARY SURVEY (KPG) 2.10 Additional survey and mapping 2.12 Extend survey of Green River Trail - Supp 10 TASK DELETED $0.00 $0.00 2.13 Survey North GRT, Addtl Christ. Rd, New Bridge Abut Locations - Supp 12 TASK ADDED $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables $0.00 $0.00 3.0 ALT. ALIGNMENT PRELIMINARY DESIGN & NEW ALT. ALIGNMENTS (KPFF & KPG) 3.10 Survey at Riverview Plaza Parking Lot - Supp 10 TASK DELETED 3.11 Utility Locating Not Used- Supp 10 TASK DELETED $0.00 $0.00 3.20 Walkway Section Parking Lot Troll Alignment Studies - Supp 10. TASK DELETED 3.21 Trail Realignment Alternatives For Riverview Plaza- Supp 10 TASK DELETED - $279.40 $0.00 3.22 Riverview frontage 1 property studies - Supp 10 TASK DELETED -2 - $279.40 $0.00 3.23 Meetings for Riverview Plaxa property owner coordination- Supp 10 TASK DELETED -6 - $838.19 $0.00 3.24 Alt alignments schematic cost estimate comparison - Supp 10 TASK DELETED -8 -16 - $2,565.59 $0.00 3.30 30% Plans - Supp 10 TASK DELETED -2 - $343.95 $0.00 3.31 Site Preparation - Supp 10 TASK DELETED -4 -8 -8 - $2,057.43 $0.00 3.32 Utilities - Supp 10 TASK DELETED -8 -4 -4 - $1,866.91 $0.00 3.33 Storm Drainage and Grading - - Supp 10 TASK DELETED -8 -8 -8 - $2,844.71 $0.00 3.34 Paving Plans- Supp 10 TASK DELETED -4 -8 -8 - $2,057.43 $0.00 3.35 Pavement Marking Plans - Supp 10 TASK DELETED -4 -8 -8 - $2,057.43 $0.00 3.40 Update Storm Drainage Report - Supp 10 TASK DELETED -2 -4 -32 -8 -4 - $5,760.42 $0.00 3.50 Update Cost Estimate- Supp 10 TASK DELETED -8 -16 - $2,565.59 $0.00 3.60 New Trail Alignment - Supp 12 NEW TASK EMI $0.00 $0.00 3.61 Trail alignment urban design to 60% - Supp12 NEW TASK 3.62 Trail alignment landscape design to 60% - Supp 12 NEW TASK $0.00 80.00 3.63 Trail alignment illumination design to 60%- Supp 12 NEW TASK $0.00 $0.00 3.70 TS&L Supplement 01 - Supp 12 NEW TASK 2 , 16 23 24 80.00 $7,243.53 3.71 Alternative Alignment Layouts- Supp 12 NEW TASK 3.72 Evaluation of Alternative Alignments - Supp 12 NEW TASK 2 16 76 $0.00 $9,698.19 3.73 TSBLReport Supplement 0l- Supp 12 NEW TASK 2 16 88 24 4 $0.00 $13,496.51 3.74 Design Team and City Review Meetings - Supp 12 NEW TASK 4 8 8 $0.00 $2,567.69 3.80 Fatal Flaw Assessment of New Preferred Alignment - Supp 12 NEW TASK $0.00 $0.00 3.81 River and Levee Constraints - Supp 12 NEW TASK 16 15 $0.00 $3,688.76 3.82 Horizontal and Vertical Alignment Alternatives - Supp 12 NEW TASK 2 32 55 16 $0.00 $11,688.53 3.83 Design Team and City Review Meetings - Supp 12 NEW TASK 2 8 20 4 80.00 $3,756.99 3.90 Presentation Graphics - Sapp 12 NEW TASK 2 15 8 $0.00 $2,505.50 Supp 10 Labor Removed Subtotal: -4 0 -58 -40 -60 -44 -4 0 $23,516.44 $54,645.71 Supp 12 Labor Added Subtotal: 14 0 114 0 300 76 0 4 Reimbursables 80.00 80.00 4.0 CIVIL (KPFF) 16 9.30 Trail Alignment and Modeling - Supp 12 NEW TASK 40 40 $0.00 $10,133.98 4.40 Storm Drainage Approach - Supp 12 NEW TASK 16 40 16 $0.00 $7,661.36 9.50 Quantities and Cost Estimate - Supp 12 NEW TASK 8 40 $0.00 $4,865.82 9.60 Wallr Railing Assessment - Supp 12 NEW TASK 16 24 8 $0.00 $5,349.67 4.70 30 %Plansheet Setup and Layout- Supp 12 NEW TASK 4 14 14 32 32 8 $0.00 $11,216.71 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $39,227.55 Supp 12 Labor Added Subtotal: 4 0 70 14 176 96 8 0 5.0 Reimbursables ENVIRONMENTAL AND PERMITTING SERVICES (Landau) $0.00 80.00 5.10 USCG Navigation Survey and Bridge Permit App. - Supp 10 TASK DELETED 80.00 $0.00 5.20 Tree Assessment- Supp 10 TASK MODIFIED 80.00 $0.00 5.20 Tree Assessment - Supp 12 TASK MODIFIED $0.00 $0.00 5.21 Biological Assessment (KPFF Civil) - Supp 10 TASK DELETED -24 -16 - $4,902.03 $0.00 5.30 Lighting Study Support - Stipp 10 TASK MODIFIED 80.00 $0.00 5.30 Lighting Study Support - Supp 12 TASK MODIFIED $0.00 $0.00 5.40 De Minimis Section 4(1) Evaluation - Supp 12 NEW TASK 80.00 $0.00 5.50 Historic Inventory - Supp 12 NEW TASK 80.00 80.00 Supp 10 Labor Removed Subtotal: 0 0 -24 0 0 -16 0 0 $4,902.03 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursable File: 2014.11.04 Combined Fee Estimate (Add &Removed) 01.0)6 00.00 Page 1 of 14 42 Hour Summary ENGINEERING COST ESTIMATE: KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 KPFF Consulting Engineers KPFF Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Principal 01 Charge Technical Specialist Project Manager Senior Engineer Design Engineer CADD Technician Project Coordinator Administratio n Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER Item I Supp 10 Rates 862.50 060.10 $50.77 043.27 032.89 835.19 024.81 820.00 2.7516 SCOPE OF WORK Supp 12 Rates $64.43 $64.04 $54.60 $45.00 $35.40 $39.23 $28.85 $20.00 2.6262 7.0 GEOTECHNICAL - Supp. 12 NEW TASK (Landau) 80.00 1 $0.00 7.10 Field Exploration and Laboratory Testing - Supp 12 NEW TASK 7.20 Geotechnical Evaluation, Reporting and Meetings - Supp 12 NEW TASK 50.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables $0.00 $0.00 8.0 RIGHT -OF -WAY SERVICES (UFS) 8.20 Title/Ownership Review 8.21 UFS Title/Ownership Review- Supp 10 TASK MODIFIED $0.00 8 0.0 0 8.30 Data Collection and Limit Identification 8.32 Right -of -Way Limits and Easements - Supp 10 TASK MODIFIED -40 -SO -16 - 814,377.22 80.00 8.32 Right-of -Way Limits and Easements- Supp 12 TASK MODIFIED 8 12 4 $0.00 $2,674.84 8.33 Temporary Right of Entry/Access Permit - Supp 10 TASK DELETED $0.00 80.00 8.34 Legal Descriptions and Exhibits for Acquisition - TASK DELETED 80.00 00.00 8.60 Relocation Plan - Supp 12 TASK DELETED $0.00 $0.00 8.61 FHW A Funds Authorization for ROW - Supp 10 TASK DELETED $0.00 $0.00 8.80 Acquisition Negotiation, Relocation and Closeout $0.00 $0.00 8.81 Parcel Acquisition Negotiation 1 - Nelson / Frohmuth Single Family Residence Parcel (000580 -0033) Supp 12 TASK MODIFIED 2- City of Tukwila River Trail Parcel (252304-9081) Supp 12 TASK MODIFIED 80.00 80.00 3A- BRCP Riverview Plaza LLC Office Building Parcel (252304-9039) - Supp 10 TASK DELETED $0.00 80.00 38 - BRCP Riverview Plaza LLC Office Building Parcel (252304-9039) - Supp 10 TASK DELETED 80.00 80.00 4A- BRCP Riverview Plaza LLC Office Building Parcel (252304-9077) - Supp 10 TASK DELETED $0.00 80.00 48 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9077) - Supp 10 TASK DELETED $0.00 80.00 5- BRCP Riverview Plaza LLC Office Building Parcel (252304-9078) - Supp 10 TASK DELETED $0.00 $0.00 6 - SeatePublic Utilitias Storm W at Wilily Parcel (252304- 9048) - Supp 10 TASK DELETED $0.00 80.00 7 - Park Real Estate LLC Office Bldg /Bank Pared (002310 -0040) - Supp 12 TASK MODIFIED 80.00 80.00 8- Andover Plaza LLC Retail Parcel (002310-0099) - Supp 12 TASK MODIFIED 80.00 80.00 8.82 Relocation ( Nelson / Frohmuth Parcel) - Supp 10 TASK DELETED $0.00 80.00 8.100 Green River Trail Easement Negotiation and Modification- Supp. 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 -40 0 -80 -16 0 0 014,377.22 $2,674.84 Supp 12 Labor Added Subtotal: 0 0 8 0 12 4 0 0 R4smbursables $0.00 $0.00 9.0 9.10 ADDITIONAL STRUCTURAL DESIGN - Supp. 12 NEW TASK (KPFF) Additonal Structural Design - Supp 12 NEW TASK 25 60 9.11 Update 306 Bridge Drawings to New Alignment- Supp 12 NEW TASK 2 $0.00 $8,844.15 9.12 Approach Span Design and Drafting - Supp 12 NEW TASK 2 70 45 $0.00 $11,482.30 9.13 Abutment Design and Drafting - Supp 12 NEW TASK 2 70 45 80.00 $11,482.30 9.14 Revise Dulled Shaft Design - Supp 12 NEW TASK 2 50 30 $0.00 $8,077.56 Supp 10 tabor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $39,886.31 Supp 12 Labor Added Subtotal: 8 0 0 0 215 180 0 0 Reimbursables 80.00 80.00 10.0 BRIDGE AESTHETICS COLLABORATION - Supp. 12 NEW TASK (LMN) $0.00 10.10 Bridge Structure - Supp 12 NEW TASK 10.11 Arch Geometry - Supp 12 NEW TASK $0.00 10.12 Connections - Susp Cables- Supp 12 NEW TASK 80.00 $0.00 10.13 Connections - Bridge Deck - Supp 12 NEW TASK 00.00 $0.00 10.14 Connections - Tied Arch - Supp 12 NEW TASK 80.00 $0.00 10.20 Approach Ramps - Supp 12 NEW TASK 10.21 Deck Treatments - Supp 12 NEW TASK $0.00 80.00 10.22 Handrail System - Supp 12 NEW TASK 80.00 $0.00 10.30 Design Development and Coordination - Supp 12 NEW TASK 10.31 Tied Arch Sketches - Supp 12 NEW TASK $0.00 80.00 10.32 West Approach Sketches - Supp 12 NEW TASK 80.00 $0.00 10.33 East Approach Sketches - Supp 12 NEW TASK $0.00 $0.00 10.34 Study Model Development- Supp 12 NEW TASK 80.00 $0.00 10.35 Renderings - Supp 12 NEW TASK 00.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0,00 80.00 Supp 12 tabor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables III 00.00 $0.00 Supp 10 Labor Removed Sum -4 0 -122 -40 -140 -76 -4 0 $42,795.69 $142,583.07 Supp 12 Labor Added Sum 42 0 216 14 703 356 8 4 Reimbursables Firm Total DESIGN TEAM TOTAL Reimbursables Sum $0.00 $0.00 KPFF SUBTOTAL: - $42,795.69 $142,583.07 Total Addtl Fee (Supp 12 - Supp10) $99,787.38 File: 2014.11.04 Combined Fee Estimate (Add &Removed) v1.4(5 Page 20)14 43 - $18,478.20 Fee Removed Supplement 10 EXHIBIT G -1 KPG CONSULTANT FEE DETERMINATION SUMMARY OF COST Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Classification Senior UD /L /E Project E/S Designer UD /L /E /S CAD Technician Survey Crew Office Admin Overhead (OH) Cost OH Rate x DSC of Fixed Fee (FF) Reimbursables Adjustments FF Rate Subtotal Total Hours X Rate = Cost 74.00 X $64.90 = $4,802.60 0.00 X $56.56 = $0.00 164.00 X $40.13 = $6,581.32 216.00 X $31.25 = $6,750.00 20.00 X $47.66 = $953.20 0.00 X $23.08 = $0.00 163.17% 30.00% DSC Subtotal $19,087.12 $19,087.12 $31,145.31 $19,087.12 $5,726.14 - $18,478.20 Subconsultant Total: $37,480.37 Date: 4/23/2015 44 Hour Summary ENGINEERING COST ESTIMATE: KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 KPG KPG Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Senior UD /L/E Project E/S Designer UD /IJE/S CAD Technician Survey Crew Office Admin Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER Item I Supp 10 Rates 064.90 $56.56 040.13 031.25 $47.66 $23.08 2.9317 SCOPE OF WORK Supp 12 Rates $64.90 $56.56 $40.13 $31.25 $47.66 $23.08 2.9317 1.0 PROJECT MANAGEMENT 4 6 VIEW $0.00 $1,466.99 1.40 Design Team Meetings (Assume 2) and Coordination - Supp 12 NEW TASK (KPG & KPFF) 1.50 Project Team Meetings with City (2) - Supp 12 NEW TASK (KPG & KPFF) 4 6 $0.00 $1,466.99 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 80.00 $2,933.97 Supp 12 Labor Added Subtotal: 8 0 12 0 0 0 Reimbursables IIII $0.00 $0.00 2.0 TOPOGRAPHIC AND BOUNDARY SURVEY (KPG) A. 2.10 Additional survey and mapping 2.12 Extend survey of Green River Trail- Supp 10 TASK DELETED -1 -3 -4 - 595141 $0.00 2.13 Survey North GRT, Addtk Christ. Rd, New Bridge Abut Locations - Supp 12 TASK ADDED 2 8 16 20 $0.00 $5,582.16 Supp 10 Labor Removed Subtotal: 0 0 -1 -3 -4 0 $951.41 $5,582.16 Supp 12 Labor Added Subtotal: 2 0 8 16 20 0 Reimbursables Ilp $0.00 $0.00 3.0 ALT. ALIGNMENT PRELIMINARY DESIGN & NEW ALT. ALIGNMENTS (KPFF & KPG) 3.10 Survey at Riverview Plaza Parking Lot - Supp 10 TASK DELETED 111 Utility Locating Not Used- Supp 10 TASK DELETED -4 -12 -16 - $3.805.64 $0.00 3.20 Walkway Section/ Parking Lot Trail Alignment Studies - Supp 10. TASK DELETED 121 Trail Realignment Alternatives For Riverview Plaza- Supp 10 TASK DELETED -4 -12 -32 - $5,104.64 $0.00 122 Riverviewf tentage / property studies - Supp 10 TASK DELETED -4 -8 -16 - $3,168.16 00.00 123 Meetings for Riverview Plaza property owner coordination- Supp 10 TASK DELETED -6 -6 - $1,847.53 $0.00 124 Alt alignments schematic cost estimate comparison - Supp 10 TASK DELETED $0.00 $0.00 3.30 30 % Plans - Sapp 10 TASK DELETED $0.00 $0.00 131 Site Preparation - Supp 10 TASK DELETED $0.00 $0.00 132 Utilities - Supp 10 TASK DELETED $0.00 $0.00 3.33 Storm Drainage and Grading - - Supp 10 TASK DELETED $0.00 $0.00 134 Paving Plans - Sapp 10 TASK DELETED $0.00 $0.00 135 Pavement Marking Plans - Supp 10 TASK DELETED $0.00 $0.00 3.90 Update Storm Drainage Report - Supp 10 TASK DELETED $0.00 $0.00 3.50 Update Cost Estimate- Sapp 10 TASK DELETED $0.00 $0.00 3.60 New Trail Alignment- Sapp 12 NEW TASK 24 60 80 $0.00 $18,954.90 3.61 Trail alignment urban design to 60%- Supp 12 NEW TASK 162 Trail alignment landscape design to 60%- Supp 12 NEW TASK 16 24 40 $0.00 $9,532.63 3.63 Trail alignment illumination design to 60 %- Supp 12 NEW TASK 24 60 80 $0.00 $18,954.90 3.70 TS &L Supplement 01 - Sapp 12 NEW TASK 171 Alternative Alignment Layouts- Supp 12 NEW TASK P0.00 $0.00 172 Evaluation of Aftemative Alignments - Supp 12 NEW TASK $0.00 $0.00 173 TSBL Report Supplement 01- Supp 12 NEW TASK $0.00 $0.00 174 Design Team and CM Review Meetings - Supp 12 NEW TASK $0.00 $0.00 3.80 Fatal Flaw Assessment of New Preferred Alignment- Sapp 12 NEW TASK $0.00 $0.00 181 River and Levee Constraints - Supp 12 NEW TASK $0.00 $0.00 3.82 Horizontal and Vertical Alignment Alternatives - Supp 12 NEW TASK $0.00 $0.00 183 Design Team and City Review Meetings - Supp 12 NEW TASK $0.00 $0.00 3.90 Presentation Graphics- Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: -14 0 -30 -60 .16 0 $13,925.96 $47,442.44 Supp 12 Labor Added Subtotal: 64 0 144 200 0 g Reimbursables $0.00 $0.00 4.0 CIVIL (KPFF) 4.30 Trail Alignment and Modeling - Supp 12 NEW TASK $0.00 $0.00 4.90 Storm Drainage Approach- Supp 12 NEW TASK $0.00 $0.00 4.50 Ouantities and Cost Estimate- Supp 12 NEW TASK $0.00 $0.00 4.60 Wall / Railing Assessment - Supp 12 NEW TASK $0.00 $0.00 4.70 30 %Plansheet Setup and Layout - Supp 12 NEW TASK $0.00 $8.80 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 Reimbursables $0.00 $0.00 5.0 ENVIRONMENTAL AND PERMITTING SERVICES (Landau) $0.00 I. $0.00 5.10 USCG Navigation Survey and Bridge Permit App. - Supp 10 TASK DELETED 5.20 Tree Assessment- Supp 10 TASK MODIFIED $0.00 $0.00 5.20 Tree Assessment - Supp 12 TASK MODIFIED 621 Biological Assessment (KPFF Civil) - Sapp 10 TASK DELETED $0.00 $0.00 5.30 Lighting Study Support - Supp 10 TASK MODIFIED $0.00 $0.00 5.30 Lighting Study Support - Supp 12 TASK MODIFIED 5.40 De Minimis Section 4(f) Evaluation - Sapp 12 NEW TASK $0.00 $0.00 5.50 Historic Inventory - Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 Reimbursables $0.00 $0.00 File, 2014.11.04 Combined Fee Estimate (Add &Removed) 01.01s Page 30(14 45 Hour Summary ENGINEERING COST ESTIMATE: KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 KPG KPG Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Senior UD /L/E Project E/S Designer CAD UD /LIEJS Technician Survey Crew Office Admin Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER Item Supp 10 Rates $64.90 $56.56 $40.13 $31.25 $47.66 $23.08 2.9317 SCOPE OF WORK Supp 12 Rates $64.90 $56.56 $40 13 $31.25 $47.66 $23.08 2.9317 7.0 GEOTECHNICAL - Supp. 12 NEW TASK (Landau) w $0.00 $0.00 7.10 Field Exploration and Laboratory Testing - Supp 12 NEW TASK 7.20 Geotechnical Evaluation, Reporting and Meetings- Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 Moo $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables I Sr 00.00 50.00 8.0 RIGHT -OF -WAY SERVICES (UFS) 8.20 Title /Ownership Review 8.21 UFS Title /Ownership Review- Supp 10 TASK MODIFIED 1 S0.00 $0.00 8.30 Data Collection and Limit Identification i 8.32 Right•of -Way Limits and Easements • Supp 10 TASK MODIFIED 50.00 $0.00 832 Right -of -Way Limits and Easements- Supp 12 TASK MODIFIED $0.00 $0.00 8.33 Temporary Right of Entry /Access Permit- Supp 10 TASK DELETED $0.00 $0.00 8.34 Legal Descriptions and Exhibits for Acquisition -TASK DELETED -2 -20 -10 - $3,600.83 $0.00 8.60 Relocation Plan- Sapp 12 TASK DELETED $0.00 $0.00 8.61 FHWA Funds Authorization for ROW - Supp 10 TASK DELETED $0.00 $0.00 8.80 Acquisition Negotiation, Relocation and Closeout $0.00 $0.00 8.81 Parcel Acquisition Negotiation 1 - Nelson / Frohmuth Single Family Residence Parcel (000580 -0033) Supp 12 TASK MODIFIED 2 - 0ty of Tukwila River Trail Parcel (252304 -9081) Supp 12 TASK MODIFIED $0.00 $0.00 3A - BRCP Riverview Plaza LLC Office Building Parcel (252304-9039) - Supp 10 TASK DELETED $0.00 $0.00 3B - BRCP Riverview Plaza LLC Office Building Parcel (252304- 9039) - Supp 10 TASK DELETED $0.00 $0.00 4A - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9077) - Supp 10 TASK DELETED $0.00 $0.00 4B- BRCP Riverview Plaza LLC Office Building Parcel (252304-9077) - Supp 10 TASK DELETED $0.00 $0.00 5 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9078) - Supp 10 TASK DELETED $0.00 $0.00 6 • Seattle Public Utilities Storm Water Utility Parcel (252304 -9048) - Supp 10 TASK DELETED $0.00 $0.00 7 - Park Real Estate LLC Office Bldg /Bank Parcel (002310 -0040) - Supp 12 TASK MODIFIED $0.00 $0.00 8 - Andover Plaza LLC Retail Parcel (002310-0099) - Supp 12 TASK MODIFIED $0.00 $0.00 8.82 Relocation (Nelson / Frohmuth Parcel) - Supp 10 TASK DELETED $0.00 $0.00 8.100 Green River Trail Easement Negotiation and Modification - Supp. 12 NEW TASK = = 80.00 $0.00 Supp 10 Labor Removed Subtotal: 0 -2 -20 -10 0 0 $3,600.83 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 Reimbursables $0.00 $0.00 9.0 ADDITIONAL STRUCTURAL DESIGN - Supp. 12 NEW TASK (KPFF) 9.10 Addilonal Structural Design - Supp 12 NEW TASK 9.11 Update 30% Bridge Drawings to New Alignment- Supp 12 NEW TASK $0.00 $0.00 9.12 Approach Span Design and Drafting - Supp 12 NEW TASK $0.00 $0.00 9.13 Abutment Design and Drafting - Supp 12 NEW TASK $0.00 $0.00 9.14 Revise Drilled Shaft Design - Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal. 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 Reimbursables $0.00 $0.00 $0.00 $0.00 10.0 BRIDGE AESTHETICS COLLABORATION - Supp. 12 NEW TASK (LMN) 10.10 Bridge Structure - Supp 12 NEW TASK 10.11 Arch Geometry - Supp 12 NEW TASK 10.12 Connections - Susp Cables - Supp 12 NEW TASK $0.00 $0.00 10.13 Connections - Bridge Deck - Supp 12 NEW TASK $0.00 $0.00 10.14 Connections - Tied Arch - Supp 12 NEW TASK $0.00 $0.00 10.20 Approach Ramps - Supp 12 NEW TASK NIE. 10.21 Deck Treatments- Supp 12 NEW TASK $0.00 $0.00 1022 Handrail System- Supp 12 NEW TASK $0.00 $0.00 10.30 Design Development and Coordination - Supp 12 NEW TASK at 10.31 Tied Arch Sketches - Supp 12 NEW TASK $0300 $0.00 10.32 West Approach Sketches- Supp 12 NEW TASK $0.00 $0.00 10.33 East Approach Sketches- Supp 12 NEW TASK $0.00 $0.00 1034 Study Model Development- Supp 12 NEW TASK $0.00 $0.00 10.35 Renderings - Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal. 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 Reimbursables $0.00 $0.00 Supp 10 Labor Removed Sum -14 -2 -51 -73 -20 0 $18,478.20 $55,958.57 Supp 12 Labor Added Sum 74 0 164 216 20 0 Reimbursables Firm Total DESIGN TEAM TOTAL Total Addtl Reimbursables Sum $0.00 $0.00 KPG SUBTOTAL: - $18,478.20 $55,958.57 Fee (Supp 12 - Supp10) $37,480.37 File: 2014.11.04 Combined Fee Estimate (Add &Removed) 01.x5 Page 4 of 14 46 Quality Assurance Project Manager Acquisition Specialist Relocation Specialist Sr. Administrative Specialist EXHIBIT G -1 Universal Field Services CONSULTANT FEE DETERMINATION SUMMARY OF COST Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Classification Overhead (OH) Cost OH Rate x DSC of Fixed Fee (FF) FF Rate Reimbursables Mileage Misc Expendables Adjustments Supplement 10 Supplement 10 Subtotal Total Hours X Rate 7.00 X 41.00 X 46.00 X 80.00 X 14.00 X 48.09% 30.00% $52.00 $42.00 $38.00 $38.00 $30.00 DSC Subtotal Cost $364.00 $1,722.00 $1,748.00 $3,040.00 $420.00 $7,294.00 $7,294.00 120 miles @ $0.575 Photographs, equip rental, etc Reimbursable Removed Fee Removed $7,294.00 $3,507.68 $2,188.20 $69.00 $150.00 - $12,584.50 - $25,226.93 - $37,592.43 Subconsultant Total: - $24,602.55 Date: 4/23/2015 47 Hour Summary KPFF Consulting Engineers ENGINEERING COST ESTIMATE: Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 Universal Field Services Tukwila Urban Center - Pedestrian/Bicycle Bridge, y g Supplement No. 12 Quality Assurance Project Manager Acquisition Specialist Relocation Specialist Sr. Administrative Specialist Item Supp 10 Rates $50.24 $42.00 $38.00 $38.00 $29.00 SCOPE OF WORK Supp 12 Rates $52.00 $42.00 $38.00 $38.00 $30.00 1.0 PROJECT MANAGEMENT r- 1.40 Design Team Meetings (Assume 2) and Coordination -Supp 12 NEW TASK (KPG & KPFF) 1.50 Project Team Meetings with City (2) - Supp 12 NEW TASK (KPG & KPFF) Supp 10 Labor Removed Subtotal: 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables 2.0 TOPOGRAPHIC AND BOUNDARY SURVEY (KPG) lit 2.10 Additional survey and mapping 2.12 Extend survey of Green River Trail - Supp 10 TASK DELETED 2.13 Survey North GRT, Addll Christ. Rd, New Bridge Abut Locations - Supp 12 TASK ADDED Supp 10 Labor Removed Subtotal: 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables p 3.0 ALT. ALIGNMENT PRELIMINARY DESIGN & NEW ALT. ALIGNMENTS (KPFF & KPG) 3.10 Survey at Riverview Plaza Parking Lot - Sapp 10 TASK DELETED 111 Utility Locating Not Used- Supp 10 TASK DELETED 3.20 Walkway Section/ Parking Lot Trail Alignment Studies- Supp 10. TASK DELETED 121 Trail Realignment Alternatives For Riverview Plaza - Supp 10 TASK DELETED 122 Riverview frontage / property studies - Supp 10 TASK DELETED 123 Meetings for Riverview Plaza property owner coordination - Supp 10 TASK DELETED 124 Alt alignments schematic cost estimate comparison - Supp 10 TASK DELETED 3.30 30% Plans - Supp 10 TASK DELETED 131 Site Preparation - Supp 10 TASK DELETED 132 Utilities - Supp 10 TASK DELETED 3.33 Stem Drainage and Grading - - Supp 10 TASK DELETED 134 Paving Plans - Supp 10 TASK DELETED 135 Pavement Marking Plans - Supp 10 TASK DELETED 3.40 Update Storm Drainage Report - Supp 10 TASK DELETED 3.50 Update Cost Estimate - Sapp 10 TASK DELETED 3.60 New Trail Alignment- Sapp 12 NEW TASK _ 161 Trail alignment urban design to 60% - Supp 12 NEW TASK 162 Trail alignment landscape design to 60%- Supp 12 NEW TASK 163 Tral alignment illumination design to 60% - Supp 12 NEW TASK 3.70 TS &L Supplement 01 - Supp 12 NEW TASK M 171 Alternative Alignment Layouts- Supp 12 NEW TASK 172 Evaluation of Alternative Alignments- Supp 12 NEW TASK 173 TS &L Report Supplement 01 - Supp 12 NEW TASK 174 Design Team and City Review Meetings - Supp 12 NEW TASK 3.80 Fatal Flaw Assessment of New Preferred Alignment- Supp 12 NEW TASK 181 River and Levee Constraints - Supp 12 NEW TASK 182 Horizontal and Vertical Alignment Alternatives - Supp 12 NEW TASK 183 Design Team and Ciy Review Meetings - Supp 12 NEW TASK 3.90 Presentation Graphics - Stipp 12 NEW TASK Supp 10 Labor Removed Subtotal: 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables 4.0 CIVIL (KPFF) 4.30 Trail Alignment and Modeling - Sapp 12 NEW TASK 4.40 Storm Drainage Approach - Supp 12 NEW TASK 4.50 Ouantities and Cost Estimate - Supp 12 NEW TASK 4.60 Wall / Railing Assessment - Sapp 12 NEW TASK 4.70 30 %Plansheet Setup and Layout - Supp 12 NEW TASK Supp 10 Labor Removed Subtotal: 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables 5.0 ENVIRONMENTAL AND PERMITTING SERVICES (Landau) lir 5.10 USCG Navigation Survey and Bridge Permit App. - Sapp 10 TASK DELETED 5.20 Tree Assessment - Supp 10 TASK MODIFIED 5.20 Tree Assessment - Supp 12 TASK MODIFIED 5.21 Biological Assessment (KPFF Civil) - Sapp 10 TASK DELETED 5.30 Lighting Study Support - Supp 10 TASK MODIFIED 5.30 Lighting Study Support - Supp 12 TASK MODIFIED 5.40 De Minimis Section 40) Evaluation - Sapp 12 NEW TASK 5.50 Historic inventory- Sapp 12 NEW TASK Supp 10 Labor Removed Subtotal: 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables UFS Supp 10 Fee Supp 12 Fee Removed: Added: MULTIPLIER MULTIPLIER 2.0210 .7809 50.00 $0.00 5000 80.00 00.00 80.00 $0.00 $0.00 $0.00 $000 00.00 $0.00 00.00 00.00 $0.00 $0.00 $0.00 80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Moo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Moo Moo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 80.00 $0.00 80.00 $0.00 00.00 80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Moo Moo 80.00 80.00 80.00 $0.00 80.00 80.00 $0.00 $0.00 80.00 000 $0.00 0.00 $0.00 0.00 80.0o 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 80.00 80.00 Moo $0.00 48 File: 2014.11.04 Combined Fee Estimate (Add &Removed) 51.0)5 Page 5 of 14 Hour Summary KPFF Consulting Engineers ENGINEERING COST ESTIMATE: Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 Universal Field Services UFS Tukwila Urban Center Pedestrian /Bicycle Bridge, Supplement No. 12 Quali y Assurance Pm;ec Manager Acquisition Specialist Relocation Specialist Sr' Administrative Specialist Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER Item I Supp 10 Rates $50.24 $42.00 $38.00 $38.00 $29.00 2.0210 SCOPE OF WORK Supp 12 Rates $52.00 $42.00 $38.00 $38.00 $30.00 1.7809 7.0 GEOTECHNICAL - Supp. 12 NEW TASK (Landau) r vor- $0.00 $0.00 7.10 Field Exploration and Laboratory Testing - Supp 12 NEW TASK 7.20 Geotechnical Evaluation, Reporting and Meetings- Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 $0.00 50.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables Mr $0.00 $0.00 8.0 RIGHT -OF -WAY SERVICES (UFS) 8.20 Title /Ownership Review I i -6 -3 - $636.62 $0.00 8.21 UFS Title/Ownership Review- Supp 10 TASK MODIFIED 8.30 Data Collection and Limit Identification $0.00 $0.00 832 Right -of -Way Limits and Easements- Supp 10 TASK MODIFIED 832 Right -of -Way Limits and Easements- Supp 12 TASK MODIFIED $0.00 $0.00 8.33 Temporary Right of Entry/Access Permit- Supp 10 TASK DELETED -1 -2 -10 -4 - 81,273.72 $0.00 8.34 Legal Descriptions and Exhibits for Acquisition- TASK DELETED $0.00 $0.00 8.60 Relocation Plan - Supp 12 TASK DELETED 4 $0.00 $299.19 8.61 FHWA Funds Authodzati0n for ROW - Supp 10 TASK DELETED -6.5 - $499.19 $0.00 8.80 Acquisition Negotiation, Relocation and Closeout 8.81 Parcel Acquisition Negotiation 3 13 80 6 $0.00 M $6,984.69 1 - Nelson / Frohmuth Single Family Residence Parcel (000580 -0033) Supp 12 TASK MODIFIED 2 - City of Tukwila River Trail Pared (252304 -9081) Supp 12 TASK MODIFIED 2 16 $0.00 $1232.38 3A - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9039) - Supp 10 TASK DELETED -1 -3 -25 -4 - $2,510.57 $0.00 38 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9039) - Supp 10 TASK DELETED -1 -3 -25 -4 - $2,510.57 $0.00 4A - BRCP Riverview Plaza LLC Office Building Pared (252304 -9077) - Supp 10 TASK DELETED -1 -3 -25 -4 - $2,510.57 $0.00 48 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9077) - Supp 10 TASK DELETED -1 -3 -25 -4 - $2,510.57 $0.00 5 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9078) - Supp 10 TASK DELETED -1 -4 -30 -6 - $3,096.66 $0.00 6 - Seattle Public Utilities Storm Water Utility Parcel (252304 -9048) - Supp 10 TASK DELETED -1 -5 -30 -6 - $3,181.54 $0.00 7 - Park Real Estate LLC Office Bldg /Bank Parcel (002310- 0040) - Supp 12 TASK MODIFIED 4 $0.00 $299.19 8- Andover Plaza LLC Retail Parcel (002310-0099) - Supp 12 TASK MODIFIED 4 $0.00 $299.19 8.82 Relocation (Nelson / Frohmuth Parcel) - Supp 10 TASK DELETED -3 -10 -65 -6 - $6,496.95 $0.00 8.100 Green River Trail Easement Negotiation and Modification - Sapp. 12 NEW TASK 4 14 30 8 $0.00 $3,875.24 Supp 10 Labor Removed Subtotal: -10 -33 -182.5 -65 -41 $25,226.93 $12,989.88 Supp 12 Labor Added Subtotal: 7 41 46 80 14 Reimbursables $0.00 $0.00 9.0 9.10 ADDITIONAL STRUCTURAL DESIGN - Su... 12 NEW TASK KPFF Additonal Structural Design - Supp 12 NEW TASK 9.11 Update 30% Bridge Drawings t0 New Alignment- Supp 12 NEW TASK 80.00 80.00 9.12 Approach Span Design and Drafting - Supp 12 NEW TASK 80.00 $0.00 9.13 Abutment Da0gn and Drafting - Supp 12 NEW TASK 80.00 80.00 9.14 Revise Drilled Shaft Design- Supp 12 NEW TASK $0.00 80.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 $0'00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables 1 00.00 $219.00 10.0 BRIDGE AESTHETICS COLLABORATION - Supp. 12 NEW TASK (LMN) 10.10 Bridge Structure- Supp 12 NEW TASK 10.11 Arch Geometry - Supp 12 NEW TASK $0.00 $0.00 10.12 Connections - Susp Cables- Supp 12 NEW TASK 50.00 50.00 10.13 Connections - Bridge Deck - Supp 12 NEW TASK $0.00 $0.00 10.14 Connec lions - Tied Arch - Supp 12 NEW TASK $0.00 $0.00 10.20 Approach Ramps- Supp 12 NEW TASK 10.21 Deck Treatments- Supp 12 NEW TASK $0.00 $0.00 10.22 Handrail System - Supp 12 NEW TASK $0.00 $0.00 10.30 Design Development and Coordination - Supp 12 NEW TASK ....L 10.31 Tied Arch Sketches - Supp 12 NEW TASK $0.00 $0.00 10.32 West Approach Sketches - Supp 12 NEW TASK 80.00 $0.00 10.33 East Approach Sketches - Supp 12 NEW TASK 80.00 00.00 10.34 Study Model Development - Supp 12 NEW TASK $0.00 $0.00 10.35 Renderings - Supp 12 NEW TASK 00.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 Reimbursables 1 .1 - $12,584.50 $0.00 Supp 10 Labor Removed Sum -10 -33 -183 -65 -41 $25,226.93 $12,989.88 Supp 12 Labor Added Sum 7 41 46 80 14 Reimbursables Firm Total DESIGN TEAM TOTAL Total Addtl Reimbursables Sum - $12,584.50 $219.00 SUBTOTAL: - $37,811.43 $13,208.88 Fee (Supp 12 - Supp10) - $24,602.55 Ale: 2014.11.04 Combined Fee Estimate (Add &Removed) v1.6(5 Page 6 at 14 49 EXHIBIT G -1 Landau Associates CONSULTANT FEE DETERMINATION SUMMARY OF COST Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Classification Principal Associate Senior Senior Project Project Senior CAD Staff /Senior Technician II Project Coordinator CAD /GIS Technician Overhead (OH) Cost OH Rate x DSC of Fixed Fee (FF) FF Rate Reimbursables Mileage Field Equipment /Supplies Cultural Resources Geotechnical Geotechnical Geotechnical Geotechnical Geotechnical Adjustments Supplement 10 Supplement 10 Subtotal Total Hours X 1.00 X 42.00 X 0.00 X 16.00 X 50.00 X 28.00 X 79.00 X 21.00 X 0.00 X 209.53% 30.00% Rate $72.22 $45.85 $42.20 $39.37 $33.57 $31.17 $26.37 $30.91 $27.64 DSC Subtotal Cost $72.22 $1,925.70 $0.00 $629.92 $1,678.50 $872.76 $2,083.23 $649.11 $0.00 $7,911.44 $7,911.44 $7,911.44 (LS - Tree Assessment) (LS - Tree Assessment) Historic Building Inventory Mileage Laboratory Driller Site Restoration Private Utility Location Remibursable Removed Fee Removed $16,576.84 $2,373.43 $40.00 $49.27 $3,816.75 $100.00 $1,520.00 $13,956.00 $300.00 $340.00 - $104.04 - $20,696.00 - $678.02 Subconsultant Total: $26,183.69 Date: 4/23/2015 50 Hour Summary ENGINEERING COST ESTIMATE, KPFF Consulting Engineers Tukwila Urban Center • Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 Landau Associates Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Principal Associate Senior senior project Pr °lest senior CAD Stall /Senior Technician II Project Coordinate CAD /GIS Technician Item Supp 10 Rates $65.00 $47.00 $40.00 $36.00 - $31.00 $25.00 $29.00 $24.00 SCOPE OF WORK Supp 12 Rates $72 22 545.85 $42.20 $39.37 $33.57 $31.17 $26.37 830.91 $27.64 1.0 1.40 PROJECT MANAGEMENT Design Team Meetings (Assume 2) and Coordination - Supp 12 NEW TASK (KPG & KPFF) r 1.50 Project Team Meetings with City (2) - Supp 12 NEW TASK (KPG & KPFF) Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 Supp 12 tabor Added Subtotal: 0 0 0 0 0 0 0 0 0 Reimbursables 2.0 TOPOGRAPHIC AND BOUNDARY SURVEY (KPG) 2.10 Additional survey and mapping 2.12 Extend survey of Green River Trail - Supp 10 TASK DELETED 2.13 Survey North GRT. Addll Christ. Rd, New Bridge Abut Locations - Supp 12 TASK ADDED Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 0 Reimbursables 3.0 ALT. ALIGNMENT PRELIMINARY DESIGN & NEW ALT. ALIGNMENTS (KPFF & KPG) 3.10 Survey at Riverview Plaza Parking Lot - Supp 10 TASK DELETED 111 Utility Locating Not Used- Supp 10 TASK DELETED 3.20 Walkway Section/ Parking Lot Trail Alignment Studies - Stipp 10. TASK DELETED 3.21 Trail Realignment Alternatives For Riverview Plaza- Supp 10 TASK DELETED 3.22 Riverview frontage 1 property studies - Supp 10 TASK DELETED 3.23 Meetings for Riverview Plaxa property owner coordination - Supp 10 TASK DELETED 3.24 Alt alignments schematic cast estimate comparison - Supp 10 TASK DELETED 3.30 30% Plans - Supp 10 TASK DELETED 3.31 Site Preparation - Supp 10 TASK DELETED 3.32 Utilities - Supp 10 TASK DELETED 3.33 Storm Drainage and Grading -- Supp 10 TASK DELETED 3.34 Paving Plans - Supp 10 TASK DELETED 3.35 Pavement Marking Plans - Supp 10 TASK DELETED 3.40 Update Storm Drainage Report - Supp 10 TASK DELETED 3.50 Update Cost Estimate - Supp 10 TASK DELETED 3.60 New Trail Alignment - Stipp 12 NEW TASK 3.61 Trail alignment urban design to 60 %- Supp 12 NEW TASK 162 Trail alignment landscape design to 60% -Supp 12 NEW TASK 3.63 Trail alignment illumination design to 60%- Supp 12 NEW TASK 3.70 TS &L Supplement 01 - Supp 12 NEW TASK 3.71 Alternative Alignment Layouts - Supp 12 NEW TASK 3.72 Evaluation of Alternative Alignments - Supp 12 NEW TASK 173 TS &L Report Supplement 01 - Supp 12 NEW TASK 3.74 Design Team and City Review Meetings - Supp 12 NEW TASK 3.80 Fatal Flaw Assessment of New Preferred Alignment - Supp 12 NEW TASK 161 River and Levee Constraints - Supp 12 NEW TASK 3.82 Horizontal and Merkel Alignment Alternatives - Supp 12 NEW TASK 3.83 Design Team and City Review Meetings - Supp 12 NEW TASK 3.90 Presentation Graphics - Supp 12 NEW TASK Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 0 Reimbursables 4.0 CIVIL (KPFF) 4.30 Trail Alignment and Modeling - Supp 12 NEW TASK 4.40 Storm Drainage Approach - Supp 12 NEW TASK 0.50 Quantities and Cost Estimate - Supp 12 NEW TASK 4.60 Wall / Railing Assessment - Supp 12 NEW TASK 4.70 30% Plansheet Setup and Layout- Supp 12 NEW TASK Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 0 5.0 5.10 Reimbursables ENVIRONMENTAL AND PERMITTING SERVICES Landau) USCG Navigation Survey and Bridge Permit App. - Supp 10 TASK DELETED -3 -46 -8 -4 5.20 Tree Assessment - Supp 10 TASK MODIFIED -3 -24 -12 -12 -3 -48 5.20 Tree Assessment - Supp 12 TASK MODIFIED 16 16 16 12 3 521 Biological Assessment (KPFF Civil) - Supp 10 TASK DELETED 5.30 Lighting Study Support - Supp 10 TASK MODIFIED -2 -16 -8 5.30 Lighting Study Support - Supp 12 TASK MODIFIED 12 8 5 5.40 De Minimis Section 4(0 Evaluation - Supp 12 NEW TASK 1 10 2 4 2 5.50 Historic Inventory - Supp 12 NEW TASK 4 4 Supp 10 Labor Removed Subtotal: 0 -8 -86 -12 0 -8 -20 -7 -48 Supp 12 Labor Added Subtotal: 1 42 0 16 0 26 21 9 0 Reimbursables Landau Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER 3.2587 3.3953 80.00 $000 50.00 50.00 $0.00 $0.00 50.00 0.00 000 000 80.00 80.00 0.00 90.00 $000 0.00 50 00 50 00 $0 00 $0 00 0.00 0.00 $0.00 0.00 0.00 $0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Woo woo $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 80.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 80.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 $0.00 0.00 0.00 7,485.23 0.00 $10,010.73 0.00 $0.00 $7,712.12 $0.00 $0.00 3,200.04 $0.00 0.00 $3,162.42 0.00 $2,581.65 0.00 ,042.49 520,696.00 $14,498.68 04.04 File: 2014.11.04 Combined Fee Estimate (Add &Removed) 81.6)5 Page 7 of 14 $3,906.02 51 Hour Summary ENGINEERING COST ESTIMATE, KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 Landau Associates Landau Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Principal Associate Senior senior Project Protect senior CAD Stall /Senior Technician II Project Coordinato r CAD /GIS Technician Supp 10 Fee Removed: Supp l2 Fee Added: MULTIPLIER MULTIPLIER Item I Supp 10 Rates $65.00 547.00 $40.00 036.00 - 031.00 $25.00 529.00 524.00 3.2587 SCOPE OF WORK Supp 12 Rates $72.22 $45.85 $42.20 $39.37 $33.57 $31.17 $26.37 $30.91 $27.64 3.3953 7.0 GEOTECHNICAL - Supp. 12 NEW TASK (Landau) t 1 7.10 Field Exploration and Laboratory Testing - Supp 12 NEW TASK 20 58 2 $0.00 $7,682.48 7.20 Geotechnical Evaluation, Reporting and Meetings - Supp 12 NEW TASK 30 2 10 50.00 $4,680.56 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 $0.00 $12,363.03 Supp 12 Labor Added Subtotal: 0 0 0 0 50 2 58 12 g Reimbursables $0.00 $16.216.00 8.0 RIGHT-OF-WAY SERVICES (UFS) 8.20 Title/Ownership Review 8.21 UFS Title/Ownership Review- Supp 10 TASK MODIFIED $0.00 80.00 8.30 Data Collection and Limit Identification 832 Right -of -Way Limits and Easements- Supp 10 TASK MODIFIED $0.00 $0.00 832 Right -of -Way Limits and Easements- Supp 12 TASK MODIFIED 50.00 50.00 8.33 Temporary Right of Entry/Access Permit - Supp 10 TASK DELETED $0.00 $0.00 884 Legal Descriptions and Exhibits for Acquisition- TASK DELETED $0.00 $0.00 8.60 Relocation Plan - Supp 12 TASK DELETED $0.00 $0.00 881 FHW A Funds Authorization for ROW - Supp 10 TASK DELETED $0.00 $0.00 8.80 Acquisition Negotiation, on and Closeout 8.81 Negotiation Parcel Acquisition Negotiation 50.00 $0.00 1 - Nelson / Frohmuth Single Family Residence Parcel (000580 -0033) Supp 12 TASK MODIFIED 2 - City ol Tukwila River Trail Parcel (252304-9081) Supp 12 TASK MODIFIED $0.00 50.00 3A- BRCP Riverview Plaza LLC Office Building Parcel (252304-9039) - Supp 10 TASK DELETED 50.00 $0.00 38- BRCP Riverview Plaza LLC Office Building Parcel (252304-9039) - Supp 10 TASK DELETED $0.00 $0.00 4A- BRCP Riverview Plaza LLC Office Building Parcel (252304-9077)- Supp 10 TASK DELETED $0.00 $0.00 48 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9077) - Supp 10 TASK DELETED $0.00 $0.00 5- BRCP Riverview Plaza LLC Office Building Parcel (252304-9078)- Supp 10 TASK DELETED 50.00 $0.00 6 - Seattle Public Utilities Storm Water Utility Parcel (252304 -9048) - Supp 10 TASK DELETED 80.00 $0.00 7 - Park Real Estate LLC Office Bldg /Bank Parcel (002310 -0040) - Supp 12 TASK MODIFIED $0.00 $0.00 8- Andover Plaza LLC Retail Parcel ( 002310 - 0099) - Supp 12 TASK MODIFIED $0.00 80.00 8.80 Relocation (Nelson 1 Frohmuth Parcel) - Supp 10 TASK DELETED $0.00 $0.00 8.100 Green River Trail Easement Negotiation Modification Supp. 12 NEW TASK 80.00 50.00 and - Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 0 Reimbursables r $0.00 $0.00 9.0 ADDITIONAL STRUCTURAL DESIGN - Supp. 12 NEW TASK (KPFF) 9.10 Additonal Structural Design - Supp 12 NEW TASK 8 9.11 Update 30% Bridge Drawings to New Alignment- Supp 12 NEW TASK $0.00 80.00 9.12 Approach Span Design and Drafting - Supp 12 NEW TASK $0.00 $0.00 9.13 Abutment Design and Drafting - Supp 12 NEW TASK $0.00 $0.00 914 Revise Dulled Shaft Design - Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 0 Reimbursables 1111F 50.00 50.00 10.0 BRIDGE AESTHETICS COLLABORATION - Supp. 12 NEW TASK (LMN) $0.00 $0.00 10.10 Bridge Structure - Supp 12 NEW TASK 10.11 Arch Geometry - Supp 12 NEW TASK 10.12 Connections - Susp Cables - Supp 12 NEW TASK 50.00 50.00 10.13 Connections - Bridge Deck - Supp 12 NEW TASK $0.00 $0.00 10.14 Connections - Tied Arch - Supp 12 NEW TASK $0.00 $0.00 10.20 Approach Ramps - Supp 12 NEW TASK 10.21 Deck Treatments - Supp 12 NEW TASK 50.00 50.00 10.22 Handrail System- Supp 12 NEW TASK $0.00 $0.00 10.30 Design Development and Coordination - Supp 12 NEW TASK 10.31 Tied Arch Sketches- Supp 12 NEW TASK $0.00 $0.00 10.32 West Approach Sketches -Supp 12 NEW TASK $0.00 $0.00 10.33 East Approach Sketches - Supp 12 NEW TASK $0.00 80.00 10.34 Study Model Development- Supp 12 NEW TASK $0.00 $0.00 10.35 Renderings - Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 0 Reimbursables $0.00 $0.00 Supp 10 Labor Removed Sum 0.0 -8.0 -86.0 -12.0 0.0 -8.0 -20.0 -7.0 -48.0 $20,696.00 $26,861.71 Supp 12 Labor Added Sum 1.0 42.0 0.0 16.0 50.0 28.0 79.0 21.0 0.0 Reimbursables Firm Total DESIGN TEAM TOTALI Total Reimbursables Sum - $104.04 $20,122.02 Landau SUBTOTAL: - $20,800.04 $46,983.73 Addtl Fee (Supp 12 - Supp10) $26,183.69 File: 2014.11.04 Combined Fee Estimate (Add &Removed) v1.6(6 Page 80114 52 EXHIBIT G -1 LMN Architects CONSULTANT FEE DETERMINATION SUMMARY OF COST Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Classification Partner Project Manager Project Designer Project Architect Intern Admin Specs QA /QC Overhead (OH) Cost OH Rate x DSC of Fixed Fee (FF) Reimbursables FF Rate Subtotal Total Hours X Rate = Cost 8.00 X $81.73 = $653.84 0.00 X $32.69 = $0.00 34.00 X $49.53 = $1,684.02 20.00 X $33.17 = $663.40 216.00 X $23.56 = $5,088.96 0.00 X $18.75 = $0.00 0.00 X $39.42 = $0.00 0.00 X $38.42 = $0.00 190.47% 25.00% DSC Subtotal $8,090.22 $8,090.22 $15,409.44 $8,090.22 $2,022.56 $0.00 Subconsultant Total: $25,522.22 Date: 4/23/2015 53 Hour Summary ENGINEERING COST ESTIMATE: KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 LMN Architects Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Partner Project Manager Project Designer Project Architect Intern Admin Specs QA/QC Supp 10 Fee Removed: Supp 12 Foe Added: MULTIPLIER MULTIPLIER Item I Supp 10 Rates SCOPE OF WORK Supp 12 Rates $81.73 $32.69 $49.53 $33.17 $23.56 $18.75 539.42 $38.42 3.1547 1.0 PROJECT MANAGEMENT 11 1.40 Design Team Meetings (Assume 2) and Coordination - Supp 12 NEW TASK (KPG & KPFF) $0.00 80.00 1.50 Project Team Meetings with City (2)- Supp 12 NEW TASK (KPG & KPFF) $0.00 80.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 80.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables $0.00 $0.00 2.0 TOPOGRAPHIC AND BOUNDARY SURVEY (KPG) 11. 2.10 Additional survey and mapping 2.12 Extend survey of Green River Trail - Supp 10 TASK DELETED $0.00 $0.00 2.13 Survey North GRT, Addt1 Christ. Rd, New Bridge Abut Locations - Supp 12 TASK ADDED I{ $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables $0.00 80.00 3.0 ALT. ALIGNMENT PRELIMINARY DESIGN & NEW ALT. ALIGNMENTS (KPFF & KPG) 3.10 Survey at Riverview Plaza Parking Lot - Supp 10 TASK DELETED 3.11 Utility Locating Not Used- Supp 10 TASK DELETED $0.00 $0.00 3.20 Walkway Section/ Parking Lot Trail Alignment Studies - Stipp 10. TASK DELETED 3.21 Trail Realignment Alternatives For Riverview Plaza- Supp 10 TASK DELETED $0.00 $0.00 3.22 Riverview front age / property studies- Supp 10 TASK DELETED $0.00 $0.00 3.23 Meetings for Riverview Piaxa property owner coordination - Supp 10 TASK DELETED 0.00 $0.00 3.24 Alt alignments schematic cast estimate comparison - Supp 10 TASK DELETED $0.00 $0.00 3.30 30 % Plans -Supp 10 TASK DELETED $0.00 $0.00 3.31 Site Preparation- Supp 10 TASK DELETED $0.00 $0.00 3.32 Utilities - Supp 10 TASK DELETED $0.00 $0.00 3.33 Storm Drainage and Grading - - Supp 10 TASK DELETED $0.00 $0.00 3.34 Paving Plans- Supp 10 TASK DELETED $0.00 $0.00 3.35 Pavement Marking Plans - Supp 10 TASK DELETED $0.00 $0.00 3.90 Update Storm Drainage Report - Supp 10 TASK DELETED 80.00 $0.00 3.50 Update Cost Estimate- Supp 10 TASK DELETED $0.00 80.00 3.60 New Trail Alignment - Supp 12 NEW TASK 3.61 Trail alignment urban design to 60 %- Supp 12 NEW TASK $0.00 $0.00 3.62 Trail alignment landscape design to 60%- Supp 12 NEW TASK $0.00 $0.00 3.63 Trail alignment illumination design to 60 %- Supp 12 NEW TASK $0.00 $0.00 3.70 TS&L Supplement 01 - Stipp 12 NEW TASK 3.71 Alternative Aligned Layouts - Supp 12 NEW TASK $0.00 $0.00 3.72 Evaluation of Alternative Alignments- Supp 12 NEW TASK $0.00 $0.00 3.73 TSBL Report Supplement 01 - Supp 12 NEW TASK $0.00 $0.00 3.74 Design Team and City Review Meetings - Supp 12 NEW TASK $0.00 $0.00 3.80 Fatal Flaw Assessment of New Preferred Alignment - Supp 12 NEW TASK $0.00 $0.00 3.81 River and Levee Constraints - Supp 12 NEW TASK $0.00 $0.00 3.82 Horizontal and Vertical Aligned Alternatives - Supp 12 NEW TASK $0.00 $0.00 3.83 Design Team and City Review Meetings - Supp 12 NEW TASK $0.00 $0.00 3.90 Presentation Graphics- Supp 12 NEW TASK 80.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursable5 $0.00 $0.00 4.0 CIVIL (KPFF) 4.30 Trail Alignment and Modeling - Supp 12 NEW TASK $0.00 $0.00 4.90 Storm Drainage Approach- Supp 12 NEW TASK $0.00 00.00 4.50 Quantities and Cost Estimate - Supp 12 NEW TASK $0.00 $0.00 4.60 Well / Railing Assessment- Stipp 12 NEW TASK $0.00 00.00 4.70 30 %Plansheet Setup and Layout - Supp 12 NEW TASK $0.00 $0.00 Supp 00 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables $0.00 $0.00 5.0 ENVIRONMENTAL AND PERMITTING SERVICES (Landau) 5.10 USCG Navigation Survey and Bridge Permit App. - Supp 10 TASK DELETED 00.00 $0.00 5.20 Tree Assessment- Supp 10 TASK MODIFIED $0.00 $0.00 5.20 Tree Assessment • Sapp 12 TASK MODIFIED $0.00 $0.00 5.21 Biological Assessment (KPFF Civil) - Supp 10 TASK DELETED $0.00 $0.00 5.30 Lighting Study Support - Supp 10 TASK MODIFIED $0.00 $0.00 5.30 Lighting Study Support - Supp 12 TASK MODIFIED $0.00 $0.00 5.40 De Minimis Section 4(f) Evaluation - Stipp 12 NEW TASK $0.00 $0.00 5.50 Historic Inventory - Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0.00 80.00 Supp 12 Labor Added Subtotal: 0 0 0 0 0 0 0 0 Reimbursables 5000 80 00 File: 2014.11.04 Combined Fee Estimate (Add &Removed) 01.xls Page of 14 54 Hour Summary ENGINEERING COST ESTIMATE: KPFF Consulting Engineers Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 April 23, 2015 LMN Architects I Tukwila Urban Center - Pedestrian /Bicycle Bridge, Supplement No. 12 Partner Prefect Manager Project Designer Project Architect Intern Admin Specs QA/QC Supp 10 Fee Removed: Supp 12 Fee Added: MULTIPLIER MULTIPLIER Item Supp 10 Rates SCOPE OF WORK Supp 12 Rates $81.73 $32.69 $49.53 $33.17 $23.56 $18.75 $39.42 $38.42 3.1547 7.0 7.10 GEOTECHNICAL - Supp. 12 NEW TASK (Landau) Field Exploration and Laboratory Testing - Supp 12 NEW TASK M $0.00 $0.00 7.20 Geotechnical Evaluation, Reporting and Meetings- Supp 12 NEW TASK $0.00 $0.00 Supp 10 Labor Removed Subtotal 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal. 0 0 0 0 0 0 0 0 Reimbursables 20.00 • $0.00 8.0 RIGHT -OF -WAY SERVICES (UFS) 8.20 Title /Ownership Review 8.21 UFS Title/Ownership Review- Supp 10 TASK MODIFIED 50.00 $0.00 8.30 Data Collection and Limit Identification 8.32 Right -of -Way Limits and Easements - Supp 10 TASK MODIFIED 50.00 $0.00 8.32 Right -of -Way Limits and Easements - Supp 12 TASK MODIFIED 80.00 $0.00 8.33 Temporary Right of En try/Access Per Supp 10 TASK DELETED $0.00 $0.00 8.34 Legal Descriptions and Exhibits for Acquisfion -TASK DELETED $0.00 $0.00 8.60 Relocation Plan - Supp 12 TASK DELETED $0.00 00.00 8.61 FHWA Funds Authorization for ROW -Supp 10 TASK DELETED $0.00 $0.00 8.80 Acquisition Negotiation, Relocation and Closeout $0.00 $0.00 8.81 Parcel Acquisition Negotiation 1 - Nelson / Frohmuth Single Family Residence Parcel (000580 -0033) Supp 12 TASK MODIFIED 2- City of Tukwila River Trail Parcel (252304-9081) Supp 12 TASK MODIFIED $0.00 80.00 3A - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9039) - Supp 10 TASK DELETED $0.00 $0.00 3B - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9039) - Supp 10 TASK DELETED $0.00 $0.00 4A- BRCP Riverview Plaza LLC Office Building Parcel (252304-9077) - Supp 10 TASK DELETED $0.00 00.00 4B - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9077) - Supp 10 TASK DELETED $0.00 00.00 5 - BRCP Riverview Plaza LLC Office Building Parcel (252304 -9078) - Supp 10 TASK DELETED 80.00 $0.00 6 - Seattle Public Utilities Storm Water Utility Parcel (252304 -9048) - Supp 10 TASK DELETED $0.00 $0.00 7 - Park Real Estate LLC Office Bldg/Bank Parcel (002310 -0040) - Supp 12 TASK MODIFIED $0.00 $0.00 8 - Andover Plaza LLC Retail Parcel (002310 -0099) - Supp 12 TASK MODIFIED $0.00 80.00 8.82 Relocation (Nelson / Frohmuth Parcel) - Supp 10 TASK DELETED $0.00 80.00 8.100 Green River Trail Easement Negotiation and Modification - Supp. 12 NEW TASK 80.00 80.00 Supp 10 Labor Removed Subtotal. 0 0 0 0 0 0 0 0 $0.00 $0.00 Supp 12 Labor Added Subtotal. 0 0 0 0 0 0 0 0 Reimbursables 5 0.0 0 $0.00 9.0 ADDITIONAL STRUCTURAL DESIGN - Supp. 12 NEW TASK (KPFF) 1 9.10 Additonal Structural Design - Supp 12 NEW TASK II 9.11 Update 30% Bridge Drawings to New Alignment- Supp 12 NEW TASK $0.00 $0.00 9.12 Approach Span Design and Drafting - Supp 12 NEW TASK $0.00 $0.00 9.13 Abutment Design and Drafting - Supp 12 NEW TASK 80.00 $0.00 9.14 Revise Drilled Shaft Design - Supp 12 NEW TASK 80.00 $0.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 Moo $0.00 Supp 12 Labor Added Subtotal. 0 0 0 0 0 0 0 0 Reimbursables $0.00 $0.00 80.00 $1,774.74 10.0 BRIDGE AESTHETICS COLLABORATION - Supp. 12 NEW TASK (LMN) - 12 10.10 Bridge Structure- Supp 12 NEW TASK 10.11 Arch Geometry - Supp 12 NEW TASK 1 4 10.12 Connections - Susp Cables - Supp 12 NEW TASK 1 2 12 $0.00 $1,462.23 10.13 Connections - Bridge Deck- Supp 12 NEW TASK 1 2 12 $0.00 $1,462.23 10.14 Connections - Tied Arch - Supp 12 NEW TASK 1 2 12 80.00 $1,462.23 10.20 Approach Ramps- Supp 12 NEW TASK 10.21 Deck Treatments - Supp 12 NEW TASK 1 2 12 80.00 $1,462.23 1022 Handrail System - Supp 12 NEW TASK 1 2 12 $0.00 $1,462.23 10.30 Design Development and Coordination- Sapp 12 NEW TASK 1 10.31 Tied Arch Sketches - Supp 12 NEW TASK 1 6 10 24 $0.00 $4,025.55 10.32 West Approach Sketches- Supp 12 NEW TASK 2 16 $0.00 $1,501.70 10.33 East Approach Sketches - Supp 12 NEW TASK 1 6 10 24 $0.00 $4,025.55 10.34 Study Model Development - Supp 12 NEW TASK 2 40 $0.00 $3,285.49 10.35 Renderings - Supp 12 NEW TASK 4 40 $0.00 $3,598.00 Supp 10 Labor Removed Subtotal: 0 0 0 0 0 0 0 0 $0'00 $25,522.22 Supp 12 Labor Added Subtotal: 8 0 34 20 216 0 0 0 Reimbursables - $0.00 $0.00 Supp 10 Labor Removed Sum 0 0 0 0 0 0 0 0 $0.00 $25,522.22 Supp 12 Labor Added Sum 8 0 34 20 216 0 0 0 Reimbursables Firm Total DESIGN TEAM TOTAL Total Addtl Reimbursables Sum $0.00 $0.00 $25,522.22 LMN SUBTOTAL: $0.00 Fee (Supp 12 - Supp10) $25,522.22 File: 2014.11.04 Combined Fee Estimate (Add &Removed) 81.0)5 Page 1 0 0 8 1 4 55 CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2015 to 2020 PROJECT: Tukwila Urban Center - Pedestrian /Bicycle Bridge Project No. 90510403 DESCRIPTION: Construct a new pedestrian /bicycle bridge over the Green River. JUSTIFICATION: Pedestrian /bicycle connection between Tukwila's Urban Center and commuter rail /Amtrak station. Supports local and regional goals and policies regarding land use and transportation in Urban Center. Pedestrian System Report identified the optimal location for bridge crossing to be south of the Ramada Inn at STATUS: 15901 West Valley Hwy. Type, Size, and Location Report was completed in 2011. Council approved a design of a twin -tied arch bridge with no accommodation for a future bridge crossing over West Valley Highway. MAINT. IMPACT: To be determined. Design grants: State Enhancement for $190k & $500k, Transit Oriented Development (TOD) planning grant COMMENT: of $55k, and Federal CMAQ grant of $751 K. WSDOT Regional Mobility construction grant of $6.870M. Project is on Park Impact Fee list with funding of $2 million with an 80 %/20% split for $1.6M. FINANCIAL Through Estimated in $000's 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL EXPENSES Design 921 200 442 1,563 Land (R/W) 1,100 1,100 Const. Mgmt. 150 700 850 Construction 1,000 5,485 6,485 TOTAL EXPENSES 921 200 2,692 6,185 0 0 0 0 0 9,998 FUND SOURCES Awarded Grant 842 100 554 1,496 Awarded Reg Mobility 870 6,000 6,870 Park Impact Fees 79 44 70 75 268 Bond /Interfund Loan 0 City Oper. Revenue 0 56 1,198 110 0 0 0 0 0 1,364 TOTAL SOURCES 921 200 2,692 6,185 0 0 0 0 0 9,998 2015 - 2020 Capital Improvement Program 12 56